Professional Documents
Culture Documents
BRS1-DB-E-BRS-0001.RD2 Electrical Design Basis
BRS1-DB-E-BRS-0001.RD2 Electrical Design Basis
COMPLEX DEVELOPMENT
11 September
D1 Issued Approved for Design AM MC GS
09
TABLE OF CONTENTS
GLOSSARY ......................................................................................................................... 5
1.0 INTRODUCTION........................................................................................................ 8
1.4 Scope..................................................................................................................... 9
Page 2 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
4.13 D.C. System Maximum Voltage Variation (with Ni-Cd Batteries) ..................... 34
Page 3 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
4.48 Wellhead, Gathering Stations and Pipeline Solar Power Supplies ................. 56
Page 4 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
GLOSSARY
The following terms are generic to the Bir Seba Project and may be referred to in this
document:
A Ampere
A.C. Alternating Current
AFC Automatic Frequency Controller
ALARP As Low As Reasonably Possible
API American Petroleum Institute
ATEX Directive for the supply and use of equipment in potentially explosive
atmospheres (ATmosphere EXplosive)
BOPD Barrels of Oil Per Day
CACA Closed Air to Closed Air (Heat Exchanger on a motor)
CENELEC European Committee for Electrotechnical Standardisation
CIBSE Chartered Institute of Building Services Engineers
°C Degrees Centigrade
DAVR Digital Automatic Voltage Regulator
D.C. Direct Current
EI Energy Institute (formerly the Institute of Petroleum)
EN Euro Norm
ENA Energy Networks Association
Page 5 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 6 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 7 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
1.0 INTRODUCTION
1.1 General
Production Sharing Contract (PSC) for Blocks 433a & 416b, Touggourt Permit,
Algeria has been executed between Sonatrach and Petrovietnam Exploration and
Production Corporation – PVEP (formerly named PIDC) on 10th July 2002 and
became effective since 30th June 2003. These blocks span an area of about
6,472 sq. km and located 550km southeast of Algiers and 130km northeast of the
giant oil field Hassi Messaoud (HMD). The original area was 6,472 sq. km and
the current area is about 4,530 sq. km after the first relinquishment.
The Participating Interests are shared between PVEP (40%), PTTEP Algeria
(35%) and SONATRACH (25%).
Development of BRS will be divided in two phases to mitigate technical
uncertainties and up-front expenditure. The first priority is to execute Phase 1 in a
good manner; the success of Phase 1 will be the key foundation for full scale
development.
BRS Phase 1 Development will be implemented with the objectives of providing
detailed information of the reservoir characteristics and performance, provide
better definition of the reserves in the BRS field and provide revenue. BRS is a
marginal development and the key objectives shall be to minimize CAPEX,
achieve first oil production in late 2011 and provide a facility with sufficient
flexibility in the design to accommodate possible upside, tie-in of future facilities,
etc.
The core facilities for BRS Phase 1 Oil Development will comprise:
• The production facilities will be designed to handle and process capacity of
20,000 BOPD without reservoir pressure maintenance. All production facilities
will be installed in modules with flexibility for future upgrade and extension.
• The crude oil and condensate will be exported to Haoud El Hamra (HEH) via a
14” 130km oil export pipeline. A 12” 130km gas delivery pipeline will also be
installed from day 1 of production to deliver raw gas to HMD.
Page 8 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
1.2 Definitions
EPC Contractor or
The Contractor(s) appointed by the CA for the supply of the
CONTRACTOR equipment. Requirements of this specification shall be
enforced at all levels of the CONTRACTOR’S procurement
process. CA shall have access to all CONTRACTOR’S
suppliers to the same extent as required of CONTRACTOR.
1.3 Terminology
1.4 Scope
This document describes the electrical system for the BRS project. It also
describes the design philosophy for the Electrical System and the minimum
requirements and standards to which it must be designed.
The scope covers the power generation, distribution equipment and system,
protection, power and control cabling, UPS systems, small power distribution and
wiring, lighting, Local Control Units, Aircraft Warning Lights, Earthing, Cathodic
Protection and any other electrical items necessary for completion of the works
within the overall scope of the project.
Page 9 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Refer to the Safety and Fire Protection Design Philosophy document number
BRS1-PH-L-BRS-0001 for the fire detection and alarm requirements, safety signs
and eye wash bottle requirements etc., in substations and other electrical areas.
Refer to the EPC Scope of Work for Production Facilities and Pipelines document
number BRS1-RP-G-BRS-0022 for details of contractual issues and project
procedures.
Page 10 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
2.1 General
The design, construction and supply of the equipment shall be in accordance with
the latest revisions of the following specifications, data sheets, codes and
standards.
Where national Algerian regulations, codes and standards exist, their
recommendations shall always apply. Such national regulations shall therefore
supplement or amend the provisions of this document.
In the event of any conflict between this specification and the documents listed
herein, the decreasing order of precedence shall be:
The design shall meet the requirements and regulations of the Algerian
Government and Sonatrach including all laws, decrees and ordinances.
Page 11 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 12 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 13 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 14 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 15 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 16 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 17 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 18 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 19 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 20 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 21 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 22 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 23 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
3.1 Parameters
The environmental data to be used in the design of the BRS Plant are as detailed
below:
Location:
Country Algeria
Altitude 110-172m (CPF @ 132 m)
Climate Dry, sandy desert, environment (Sahara)
Air:
Design minimum temperature -5°C
Design maximum temperature 55°C
Design Temperature For Electric Motors 50°C
Black Bulb Temperature, Equipment Exposed to 90°C
Direct Sunlight
Average Medium Temperature – Winter 15°C
Average Medium Temperature – Summer 29°C
Medium Temperature - Annual 22°C
Average summer humidity 34%
Average winter humidity 54%
Maximum humidity 97%
Minimum humidity 9%
Max. Soil Temp. 29°C at 1.0 m below grade
Min. Soil Temp 15°C at 1.0 m below grade
Rainfall:
Maximum monthly 57 mm
Typical 60 minutes max. 20 mm
Typical 24 hours max. 45 mm
Local Contamination:
Dust High
Saline Air Low
Sandstorms High
Wind:
Maximum wind speed (for structural design) 50 m/s
Maximum recorded wind speed (1998-2007) 38 m/s
Annual Medium 3.3 m/s
Seismic Design Criteria: Seismic Zone 0
Lightning: High concentration of direct lightning phenomena
during seasonal storms
Page 24 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
For equipment installed inside air conditioned buildings (Substations and Control
Building), the ambient temperature inside the buildings will be in the range of 5°C
to + 40°C. However, equipment shall be capable of performing satisfactorily up to
its rated capacity without deterioration and not suffer any damage during failure
of the air-conditioning system. For up to twenty-four hours a temperature of 45°C
and relative humidity of 95% (non-condensing) may occur.
