QUOTATION FOR R15-2

IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

MT PHOENIX I DRY DOCK COST COMPARISION SHEET


ZHOUSHAN ZHOUSHAN ZHOUSHAN XINYA ZHOUSHAN COSCO &
IMCYY YARD HAUFENG YARD NANTONG YARD
ITEM 4TH SPECIAL SURVEY DOCKING --(35) Days Docking & BWTS PAYMENT PAYMENT PAYMENT PAYMENT
No. Installation US$ US$ US$ US$
MT "PHOENIX I "
IMO No.:9236248
CRUDE OIL TANKER / YEAR OF BUILD 2002-04-29, CLASS: LLOYD
LOA / BM / DM=248 / 43.03 / 21.0 M
GRT / NET / DWT=59,693 / 31,164 / 105,851 MT

G 1 GENERAL SECTION Err:508 Err:508 224,554 Err:508


DD 2 DECK SECTION 350,815 323,964 352,597 380,256
EL 3 ENGINE SECTION 248,762 218,583 243,148 248,436
EL 4 ELECTRIAL SECTION 108,439 100,869 100,121 101,003
N 5 BRIDGE SECTION 16,280 14,340 17,720 18,510
TOTAL Err:508 Err:508 938,140 Err:508

Discount on final invoice amount agreed by Yards 25% Err:508 24% Err:508 24% 712986.09904 5% Err:508

2.5
Steel renewal estimation --Approx 25 MT ( Yard cost /kg ) For work inside 2.3us 2.3usd 2.25u
6 57500 57500 56250 usd/k 62500
ballast tanks . d/kg /kg sd/kg
g
UT gauging service charges ( Cargo tanks rope access method cost
7 20000 20000 20000 20000
included)
8 Demucking & Deslopping charges ( Basis as per MT Astrid ) 150000 150000 150000 150000
9 BWTS plan class approval charges 12500 12500 12500 12500
BWTS Installation & Fabrication jobs cost ( including Valves , cables
10 supply & ekectrical accesories cost & IMO D-2 sampling test by third 482000 452000 475000 470000
party ). Turnkey cost for complete installation job
11 Machinery Spares for overhauling jobs during docking 225106 225106 225106 225106
12 Service Engineers charges 57000 57000 57000 57000
13 Hull Paints ( 24 months scheme )--By Jotun 95000 95000 95000 95000
14 Logistics ( Freight charges , customs clearances & transport charges ) 15000 15000 15000 15000
Consumable stores ( Valves , U clamps , Nuts & Bolts , Engine & Electrical
15 store , lsa/ffa store, Gaskets , etc.) 15000 15000 15000 15000

16 Agency Charges 49000 49000 49000 49000


Sundries ( Suptd Fees , Flight charges , Fooding & Lodging, Quarantine
17 charges ( approx 21 days) 35000 35000 35000 35000
18 BWTS Equipment cost --Order placed to SUNRUI 389000 389000 389000 389000
19 MISC Cost for emergency repair jobs 75000 75000 75000 75000
Total DD cost Err:508 Err:508 2381842.09904 Err:508

40% of invoice
50% of invoice
prior departure, 50% of invoice prior
prior departure & 100% prior departure
Payment Terms 50% within 30
30 %within 30 departure & 50%
of the vessel
days &30%within within 60 days
days
60 days

REMARKS :-

1 Spares requistions sent to vendors & few quotes received . Price captured in the DD spares sheet basis best discounted quotes. Orders not yet placed .

2 Class annual survey completed in March'2022 .

3 Vessel is under special survey scheme , All CSM items are due in this docking. Class surveyor will inspect main engine major components & Other major equipment inspection & operational tests, bunker tanks inspection , DB tanks inspection,

4 Makers service engineer services & major equipment health check up costs are taken basis experience of other vessels docking.
5 Demucking & Deslopping costs assumed basis MT ASTRID .
6 We are not planning CAP survey & same confirmed by owners

7 Cargo tanks & Bottom UT gauging pending . Ballast tanks & Main deck plating UT gauging completed during class annuals in March'2022

8 Steel renwal estimation not yet finalised . We have assume atleast 25 MT steel renewal .

As per feedback from Yards , Owners superintendents are now attending vessel for docking . 35 days require for Yard to apply LOI for visiting superintendent from Dubai . For e.g , if we confirm yard today then yard will apply for LOI today to
9
china immigration & after 35 days LOI will be issued basis which China visa will be issued .

CURRENCY: USD 1 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

XINYA SHIPYARD
ITEM UNIT PAYMENT
# QUOTATION DESCRIPTION UNIT QTY
No. PRICE US$
2 REPAIR/DRYDOCKING PERIOD SERVICES.
2.1 CIRCULATING WATER.
COOLING WATER CON. / DISCON. LINE.TIME 16 6 96
COOLING WATER SUPPLY,
LINE.DAY 16 45 720
DURING VSL STAY IN DD
2.2 SUPPLY OF BALLAST WATER BY HOSE.
b BALLAST WATER CON. / DISCON. LINE.TIME 16 8 128
BALLAST WATER SUPPLY
a MT 0.2 10500 2100
(FLOW CAPACITY 450~750T PER HOUR)
VENT HEAD REMOVE & REFIT PC 40 8 320

2.3 SUPPLY OF POTABLE FRESH WATER


b FRESH WATER CON. / DISCON. LINE.TIME 16 2 32
a FRESH WATER SUPPLY MT 1.5 600 900
2.4 ELECTRICAL POWER
CONNECTION / DISCONNECTION LINE.TIME 40 4 160
SHORE POWER SUPPLY KWH 0.35 15000 5250
FREQUENCY CHARGER RENTAL Set.Day 450 10 4500
SHORE GENERATOR RENTAL ( FUEL COST EXCLUDED) Set.Day 450 2 900
2.5 HEATING APPLIANCES
HEATING LAMPS OR CABIN HEATER INSTALLATION PC 9 0 0
HEATING LAMPS OR CABIN HEATER USAGE PC.DAY 10 0 0
2.6 FIRE LINE SUPPLY
FIRE LINE CONNECTION / DISCONNECTION
LINE.TIME 16 6 96
ASSUME 2LINE
KEEP PRESSURE ( 30 days) LINE.DAY 16 60 960
2.7 FIRE WATCH
FIRE WATCHMAN (FIRE PATROL)--30 DAYS MAN.DAY 48 35 1680
2.8 SECURITY WATCH
SECURITY WATCHMAN---26 DAYS MAN.DAY 48 35 1680
2.9 SAFETY SERVICES
FIXED FF SYSTEM ISOLATION (CO2), IF REQURIED TIME 300 1 300
FIRE EXTINGUISHER PUT ON BOARD, IF REQURIED DAY 30 26 780
2.10. GARBAGE
DOMESTIC GARBAGE DISPOSAL (NON INDUSTRIAL, NON
DAY 60 30 1800
OILY)
ISSUE CERTIFICATE FROM MSA, IF REQUIRED TIME 1000 1 1000
PLASTIC DISPOSAL KG 2 200 400
OILY RAGS DISPOSAL TON 800 1 800
GARBAGE SKIP PC.DAY 45 35 1575
NOTE: FLAMMABLE MATERIAL, CHEMICAL,MEDICAL,OILY
WASTE,BATTERY ETC. TO BE CHARGED EXTRA.
2.11 CLEANING
DECK & E/R WORK AREAS FINAL CLEANING AFTER
LOT 1200 1 1200
COMPLETION OF ALL WORKS
E/R BOTTOM FLOOR CLEANING ON COMPLETION LOT 600 1 600
PUMP ROOM FINAL CLEANING ON COMPLETION LOT 850 1 850
CHEMICAL CLEANING TO BE EXTRA. M² 4 0 0
2.12 SEWAGE, CASE BY CASE
2.13 TELEPHONE m3
TELEPHONE INSTALLATION SET 14 0 0
TELEPHONE USAGE (LOCAL CALLS)
ASSUME 26DAYS SET.DAY 4 30 120

MOBILE PHONE (DOMESTIC CALL ONLY) SET.DAY 15 30 450


WIFI SERVICE
LAND INTERNET LINE WITH ROUTER INSTALLATION LINE.TIME 36 3 108
LAND INTERNET USAGE LINE.DAY 30 30 900
TELEPHONE / FAX / COMPUTER / COPYING FACILITIES
FOR SUPERINTENDENTS ROOM-FREE OF CHARGE
2.14 CRANAGE
SHORE CRANE SERVICE FOR SHIP’S PROVISIONS ≤5T,
ASSUME 52LIFT LIFT.TIME 50 52 2600
SECURING OWNER'S SPARE BY SHIP'S STAFF OR
SUPLLIER,YARD RIGGERS TO BE EXTRA.
2.15 COMPRESSED AIR
COMPRESSED AIR CON. / DISCON. LINE.TIME 16 6 96
COMPRESSED AIR SUPPLY
LINE.DAY 16 35 560
(ASSUME 26DAYS)
2.16 STEAM SUPPLY, N/A
2.17 BOTTOM PLUGS
PLS REFER TO DECK SECTION ITEM DD 35
2.18 GAS FREE CERTIFICATE
STATE CHEMIST FOR GAS FREE CERTIFICATE
INITIAL GAS FREE CERTIFICATE LUMPSUM 100 1 100
LAUNCH TUG BOAT ASSISTANCE SET.HR 3200 1 3200
DAILY GAS FREE CERTIFICATE
DAILY GAS FREE INSPECTION FOR CARGO OIL & SLOP
TANKER DAY 32 35 1120

DAILY HOT WORK CERTIFICATES


ADDITION INSPECTION FOR REPAIR WORK & HOT WORK
ASSUME 26DAYSX6 VISIT VISIT.TK 32 200 6400

2.19 FORKLIFT SERVICE


FORKLIFT SERVICE SERVICES ≤5T TIME 50 50 2500
2.20. CHERRY PICKER
CHERRY PICKER / LIFTABLE PLATFORM SET.HR 50 96 4800
2.21 TEMPORARY VENTILATION
SUPPLY AND FIT CARGO TANK VENTILAITON FAN TO
MAINTAIN GAS FREE CONDITION
AA (12COT+2SLOP)
VENTILATION FAN INSTALLATION, DISCONNECT
(ASSUME 24 SETX2TIMEX3SHIFT) SET.TIME 32 144 4608
VENTILATION FAN USAGE (24HOURS. -PER SET.DAY)
(ASSUME24SET*35DAY) SET.DAY 32 850 27200
VENTILATION FAN USAGE DURING VESSELE STAY IN DRY
DOCK SET.DAY 32 70 2240
(24HOURS. -PER SET.DAY) (ASSUME14SET*5DAYS)
FAN DUCT SUPPLY/ ARRANGEMENT/ DISPOSAL M 20 420 8400
POWER CONSUMPTION 15KW/SET (TOTAL 8500 KWH) KWH 0.35 8500 2975
BB OTHER REPAIR WORK
VENTILATION INSTALLATION SET.TIME 16 10 160
VENTILATION USAGE (8HOURS.-PER SET.) SET.DAY 32 80 2560
VENTILATION USAGE (24HOUR.-PER SET.) SET.DAY 120 0 0
FAN DUCT SUPPLY/ ARRANGEMENT/ DISPOSAL M 20 100 2000
2.22 TEMPORARY LIGHTING
TEMP LIGHTING INSTALLATION PC 10 6 60
TEMP LIGHTING USAGE (8HOUR,PER SET.DAY) PC.DAY 10 90 900
2.23 ACCOMMODATION PROTECTION
ACCOMMODATION / DECK FLOOR PROTECTION, IF
REQURIED M² 2 250 500

