Professional Documents
Culture Documents
Tcsp12202r0-Material Handling
Tcsp12202r0-Material Handling
TABLE OF CONTENTS
1.0 SCOPE
2.0 PURPOSE
4.1 General
4.2 Location
4.3 Size of Storage Area
4.4 Office in Storage Area
1.0 SCOPE
2.0 PURPOSE
This Standard is applicable to Lump Sum Turnkey Projects (LSTK projects) where
material is arranged by the contractor for erection and installation of transmission lines
as well as to the projects where material is supplied by SEC to the contractor. The
purpose is to present the methods adopted and the equipment commonly used to store
and handle materials in the construction storage yards and delivery to construction
sites.
For the return of surplus and salvaged material to SEC central stores, the construction
superintendent shall give at least 24 hours advance notice to SEC, including the items
and quantities involved. The procedures as set out in the MMD Manual 370-001 of
SEC shall be followed for return of material. Return of materials at times other than
SEC regular working hours shall be permitted only with the written approval of SEC
site engineer and the SEC MMD/W&DD Superintendent.
4.1 General
4.1.1 All materials provided shall be stored in safe and secured locations
protected by proper fence, even if it is stored for a short period of time.
4.2 Location
4.2.1 Storage areas shall be near the project site, preferably near the center of
the transmission line project under consideration. If the length of the
transmission line is in excess of 80 km, two or more storage areas shall
be considered depending on the actual length, in order to reduce the
time for delivery of materials to various structures.
4.2.2 To the extent possible, storage area shall be located near existing
Highways or good roads. Where this is not feasible, contractor shall be
responsible for making suitable arrangements to ensure safe transport of
materials to and from the storage areas.
4.2.3 Storage areas shall be located away from low level areas to avoid
inundation during rains and shall be accessible at all times during the
period of the contract.
4.2.4 Camp facilities for workmen of the contractor shall be provided near the
storage areas. The storage area shall not be used as a parking place for
contractor’s vehicles and equipment.
This will depend upon the Size and type of Transmission line to be erected.
Figures 02-1 and 02-2 show the approximate space requirements to store
materials for five to fifty steel towers. These are for estimation and guidance
purposes only and the contractor shall submit detailed layout for SEC approval
before finalizing the storage area. Sufficient space shall be provided for
maneuvering trucks and lifting equipment for unloading and loading of
material.
4.4.1 Office space shall be provided within the storage area for the store
keeper for preserving and maintaining records of receipts and deliveries
of material to the construction crew. Porta-camps or portable houses
may be used for this purpose.
Office facilities shall be provided in the same enclosure for SEC Site
Engineer and Project quality Engineer, as specified in the project scope
of work.
4.4.2 The storekeeper designated by the contractor shall have a complete set
of the plants and specifications of the project. He shall also have a
complete bill of materials, bills of lading etc. and copies of all shop and
fabrication drawings for checking the materials as and when they are
delivered to the site for storage.
4.4.3 Adequate number of approved class ‘A’ or ‘ABC’ portable fire
extinguishers shall be provided in accordance with SEC safety
standards within the storage yard, site office and also located at the
outside wall, near the entrance door of the office building.
5.2 Storage
Materials shall be carefully handled during all phases of the work and shall be
stored by placing them on suitable blocks or racks so that no part of the
material is in contact with the ground
In storage and at tower site, all tower steel shall be kept clear of the ground in a
clean and tidy condition. Contact with standing water or other substances likely
to attack galvanizing shall be avoided.
Where lumber form, damaged poles or similar materials are used as blocks,
they shall be free of any protruding nails or other metal which could damage
any material stored on them and/or cause injury to personnel
During the course of the project, the material storage area shall be kept neat
and clean and the growth of any vegetation kept to a minimum.
The equipment used for unloading and loading of material shall be of suitable
size and capacity. For safety reasons as well as to avoid damage to the
materials, under no circumstances shall any handling loading/unloading
equipment be overloaded. The handling loading/unloading equipment will
generally range from a truck with an A-frame, Carry-lift loader, crane to
flatbed trucks with hydraulic lift. The actual equipment required will depend
on the type of materials to be used for the project.
b. Bare wire rope or steel chains shall not be used for loading and
unloading of steel members, unless adequate protection of the
surface coating is ensured.
f. All superficial rust stains, corrosive salts and other foreign materials
deposited prior to or during installation of the towers shall be
removed without causing damage to the protective surfaces.
a. Care shall be exercised at all times so that the wood poles are not
scuffed or piked to the point that damage may occur. The
storekeeper and SEC site engineer shall inspect the poles for any
damages and shall set the damaged poles aside. Rejected poles are
to be replaced. Any damages due to mishandling or use of improper
equipment by the contractor, shall be replaced at the cost of the
contractor.
e. Three or more poles per stock or pile shall be used. For poles more
than 21 meters long, additional blocks shall be used. The poles shall
be stacked or piled such that the pole taper position alternates on
consecutive layers.
The contractor shall be responsible for the safe transport and delivery of all material to
the project site. Before delivery to site, all items shall be segregated based on the
actual requirements at the structure site. The contractor shall designate his
representative who will be responsible for the materials delivered to project site and
also maintain a record of such deliveries.
6.2.1 The unloading of poles at the project site is the reverse of the loading
procedure used to load the poles on the trailer. The top pole is unloaded
at the first structure location, the next pole at the second structure
location and so on. The pole shall be unloaded with the butt placed
closer to the pole stakes, with tops toward the direction of the next
structure location. Hardware shall be placed in wooden boxes to ensure
that the material will not be lost, misplaced or buried in the sand.
6.3.1 For the handling, loading and unloading of conductors and ground
wires refer TCS-P-104.02.
6.3.2 The conductor and overhead ground wire reels shall be delivered at
designated tension sites along the transmission line right-of-way,
adjacent to the location of the tensioning equipment.
Large materials such as steel tower members, steel monopoles and wood poles shall be
loaded on a flatbed trailer, and pulled by a line truck to the work site. The brakes of
the trailer shall be set and the wheels chocked while the materials are loaded on the
trailer.
Tower members shall be loaded on the flatbed trailer in bundles. Loading shall
be done per structure type, per structure location. After loading, bundles shall
be secured with nylon strings to avoid their movement during transit. Care
shall be exercised not to damage the coating or deform the members. Throwing
of tower steel into piles on conveyances, onto the ground, or skidding of steel
members over each other is not permitted.
Special care shall be taken to prevent damage to the surface of the steel
monopoles and arms. Slings for handling the poles shall be made of, or covered
with nylon to protect the finish. No part of the monopole shall be dragged
along the ground or against the flatbed trailer or other objects that could
damage the structure or the surface.
Wood poles shall be loaded on the flatbed trailers in alternate taper position to
balance the weight of the poles on the trailer. After loading, they shall be
secured with dunnage, slings or chains, or both, to keep the load from shifting
during transit. Flags shall be installed at the ends of the poles during daylight
and warning red lights after dark,escorted by safety vehicle if load is exceeding
the truck bed by 2-3 meters. Care shall be taken to caution and protect the
public while hauling the poles on a highway.