Page 25 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
4.1 General
• Personnel safety
• Plant and equipment integrity
• Environmental conditions of the site
• Reliability of supply depending on the importance of service
• Reduction of spaces and cost
• Easiness of management and maintenance
• Commonality of electrical equipment for operator familiarity
• Adequate flexibility for future installations and inter-changeability
• Standardisation and availability of components
• Reduced risk of fire or explosion to ALARP
• The plant and equipment shall have a design life of 25 years
• Generation and distribution equipment shall be capable of supplying 125% of
peak load without exceeding specified voltage limit and equipment ratings
• Fail safe features for safety related controls
The utilized units shall comply with the International System (S.I.).
The following voltage levels shall be selected for the electrical system at +/-2% of
power system rated frequency of 50Hz. Under steady state conditions the voltage
at all points on the system shall be kept between +/-5% and the frequency rated
at +/-2%.
Electrical equipment shall be suitable for operation with voltage variations ranging
within +/-10% of rated values.
The applicable voltage levels, frequencies and neutral systems shall be as
follows:
Page 26 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 27 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
All classified areas shall be deemed as Zone 1 or Zone 2, with suitable electrical
equipment selection as detailed above.
Proper zone classification shall be made for an area, before specifying or
installing electrical equipment. The Energy Institute Model of Safe Practice Part
15 describes the process for classifying an area as Zone 0, Zone 1, Zone 2 or
unclassified.
The extent of Zone 1, Zone 2 and non-hazardous areas shall therefore be as
indicated on the 'Hazardous Area Classification Drawings' which will be prepared
by the Contractor, based on the boundaries of the hazardous areas and indicate
safe distances between sources of ignitable vapours and ignition sources and
unclassified areas.
The equipment protection technique as utilised (e.g. flameproof Ex d, increased
safety Ex e, non-sparking Ex nA and pressurised Ex p), shall without exception
be suitable for the associated classified area (Zone 1 or Zone 2).
Typical examples of equipment that must be checked include:-
• Motors
• Instrument control system enclosures
• Actuators
• Luminaires
• Junction Boxes
• Local Control Units (LCUs)
Page 28 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
This may in certain instances, include portable equipment that can be brought
into the area for normal operational use.
Electrical items such as sub-distribution boards, D.C. control and converters,
D.C. motor starters together with regulation equipment and batteries, should as
far as is reasonably practicable and economic, be located within a non-hazardous
area.
Where electrical equipment is to be installed in hazardous areas, equipment with
a type of protection suitable for the relevant Zone of hazard will be selected and
specified in accordance with IEC 60079, or equivalent International Standard.
Although many types of protection concepts are available, the following should be
used in the final selection:-
Non-Hazardous Areas:-
For the purpose of commonality of spares and to cater for the possibility of re-
classification of areas, Zone 2 certified equipment will be installed in all outdoor
non-hazardous areas within process installations.
This applies specifically to motors and motor control stations, lighting and small
power outlets.
Electrical equipment installed in indoor, non-hazardous areas outside of process
installations may be of a standard industrial type.
Any equipment required to operate on detection of a facility gas release (i.e.
emergency lighting etc.) shall be certified for use in Zone 1 area.
Street Lighting shall either be certified for hazardous area use or be switched off
via an ESD signal in the event of a gas release.
Floodlighting shall be certified for hazardous area use.
With reference to equipment for use in hazardous area location (Zone 1 or Zone
2), selection shall be based on the selection of one of the following categories of
certification: -
Page 29 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Zone 1 Areas
• Increased Safety (Ex e equipment)
• Flameproof or Explosion Proof (Ex d equipment)
• Pressurised (Ex p equipment)
Zone 2 Areas
• Non-Sparking (Ex nA equipment) – L.V. motors up to 100kW
• Flameproof (Ex d equipment) – L.V. motors above 100kW
• Equipment complying with Zone 1 requirements
All electrical apparatus designated for use in hazardous areas shall be certified to
a CENELEC Standard (European Standard) and will have been tested and
certified by an independent recognised authority. Equipment for use in hazardous
locations will be required to have ATEX certification.
The practice of having Ex i and Ex e circuits in a common junction box shall be
avoided.
Electrical equipment comprising of luminaires, junction boxes, socket outlets,
cable glands etc., shall be suitable for the project environment and hazardous
area locations.
The electrical installation shall be in compliance with IEC 60079-14.
• Identification
• Equipment Rating
• Safety / Warning Notices
• Instructional Notices
Page 30 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 31 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Page 32 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
provided with push bars. This applies to battery room doors. Emergency doors
shall be permanently closed and shall be sealed with gaskets.
Design of electrical system shall assure a safe and reliable supply of electrical
power to the users.
The design of the electrical installations will be based on the provision of a safe
and reliable supply of electricity at all times, with an availability target in excess of
99.8%. Where an equipment failure would result in loss of the production facility,
duplicated units on a duty / standby basis will be provided.
Safe conditions should be ensured under all operating conditions, including those
associated with start-up and shutdown of plant and equipment, and throughout
the intervening shutdown periods.
The design of electrical systems and equipment shall ensure that all operating
and maintenance activities can be performed safely and conveniently.
The insulating and dielectric materials used in all electrical equipment shall be
non-toxic and shall not contain compounds that are persistent and / or hazardous
environmental contaminants, e.g. polychlorinated biphenyls (PCBs) such as
Askarel.
The design of the electrical installation and equipment will also ensure that easy
and adequate access is provided for all operational and maintenance purposes.
Special attention will be paid to provisional and temporary installations required
for the erection of permanent installations, to ensure compliance with basic rules
for good working practice and safety and to cope with increased hazards which
may exist in temporary installations.
To fulfil the above requirements, the following provisions shall be made:
• Alternative power supply sources
• Use of fire resistant cables (IEC 60331 series) for safety services
• Spare power capacity
• Selective protection system
• Provision of uninterruptible power supply (A.C. and D.C.) systems with back
up floating battery
• Provision of emergency generators with automatic start-up in case of mains
failure.