2.24 MANHOLE
WBT MANHOLE TO BE OPENED AND CLOSED WITH O/S
PACKING PC 30 14 420

NEW RUBBER PACKING SUPPLY PC 20 14 280


MANHOLE/ACCESS SAFETY GUARD RAILING INSTALL LOCATIOIN 15 14 210
GALV. STUD BOLT RENEWAL PC 5 40 200
2.25 GANGWAY
GANGWAYS ON / OFF SET.TIME 730 6 4380
2.26 SKYLIGHT
E/R & PR SKYLIGHT TO REMOVAL & REFIT WITH GASKET
PC 250 2 500
O/S
THE RUBBER GASKET TO BE RENEWED. M 10 5 50
SAFETY GUARD PC 50 2 100
2.27 STAGING
MINIMUM CHARGE USD $50. -PER PC
OPEN AREAS STAGING (IN DOCK BOTTOM) M3 2 2000 4000
OPEN AREAS STAGING (ON DECK) M3 2.5 2000 5000
TANKS AREAS STAGING M3 2 3000 6000
CARGO HOLDS AREAS STAGING M3 2 2000 4000
ENGINE ROOM STAGING M3 2 2000 4000
HANGING STAGING M3 8 500 4000
2.28 PIPE RENEWALS 8000

CURRENCY: USD 2 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY
No. PRICE US$
* STANDARD RATES, PLS REFER TO OUR YARD TARIFF
2.29 VALVE RENEWALS 2000
STANDARD RATES, PLS REFER TO OUR YARD TARIFF
2.30. SLOP AND WASTE DISPOSAL
DESLOPING& CARGO HOLD DEMUCKING, NORMALLY
1
WOULD BE ARRAANGED BY OWNER DIRECTLY
OTHER TANKS TO BE CLEANED DURING VSL IN
2
SHIPYARD, PLS REFER TO BELOW ITEM ENGINE SECTION
2.31 ASSISTANCE TO SERVICE ENGINEERS
Unskilled work man.hr 10 72 720
Electrician man.hr 25 24 600
Fitter & welder man.hr 25 72 1800
2.32 REMOVE AND REFITS
REMOVE AND REFIT INSULAITON ON BAORD FOR
a) M2 40 50 2000
ACCESS T50MM
b) REMOVE AND REFIT ACC. PANELS FOR ACCESS M2 60
c) REMOVE AND REFIT EL CABLES FOR ACCESS M 6 100 600
2.33 SURVEY COMMENMENT- STAGING AND CHERRY PICKER
a) CHERRY PICKER SERVICES SET.HR 40 100 4000
2.34 OWNER ARRANGED SERVICE ENGINEER
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD
ASSISTANCE WORK TO BE EXTRA
2.35 PUBLIC HOLIDAYS
NOTE: TO BE DISCUSSED IF DURING CHINESE NEW YEAR
2.36 SHIPYARD WORKING SCHEDULE
NORMAL WORK TIME: 08:00-17:00 X7DAYS,24HOUR IN DD
2.37 TRANSPORTATION OF EQUIPMENT
NOTE:CONFIRM THAT IN EXCEPTION OF SPECIAL NOTICE
2.38 EQUIPMENT OVERHAULING
NOTE:CONFIRM THAT IN EXCEPTION OF SPECIAL NOTICE

3 REPAIR BERTH / DRYDOCKING


3.1 VESSEL SHIFTING AND MOORING
TUGGAGE
SHIFTING 3200 4 12800
FOR ARRIVAL / DEPARTURE & DOCKING / UNDOCKING
PILOTAGE
SHIFTING 1100 4 4400
FOR ARRIVAL / DEPARTURE & DOCKING / UNDOCKING
MOORING RIGGER
SHIFTING 850 4 3400
FOR ARRIVAL / DEPARTURE & DOCKING / UNDOCKING
ADDITIONAL REQUIREMENTS FOR DISFECTION/ PCR
TEST BY THE AUTHORITIEST O BE EXTRA, IF NECESSARY.
3.2 REPAIR BERTH / DRY DOCKING
WHARFAGE / REPAIR BERTH DAY 630 30 18900
ADDITIONAL REQUIREMENTS FOR DISFECTION/ PCR
TEST BY THE AUTHORITIEST O BE EXTRA
3.3 DRY‐DOCKING
DRYDOCK COST 1ST DAY & LAST DAY
DOCKAGE FOR FIRST + LAST CALENDAR DAYS LOT 5300 1 5300
DRYDOCK DAILY COST
DOCKAGE FOR SUBSEQUENT LAY CALENDAR DAYS DAY 2600 5 13000
ADDITIONAL FOR SUBSEQUENT LAY DAYS
DAY 2600
( FOR MORE THAN 5DAYS PARTS)
3.3.1 GENERAL DOCKING SERVICES
INITIAL BLOCK PREPARATION, PLS REFER TO 3.3.3
3.3.2 EARTHING CABLE
EARTH CONNECTING TIME 100 2 200
3.3.3 BLOCK REMOVAL
SIDE BLOCK / KEEL BLOCK ARRANGEMENT/REMOVAL
SHIFT / ADJUSTMENT / REARRANGEMENT OF THE SIDE
BLOCKS PC 40 12 480

SHIFT / ADJUSTMENT / REARRANGEMENT OF THE KEEL


BLOCKS PC 60 8 480

3.4 TRIALS BERTH


ADDITIONAL SHIFTING TO TRIALS BERTH IF REQUIRED,
PLS REFER TO ABOVE ITEM:3.1
BERTH TRIALS TIME 680 0 0
3.5 GANGWAY
3.6 DOCK TRIALS
BERTH TRIALS TIME 850 1 850
3.7 SEA TRIALS
SEA TRIALS (INNER ANCHORAGE)
SEA TRIALS (SHIP YARD TO INNER ANCHORAGE AS
HOUR 1050 2 2100
1HOUR)
TUG ASSISTANCE SET.HR 3200 1 3200
LAUNCH TUG BOAT ASSISTANCE FOR RETURN BACK TO
SET.HR 3200 1 3200
YARD
SUB TOTAL 221,354

******END OF THE GERNERAL SECTION QUOTATION******

CURRENCY: USD 3 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

IMCY SHIPYARD HAUFENG SHIPYARD XINYA SHIPYARD COSCO SHIPYARD


ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT
# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
MT "PHOENIX I "
IMO No.:9236248
CRUDE OIL TANKER / YEAR OF BUILD 2002-04-29, CLASS: LR
LOA / BM / DM=248 / 43.03 / 21.0 M
GRT / NET / DWT=59,693 / 31,164 / 105,851 MT

DD DECK / HULL / PUMP ROOM


DD 01 UT GAUGING
MINIMUM CHARGE UP TO 300POINTS FOR E/R SEA WATER OVERBOARD
PIPES VISIT 800 1 800 VISIT 800 1 800 VISIT 800 1 800 VISIT 800 1 800

ULTRASONIC THICKNESS MEASUREMENTS


POINT 1.5 500 750 POINT 1.2 500 600 POINT 1.5 500 750 POINT 1.5 500 750

SPIDER-MAN SERVICE CASE BY CASE


NOTE:ACCESSORY WORKS TO BE CHARGED EXTRA
* MANHOLE
WBT MANHOLE TO BE OPENED AND CLOSED WITH O/S PACKING PC 27 14 378 PC 24 14 336 PC 30 14 420 PC 24 14 336
WBT NEW RUBBER PACKING PC 15 14 210 PC 10 14 140 PC 20 14 280 PC 15 14 210
MANHOLE/ACCESS SAFETY GUARD RAILING INSTALL LOCATIOI LOCATIOI LOCATIOI
25 0 0 LOCATIOIN 25 0 0 25 0 0 25 0 0
N N N
BOOBY HATCH SAFETY GUARD RAILING INSTALL PC 50 3 150 PC 10 3 30 PC 15 3 45 PC 10 3 30
* GAS FREE INSPECITON FOR TANK ENTRY PERMIT VISIT.TK 36 42 1512 VISIT.TK 24 42 1008 VISIT.TK 32 42 1344 VISIT.TK 16 42 672
CHERRY PICKER / LIFTABLE PLATFORM SET.HR 36 10 360 SET.HR 36 10 360 SET.HR 40 10 400 SET.HR 32 10 320
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 1500 1500 1500 1500
DD 02 SEACHEST CLEANING & INSPECTION
SEA CHEST TO BE OPENED,CLEANED,INSPECTION,PAINTING WITH
PC 180 5 900 PC 65 5 325 PC 50 5 250 PC 180 5 900
O/S,CLOSED
FULL BLASTING FOR EACH SEA CHEST, IF REQUIRED PC 300 5 1500 PC 150 5 750 PC 150 5 750 PC 150 5 750
AIR BLOWING / STEAM PIPE TO BE REMOVED, CLEANING AND REFIT LINE.TIME 50 2 100 LINE.TIME 50 2 100 LINE.TIME 50 2 100 LINE.TIME 50 2 100
PORTABLELADDER FOR ACCESS BOTTOM SEA CHEST PC 50 1 50 PC 35 1 35 PC 45 1 45 PC 45 1 45
ENGINE ROOM HIGH SEA CHEST STBD
TOWER STAGING IN DRY DOCK BOTTOM FOR OTHER SEACHEST M³ 2 200 400 M³ 1.8 200 360 M³ 2 200 400 M³ 2.5 200 500
CHERRY PICKER ASSISTANCE FOR EMERGENCY FIRE PUMP SEA
SET.HR 36 5 180 SET.HR 36 5 180 SET.HR 40 5 200 SET.HR 32 5 160
CHEST.
ANODES TO BE RENEWED WITH OWNER SUPPLY PC 15 20 300 PC 20 20 400 PC 20 20 400 PC 10 20 200
RENEWAL OF STUD AND BOLT PAIR 15 10 150 PAIR 10 10 100 PAIR 10 10 100 PAIR 10 10 100
ANODS TO BE SUPPLIED BY SHIPYARD KG 8 500 4000 KG 8.5 500 4250 KG 8 500 4000 KG 7.5 500 3750
DD 03 ALL FFA EQUIPMENT (ACCOMODATION , DECK AND ENGINE ROOM.)
NO DETAILED, PLS PROVIDE THE FFA EQUIPMENT LIST--CO2 Flexible
hoses renewal due . We will engage external LSA/FFA service provider. 15000 15000 15000 15000

DD 04 ANCHOR AND ANCHOR CHAIN


ANCHORS AND CABLES WORK DURING VESSEL IN DRY DOCK
ANCHORS AND ANCHOR CHAINS TO BE RANGED DOWN AND CLEANED
chain 600 2 1200 chain 650 2 1300 chain 480 2 960 chain 720 2 1440
WITH HPFW
ANCHOR CHAINS TO BE MEASURED/CALIBRATED TIME 162 2 324 TIME 125 2 250 TIME 125 2 250 TIME 180 2 360
HANMERING TEST FOR CHECK THE LOOSE STUD & KENTER-SHACKLE PC 5 100 500 PC 5 100 500 PC 5 100 500 PC 5 100 500
LOOSE SUTDS TO BE REWELDED PC 25 50 1250 PC 15 50 750 PC 20 50 1000 PC 20 50 1000
CLEANING & COAT ANCHORS
MARK CHAINS ANCHORS BOTH 144 1 144 BOTH 280 1 280 BOTH 300 1 300 BOTH 360 1 360
SS BEND SUPPLY / INSTALLATION PC 15 0 0 PC 15 0 0 PC 15 0 0 PC 15 0 0
ANCHOR BLASTING AND COATED WITH O/S, IF REQURIED PC 300 2 600 PC 300 2 600 PC 300 2 600 PC 150 2 300
ANCHOR CHAIN TO BE DISCONNECT FROM BITTER END (DURING
VESSEL IN DRY DOCK) PC 350 2 700 PC 350 2 700 PC 350 2 700 PC 180 2 360

