Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 5

PROJECT NAME : PROPOSED RENOVATION OF NISSAN COMMONWEALTH SHOW

PROJECT ADDRESS : 41 COMMONWEALTH AVE., UNIVERSITY DISTRICT, QUEZON C


OWNER : ATTY. ANNA LYNE S. PONFERRADA
ARCHITECT : BCOVES BUILDERS AN DEVELOPMENT CORPORATION
CONTRACTOR : BCOVES BUILDERS AN DEVELOPMENT CORPORATION

SUBJECT : MANPOWER ANALYSIS OF TIME AND DURATION FOR MASONR

GENERAL CONDITIONS:
MANPOWER RATE AND NUMBER OF DAYS PER SQUARE METER 1. Ground floor height at bot
2. Ground floor bottom beam
FOR CHB MASONRY 3. Second Floor height at bo
sq.m per 4. Second floor bottom beam
100 pcs per day 8
day 5. CHB and Cement Plasteri
FOR CEMENT PLASTERING 6. Minimum/Maximum time f

Full Wall Rate 10 sq.m. per


day
sq.m. per Ave. Corner Width of average
Plast Corner Rate 5 Plaster (One Side)
0.15
day meter
7. Height for Masonry and C
8. Number of Working Hours

L E G E N D S : As per revise

Fill the datas at below 1800mm

CHB LAYOUT BETWEEN LM (mts) AREA UNIT CHB LA


1 0.00 S.M. 1
2 0.00 S.M. 2
3 0.00 S.M. 3
4 0.00 S.M. 4
5 0.00 S.M. 5
6 0.00 S.M. 6
7 0.00 S.M. 7
8 0.00 S.M. 8
TOTAL 0.00 0.00 S.M.
PARTICULAR AREA INTERIOR PLASTERING LM (mts) AREA UNIT PARTICULAR AR
1 0.00 S.M. 1
2 0.00 S.M. 2
3 0.00 S.M. 3
4 0.00 S.M. 4
5 0.00 S.M. 5
6 0.00 S.M. 6
7 0.00 S.M. 7
8 0.00 S.M. 8
TOTAL 0.00 0.00 S.M.
FOR CORNERS (as per plan inspection) FOR CORNERS (as per plan
NO. OF CORNERS set
HEIGHT 1.80 MTS
TOTAL AREA s.m.
FOR COMPUTATION FOR COMPUTATION
CHB MASONRY day
CEMENT PLASTERING day
PLAST CORNER RATE (as per inspection) day
OMMONWEALTH SHOWROOM
Y DISTRICT, QUEZON CITY, NCR, P

CORPORATION
CORPORATION

DURATION FOR MASONRY AND CE

GENERAL CONDITIONS: height (mts)


1. Ground floor height at bottom beam 3.10 PP governed
2. Ground floor bottom beam to soffit 0.55
3. Second Floor height at bottom beam 2.80 PP governed
4. Second floor bottom beam to soffit 0.45
5. CHB and Cement Plastering at 1800mm height above, adjustment of time, due to preparation of scaffolds and safety.
6. Minimum/Maximum time for preparation of scaffolds and adjustments per whole working day at 1800mm height above:
> CHB laying 10 minutes 17 minutes/max 13.5 minutes ave.
> Cement Plastering 10 minutes 17 minutes/max 13.5 minutes ave.
> End-Corner Plastering 12 minutes 19 minutes/max 15.5 minutes ave.

7. Height for Masonry and Cement Plastering Works 1.80 meters


8. Number of Working Hours per day 8.00 hrs.

L E G E N D S : As per revised plan in color, updated


Header only
Not fully CHB yet
No CHB yet
On-going Plastering
Plastered
On-going CHB

Fill the datas at above 1800mm

CHB LAYOUT BETWEEN LM (mts) AREA UNIT


S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
TOTAL 0.00 0.00 S.M.
PARTICULAR AREA INTERIOR PLASTERING LM (mts) AREA UNIT
S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
S.M.
TOTAL 0.00 0.00 S.M.
FOR CORNERS (as per plan inspection)
NO. OF CORNERS set
HEIGHT 1.30 MTS
TOTAL AREA s.m.
FOR COMPUTATION
CHB MASONRY day
CEMENT PLASTERING day
PLAST CORNER RATE (as per inspection) day
minutes ave.
minutes ave.
minutes ave.

You might also like