With reference to the reliability and continuity of service required, the electrical
system summary classifies the loads as follows:
• Non-Essential
• Essential
Page 33 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
• Vital
CPF essential users shall have the operational facility to be fed both from normal
power supply and from emergency generation, which supplies the CPF and
Industrial Base Essential Loads. Vital load users shall have the operational facility
to be supplied from the normal power supply or the emergency generation
facilities and their sub-distribution shall be fed from UPS equipment A.C. and
D.C. systems and associated batteries.
The Living Quarters (Base de Vie) and the Military Camp shall have their own
emergency diesel generators.
The Industrial Base, Living Quarters (LQ) and Military Camp shall have their own
individual A.C. and D.C. UPS systems.
A separate A.C. UPS is also required in the Instrument Local Equipment Room
(LER) at the CPF.
Telecoms equipment shall have their dedicated A.C. UPS. These shall be located
at the CPF, LQ and Military Camp.
Electric system components shall be chosen in such a way that maximum voltage
variations, in normal operating conditions, shall never exceed the following
values:
• Main feeders: +/- 1%
• Lighting circuits: +/- 3%
• Power circuits: +/- 5%
• D.C. circuits: +/- 2%
The maximum permissible transient voltage drop at the induction motor terminals
shall not exceed 15%.
Electrical studies shall be carried out using ETAP software (proprietary software).
Unless otherwise specified, the calculation of the short circuit currents shall be
done according to the IEC 60909 Normative Reference (IEC 61660 for D.C.
currents).
For the current stage of the project, the following design criteria shall apply:
Page 34 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
a) The fault level studies shall be performed for maximum load flow conditions,
for a maximum of two configurations in terms of number of motors which are
operational. The studies shall consider the 11kV and 5.5kV bus tie circuit
breakers in both the open and closed positions, to assess any changes that may
be required in the design. In addition, the short circuit current study shall
determine the minimum fault rating of the new switchgear.
During the detailed engineering design phase of the project, the following design
criteria shall also be included:
b) As a minimum, the design case of a three phase fault and phase to earth fault
shall be taken into account in the calculations. The short circuit minimum current
shall also be calculated in relation to the overall power distribution system
configuration, in order to verify the protection system equipment requirements,
together with the operational function of the protection relay system.
During the detailed engineering design phase of the project, the following design
criteria shall also be included as part of the work scope:
• Intelligent relays shall be selected and coordinated to provide selective
isolation with minimum delay of the equipment at fault, or of the portion of the
electrical system involved by the power system fault. In any event this shall be
within a time corresponding to the short circuit current with stand capability of
equipment and to the overall system stability. Protection relays shall be of the
static electronic multi-function type.
Page 35 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
voltages in module and phase, flows of active and reactive power and the
voltage drops on the level of main panels, including M.V. Switchboards and
L.V. Motor Control Centres).
If calculated values exceed the ratings and / or permitted values to the overall
distribution system including additional power requirements, all the necessary
modifications to the design of the plant shall be provided in order to prevent
equipment ratings and design parameters from being exceeded.
Short circuit studies shall be made accordingly with IEC 60909 Normative
References.
During the detailed engineering design phase of the project, the following design
criteria shall also be included as part of the work scope:
• The check is performed considering such events of prime importance as
abrupt power surges, either generated or required, caused by the opening of
machine switches or main distribution switches, short circuits in the main
panels or start-up of large motors.
The calculation should contain fully detailed diagrams that show the overall
network power capacity to recapture the nominal rating parameters in the pre-set
time periods.
Motor starting studies shall be performed for all the large motors for which the
starting requirements are deemed as critical. As a minimum, the starting of the
largest motor at each voltage level associated with each site shall be
Page 36 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
investigated. The ability to start, starting run up duration, associated voltage and
frequency drops, power system recovery time and the real and reactive power
shall be calculated, comprehensively checked and specifically shown within
detailed plots, for a maximum of two configurations. This includes the Black Start
and Emergency Power scenarios, when all power is derived from the Emergency
Diesel Generators.
For the studies the worst operating conditions must be considered (the largest
motor of the plant being started as the last one with all the other loads running
with the exception of spares). If there are problems with the starting of the larger
type motors (i.e. system voltage drop that exceeds the permitted value), all the
necessary improvements to the system shall be provided, incorporating for
example one of the following solutions:
• Auto-transformer
• Soft-starter
• Variable Speed Drive
General design criteria will cover continuous ratings, short circuit duty, and
allowable voltage and frequency drops.
All the equipment of electrical system shall be suitable to withstand dynamic,
thermal and electrical stresses due to the short circuit currents.
The short circuit ratings shall be defined considering the worst operating
conditions and the initial value, the peak value and transient symmetrical r.m.s.
value.
The initial symmetrical r.m.s. value is the maximum r.m.s. value of the
symmetrical component, calculated taking into account the sub-transient
reactance of generators, the induction motors contribution, the short circuit
voltage of transformers, the impedance of the other components as cable, circuit
breakers etc.
The peak value is the maximum instantaneous value that the short circuit current
can reach, considering the effect of D.C. components. In absence of other
considerations and / or detailed calculations, this value shall be considered equal
to 2.5 times initial symmetrical r.m.s. value.
The transient symmetrical r.m.s. value is the symmetrical r.m.s. value calculated
after the effect of sub-transient reactance disappeared (i.e. after 5 times the sub-
transient time constant), deleting the contribution of induction motors (the
impedance of other components remaining unchanged).
The Main Power Generation shall be provided by two (2) 11kV Gas Turbine
Generators (GTGs) operating on the ‘n + 1’ principle for Phase 1 at 100% each. If
one GTG fails the other shall begin start up immediately. On change over from
Page 37 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
one unit to the other the second unit shall be run up before the first unit is run
down.
In Phase 2 a third GTG is required and two (2) GTGs operate at 50% with the
third unit as a spare. As with Phase 1, if one GTG fails the third unit shall start
immediately. On change over from one unit to another the third GTG shall be run
up before one of the other units is run down.
The GTGs shall be controlled by a UCP, which consists of a Turbine Control
Panel (TCP) and a Generator Control Panel (GCP). In addition the Power
Management System (PMS) shall monitor the GTGs and in some circumstances
shall control the GTGs.
The GTGs shall be located in the Utility Area of the CPF in the Power Generation
Building.