BITTER END INSPECTION PC 120 1 120 PC 120 1 120 PC 120 1 120 PC 120 1 120
REPLACEMENT / RELOCATION OF ANCHOR CHAIN & D-SHACKLE WITH
O.S
NEW ANCHOR CHAIN TO BE REPALCED WITH O.S LENGTH 120 3 360 LENGTH 120 3 360 LENGTH 120 3 360 LENGTH 240 3 720
REPLACEMENT OF ANCHOR KENTER-SHACKLE WITH O.S PC 80 2 160 PC 60 2 120 PC 80 2 160 PC 60 2 120
NOTE: ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA--2
LENGTHS OF ANCHOR CHAIN , KENTER SHACKLE , TRANSPORT & 23620 23620 23620 23620
CUSTOM
DD 05 BALLAST PUMP NO.1 AND 2 OVERHAUL
BALLAST PUMP (CV350) SIDE CASING COVER TO BE OPENED AND
REMOVED THE IMPELLER WITH SHAFT ASSEMBLY TO WORKSHOP,
SET 2350 2 4700 SET 2500 2 5000 SET 1600 2 3200 SET 2000 2 4000
CALIBRATION,AND REPALCE BEARING, BUSH OR MOUTH
RINGS ,MECHANICAL SEAL, AND CASING GASKET WITH O/S
IMPELLER WITH PUMP SHAFT TO BE DYNAMICALLY BALANCED SET 1350 2 2700 SET 800 2 1600 SET 650 2 1300 SET 650 2 1300
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
3500 3500 3500 3500
EXTRA,--Any erosion in casing , pitting in shaft , wear rings fabrication etc
DD 06 BALLAST TANK INSPECTION AND PUMPROOM
NO DETAILED, PLS PROVIDE THE DIAGRAM DRAWING FOR OUR
REFERENCE--Already completed by class survyor during class annuals on 15th
March'2022
DD 07 CHOKES FWD AND AFT
CHOCKS GROOVES TO BE CLEANED WELDED UP WITH FOLLOWING
PC 320 6 1920 PC 250 6 1500 PC 180 6 1080 PC 150 6 900
HAND-GRINDING OF WELDS.
HANG STAGING M³ 8 300 2400 M³ 8 300 2400 M³ 8 300 2400 M³ 21 300 6300
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA.
DD 08 ACCO. GANGWAY SHEAVES AND MOTOR.
A LADDER INSPECITON AND REPAIRS
ACC LADDER WIRE ROPE TO BE RENEWED OR END TO END WITH O.S WIRE 120 2 240 WIRE 250 2 500 WIRE 250 2 500 WIRE 150 2 300
APPLY GREASE WITH O.S M 2 25 50 M 2 25 50 M 2 25 50 M 2 25 50
ACCOMMODATION LADDER TO BE REMOVED & SHIFT TO WORKSHOP
SET 450 2 900 SET 450 2 900 SET 450 2 900 SET 120 2 240
FOR REPAIR WORK
TOP TURN TABLE AND LOWER PLATFROM TO BE OVERHAULED FOR
INSPECITON AND FREE UP SET 360 2 720 SET 360 2 720 SET 360 2 720 SET 300 2 600

STIFFENERS TO BE RENEWED UNDER THE TURN TABLE ASSUME


PC 30 5 150 PC 30 5 150 PC 30 5 150 PC 30 5 150
FB100X10MM L <1MTR FOR EACH
WINCH TO BE OVERHAUELD WITH O.S , IF NECESSARY SET 680 2 1360 SET 680 2 1360 SET 680 2 1360 SET 680 2 1360
SHEAVES / SIDE BLOCK TO BE OVERAHULED WITH O.S PC 40 2 80 PC 40 2 80 PC 40 2 80 PC 40 2 80
SUPPORT PLATE FOR SHEAVES TO BE RENEWAED AS MS, IF PC 45 4 180 PC 40 4 160 PC 45 4 180 PC 45 4 180
B NECESSARY
ACCOMODATION LADDER LOAD TEST
OPT ACCOMODATION LADDER LOAD TEST, IF TOTAL TEST WEIGHT <600KG
ION SET.TIME 300 2 600 SET.TIME 500 2 1000 SET.TIME 350 2 700 SET.TIME 550 2 1100
2
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 1000 1000 1000 1000
DD 09 LIFEBOAT DAVIT INSPECTION.
MAKER / SERVICE ENGINEER TO BE ARRANGED BY OWNER.YARD
ASSISTANCE WORK AS FOLLOW.
LIFE BOAT & RESCUE BOAT REMOVE,REFIT BOAT.TIME 300 2 600 BOAT.TIME 200 2 400 BOAT.TIME 450 2 900 BOAT.TIME 220 2 440
LIFE BOAT & RESCUE BOATT LOAD TEST BOAT.TIME 350 2 700 BOAT.TIME 200 2 400 BOAT.TIME 450 2 900 BOAT.TIME 650 2 1300
LIFE BOAT & RESCUE BOAT DAIVT LOAD TEST DAVIT.TIME 350 2 700 DAVIT.TIME 500 2 1000 DAVIT.TIME 350 2 700 DAVIT.TIME 550 2 1100
DAVIT SHEAVE TO BE OVERHAULED AND REPALCE BUSH WITH O/S, IF
NECESSARY PC 80 4 320 PC 80 4 320 PC 80 4 320 PC 80 4 320

TOWER STAGING ASSISTANCE ON DECK FOR BOTH DAVIT M3 2.5 80 200 M3 2 80 160 M3 2 80 160 M3 2.5 80 200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
DD 10 LIFTING GEAR LOAD TEST (PUMP ROOM DAVIT)
PUMP ROOM DAVIT DAVIT TO BE LOAD TESTED SET.TIME 108 1 108 SET.TIME 250 1 250 SET.TIME 300 1 300 SET.TIME 250 1 250
WIRE ROPES RENEWAL, CRANE OPERATION AND CONDITION
TO BE EXAMINED BY SHIPS STAFF.
DD 11 LIFTING GEAR LOAD TEST (HOSE HANDLING CRANE)
HOSE HANDLING CRANE LOAD TEST(SWL 15 TONS) SET.TIME 350 2 700 SET.TIME 250 2 500 SET.TIME 450 2 900 SET.TIME 450 2 900
WIRE ROPES RENEWAL, CRANE OPERATION AND CONDITION
TO BE EXAMINED BY SHIPS STAFF. 1500 1500 1500 1500

DD 12 LIFTING GEAR LOAD TEST(PROVISION CRANE PORT)


PROVISION HANDLING CRANES (SWL 5 TONS) SET.TIME 168 1 168 SET.TIME 250 1 250 SET.TIME 300 1 300 SET.TIME 350 1 350
WIRE ROPES RENEWAL, CRANE OPERATION AND CONDITION
TO BE EXAMINED BY SHIPS STAFF. 500 500 500 500

DD 13 LIFTING GEAR LOAD TEST(PROVISION CRANE STBD)


PROVISION HANDLING CRANES (SWL 5 TONS) SET.TIME 168 1 168 SET.TIME 250 1 250 SET.TIME 300 1 300 SET.TIME 350 1 350
WIRE ROPES RENEWAL, CRANE OPERATION AND CONDITION
TO BE EXAMINED BY SHIPS STAFF. 500 500 500 500

DD 14 LOAD TEST OF LIFEBOAT


PLS REFER TO ABOVE ITEM:DD 09
DD 15 PRESSURE TESTING OF CARGO AND BALLAST TANK VALVES
NO DIMENSION, VALVES OVERAHUL, PLS REFER TO YARD TARIFF 750 750 750 750
DD 16 PRESSURE TESTING LINES
CARGO LINE PRESSURE TEST LINE.TIME 1200 6 7200 LINE.TIME 500 6 3000 LINE.TIME 860 6 5160 LINE.TIME 550 6 3300
COW LINE PRESSURE TEST LINE.TIME 450 1 450 LINE.TIME 450 1 450 LINE.TIME 860 1 860 LINE.TIME 550 1 550
MARPOL LINE PRESSURE TEST LINE.TIME 500 1 500 LINE.TIME 500 1 500 LINE.TIME 320 1 320 LINE.TIME 350 1 350
BALLAST LINE LINE LINE.TIME 1800 LINE.TIME 400 LINE.TIME 320 LINE.TIME 350
FOAM LINE PRESSURE TEST LINE.TIME 420 1 420 LINE.TIME 350 1 350 LINE.TIME 320 1 320 LINE.TIME 350 1 350
FIRE LINE PRESSURE TEST LINE.TIME 420 1 420 LINE.TIME 420 1 420 LINE.TIME 420 1 420 LINE.TIME 450 1 450
IG LINE PRESSURE TEST LINE.TIME 680 LINE.TIME 350 LINE.TIME 860 LINE.TIME 550
FW WATER SUPPLY TON 3 100 300 TON 2 100 200 TON 1.5 100 150 TON 2.5 100 250
OIL WATER DISPOSAL IF ANY TON 45 150 6750 TON 36 150 5400 TON 36 150 5400 TON 45 150 6750

CURRENCY: USD 4 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
DD 17 PUMPROOM FAN
PLS REFER TO BELOW ITEM DD 28
DD 18 HIGH VELOCITY PV VALVES.
PV VALVES REMOVED TO W/S,DISMANTLED,OVERHAULED WITH
SET 400 14 5600 SET 450 14 6300 SET 650 14 9100 SET 500 14 7000
O/S,PRESSURE & VACCUM TEST,REFITTED
TO MACHINE P/V V/VS SEAT, IF REQUIRED PC 125 28 3500 PC 85 28 2380 PC 135 28 3780 PC 130 28 3640
BLASTING OF BODIES INTERNALLY AND EXTERNALLY PC 30 14 420 PC 20 14 280 PC 20 14 280 PC 20 14 280
STAGING ASSISTANCE, IF REQUIRED PC 50 14 700 PC 50 14 700 PC 50 14 700 PC 50 14 700
NOTE: ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA.
DD 19 TESTING OF MOORING WINCHES
MOORING WINCH BRAKE HOLDING TEST SET.TIME 300 16 4800 SET.TIME 150 16 2400 SET.TIME 250 16 4000 SET.TIME 600 16 9600
DD 20 HULL MARKINGS
TO PAINT NAME AND OTHER MARKS ON OUTER HULL WITH O/S LOT 576 1 576 LOT 1200 1 1200 LOT 1200 1 1200 LOT 1400 1 1400
DEMARCATION LINE TO BE PAINTED WITH O/S M 2 450 900 M 2 450 900 M 2 450 900 M 2 450 900
PLIMSOLL MARKS OR CLASS MARKS LETTER RENEWAL, IF REQUIRED LETTER 60 5 300 LETTER 60 5 300 LETTER 60 5 300 LETTER 60 5 300

