A B C D Merged

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Check List - Hvac Work Nesto(Ground Floor)

Area : Zone A

Sl No Check Points Completed Total Qty Status Remarks


1 Indoor Unit Instalation 3 4 Pending Roastery Design Pending

2 Copper Piping 3 4 Pending Roastery Design Pending

3 Copper pipe Tray 3 4 Pending Roastery Design Pending

4 Refnet 3 4 Pending Roastery Design Pending

5 Copper pipe flaring 3 4 Pending Roastery Design Pending

6 Communication Cabling work 3 4 Pending Roastery Design Pending

7 Drainage work 3 4 Pending Roastery Design Pending

8 Drainage tray 0 4 Pending Ordered not yet received

9 Supply Duct Instalation 3 4 Pending Roastery Pending

10 Exhaust Duct Instalation Nil Nil

11 Fresh Air Duct Instalation Nil Nil

12 Duct Mouth connection 3 4 Pending Canvas Connection Pending

13 Instalation of VCD Nil Nil

14 Air tight Partitions Nil Nil

15 Exhaust Fan Nil Nil


Check List - Hvac Work Nesto(Ground Floor)
Area : Zone B

Sl No Check Points Completed Total Qty Status Remarks


1 Indoor Unit Instalation 6 12 Pending Escalator Parts, Tiles to be Cleared

2 Copper Piping 6 12 Pending Escalator Parts, Tiles to be Cleared

3 Copper pipe Tray 6 12 Pending

4 Refnet 7 10 Pending Escalator Parts, Tiles to be Cleared

5 Copper pipe flaring 6 12 Pending Escalator Parts, Tiles to be Cleared

6 Communication Cabling work 6 12 Pending Escalator Parts, Tiles to be Cleared

7 Drainage work 6 12 Pending Escalator Parts, Tiles to be Cleared

8 Drainage tray 0 12 Pending Ordered not yet received

Escalator Parts, Tiles to be Cleared, 2


9 Supply Duct Instalation 4 8 Pending
Spiral Duct not received

10 Exhaust Duct Instalation Nil Nil

11 Fresh Air Duct Instalation Nil Nil

Canvas Connection Pending,


12 Duct Mouth connection 0 12 Pending
Plenum box not received

13 Instalation of VCD 2 10 Pending Plenum Box not received

14 Wall Cutting 0 2 Pending Cannot mark due to tiles stack

15 Exhaust Fan Nil Nil


Check List - Hvac Work Nesto(Ground Floor)
Area : Zone C

Sl No Check Points Completed Total Qty Status Remarks


1 Indoor Unit Instalation 3 3 Completed

2 Copper Piping 3 3 Completed

3 Copper pipe Tray Nil Nil

4 Refnet 1 1 Completed

5 Copper pipe flaring 1 3 Pending Ongoing

6 Communication Cabling work 3 3 Completed

7 Drainage work 1 3 Pending Ongoing

8 Drainage tray 0 3 Pending Ordered not yet received


Branches not complete,
9 Supply Duct Instalation 3 3 Pending
Spiral duct branch not received
10 Exhaust Duct Instalation Nil Nil

11 Fresh Air Duct Instalation Nil Nil

12 Duct Mouth connection 0 3 Pending Canvas Connection Pending

13 Instalation of VCD 0 4 Pending

14 Flexible Duct 0 2 Pending Not yet received

15 Split A/C Piping 2 2 Completed


Check List - Hvac Work Nesto(Ground Floor)
Area : Zone D

Sl No Check Points Completed Total Qty Status Remarks


1 Indoor Unit Instalation 9 10 Pending 11TR Machine not received

2 Exhaust and Fresh Air Fan 0 10 Pending Not yet received

3 Copper Piping 9 10 Pending 11TR Machine not received

4 Copper pipe Tray 8 10 Pending 11TR Machine not received

5 Refnet Nil Nil

6 Copper pipe flaring 9 10 Pending 11TR Machine not received

7 Communication Cabling work Nil Nil

8 Drainage work 9 10 Pending 11TR Machine not received

9 Drainage tray 0 10 Pending Ordered not yet received

10 Supply Duct Instalation 9 10 Pending 11TR Machine not received


Ongoing, Fire pipe branch
11 Exhaust Duct Instalation 4 5 Pending
to be closed, 2 hood remaining
12 Fresh Air Duct Instalation 2 4 Pending Branches, VCD Pending
11TR Machine not received
13 Duct Mouth connection 8 10 Pending
Hood Connection pending
450x 300 VCD needed
14 Instalation of VCD 12 19 Pending
additionally
15 Butterfly Damper 2 8 Pending

16 Flexible Duct 0 8 Pending Not yet received