For details of the GTGs refer to the Specification for Gas Turbine Driven
Generator Packages document number BRS1-SP-M-BRS-0017 and Data Sheet
for Gas Turbine Driven Generator Packages document number BRS1-DS-M-
BRS-0090.
For more details on the Main Power Generating Philosophy refer to the Power
Management System Specification document number BRS1-SP-E-BRS-0009.
The 5.5 and 11kV power systems are high resistance earthed to reduce earth
fault currents in the system to a level where physical damage that could occur in
the generator windings, transformer windings or even in motor windings and
switchboards is minimised. The minimum value of earth fault shall include the
capacitive charging current (for cables, motors, transformers, generators and
switchboard bus-bars) in the network, where each component can be
represented by a single capacitor connected between each phase and the
earthed neutral reference.
For further details on the requirements of the NERs refer to the Neutral Earthing
Resistor Specification document number BRS1-SP-E-BRS-0022 and the Neutral
Earthing Data Sheet document number BRS1-DS-E-BRS-0010.
The Power Management System (PMS) takes the place of the traditional mimic
panel and is the normal location for all operation, alarming and indication
functions.
The ICSS is not a point of control for the electrical power system. However, the
PMS shall provide all signals, metering, and indications to the ICSS through a
serial link.
The main functions that the PMS will perform are:
• Power generation system monitoring and control
• Power distribution system monitoring and control
Page 38 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Motors shall be controlled either from individual Local Control Units (LCU’s), Unit
Control Panels (UCP’s) or from the ICSS via hardwired signals. The Switchboard
shall receive start and stop commands from either the UCP’s or the ICSS via an
Interface Relay Panel (IRP).
Status signals (open, closed, tripped and available) shall be made available for
either the UCP’s or ICSS. The Switchboard shall receive 24V D.C. pulsed signals
Page 39 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
to start and stop motors from the UCP’s and the ICSS via hardwired signals via
the IRP.
The field control will consist of Start and Stop signals via LCU’s. A remote start
facility (enabled by the ICSS or UCP) will be provided for as well as at the LCU.
Manual trip facilities shall be provided on the Switchboard. These shall be
operable in all operating conditions.
Test facilities (start / stop) shall be provided so that testing of the motor control
circuit is possible.
Each motor starter will be provided with equipment to receive a shutdown signal
from the plant Emergency Shut Down (ESD) system This signal will be in the
form of a powered 24V D.C. signal (de-energised to trip) via the ESD IRP.
Monitoring and metering information from the Intelligent Electronic Devices
(IEDs) including Amps, Volts, Watts, VAr, VA, power factor, event recording etc.
shall be transferred to the PMS. The PMS shall make this information available to
the ICSS via the PMS HMI, which forms part of the ICSS control desk in the
CCR.
The 11kV Overhead Lines (OHLs) run from the outdoor switchyard at the CPF to
the Living Quarters (Base de Vie) substation approximately 5km away. The OHLs
shall be mounted on pre-cast concrete poles with an Optical Protective Guard
Wire (OPGW) for data transmission between the Living Quarters, the Military
Camp and the CPF.
A small outdoor switchyard is required at the CPF and the Living Quarters which
includes an outdoor isolation switch, earth switch, surge protection and a cable
box for transition from OHL to underground cables. A second outdoor switchyard
is required at the LQ with the same equipment.
Refer to the Medium Voltage Overhead Line Specification document number
BRS1-SP-E-BRS-0010 for more details.
400V emergency diesel generators shall be located at the CPF, Living Quarters
and Military Camp, sized for the emergency running load. The generators at the
Living Quarters and Military Camp shall be sized to supply the complete load of
each of those facilities in order that they can operate at full capacity during a
main power generation failure or disruption of the OHL supply.
The CPF generator shall be sized in accordance with the Black Start and
Emergency Load requirements listed in the Electrical Load List, document
number BRS1-SH-E-BRS-0001, with enough capacity to start the largest motor
on the emergency load requirement.
The generators shall supply the required power in order to withstand:
• a 50% overload for 2 minutes with a 3% maximum voltage drop
Page 40 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
11 / 5.78kV and 11 / 0.42kV ONAN power transformers shall be provided with the
following main characteristics:
• M.V. coils encapsulated, class F insulated, class B temperature rise.
• L.V. coils impregnated, class F insulated, class B temperature rise
• Outdoor installation
• Cooling system: ONAN (with facilities for easy conversion to ONAF operation)
• Frequency: 50Hz
The high levels of insulation for the windings may be achieved by using materials
such as NOMEX for insulation and Midel as a coolant. Where the high levels of
insulation for transformers cannot be achieved by a Supplier / Vendor the
alternative of Class A insulation may be acceptable with a suitable de-rating of
the transformer to ensure the maximum operating temperature and temperature
Page 41 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
4.28 Switchgear
Incomers shall be sized for, at least, the rating of relevant supply line, generator
or transformer.
Bus-bar and Bus-tie circuit breakers shall be sized for the Maximum Load plus
25%.
Switchgear shall withstand maximum short circuit duty for at least 1 second.
Switchgear shall be provided with IEDs for protection, monitoring and event
recording.
Low Voltage Switchboards will be provided 20% spare feeders.
For detailed switchgear / switchboard engineering requirements, refer to Medium
Voltage Switchgear Specification, document number BRS1-SP-E-BRS-0001, Low
Voltage Switchgear and Motor Control Centres Specification document number
BRS-SP-E-BRS-0002, 5.5kV Switchgear Data Sheet document number BRS1-
DS-E-BRS-0001, Low Voltage Switchgear Data Sheet (Typical) document
number BRS1-DS-E-BRS-0002, 11kV Switchgear Data Sheet document number
BRS1-DS-E-BRS-0014 and the Overall Key Single Line Diagram BRS1-DR-E-
BRS-0005.
11kV M.V. switchgear shall be metal-clad type, internal arc proof single bus bar
switchgear.
Each incoming circuit breaker shall be sized for at least 1.25 times the
corresponding transformer rated current.
The rated current of outgoing feeders shall be at least the rated current of motors
or transformers.
Motors above 1.5MW shall be fed from the 11kV switchgear. The switchgear
shall have a minimum protection degree of IP 41, unless otherwise specified on
the 11kV Switchgear Data Sheet document number BRS1-E-DS-BRS-0014.
Page 42 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Switchgear shall be modular type, floor mounted, self supporting and arranged
for future extension at both ends to accommodate the supplies required for
Phase 2.