DD 21 SURFACE PREPARATION AND HULL COATING


NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
DD21.FLAT BOTTOM -7700 m2
DD21.HAND SCRAPING
HARD SCRAPING / REMOVE BARNACLES M² 3 1500 4500 M² 3 1500 4500 M² 3 1500 4500 M² 4 1500 6000
DD21.HIGH PRESSURE WATER WASHING,(250~300 BAR) M² 0.45 7700 3465 M² 0.45 7700 3465 M² 0.5 7700 3850 M² 0.5 7700 3850
DD21.HYDRO BLASTING
SPOT HYDRO-BLASTING TO WA1.0 ---- 40 % M² 3.5 3080 10780 M² 3.5 3080 10780 M² 3.8 3080 11704 M² 4.5 3080 13860
SPOT HYDRO-BLASTING TO WA2.0----50 % M² 4.5 3850 17325 M² 4.5 3850 17325 M² 4.8 3850 18480 M² 5.5 3850 21175
FULL HYDRO-BLASTING TO WA2.0 M² 5.5 0 0 M² 5.5 0 0 M² 6 0 0 M² 6 0 0
DD21.AIR BLOWING
AIR BLOWING,IF REQUIRED M² 0.2 7700 1540 M² 0.2 7700 1540 M² 0.2 7700 1540 M² 0.25 7700 1925
DD21.APPLY PAINT
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)--T/U M².COAT 0.5 3350 1675 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)--T/U M².COAT 0.5 3350 1675 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407
APPLY PAINT WITH O/S,DFT UP TO 150MIC --F/C M².COAT 0.5 7700 3850 M².COAT 0.36 7700 2772 M².COAT 0.36 7700 2772 M².COAT 0.36 7700 2772
DD21.VERTICAL SIDE- BILGE KEEL & BOOT TOP---(4100 + 3600) 7700 m2
DD21.HAND SCRAPING
HARD SCRAPING / REMOVE BARNACLES M² 3 500 1500 M² 3 500 1500 M² 1.5 500 750 M² 4 500 2000
DD21.HIGH PRESSURE WATER WASHING,(250~300 BAR) M² 0.45 7700 3465 M² 0.45 7700 3465 M² 0.5 7700 3850 M² 0.5 7700 3850
DD21.HYDRO BLASTING
SPOT HYDRO-BLASTING TO WA1.0--40% M² 3.5 3080 10780 M² 3.5 3080 10780 M² 3.8 3080 11704 M² 4.5 3080 13860
SPOT HYDRO-BLASTING TO WA2.0--50% M² 4.5 3850 17325 M² 4.5 3850 17325 M² 4.8 3850 18480 M² 5.5 3850 21175
FULL HYDRO-BLASTING TO WA2.0 M² 5.5 0 0 M² 5.5 0 0 M² 6 0 0 M² 6 0 0
HIGH PRESSURE WATER WASHING M² 0.45 M² 0.45 M² 0.5 M² 0.5
DD21.AIR BLOWING
AIR BLOWING,IF REQUIRED M² 0.2 7700 1540 M² 0.2 7700 1540 M² 0.25 7700 1925 M² 0.25 7700 1925
DD21.Apply paint
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)--T/U M².COAT 0.5 3350 1675 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)-T/U M².COAT 0.5 3350 1675 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407 M².COAT 0.42 3350 1407
APPLY PAINT WITH O/S,DFT UP TO 150MIC --F/C M².COAT 0.5 7700 3850 M².COAT 0.36 7700 2772 M².COAT 0.36 7700 2772 M².COAT 0.36 7700 2772
DD21.TOPSIDE AREA --3750 m2
DD21.CHEMICAL CLEANING
CHEMICAL CLEANING M² 4 M² 4 M² 4 M² 4
DD21.HIGH PRESSURE WATER WASHING,(250~300 BAR) M² 0.45 3750 1687.5 M² 0.45 3750 1687.5 M² 0.5 3750 1875 M² 0.5 3750 1875
DD21.HYDRO BLASTING
SPOT HYDRO-BLASTING TO WA1.0 ---- 14 % M² 3.5 562.5 1968.75 M² 3.5 562.5 1968.75 M² 3.5 562.5 1968.75 M² 4.5 562.5 2531.25
SPOT HYDRO-BLASTING TO WA2.0--14% M² 4.5 562.5 2531.25 M² 4.5 562.5 2531.25 M² 4.5 562.5 2531.25 M² 5.5 562.5 3093.75
FULL HYDRO-BLASTING TO WA2.0 ---50% M² 5.5 1875 10312.5 M² 5.5 1875 10312.5 M² 5.5 1875 10312.5 M² 6.5 1875 12187.5
HIGH PRESSURE WATER WASHING M² 0.45 M² 0.45 M² 0.5 M² 0.5
DD21.AIR BLOWING
AIR BLOWING,IF REQUIRED M² 0.2 3750 750 M² 0.2 3750 750 M² 0.2 3750 750 M² 0.25 3750 937.5
DD21.APPLY PAINT
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)-T/U M².COAT 0.5 1875 937.5 M².COAT 0.42 1875 787.5 M².COAT 0.42 1875 787.5 M².COAT 0.42 1875 787.5
APPLY PAINT WITH O/S,DFT UP TO 150MIC (OVER COATING 20% UP)-T/U M².COAT 0.5 1875 937.5 M².COAT 0.42 1875 787.5 M².COAT 0.42 1875 787.5 M².COAT 0.42 1875 787.5
APPLY PAINT WITH O/S,DFT UP TO 150MIC --F/C M².COAT 0.5 3750 1875 M².COAT 0.36 3750 1350 M².COAT 0.36 3750 1350 M².COAT 0.36 3750 1350
NOTE :
1) ALL PAINT TO BE SUPPLIED BY OWNER
EMPTY PAINT DRUNS / CANS DISPOSAL PC 2 160 320 PC 2.5 160 400 PC 2 160 320 PC 3 160 480
2) DFT MORE THAN 150MIC TO BE EXTRA.
SPECIAL TYPE PAINT (SILICON-BASED,X-MILE,GLASS FLAKE PAINT,X7,X8
3)
ETC.) TO BE EXTRA
PROTECTION FOR VESSEL EQUIPMENT
SCUPPER PLUG / CHUTE TO BE INSTALLED AND REMOVED PC 15 20 300 PC 15 20 300 PC 20 20 400 PC 20 20 400
TEMPORARILY PUT VINYL SHEET ALONG SHIP SIDE HANDRAIL(PORT
AND STBD) TO PROTECT MAIN DECK AND OTHER EQUIPMENT DURING M² 2 500 1000 M² 2 500 1000 M² 2 500 1000 M² 2 500 1000
HULL BLASTING AND PAINTING
ECHO SOUNDER,DOPPLER LOG,ANODES,STERN TUBE AREA,BOW
THRUSTER AND PROPELLER ETC. TO BE PROTECTED AGAINST HULL LUMPSUM 450 1 450 LUMPSUM 300 1 300 LUMPSUM 250 1 250 LUMPSUM 850 1 850
SPOT BLASTING AND PAINTING
DOCK BOTTOM LIGHTING DD VSL IN DRY DOCK
ASSUME 5DAYS DAY 180 5 900 DAY 180 5 900 DAY 180 5 900 DAY 180 5 900

CHERRY PICKER & EQUIPMENT FOR HULL VERTICAL / BOTTOM HYDRO


BLASTING AND PAINTING LUMPSUM 5500 5500 LUMPSUM 5500 5500 LUMPSUM 5500 5500 LUMPSUM 5500 5500
ESTIMATION TREATMENT AREAS >30% OR FULL BLASTING
BUTTERWORTH HOLES
A BUTTERWORTH HATCHES,X26SET
BUTTERWORTH HATCHES COVER TO BE OPENED AND CLOSED WITH
O/S PACKING PC 27 0 0 PC 24 0 0 PC 27 0 0 PC 27 0 0

HATCH WELDING SEAMS IWO SEATING FLANG AND SURFACE TO BE


PC 40 5 200 PC 40 5 200 PC 40 5 200 PC 40 5 200
DERUSTED AND GRDING FOR ,MPI TEST
MPI TEST FOR WELDING SEAM M 30 M 30 M 30 M 30
B ESCAPE HATCH ON MAIN DECK FOR COT'S
ESCAPE HATCH COVER FOR COT TO BE OPENED AND CLOSED WITH O/S
PACKING PC 54 0 0 PC 54 0 0 PC 54 0 0 PC 54 0 0

C SCAPE HATCH ON MAIN DECK FOR BALLAST TANKS


ESCAPE HATCH COVER FOR WBT TO BE OPENED AND CLOSED WITH
O/S PACKING PC 54 0 0 PC 54 0 0 PC 54 0 0 PC 54 0 0

GALV BOLT WITH NUTS RENEWAL PC 3 PC 5 PC 3 PC 3


MAIN CARGO PUMPS
CARGO OIL PUMPS (CV-450) SIDE COVER TO BE OPENED,AND THE
IMPELLER WITH SHAFT ASSEMBLY TO BE REMOVED, AND OVERHAULED
SET 2750 3 8250 SET 3000 3 9000 SET 3800 3 11400 SET 3300 3 9900
IN SHIPYARD WORKSHOP,ALL CLEARACNES CALIBRATION AND
REPALCE SPARES WITH O/S
IMPELLER WITH PUMP SHAFT TO BE DYNAMICALLY BALANCED, IF
SET.TIME 1650 2 3300 SET.TIME 850 2 1700 SET.TIME 1050 2 2100 SET.TIME 1650 2 3300
REQUIRED
DD 22 ALIGNMENT OF EL MOTOR AND IM. SHAFT SET.TIME 450 2 900 SET.TIME 450 2 900 SET.TIME 450 2 900 SET.TIME 450 2 900
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
EXTRA,
CARGO TANK BELL MOUTH REMOVAL AND INSPECTION
END OF SUCTION PIPES 400 MM & 200 MM REMOVAL / INSTALLATION
FOR ACCESS TO SUCTION WELL.
BELL MOUTH REMOVE,REFIT
BELL MOUTH 400MM PC 336 12 4032 PC 200 12 2400 PC 380 12 4560 PC 230 12 2760
BELL MOUTH 350MM PC 293 2 586 PC 200 2 400 PC 330 2 660 PC 230 2 460
BELL MOUTH 200MM PC 183 12 2196 PC 200 12 2400 PC 200 12 2400 PC 230 12 2760
GALV BOLTS & NUTS WITH WASHER PC 5 15 75 PC 5 15 75 PC 5 15 75 PC 5 15 75
NON ASBESTOS GASKET 200A 5K~10K THK = 3MM PC 10 12 120 PC 10 12 120 PC 10 12 120 PC 10 12 120
DD 23 NON ASBESTOS GASKET 350A/400A 5K~10K THK = 3MM PC 20 14 280 PC 20 14 280 PC 20 14 280 PC 20 14 280
PORTABLE PUMP CONNECT / DISCONNECT LINE.TIME 36 0 0 LINE.TIME 36 0 0 LINE.TIME 36 0 0 LINE.TIME 36 0 0
OILY BILGE WATER DISPOSAL TON 45 10 450 TON 36 10 360 TON 36 10 360 TON 45 10 450
SLUDGE / RESIDUAL DISPOSAL MT 800 2 1600 MT 650 2 1300 MT 650 2 1300 MT 800 2 1600
PITTING OVER3MM DEEP TO BE BUILT UP WELDED AND GROUND
POINT 50 POINT 25 POINT 35 POINT 35
SMOOTH (DIA≤50MM)
BILGE WEEL BOTTOM FLOOR TO BE CHEMICALCLEANED, GRINDING AND
DD 24 A PAINT 2COAT WITH O.S, IF NECESSARY ( FOR SMALL AREA LESS THANK PC 30 0 0 PC 30 0 0 PC 30 0 0 PC 30 0 0
DIA200MM
BURNING AREA AND NEW METAL TO BE GRINDING AND PAINT 2COAT
B PC 60 0 0 PC 60 0 0 PC 60 0 0 PC 60 0 0
WITH O.S, IF NECESSARY
C BILGE WELL BOTTOM PLATE TO BE RENEWED KG 2.535 KG 2.535 KG 2.535 KG 2.535
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
EXTRA,
CARGO STRIPPING EDUCTORS
CARGO EDUCTOR TO BE REMOVE,REFIT FOR INSPECTION SET 650 2 1300 SET 200 2 400 SET 450 2 900 SET 1300 2 2600
NON ASBESTOS GASKET 350~450A 5K~10K THK = 3MM PC 20 0 0 PC 20 0 0 PC 20 0 0 PC 20 0 0
GALV BOLTS & NUTS WITH WASHER RENEWAL, IF REQUIRED PC 5 48 240 PC 5 48 240 PC 5 48 240 PC 5 48 240
VALVE TO BE REMOVED AND REFIT FOR INSPECTION, NO
DIMENSION,PLS REFER TO OUR TARIFF
VALVES ACTUATOR TO BE OVEHRAULED WITH O.S PC 450 5 2250 PC 250 5 1250 PC 400 5 2000 PC 1300 5 6500

CURRENCY: USD 5 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
TOWER STAGING IN P.ROOM FOR ABOVE WORK PC 100 2 200 PC 100 2 200 PC 100 2 200 PC 100 2 200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
EXTRA,
MOVE CLEAN AND PAINT SPARE ANCHOR
ANCHOR WEIGHT 10,125 KG ) TO BE REMOVED TO DRY DOCK BOTTOM ,
BLASTING AND APPLY TWO COAT BLACK EPOXY WITH Y/S SET 350 1 350 SET 350 1 350 SET 350 1 350 SET 300 1 300

SUPPORT CRADLE TO BE DERUSTED AND PAINT WITH O.S PC 120 1 120 PC 120 1 120 PC 120 1 120 PC 120 1 120
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
EXTRA,
EMERGENCY TOWING WIRE AFT
EMERGENCY TOWING WIRE TO BE INSPECTED AND REGREASING WITH
SET 650 1 650 SET 650 1 650 SET 350 1 350 SET 300 1 300
O.S, AND TURNING UP BY SYSTEM DRIVE WINCH
DD 25 NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
PUMPROOM FANS
FAN CASING TO BE REMOVED REFIT FOR TAKE OUT THE EL MOTOR AND
FAN IMPELLER SET 350 2 700 SET 350 2 700 SET 250 2 500 SET 450 2 900

FAN MOTORS TO BE OVERHAUL WITH O/S SET 410 2 820 SET 365 2 730 SET 365 2 730 SET 350 2 700
FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 350 2 700 SET 350 2 700 SET 450 2 900 SET 350 2 700
FAN MUSHROOM BLASTING AND PAINTING WITH O.S, IF REQUIRED SET 350 2 700 SET 350 2 700 SET 200 2 400 SET 200 2 400
CASING GASKET RENEWAL PC 50 2 100 PC 50 2 100 PC 50 2 100 PC 50 2 100
DD 26 GALV BOLT WITH NUTS RENEWAL PC 12 48 576 PC 12 48 576 PC 12 48 576 PC 12 48 576
TOWER STAGING ON DECK M3 2.5 200 500 M3 2 200 400 M3 2 200 400 M3 2.5 200 500
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
BALLAST EDUCTOR PUMPROOM
DD 27 BALLAST EDUCTOR TO BE REMOVE,REFIT FOR INSPECTION SET 450 1 450 SET 250 1 250 SET 200 1 200 SET 150 1 150
NON ASBESTOS GASKET 250~350A 5K~10K THK = 3MM PC 15 1 15 PC 15 1 15 PC 15 1 15 PC 15 1 15
GALV BOLTS & NUTS WITH WASHER RENEWAL, IF REQUIRED PC 3 8 24 PC 3 8 24 PC 3 8 24 PC 3 8 24
DD 28 TOWER STAGING IN P.ROOM FOR ABOVE WORK PC 100 PC 100 PC 100 PC 100
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE CHARGE
EXTRA,
CLEAN INSPECT CHAIN LOCKER
SIDE MANHOLE TO BE OPNED / CLOSED pc 30 2 60 pc 24 2 48 pc 30 2 60 pc 30 2 60
PROVIDE ROPE LADDER ACCESS INTO THE CHAIN LOCKER PC 50 2 100 PC 50 2 100 PC 50 2 100 PC 50 2 100
CHAIN LOCKERS TO BE CLEANED locker 360 2 720 locker 192 2 384 locker 340 2 680 locker 600 2 1200
BOTTOM GRATINGS TO BE REMOVED, REFITTED PC 54 2 108 PC 50 2 100 PC 50 2 100 PC 50 2 100
DISPOSAL OF MUD AFTER CLEANING TON 45 10 450 TON 32 10 320 TON 26 10 260 TON 65 10 650
DISPOSAL OF REMAINING WATER / WASHING WATER TON 45 2 90 TON 12 2 24 TON 12 2 24 TON 36 2 72
PUMP WITH PIPELINE CON. / DISCON. LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72
DD 29 WASHING / CLEANING WITH HP WATER 200-300BAR BOTH 360 0 0 BOTH 360 0 0 BOTH 360 0 0 BOTH 360 0 0
POWER TOOLING.
M² 10 5 50 M² 10 5 50 M² 10 5 50 M² 10 5 50
(TREATMENT AREA DECIDE ON SPOT)
CHAIN LOCKERS TO BE 2 COATED WITH O/S PAINT UP 2M FROM THE
BOTH 243 1 243 BOTH 120 1 120 BOTH 680 1 680 BOTH 400 1 400
BOTTOM
STAGING IN CHAIN LOCKER M3 3 10 30 M3 3 10 30 M3 3 10 30 M3 2.5 10 25
BILGE EDUCTOR TO BE INSPECTED AND TESTED PC 120 2 240 PC 100 2 200 PC 100 2 200 PC 150 2 300
NOTE:
DD 30 GAS FREE INSPECTION VISIT 36 2 72 VISIT 24 2 48 VISIT 30 2 60 VISIT 150 2 300
VENTILATION FAN INSTALLATION SET 18 1 18 SET 18 1 18 SET 18 1 18 SET 18 1 18
VENTILATION FAN USAGE (8 HOURS. -PER SET.SHIFT) SET.DAY 40 2 80 SET.DAY 40 2 80 SET.DAY 40 2 80 SET.DAY 40 2 80
TEMPORARILY LIGHTING ON BOARD, CON. / DISCON. PC 9 2 18 PC 9 2 18 PC 9 2 18 PC 9 2 18
TEMPORARILY LIGHTING ON BOARD, USAGE PC.DAY 10 4 40 PC.DAY 10 4 40 PC.DAY 10 4 40 PC.DAY 10 4 40
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA. 800 800 800 800
IG BRANCH VAVE ISOLATION AND NRV VALVE TO OVERHAUL PC 116.6 0 0 PC 116.6 0 0 PC 116.6 0 0 PC 116.6 0 0
BRANCH IG VALVE
VALVES OVERAHUL, PLS REFER TO YARD TARIFF PC 116.16 0 0 PC 116.16 0 0 PC 116.16 0 0 PC 116.16 0 0
IG ISOLATION VALVES
NRV VALVES OVERAHUL, PLS REFER TO YARD TARIFF PC 116 1 116 PC 116 1 116 PC 116 1 116 PC 116 1 116
NRV
UPGRADATION OF UPHOSLTERY Lumpsum 10000 Lumpsum 10000 Lumpsum 10000 Lumpsum 10000
SOFA SET COVER FOR BRIDGE, OFFICER ABD CREW SMOKING ROOM
1) RENEWAL. M² 75 M² 75 M² 75 M² 75

DRY CLEANING AND RENEWAL OF HANGING PINS OF WHEELHOUSE


2) CURTAINS. M² 10 M² 10 M² 10 M² 10

3) RENEWAL OF ALL CABIN CURTAINS AND ROLLER BLINDS. M² 75 M² 75 M² 75 M² 75


4) MASTER'S, CH.ENG'S, CH.OFF'S AND 2ND ENG'S CABINS TO BE M² 75 M² 75 M² 75 M² 75
CARPETED.
CEMENT REPAIR BELOW FLOORING IF NECESSARY M² 60 M² 60 M² 60 M² 60
FLOORS TO BE COVER BY PLASTIC FILM M² 2 M² 2 M² 2 M² 2
REPLACING BATHROOM TILES IN CABIN
DD 31 FLOOR TILES TO BE RENEWED WITH O,S. M2 75 50 3750 M2 50 50 2500 M2 55 50 2750 M2 65 50 3250
CEMENT REPAIR BELOW FLOORING IF NECESSARY M2 25 M2 25 M2 25 M2 25
FLOORS TO BE COVER BY PLASTIC FILM M2 2 10 20 M2 2 10 20 M2 2 10 20 M2 2 10 20
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
WHARF LADDER LOAD TEST
WHARF LADDER LOAD TEST, IF TOTAL TEST WEIGHT <600KG SET.TIME 300 1 300 SET.TIME 500 1 500 SET.TIME 300 1 300 SET.TIME 550 1 550
DD 32 BOTTOM PLUG
BOTTOM PLUG TO BE RMEOVED AND REFIT WITH O.S SEAL KIT PC 9 14 126 PC 12 14 168 PC 20 214 4280 PC 12 214 2568
BOTTOM PLUG TO BE VACUUM TESTED PC 15 14 210 PC 10 14 140 PC 20 14 280 PC 12 14 168
LEAD SEAL WASHER SUPPLY, IF NECESSARY PC 10 14 140 PC 10 14 140 PC 10 14 140 PC 15 14 210
Additional in case of plug threads worn out 500 500 500 500
ODMCS SERVICING AND CALIBRATION, S-3000
ODMCS TO BE CALIBRATED BY MAKER ENGINEER SYSTEM 3800 1 3800 SYSTEM 3800 1 3800 SYSTEM 3800 1 3800 SYSTEM 3800 1 3800
DD 33 CALIBRATION OF FIXED GAS DETECTION SYSTEM
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA SYSTEM 1500 1 1500 SYSTEM 1500 1 1500 SYSTEM 1500 1 1500 SYSTEM 1500 1 1500

TANK CLEANING MACHINE OVERHAUL


TO DRAWOUT TANK CLEANING MACHINE (POLAR JET PJ 120T) AND
SEND TO W/S FOR REPAIR WORK PC 180 12 2160 PC 180 12 2160 PC 180 12 2160 PC 350 12 4200

TANK CLEANING MACHINE TO BE OVERHAULED AND REPALCE THE


SEAL KIT & BEARINGS WITH O.S SET 580 12 6960 SET 650 12 7800 SET 850 12 10200 SET 850 12 10200

DD 34 NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA


TANK RADAR SYSTEM
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
DD 35 WORK TO BE EXTRA---To be arranged by workshop approved by makers in 5000 5000 5000 5000
china
FOAM SAMPLE ANALYSIS
NORMAL FOAM CONCENTRATE ANALYSIS TIME 450 1 450 TIME 300 1 300 TIME 350 1 350 TIME 600 1 600
RENEWAL OF LIFEBOAT WIRE
LIFEBOAT FALL WIRE TO BE RENEWED BY O/S, IF NECESSARY WIRE 150 0 0 WIRE 150 0 0 WIRE 150 0 0 WIRE 150 0 0
DD 36 PRESSURE TESTING OF IMMERSION SUIT
IMMERSION SUITS SHORE SERVICE & PRESSURE TEST PC 18 30 540 PC 18 30 540 PC 18 30 540 PC 30 30 900
DD 37 SITTING AREA ON THE PIPE LINE.--Clamps & teflon gaskets renewal PC 15 100 1500 PC 15 100 1500 PC 15 100 1500 PC 15 100 1500

DD 38 RENEWAL OF GRATINGS ON MANIFOLD.