Communication between the switchboard and the PMS shall be carried out via a
serial link, except for permissive and status signals, which are hardwired.
Each cubicle shall be equipped with necessary current and potential transformer,
relays, instruments and other ancillary equipment.
Power circuit breakers shall be SF6; electrically operated. Circuit breakers shall
be used for incomers, bus-ties, transformer feeders, Overhead Lines, Variable
Speed Drives (VSDs) and motors rated above 2500kW.
Fused vacuum contactors shall be used for motors up to 2500kW.
Switchgear relay protection and control devices shall be installed inside the
relevant instrument compartment. Protection relays shall be of the static type and
suitable for communication with the PMS via a serial link. Monitoring and Control
of the switchgear and control of circuit breakers shall be carried out for general
operation and load shedding.
Remote motor control signals shall be via an Interface Relay Panel (IRP) to and
from the ICSS and UCPs as indicated on the P&IDs. Local control of motors shall
also be possible with the use of Local Control Units (LCUs) with Hand-Off-Auto
selector switches if shown on the P&IDs.
ESD signals from the ICSS shall be taken directly to the switchgear control
circuits.
The PMS shall provide permissive signals for 11kV motors to start based on the
spinning reserve calculated by the PMS.
5.5kV switchgear shall be metal-clad type, internal arc proof single bus bar
switchgear.
Each incoming circuit breaker shall be sized for at least 1.25 times the
corresponding transformer rated current.
The rated current of outgoing feeders shall be at least the rated current of motors
or transformers.
Motors above 132kW up to 1500kW shall be fed from the 5.5kV switchgear (with
some possible exceptions due to particular applications like low voltage starting
motors for turbines and compressors, fed through soft starters or variable
frequency drivers). Direct on Line 5.5kV motor circuits shall include a
multifunction electronic relay for complete motor protection. Surge protection
shall also be provided. 5.5kV switchgear shall have a minimum protection degree
of IP 41, unless otherwise specified on the 5.5kV Switchgear Data Sheet
document number BRS1-DS-E-BRS-0001.
Switchgear shall be modular type, floor mounted, self supporting and arranged
for future extension at both ends to accommodate the supplies required for
Phase 2.
Page 43 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Communication between the switchboard and the PMS shall be carried out via a
serial link.
Each cubicle shall be equipped with necessary current and potential transformer,
relays, instruments and other ancillary equipment.
Power circuit breakers shall be SF6; electrically operated. Circuit breakers shall
be used for incomers and bus-ties.
Fused vacuum contactors shall be used for motors.
The bus tie circuit breaker shall be ‘normally closed’ as the fault rating of the
switchboard is greater than the calculated fault current resulting from the two
4MVA transformers operating in parallel. This shall be confirmed during detailed
design.
Switchgear relay protection and control devices shall be installed inside the
relevant instrument compartment. Protection relays shall be of the static type and
suitable for communication with the PMS via a serial link. Monitoring and of the
switchgear and control of circuit breakers shall be carried out for general
operation and load shedding.
Remote motor control signals shall be via an Interface Relay Panel (IRP) to and
from the ICSS and UCPs as indicated on the P&IDs. Local control of motors shall
also be possible with the use of Local Control Units (LCUs) with Hand-Off-Auto
selector switches if shown on the P&IDs.
ESD signals from the ICSS shall be taken directly to the switchgear control
circuits.
The PMS shall provide permissive signals for 5.5kV motors to start based on the
spinning reserve calculated by the PMS.
The L.V. switchboards shall be provided with the following main design
characteristics:
• Minimum degree of ingress protection to IP 41.
• Only circuit breakers (including MCCBs) shall be provided.
• L.V. moulded case and miniature circuit breakers shall be suitable to
withstand, without damage, any prospective short circuit current at their output
terminals.
• The incoming supply from the 11 / 0.42kV transformers shall be via bus duct,
and the transformer neutral shall be earthed at the LV Switchboard neutral.
• Provision for 20% spare feeders.
Air Circuit Breakers (ACBs) shall be electrically operated. Circuit breakers shall
be used for incomers and bus-ties and larger static loads above 630A.
Moulded Case Circuit Breakers (MCCBs) shall be used for static loads up to
630A.
Contactors shall be used with MCCBs for motors.
Page 44 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Switchgear relay protection and control devices shall be installed inside the
relevant instrument compartment. Protection relays shall be of the static type and
suitable for communication with the PMS via a serial link. Monitoring and control
of the switchgear and control of the main incoming and bus-tie circuit breakers
only shall be carried out for general operation.
The switchboard shall have a two out of three automatic changeover system.
Remote motor control signals shall be via an Interface Relay Panel (IRP) to and
from the ICSS and UCPs as indicated on the P&IDs. Local control of motors shall
also be possible with the use of Local Control Units (LCUs) with Hand-Off-Auto
selector switches if shown on the P&IDs.
ESD signals from the ICSS shall be taken directly to the switchgear control
circuits.
Refer to the Low Voltage Switchgear Data Sheet (Typical) document number
BRS1-DS-E-BRS-0002 for more details.
The Small Power boards and Lighting Distribution boards shall be of self-
supporting, metal enclosed structure consisting of vertical sections, assembled in
a single row.
The sizing of bus-bars and incoming method of isolation shall be carried out with
regards to operational power requirements.
The small power board and lighting distribution boards shall be separated into:
• D.C. UPS Distribution Panels
• A.C. UPS Distribution Panels
• Lighting Distribution Boards
• Small Power Distribution Boards (including Heat Tracing Distribution Boards, if
required)
Distribution Boards shall be further separated into Hazardous and Non-
Hazardous Area types. Refer to the Distribution Board Specification document
number BRS1-SP-E-BRS-0023, the Non-Hazardous Area Distribution Board
Data Sheet document number BRS1-DS-E-BRS-0008 and the Hazardous Area
Distribution Board Data Sheet document number BRS1-DS-E-BRS-0009 for
further details.