EXISTING GRATING TO BE REMOVED AND REFIT PC 27 PC 27 PC 27 PC 27
NEW GRIDS TO BE FABRICIATED AND INSTALLED (SMALL PIECE LESS
THAN0.M2, CHARGE AS $60/PC) M² 180 22 3960 M² 110 22 2420 M² 120 22 2640 M² 120 22 2640

HOLDING STUDS WITH SECURING CLAMPS TO BE INSTALLED PAIR 20 25 500 PAIR 20 25 500 PAIR 20 25 500 PAIR 20 25 500
DD 39 ANGLE BAR FRAME AND STIFFENER IF REQUIRED M 30 10 300 M 30 10 300 M 30 10 300 M 30 10 300
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
DD 40 GANGWAY SUPPORT
TURNING PIPE TO BE RENEWED AS SCH40. MS, 150A
DD 41 STRASIGHT PIPE 150A,MS,SCH40,NO GALV. M 69 10.96 756.24 M 46 10.96 504.16 M 124 10.96 1359.04 M 75 10.96 822
SLEEVE FOR 150A PC 50 4 200 PC 50 4 200 PC 50 4 200 PC 50 4 200
DD 42 MOORING LINE GUIDE SUPPORT
SUPPORT PIPE TO BE RENEWED AS, MS, SCH40. 100A
DD 43 STRASIGHT PIPE 100A,MS,SCH40,NO GALV. M.PC 47 4.6 216.2 M.PC 35 4.6 161 M.PC 54 4.6 248.4 M.PC 54 4.6 248.4
DECK SEAL AND OVERBOARD VALVE
ALARM SENSOR TO BE DISCONNECTED. REMOVE AND REFIT AFTER
DD 44 1 REPAIR WORK---To be done by shipstaff PC 36 0 0 PC 50 0 0 PC 150 0 0 PC 150 0 0

2 INSPECITON COVER AND TOP COVER


SIDE INSPECION COVER OPEN / CLOSED---Shipstaff PC 27 0 0 PC 27 0 0 PC 27 0 0 PC 27 0 0
OPEN AND REMOVE DECK SEAL TANK TOP COVER INLCUDE PIPE SET 450 1 450 SET 150 1 150 SET 150 1 150 SET 150 1 150
MAIN BODY TO BE SHIFT WORKSHOP AND INSIDE SURFACE TO BE
3,4,5 BLASTED AND APPLY PAINT WTH O.S, IF NECESSARY SET 1350 1 1350 SET 1350 1 1350 SET 1300 1 1300 SET 1300 1 1300

6 WASTE STEEL PLATE RENEWAL KG 2.5 50 125 KG 2.5 50 125 KG 2.5 50 125 KG 2.5 50 125
DD 45 7 RUBBER GAKSET / PACKING RENEWAL INCH 2 INCH 2 INCH 2 INCH 2
GAV BOLT WITH NUTS PAIR 3 PAIR 3 PAIR 3 PAIR 3
8 OVERBOARD VALVES TO BE OVERHAULED & INSPECTED pc 350 1 350 pc 350 1 350 pc 350 1 350 pc 262 1 350
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
OVERHAULING OF TANK CLEANING HEATER AND PRESSURE TEST OF
DD 46 HEAT COIL.
TANK CLEANING HEATER
TANK CLEANING HEATER TO BE REMOVED AND SHIFT TO WORKSHOP
1 CLEANING LEAKING TESTED SET 1860 1 1860 SET 850 1 850 SET 950 1 950 SET 1250 1 1250

DD 47 PLUG OF LEAKING TUBES PC 25 5 125 PC 25 5 125 PC 25 5 125 PC 25 5 125


ANODES TO BE RENEWED WITH O/S PC 15 5 75 PC 15 5 75 PC 15 5 75 PC 15 5 75
ANODE SUPPLY KG 8 10 80 KG 8 10 80 KG 8 10 80 KG 8 10 80
NON ASBESTOS GASKET FOR END COVER PC 50 2 100 PC 50 2 100 PC 50 2 100 PC 50 2 100

CURRENCY: USD 6 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
NOTE:ANY OTHER REPAIR OR ACSSORY WORK TO BE EXTRA
HEATING COILS
LINE.TIM
CARGO TANK SLOP TANK, ROT HEATING COIL PRESSURE TEST 340 14 4760 LINE.TIME 400 14 5600 LINE.TIME 280 14 3920 LINE.TIME 300 0 0
E

1 FUNNEL TOP PLATING


HPWW CLEANING OF TOP PLATING AND APPLY PAINT WITH O.S LOT 450 0 0 LOT 450 0 0 LOT 450 0 0 LOT 450 0 0
2 FUNNEL EXHAUST PIPES
DD 48 FUNNEL EXHUAST PIPES TO BE CLEANED AND APPLY PAINT WITH O.S LOT 680 0 0 LOT 680 0 0 LOT 680 0 0 LOT 680 0 0
3 FUNNEL EXTERIOR & LOGO
1) HPFW WASHING (250-300 BAR) M² 0.54 0 0 M² 0.54 0 0 M² 0.54 0 0 M² 0.54 0 0
2) DEGREASING BY SOLVENT CLEANING SURFACE FROM OIL M² 4 M² 4 M² 4 M² 4
SPOT RUST POINT TO BE TREATED WITH DISC SANDING / POWER
3) TOOLING M² 10 M² 10 M² 10 M² 10

4) T/U OF A/C,DFT OF 150 MIC M².COAT 0.6 M².COAT 0.6 M².COAT 0.6 M².COAT 0.6
5) FINAL COAT,DFT UP TO 150MIC WITH O.S M².COAT 0.6 0 0 M².COAT 0.3 200 60 M².COAT 0.3 0 0 M².COAT 0.3 0 0
6) HYDRO-BLASTING 0
SPOT HYDRO-BLASTING TO WA2.0 M² 8 M² 8 M² 8 M² 8
SPOT HYDRO-BLASTING TO WA1.0 M² 7 M² 7 M² 7 M² 7
DD 49 TREATMENT AREA (MINIMUM CHARGER 30% OF TOTAL AREA)
LPFW WASHING / LPFW HOSE DOWN BEFOR APPLY 1ST COAT M² 0.36 M² 0.36 M² 0.36 M² 0.36
NOTE:
1) ALL PAINT WITH OWNER'S SUPPLY
2) EMPTY PAINT DRUMS TO DISPOSAL PC 2 PC 2 PC 2 PC 2
3) HARD SCRAPING & EDGE REPAIR PAINT WITH O.S M² 5 M² 5 M² 5 M² 5
4) PROTECTION OF ACCOM. WINDOWNS/ LIGHTING DURING PAINTING PC 20 PC 20 PC 20 PC 20
MECHANICAL POWER TOOLING TO DERUST WINDOW FRAME AND
5) TOUCH PAINTED PC 25 PC 25 PC 25 PC 25

6) LOGO ON FUNNEL BOTH SIDE


BOTH LOGO TO BE REPAINT WITH O.S STENCIL PLATE BOTH 650 1 650 BOTH 650 1 650 BOTH 650 1 650 BOTH 650 1 650
7) TOWER STAGING ON DECK M³ 2.5 200 500 M³ 2 200 400 M³ 2.5 200 500 M³ 2.5 200 500
NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA
BOTTOM PLUGS,PLS REFER TO ABOVE ITEM: DD 35
BRIDGE ALARM IN FORE PEAK TESTING AND PUMPROOM BILGE - NO
ALARM ON BRIDGE
LAY OUT CALBE WITH O/S M 8 M 8 M 8 M 8
SENSOR & SENSOR HOLDER TO BE INSTALLED WITH O.S PC 80 1 80 PC 80 1 80 PC 80 1 80 PC 80 1 80
NEW ANGLE BAR SUPPORT FOR SENSOR HOLDER SET 50 1 50 SET 50 1 50 SET 50 1 50 SET 50 1 50
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
VAPOUR MONITORING SYSTEM
VAPOUR MONITORING SYSTEM ANNUAL CALIBRCATION & RENEWAL OF
O2 SENSOR WITH O.S BY SHIPYARD VIKING ENGINEERS , IF REUIRED SYSTEM 1200 1 1200 SYSTEM 1200 1 1200 SYSTEM 1200 1 1200 SYSTEM 1200 1 1200

WEATHER TIGHT DOORS--Assume 6 doors jobs


PAINT STORE WEATHER THIGHT DOORS
WATER TIGHT DOOR TO BE REMOVED. REFIT FOR REPAIR WORK PC 54 6 324 PC 120 6 720 PC 150 6 900 PC 150 6 900
PACKING CHANNEL INNER / OUTER FLAT BAR TO BE RENEWED, IF
REQIRED M.PC 30 10 300 M.PC 20 10 200 M.PC 30 10 300 M.PC 8 10 80

REPLACE RUUBER PACKING REMOVED AND INSTALLED NEW PACKING


WITH O.S DOOR 40 6 240 DOOR 25 6 150 DOOR 30 6 180 DOOR 25 6 150

COAMMING EDGE TO BE BUILD UP, IF REQIRED M.PC 30 6 180 M.PC 20 6 120 M.PC 30 6 180 M.PC 30 6 180
W.T DOOR RAIN GUARD TO BE CROPED AND RENEWED PC 50 6 300 PC 50 6 300 PC 50 6 300 PC 50 6 300
DD 50 DERUSTING AND PAINTING OF HEATING COILS ON DECK
DERUSTING AND APPLY PAINT WITH O.S IWO HEATING COILS ON DECK LOCATIO
FOR EACH TANK STATION 350 5 1750 LOCATION 350 5 1750 LOCATION 350 5 1750 LOCATION 350 5 1750
N
NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA
LOCKERS FOR CARGO AND BUNKER SAMPLE.
ANGLE BAR ASSUME L50X50 5MM FOR NEW SHELVES M 30 20 600 M 30 20 600 M 30 20 600 M 30 20 600
DD 51 NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA
DERUSTING AND PAINTING OF ALL BUNKER SAVEALL
DERUSTING AND APPLY PAINT WITH O.S IWO BUNKER SAVE ALL FOR LOCATIO
DD 52 EACH TANK STATION 350 6 2100 LOCATION 350 6 2100 LOCATION 350 6 2100 LOCATION 350 6 2100
N
NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA
RENEWAL OF HULL ANODES
HULL ANODES TO BE RENEWED WITH O/S PC 15 15 225 PC 12 15 180 PC 20 15 300 PC 25 15 375
CHERRY PICKER / LIFTABLE PLATFORM SET.HR 36 48 1728 SET.HR 24 48 1152 SET.HR 40 48 1920 SET.HR 32 48 1536
NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA--Anode supply
cost 2000 2000 2000 2000