4.33 Motors
Generally the motors shall be 3-phase, squirrel cage induction type, totally
enclosed fan cooled, with fan directly mounted on motor shaft (IC411). Fans shall
be non-sparking type. Motors shall be suitable for direct on line starting. L.V.
motors for Zone 1 areas shall be Ex de. For Zone 2 areas L.V. motors up to
100kW shall be Ex nA. Above 100kW motors shall be Ex de type. 5.5kV motors
shall be certified as Ex de. Motors at 11kV shall be certified either as Ex de or Ex
p depending on the rating and number of poles. For the 11kV motors cooling may
Page 45 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
VSDs are not the preferred method of motor control in the CPF, Industrial Base
Living Quarters or Military Camp. However, where the process dictates a variable
speed requirement then the use of VSDs is acceptable. The FEED has identified
the Flash Gas Compressors, Export Gas Compressors and Gas Lift
Compressors as requiring motor driven VSDs. Transformers of the VSDs shall be
of the ONAN type located outdoors under sun shades in transformer pens.
Page 46 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Other smaller VSDs, for air cooler fans, GTG starter motors, pumps and fans,
may also be required and these shall be indicated either on the P&IDs or by the
Supplier / Vendor package requirements during detailed design, these VSDs
shall be incorporated into MCCs.
The VSD units shall be designed in order to minimize the amount of harmonics
seen by the electrical system by use of twenty four (24) pulse units, as a
minimum, wherever possible. Twelve (12) pulse units are acceptable (this applies
especially for smaller M.V. drives and L.V. drives) if the generated harmonics do
not exceed the limits set down in the documents referenced below.
VSDs’ harmonic output shall meet the limits as laid down in IEEE Standard 519,
Recommended Practices and Requirements for Harmonic Control in Electrical
Power Systems, the ENA Engineering Recommendation G5 / 4-1, IEC 61000-2-
12 or BS EN 50160 Voltage Characteristics of Electricity Supplied by Public
Distribution Networks.
The use of input transformers with multi-phase outputs or three winding phase
shifting transformers or (if no other option is available) filters can also be
considered as methods of reducing harmonics fed back into the electrical
network.
VSD / motor systems shall be suitable for both the operating characteristics
required in terms of quadrant operation and load characteristics without
producing switching voltage spikes, pulsating currents, pulsating torques or motor
overheating affecting the operation of the VSD / motor system. In addition the
VSD / motor system shall be certified for the hazardous area in which the motor
is located. Motors shall be Ex de certified.
Refer to the Variable Speed Drive Systems Specification document number
BRS1-SP-E-BRS-0021 and the Variable Speed Drive Data Sheet (Typical)
document number BRS1-DS-E-BRS-0012 for further details.
Design of A.C. UPS systems and D.C. UPS systems shall assure for a sufficient
period of time (autonomy period), the operation of relevant loads in the worst
operating conditions, in the event of other electric supply failures.
Supply for vital loads shall normally be from primary power and emergency
power, 100% dual redundant systems.
The A.C. UPS systems and D.C. UPS systems autonomy periods shall mainly be
provided as follows:
Page 47 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Two (2) Fuel Gas Pre-Heaters are required for the GTGs’ fuel gas system. The
control panels shall be located in the CPF substation with the electric heaters
(including the main terminal box) located in the gas conditioning area of the CPF.
The control panel may be located outdoors in the field, but this is not the
preferred option. If located outdoors the control panel shall be suitable for the
hazardous area in which it is located and also to be weather proof according to
the specification referenced below.
Page 48 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
The main terminal box shall be certified for use in the hazardous area in which it
is located.
Refer to the Electric Process Heater Specification document number BRS1-SP-
E-BRS-0020, the Specification for Pressure Vessels document number BRS1-
SP-M-BRS-0001 and the Data Sheet for Fuel Gas Pre-heater document number
BRS1-DS-M-CPF-0050 for more details.
The protection relays in the 11kV, 5.5kV and 400V switchboards shall all be of
the electronic, solid state, multi-functional type commonly referred to as Intelligent
Electronic Devices (IEDs). Communication facilities shall be provided by means
of a serial link to the PMS from the switchboards and GCPs.
Transformers shall incorporate their own thermal protection relays and where
conservators form part of the transformer a Buchholz relay shall be used. In
addition the circuit breaker supplying the transformer shall be fitted with a multi-
functional transformer protection relay, which includes restricted earth fault,
unrestricted earth fault, overcurrent and high set current. Biased differential
protection is also required on transformers rated 5MVA and above.
Motors fed from circuit breakers shall have multi-functional motor protection
relays with protection according to the size and voltage of the motor. Motors fed
from MCCB / Contactor or fuse / Contactor units shall include earth fault
protection and thermal (overload) protection as well as short circuit protection to
suit the rating of the motor. Larger motors shall include full motor protection
relays to include negative phase sequence current protection etc. and differential
protection if the motor is 2500kW and above except for motors supplied by VSD.
Cables (including feeders to VSD units) protected by circuit breakers shall also
have multi-functional protection relays that include overcurrent protection, earth
fault protection etc.
Overhead Lines (OHLs) require line differential protection, ‘blocking’ protection
with back up protection for overcurrent and earth faults.
Where differential relays are used the Current Transformers (CTs) shall be
matched and the CTs free issued from the packaged equipment Supplier /
Vendor to the switchgear Supplier / Vendor for incorporation into the relevant
feeder circuit.
Where a Bus Transfer scheme is used, appropriate logic to provide monetary
paralleling facilities and isolation of a section of the bus bar section that has a
short circuit on it is required.
All protective relays shall be static type and suitable for the following electrical
parameters:
• Rated frequency 50Hz
• CT’s rated A.C. current 1A
• VT’s rated A.C. voltage 110 √ 3V – 110V
• Rated D.C. voltage 110V D.C.
Page 49 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
CTs required for differential protection or restricted earth fault protection for
generators, transformers and motors shall be ‘free issued’ to the switchgear
Supplier / Vendor as required.
The above section outlines the minimum requirements of electrical protection
schemes. For more information on protection refer to the Medium Voltage
Switchgear Specification document number BRS1-SP-E-BRS-0001, the Low
Voltage Switchgear and Motor Control Centres Specification document number
BRS1-SP-E-BRS-0002, the 5.5kV Switchgear Data Sheet document number
BRS1-DS-E-BRS-0001, the Low Voltage Switchgear Data Sheet document
number BRS1-DS-E-BRS-0002, the 11kV Switchgear Data Sheet document
number BRS1-DS-E-BRS-0014 and the Instrumentation & Protection Diagrams
(Typical) document number BRS1-DR-E-BRS-0016.
Page 50 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Cables shall be buried in trenches, cable ducts or direct buried. Cable tray or
ladder shall only be used for high level installations such as air cooler motor
supplies and for cabling between the substation and transformers, GTGs and
Emergency Diesel Generator Sets.
In the CPF area where cables run underground they shall be installed in cable
trenches. In other areas the direct buried method is acceptable.
Cable glands shall have ISO metric threads. Cable glands for use with single
core aluminium wire armoured cables, shall be fabricated of aluminium.
For single cable runs, local steelwork may be used. Cable routes shall be
designed to ensure that cable damage is minimised in the event of fire or cable
fault.
Cable ladder rack and tray routes shall be electrically continuous and bonded to
earth at either end of the route.
The 400 / 230 / 110V electrical power and control cabling shall be routed in
dedicated trenches and segregated from instrumentation and
telecommunications cables by minimum of 300mm based on typical norms used
throughout the industry.
Cable penetrations in hazardous environments which pass through walls shall be
by an approved Multi-Cable Transit (MCT) frame fitted with cable compression
blocks designed to International and national authority standards. They shall also
be tested and have certification by a recognised testing authority.
All cables shall be terminated using appropriate brass (with the exception of
single core aluminium wire armoured cables) cable glands with dual certification
Ex de, double seal arrangement and rated for IP 56 minimum. An exception may
be packaged equipment, where protection from the environment is in some cases
provided. No shrouds shall be used over cable glands.
Spare cores will be connected to earth at both ends of the cable.
Due to the cable installation conditions there is a large de-rating factor used in
calculating the cable size. This leads to very large cables or multiple cables for
relatively modest loads. Therefore, particular care shall be taken in designing the
cable containment systems and in consideration of terminating cables into
adequately sized cable termination boxes and ensuring that the cables have a
bending radius suitable for the particular installation situation. This process
should start at the beginning of the detailed design stage.
For details of cables, refer to Power and Control Cables Specification document
number BRS1-SP-E-BRS-0012.
For detailed engineering requirements, refer to the Electrical Installation and
Testing Specification, document number BRS1-SP-E-BRS-0018.
Page 51 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
For details of cable glands, cable trays and cable ladders refer to the Electrical
Bulk Materials Specification document number BRS1-SP-E-BRS-0016.
Power outlets shall be 63 / 32A rated at 400V, 3 phase and earth; convenience
outlets will be 25 / 16A rated, 230V, single phase. They will have mechanical
protection degree IP 55 and suitable for the classification of the area where they
will be installed.
Not more than 2 (two) power outlets shall be fed from one cable feeder.
Power socket outlets shall cover a 30m2 area and convenience socket outlets
shall cover a 15m2 area.
Not more than 6 (six) convenience outlets shall be fed from one cable feeder.
A minimum of one power feeder and one convenience feeder shall be provided
for each zone.
Refer to Specification for Lighting and Small Equipment Specification, document
number BRS1-SP-E-BRS-0013 for engineering requirements.
The lighting design shall be in accordance with recognised lighting codes and
standards such as BSI BS EN 12464, the Illuminating Engineering Society of
North America (IESNA) and the Chartered Institute of Building Services
Engineers (CIBSE) or other recognised authorities or standards on lighting
design.
The lighting system shall be designed to minimise maintenance and maximise its
efficiency. Luminaires shall be suitable for the area classification where they are
installed. Outdoor Emergency / Escape lighting shall be Zone 2 certified (Ex e)
with ATEX certification marking. They shall remain operational during plant
shutdown.
Design calculations shall take into account the reduced light output of luminaries
resulting from dust, dirt and changes in reflecting surfaces due to ageing.
The design of the lighting installation shall minimise stroboscopic effects and
glare.
Outdoor lighting shall be controlled by photocells and contactors.
Indoor lighting shall be controlled by local wall mounted switches.
Re-chargeable hand lamps shall be provided in Substations and Control Rooms
in the CPF, LQ, Industrial Base and Military Camp. Hand lamps shall be located
adjacent to the main entrance. Each lamp shall comprise of a fixed battery
charger and be certified to Ex i.
Floodlight towers with High Pressure Discharge luminaries shall be used in tank
areas, for security fence lighting and to provide general lighting in open
compound areas (such as Sports fields at the Living Quarters and Military Camp).
Page 52 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
Street lighting with High Pressure Discharge luminaries shall be provided for all
roads in the CPF, Industrial Base, Living Quarters and Military Camp. At the CPF
where hazardous area certified luminaires are not available the street lighting
luminaires supplies shall, in case of a large gas release, be switched off via
contactors at the distribution board upon receipt of an ESD signal.
Lighting for local areas such as pump stations, under pipe racks and around large
packages such as Gas Compressors shall be provided by fluorescent lighting.
Fluorescent lighting shall also be used inside buildings. For areas where LCD
screens are used lighting shall be of the type suitable for VDU use.
Compact Fluorescent bulkhead fittings shall be used on walk ways and hand
rails.
Normally lighting shall be of general, even, direct type, supplemented by
additional lights to lift lighting levels locally when required for operative purposes.
In critical areas or where required by law, lighting shall be supplemented by
safety lighting.
The load on three phase or three phase with neutral circuits shall be uniformly
distributed among the three phases.
The supply for normal lighting shall be provided from the low voltage Lighting
Distribution Boards.
Similarly, the load on the single phase circuits shall be fixed so as to enable as
much as possible a balanced load on the three phase supply system.
Typical lighting levels for different areas are given in the table below:
Page 53 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
All calculations and measurements shall allow for a general light loss factor of 0.7
for the new installation. This may be reduced further for certain external areas if
this is warranted.
Emergency Lighting is the lighting which, in case of power loss of the main power
supplies, is designed to enable reduced operations to be carried out ensuring the
compliance with safety conditions until the restoration on normal power supplies
or until the plant shuts down.
Safety Lighting is the lighting in case of total power loss of either the main or
emergency supplies and is designed to provide minimum suitable conditions of
safety or survival and enable communication activities, aid immediate evacuation
of people and / or remedy actions to safeguard the plant.
Safety lighting shall be fed from the 230V A.C. maintained supply from integral
emergency battery back-up. Safety lighting shall be maintained for 1 hour
duration as a minimum.
4.45 Luminaires
Page 54 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
The luminaires for outdoor installation shall be IP 55 minimum and certified for
the classification of the area where they will be installed with a Zone 2 hazardous
area classification as a minimum.
All lighting fixtures shall be supplied at 230V single phase. The lighting circuits
shall be 3 phase + neutral.
Outgoing branch circuits will be protected by properly sized circuit breakers.