VARIOUS DECK STRUCTURE


DD 53 1 FWD MAST LADDER TO BE RENEWED
LADDER SIDE VERTICAL FLAT BAR FB50X8MM M.PC 30 4 120 M.PC 30 4 120 M.PC 30 4 120 M.PC 180 4 720
SQB ASSUME 22X22X350MM PC 25 6 150 PC 25 6 150 PC 25 6 150 PC 15 6 90
DD 54 2 PORT MANIFOLD LADDER SUPPORT
HAND RAIL PIPE VERTICAL SUPPROT TO BE RENEWED M.PC 30 4 120 M.PC 30 4 120 M.PC 30 4 120 M.PC 15 4 60
LADDER STEP TO BE RENEWED IF REQUIRED PC 60 5 300 PC 60 5 300 PC 60 5 300 PC 30 5 150
DD 55 3 PORT CRANE SAFETY DOOR.
DOOR HINGE WITH SHORT PIPE RENEWAL SET 120 2 240 SET 120 2 240 SET 120 2 240 SET 120 2 240
4 PORT SIDE L/BOAT SYMBOL PLATE RENEWAL PC 30 1 30 PC 30 1 30 PC 30 1 30 PC 30 1 30
DD 56 5 STBD SIDE ROPE SUPPORT TO CHANGE
NO DIMENSION, CHECK ON SPOT m 30 4.7 141 m 30 4.7 141 m 30 4.7 141 m 30 4.7 141
6 DECK SEAL ENTIRE HEATING COIL TO RENEW
NO DIMENSION, CHECK ON SPOT m 25 10 250 m 25 10 250 m 25 10 250 m 25 10 250
DD 58 7 SUPPORT FOR SWITCH PAINT LKR.
SWITH BOX REMOVE,REFIT IF REQUIRED PC 27 1 27 PC 27 1 27 PC 27 1 27 PC 27 1 27
SUPPORT BASE SUPPORT TO BE RENEWED PC 30 2 60 PC 30 2 60 PC 30 2 60 PC 30 2 60
8 FWD SOUNDING PIPE TO CROP AND RENEW
SOUNDING PIPE THREAD TYPE ON DECK FOR WBT TO BE CROPED AND
RENWED ASSUME DIA40~50MM PC 120 11 1320 PC 80 11 880 PC 120 11 1320 PC 80 11 880

NEW CAP FABRIAITON PC 80 2 160 PC 80 2 160 PC 80 2 160 PC 80 2 160


9 MAST RISER VALVE TO OPEN OVERHAUL
NO DIMENSION, PLS REFER TO YARD TARIFF pc 341 1 341 pc 120 1 120 pc 240 1 240 pc 240 1 240
10 MANY 'U' WASTED BOLT TO BE RENWED (NO DIMENSION) pc 45 160 7200 pc 35 160 5600 pc 45 160 7200 pc 45 160 7200
11 SOUNDING PIPE TO CROP AND RENEW
SOUNDING PIPE THREAD TYPE ON DECK FOR WBT TO BE CROPED AND
RENWED ASSUME DIA40~50MM PC 120 1 120 PC 120 1 120 PC 120 1 120 PC 120 1 120

NEW CAP FABRIAITON PC 80 2 160 PC 80 2 160 PC 80 2 160 PC 80 2 160


12 PILOT ACCESS STANCTION TO RENEW, NO DIMENSION, CHECK ON SPOT pc 40 8 320 pc 40 8 320 pc 40 8 320 pc 80 8 640
ENTIRE ETA AFT BOX TO CROP AND CHANGE, NO DIMENSION, CHECK
13 ON SPOT pc 1000 1 1000 pc 800 1 800 pc 1200 1 1200 pc 1200 1 1200

PORT SIDE ACCO. DRAIN TO CROP CHANGE. NO DIMENSION, CHECK


14 ON SPOT pc.m 40 6 240 pc.m 40 6 240 pc.m 40 6 240 pc.m 40 6 240

15 "U' BOLT TO CHANGE AT VARIOUS PLACES ON PIPE. (NO DIMENSION) INCH.PC 3 10 30 INCH.PC 3 10 30 INCH.PC 3 10 30 INCH.PC 3 10 30
16 PORT SIDE EMGY STOP BRACKET
BOX REMOVE,REFIT IF REQUIRED PC 27 1 27 PC 27 1 27 PC 27 1 27 PC 200 1 200
SUPPORT BASE SUPPORT TO BE RENEWED PC 30 4 120 PC 30 4 120 PC 30 4 120 PC 30 4 120
17 STBD MANIFOLD DRAIN TO CROP AND RENEW
STBD MANIFOLD DRAIN PIPE TO BE RENEWED LOCATION 50 1 50 LOCATION 50 1 50 LOCATION 50 1 50 LOCATION 150 1 150
18 STBD PILOT ACCES STANCTION
VERTICAL STANCHION SOCK TO BE RENEWED PC 40 2 80 PC 40 2 80 PC 40 2 80 PC 80 2 160
19 ENTIRE DRAIN PIPE FROM DECK TO SLOP RENEW
NO DIMENSION, PLS REFER TO YARD TARIFF m 30 6 180 m 30 6 180 m 30 6 180 m 30 6 180
20 O2 ROOM HINGES TO RENEW
O2 ROOM DOOR HINGE RENEWAL SET 50 3 150 SET 50 3 150 SET 80 3 240 SET 150 3 450
ACCO. DRAIN CLOGGED TO CLEAR. PIPES TO BE UNCHOCKED ASSUME
21 80MM PC 80 1 80 PC 80 1 80 PC 80 1 80 PC 80 1 80

SOUNDING PIPE THREAD TYPE ON DECK FOR WBT TO BE CROPED AND


22 RENWED ASSUME DIA40~50MM PC 120 PC 120 PC 120 PC 120

NEW CAP FABRIAITON PC 80 PC 80 PC 80 PC 80


23 CRANE SWITCH BOX N BRACKET TO RENEW
BOX REMOVE,REFIT IF REQUIRED PC 350 1 350 PC 300 1 300 PC 300 1 300 PC 550 1 550
SUPPORT BASE SUPPORT TO BE RENEWED PC 30 2 60 PC 30 2 60 PC 30 2 60 PC 30 2 60
24 NEAR 6S WBT BENT RAILING TO STRAIGHTNE
VERTICAL RAIL SUPPORT BAR FB50X1020MMX10MM PC 50 1 50 PC 50 1 50 PC 50 1 50 PC 60 1 60
RAIL
HAND RAILS PIPE DIA34MM .L≤1000MM M.PC 25 2 50 M.PC 25 2 50 M.PC 25 2 50 M.PC 25 2 50
HAND GRIPS, ROUND BAR DIA16MM .L≤1000MM M.PC 25 2 50 M.PC 25 2 50 M.PC 25 2 50 M.PC 25 2 50
ENTIRE DRAIN PIPE FROM DECK TO SLOP RENEW, NO DIMENSION,
25 CHECK ON SPOT

26 C2H2 ROOM HINGES TO RENEW


C2H2 ROOM DOOR HINGE RENEWAL SET 50 4 200 SET 50 4 200 SET 50 4 200 SET 85 4 340
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
FABRICATION OF SAFETY CHAIN SECURING EYE
SAFERY CHAINB SECURING EYE TO BE INSTALLED PC 25 4 100 PC 25 4 100 PC 25 4 100 PC 30 4 120
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
MAINTENANCE OF SUPER STRUCTURE
1) HPFW WASHING (250-300 BAR) M² 0.54 M² 0.54 M² 0.54 M² 0.54

CURRENCY: USD 7 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
2) DEGREASING BY SOLVENT CLEANING SURFACE FROM OIL M² 4 M² 4 M² 4 M² 4
SPOT RUST POINT TO BE TREATED WITH DISC SANDING / POWER
3) TOOLING M² 12 M² 12 M² 12 M² 12

4) T1ST /U OF A/C,DFT OF 150 MIC M².COAT 0.6 M².COAT 0.6 M².COAT 0.6 M².COAT 0.6
5) FINAL COAT,DFT UP TO 150MIC WITH O.S M².COAT 0.6 M².COAT 0.6 M².COAT 0.6 M².COAT 0.6
6) HYDRO-BLASTING
SPOT HYDRO-BLASTING TO WA2.0 M² 8 M² 8 M² 8 M² 8
SPOT HYDRO-BLASTING TO WA1.0 M² 7 M² 7 M² 7 M² 7
TREATMENT AREA (MINIMUM CHARGER 30% OF TOTAL AREA)
LPFW WASHING / LPFW HOSE DOWN BEFOR APPLY 1ST COAT M² 0.36 M² 0.36 M² 0.36 M² 0.36
DD 59 NOTE:
1) ALL PAINT WITH OWNER'S SUPPLY
2) EMPTY PAINT DRUMS TO DISPOSAL PC 2 PC 2 PC 2 PC 2
DD 60 3) HARD SCRAPING & EDGE REPAIR PAINT WITH O.S M² 5 M² 5 M² 5 M² 5
4) PROTECTION OF ACCOM. WINDOWNS/ LIGHTING DURING PAINTING PC 20 PC 20 PC 20 PC 20
MECHANICAL POWER TOOLING TO DERUST WINDOW FRAME AND
5) TOUCH PAINTED PC 25 PC 25 PC 25 PC 25

6) DECK FLOOR PROTECTION DURING PAINT WORK


7) TOWER STAGING ON DECK M³ 2.5 M³ 2.5 M³ 2.5 M³ 2.5
NOTE:ANY OTHER REPAIR AND ACCESSORY TO BE EXTRA
STRUCTURAL RENEWAL ON MONKEY ISLAND.
CROP & RENEW WASTED & HOLED SECTION OF MAIN VHF RADIO DSC
1 ANTENNA.