Each branch circuit should not be loaded over 3kW.
Page 55 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
• All the main metallic structures shall be utilised and configured as main earth
loop facilities
• Small Power and Lighting circuits shall have double pole isolation
• Instrument ‘clean’ earth system shall be included for instrument systems using
Zener Barrier diode protection and without Zener Barriers
• Earthing stations, where tankers containing flammable liquids are to be
unloaded
• Earthing of radio antennae
• Earthing of remote Wellheads, Gathering Stations and Block Valve Stations
Solar power supplies are required for sixteen (16) Wellheads and for two (2)
Gathering Stations (#2 and #3 for Hydraulic Power Units, Instruments and
Telemetry) and impressed current systems for Cathodic Protection on the
Pipelines and for the instrument power requirements at the five (5) valve stations,
with Telemetry and valve actuator requirements.
The fundamental parts of the power system are:
• Photovoltaic array with integral support structure
• System charge controller which can, if specified, be capable of remote
monitoring and interface with external network (ICSS)
• Battery bank
• Inverter if A.C. loads are anticipated
• D.C.-D.C. Converter, if specified
• Load distribution system
• If specified, a shelter to house the electronic components
The photovoltaic elements of the solar power system shall be designed in
accordance with IEC 60904.
All equipment, including the solar array, control equipment, batteries and
associated components, shall be suitable for installation in the area in which it is
to be installed. Unless specified otherwise by the Contractor, all equipment
should be located in a safe, non-hazardous area.
The solar array and battery bank shall be designed to supply the specified energy
requirements, taking into consideration ambient and installation considerations.
The size of the array shall be such that the energy requirements of the load can
be supplied directly or via storage in the battery bank under historical local
meteorological conditions.
The battery bank shall be designed to supply the load during conditions where
the solar array cannot meet the total energy requirements. The battery size shall
be such that at any moment the state of charge will be at least 20% and the daily
depth of discharge will not be more than 15%.
Page 56 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
The system battery bank should be capable of supporting the average continuous
load for a period of 5 days in the event of little or no insolation (solar radiation).
The 5 day time period will be from a fully charged battery (100% State of Charge)
to a 20% State of Charge level at the end of the 5th day. The Contractor shall
include this calculation in their proposal.
The above autonomy is recommended for medium critical application at site test
conditions. The Contractor shall specify the autonomy time on the requisition
based on the load criticality assessment.
The system is required to have a calculated reliability of 99.7% according to
standard reliability calculations.
The Supplier / Vendor shall provide Mean Time Between Failure (MTBF) data for
the following equipment:
• Photovoltaic Modules
• Batteries
• System Controller
• D.C.-D.C. Converter
• Inverter
In general, the system shall be designed to require no more than one
maintenance visit per year.
The Solar Power Supplies (especially the solar array) shall be adequately
protected from vandalism and theft, by use of a shelter and fencing etc.
Refer to the Solar Power Supplies Specification document number BRS1-SP-E-
BRS-0011 and the Solar Power Supplies Data Sheet BRS1-DS-E-BRS-0011 for
more details.
Page 57 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
There may be a minimal requirement for electric heat tracing of impulse lines,
dead legs in piping, potable water lines etc. These shall be identified during
detailed design either by Process and Instrumentation or by Supplier / Vendors
with regard to their Packages, for example the Hot Oil Package. Refer to the
Electric Heat Tracing Specification document number BRS1-SP-E-BRS-0019 for
design, equipment and installation requirements.
A remote metering skid is required at HEH that requires electrical supplies for
Motor Operated Valves (MOVs), electro-hydraulic valve actuator, sampling pump,
instrument and telemetry requirements. A supply from an existing switchboard
shall be obtained for a new dedicated switchboard to supply the pump and MOVs
etc. A new A.C. UPS is required for the instrumentation and telemetry units on
the metering skid.
This work, including the site survey of existing switchboard supplies and other
works required to provide the supplies to the metering skid forms part of the EPC
Contractor’s scope.
The voltage available at HEH is 380V, three phase, 50Hz.
A remote metering skid is required at HMD that requires electrical supplies for an
electro-hydraulic valve actuator and instrument and telemetry requirements. A
supply from a switchboard shall be obtained for a new dedicated switchboard to
supply the actuators and a new A.C. UPS required for the instrumentation and
telemetry units on the metering skid. The full scope of works shall be defined
during detailed design.
Page 58 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
This work, including the site survey of switchboards and other works required to
provide the supplies to the metering skid forms part of the EPC Contractor’s
scope.
The voltage available at HMD shall be determined during detailed design.
Page 59 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
5.1 Definitions
Page 60 of 61
Doc.
Bir Seba Field Development BRS1-DB-E-BRS-0001
No.:
Date: 21 October 2009
ELECTRICAL DESIGN BASIS
Rev.: D2
All equipment / circuits must be provided with off-loading and isolating devices.
These should generally form part of the source switchgear.
Isolating devices should normally allow a clear view of the isolation (a clean
break in air).
Where the isolation device does not allow viewing of the physical gap, suitable
testing and appropriate instrument for testing shall be available to ensure
contacts have broken.
All electrical isolating mechanisms shall have provision for securing (locking) in
the isolated position. Where fuses / links form part of the isolation device a
method of securing/holding them after removal shall be provided.
Auxiliary circuits provided on major items of equipment for control, indication and
protection purposes must also include isolation facilities.
Systems including Transformers, Overhead Lines, battery chargers and other
equipment with a number of supply sources must include facilities for the isolation
of each individual source.
Voltage transformers shall be the withdraw-able type having the facility for locking
in the withdrawn position.
Any isolation device with a withdraw-able part shall have facilities for locking
'closed' bus-bar or circuit shutters mounted on the fixed portion.
Where certified electrical equipment is installed in hazardous areas the isolation
provided shall include the neutral conductor.
Where isolations may be the subject of work by external agencies (e.g. by
Electricity Authorities) or multiple parties, all locking devices should be suitable
for the use of multi-hasp locks to allow individual isolations by each party.
Electrical storage devices such as large capacitors and capacitor banks with the
potential to store dangerous levels of energy must be provided with discharging
facilities complete with locking / isolation devices.
Batteries are a source of electrical supply. While they shall have provision for
their isolation from connected circuits, chargers and load, they cannot be made
dead for maintenance purposes. Appropriate procedures and physical barriers
should therefore control safe working on batteries.
Page 61 of 61