NO DIMENSION, CHECK ON SPOT


2 CROP & RENEW WASTED & HOLED SECTION OF AEIRAL AM ANTENNA.
NO DIMENSION, CHECK ON SPOT
3 GPS ANTENNA FOR AIS SUPPORT PIPE TO BE RENEWED.
NO DIMENSION, CHECK ON SPOT
4 CROP & RENEW WASTED SECTION OF NERA ANTENNA.
NO DIMENSION, CHECK ON SPOT
5 DGPS RECEIVED ANTENNA NO.2 SUPPORT PIPE TO BE RENEWED.
NO DIMENSION, CHECK ON SPOT
6 FBB ANTENNA SUPPORT BRACKETS TO BE RENEWED.
NO DIMENSION, CHECK ON SPOT
CROP & RENEW WASTED COVER PLATES SECTION OF RADAR MAST
7 PLATFORM

DD 61 NO DIMENSION, CHECK ON SPOT 4000 4000 4000 4000


8 VARIOUS SUPPORTS FOR LIGHTS ON CHRISTMAS TREE TO BE
RENEWED
NO DIMENSION, CHECK ON SPOT
SUBTOTAL 350,815 323,964 352,597 380,256

******END OF THE DECK SECTION QUOTATION******

CURRENCY: USD 8 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

IMCY SHIPYARD HAUFENG SHIPYARD XINYA SHIPYARD COSCO SHIPYARD


ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT
# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
MT "PHOENIX I "
IMO No.:9236248
CRUDE OIL TANKER / YEAR OF BUILD 2002-04-29, CLASS: LR
LOA / BM / DM=248 / 43.03 / 21.0 M
GRT / NET / DWT=59,693 / 31,164 / 105,851 MT

E MAIN ENGINE
E001 MAIN ENGINE( HSD MAN B&W 5S70)
901 M/E CYLINDER COVER
M/E CYLINDER COVER TO BE DISMANTLED OTHER ACCESSARY PARTS
AND SHIFT TO WORKSHOP,CLEANED OF COMBUSTION CHAMBER UNIT 485 5 2425 UNIT 400 5 2000 UNIT 450 5 2250 UNIT 520 5 2600
SURFACE, HYDRAULIC TESTED AND RETURNED
FIRE SURFACE OF M/E CYLINDER COVER TO BE EXAMINED BY DYE-
UNIT 150 5 750 UNIT 100 5 500 UNIT 100 5 500 UNIT 100 5 500
PENETRATION TEST.
WATER COOLING JACKET TO BE OVERHAULED WITH O/S SEAL RINGS PC 120 5 600 PC 100 5 500 PC 120 5 600 PC 120 5 600
* OTHER ACCESSOR WORK
REMOVE,OVERHAUL AND REFIT OF AIR STARTING VALVE PC 45 5 225 PC 40 5 200 PC 45 5 225 PC 45 5 225
REMOVE,OVERHAUL AND REFIT OF SAFETY V/VS PC 45 5 225 PC 40 5 200 PC 45 5 225 PC 45 5 225
REMOVE,REFIT OF FO INJECTOR PC 80 10 800 PC 50 10 500 PC 80 10 800 PC 80 10 800
REMOVE,OVERHAUL AND REFIT OF INDICATOR V/VS PC 30 5 150 PC 30 5 150 PC 30 5 150 PC 30 5 150
FO INJECTOR / AIR STARTING VALVE POCKET CLEANING & DYE CHECK
POCKET 120 10 1200 POCKET 100 10 1000 POCKET 95 10 950 POCKET 95 10 950
INSPECTION BEFORE REPAIR
CYLINDER HEAD O-RING SEATING AREA WORN OUT AREAS TO BE
1000 1000 1000 1000
REPAIRED, CHECK ON SPOT
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA
903 M/E CYLINDER LINER
M/E CYLINDER LINER CLEANING AND CALIBRATION UNIT 306 5 1530 UNIT 240 5 1200 UNIT 280 5 1400 UNIT 328 5 1640
M/E CYLINDER LINER TO BE DRAWN
OUT,CLEANED,INSPECTED,HYDRAULIC TESTED AND REFITTED WITH UNIT 680 3 2040 UNIT 486 3 1458 UNIT 680 3 2040 UNIT 350 3 1050
SHIP'S SEAL RING.
CYLINDER LINNER HONING, CASE BY CASE 240 5 1200 240 5 1200 240 5 1200 240 5 1200
ALL LUBRICATING PASSAGES TO CHECK / CLEAN AND NON RETURN
VALVE CHECK
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA--TIMING CHECKED 4500 4500 4500 4500

902 M/E PISTON


M/E PISTON TO BEM/E PISTON TO BE DRAWN OUT, TRANSPORTED TO
WORKSHOP,DISASSEMBLED,CLEANED,ASSEMBLED,HYDRAULIC TESTED UNIT 724 5 3620 UNIT 600 5 3000 UNIT 650 5 3250 UNIT 776 5 3880
AND RETURNED.
FIRE SURFACE OF M/E PISTON TO BE EXAMINED BY DYE-PENETRATION
UNIT 150 0 0 UNIT 150 0 0 UNIT 150 0 0 UNIT 150 0 0
TEST.
M/E PISTON RING TO BE RENEWED WITH SHIP'S SPARES. UNIT 175 5 875 UNIT 230 5 1150 UNIT 234 5 1170 UNIT 188 5 940

902 M/E PISTON ROD STUFFING BOX TO BE OVERHAULED WITH SHIP'S


UNIT 120 5 600 UNIT 156 5 780 UNIT 156 5 780 UNIT 128 5 640
.5.4 SPARES.

OTHER ACCESSOR WORK


CRANK CASE SPACE TO BE CLEANING UNIT 180 5 900 UNIT 120 5 600 UNIT 150 5 750 UNIT 150 5 750
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA

902 EXHAUST VALVE TO BE DISCONNECT FROM CYLINDER COVER AND


SET 450 5 2250 SET 260 5 1300 SET 434 5 2170 SET 220 5 1100
.5.5 OVERAHULED WITH O.S

NOTE:ANY OTHER ACCESSORY WORK AND SPARE SUPPLY TO BE EXTRA.


E002 MAIN ENGINE ALL UNITS FUEL PUMPS OVERHAUL
MAIN ENGINE FUEL PUMP UNITS TO BE OVERHAULED WITH O/S UNIT 1260 5 6300 UNIT 850 5 4250 UNIT 905 5 4525 UNIT 976 5 4880
M/E FUEL OIL PUMP TIMING TO BE CHECKED UNIT 180 5 900 UNIT 250 5 1250 UNIT 487 5 2435 UNIT 445 5 2225
ROLLER GUIDE TO BE TAKE OUT CLEANING / DYE CHCK INSPECITON, IF
NECESSARY UNIT 350 5 1750 UNIT 110 5 550 UNIT 193 5 965 UNIT 803 5 4015

NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA


E003 MAIN ENGINE ALL UNITS REVERSING CYLINDERS OVERHAUL
REVERSING CYLINDERS TO OVERHAUL AND REAPLCE WITH NEW
PC 260 5 1300 PC 350 5 1750 PC 650 5 3250 PC 550 5 2750
SEALING RINGS WITH O.S
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA
E004 MAIN ENGINE CAM SHAFT CHAIN TENSION CHECK
MAIN ENGINE CHAIN TENSION TO MESURED AND RECOARD TIME 650 1 650 TIME 650 1 650 TIME 750 1 750 TIME 2500 1 2500
SIDE DOOR TO BE OPENED FOR CAM SHAFT CASE INSPECTION PC 27 5 135 PC 27 5 135 PC 27 5 135 PC 27 5 135
BEARING OPEN/CLOSED FOR INSPECTION UNIT 220 UNIT 220 UNIT 220 UNIT 220
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA
E005 MAIN ENGINE MANOEUVERING SYSTEM 5-YEARLY OVERHAUL
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA--Assume service engineer charges & overhauling kits cost 18000 18000 18000 18000

E006 ME BEARINGS
1) CROSSHEAD PIN & BEARINGS
M/E CROSS HEAD BEARING TO BE OPENED,CLEANED,FOR INSPECITON
INSITU AND CLOSED. UNIT 210 5 1050 UNIT 324 5 1620 UNIT 276 5 1380 UNIT 220 5 1100

2) CRANK PIN & BEARINGS


M/E CRANKPIN BEARING TO BE OPENED,CLEANED,FOR INSPECITON
INSITU AND CLOSED. UNIT 140 5 700 UNIT 324 5 1620 UNIT 124 5 620 UNIT 150 5 750

3) MAIN JOURNAL & BEARINGS


M/E MAIN BEARING NO.2 ~5 TO BE OPENED,CLEANED, FOR INSPECITON
INSITU AND CLOSED.( END BEARING EXTRA) UNIT 243 4 972 UNIT 324 4 1296 UNIT 324 4 1296 UNIT 260 4 1040

4) THRUST BEARINGS.
M/E THRUST BEARING ONE FWD AND AFT COLLAR PAD EACH TO BE
SET 800 1 800 SET 750 1 750 SET 750 1 750 SET 500 1 500
OPENED, CLEANED, INSPECTED, MEASURED AND CLOSED
NOTE:ANY OTHER REPAIR, BEARING REPLACEMENT OR ACCESSORY
WORK TO BE EXTRA
E007 ME CRANKSHAFT DEFLECTION
M/E CRANKSHAFT DEFLECTION TO BE MEASURED. TIME 180 2 360 TIME 222 2 444 TIME 222 2 444 TIME 180 2 360
M/E CRANKCASE DOOR TO BE OPENED AND CLOSED DOOR 27 0 0 DOOR 27 0 0 DOOR 60 0 0 DOOR 60 0 0
E008 MAIN ENGINE VIBRATION DAMPER & MOMENT COMPENSATOR CHECK
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA
E009 MAIN ENGINE TIE ROD & HOLDING DOWN BOLTS TIGHTNESS CHECK
MAIN ENGINE TIE ROD & HOLDING DOWN BOLTS TO BE RETIGHTENED LOT 3200 1 3200 LOT 2100 1 2100 LOT 1500 1 1500 LOT 1600 1 1600
E010 MAIN ENGINE AUX BLOWER # 1 & 2 TO OVERHAUL
PLS REFER TO ITEM: EL012
ALL UNIT CRANKCASE RELIEF DOORS AND CHAIN CASE RELIEF DOOR
E011
FUNCTIONAL TEST
ME CRANCASE RELIEF VALVES OVERHAUL, CLEANED AND PRESSURE
TEST, IF NECESSARY PC 350 5 1750 PC 250 5 1250 PC 150 5 750 PC 550 5 2750

E012 MAIN ENGINE TOP BRACING


CYLINDER OF HYDRAULIC TOP BRACING TO BE OVERHAULED WITH O.S
SEAL KIT SET 800 4 3200 SET 450 4 1800 SET 1300 4 5200 SET 1200 4 4800

NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA


E013 NO# 1, 2 & 3 AUXILIARY ENGINE GOVERNORS TO OVERHAUL
A/E GOVERNORS UG-8 TO BE OVERHAULED WITH O/S SPARE KIT SET 1300 3 3900 SET 1900 3 5700 SET 1690 3 5070 SET 1181 3 3543
NOTE:ANY OTHER REPAIR OR ACSSORY WORK TO BE EXTRA--SPARE
5000 5000 5000 5000
PARTS KITS
E014 AUX ENGINE 1,2&3 LUB OIL COOLER (PLATE TYPE COOLER)
ALL COOLER PLATES TO BE REMOVED,AND SHIFT WORKSHOP FOR
CHEMICAL CLEANING AND REPALCE ALL GAKSET WITH O.S,AND
PLATE 30 0 0 PLATE 30 PLATE 30 PLATE 30
PRESSURE TEST (NDT TEST AND END PLATE RECONDAITON TO BE
EXTRA)--BY SHIPSTAFF.
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E015 AUX ENGINE 1,2&3 AIR COOLER
AE 1,3 CHARGE AIR COOLERS TO BE REMOVED,ULTRASONIC CLEANED,
SET 649 3 1947 SET 650 3 1950 SET 1000 3 3000 SET 680 3 2040
PRESSURE TESTED AND REFITTED.
END COVER TO BE DERUSTED AND PAINTED WITH O/S. PC 50 3 150 PC 40 3 120 PC 100 3 300 PC 100 3 300
END COVER GASKET SUPPLLY PC 45 6 270 PC 45 6 270 PC 45 6 270 PC 45 6 270
ANODES TO BE RENEWED WITH Y/S. PC 25 12 300 PC 25 12 300 PC 25 12 300 PC 25 12 300
LEAKING TUBES TO BE PLUGGED. PC 20 10 200 PC 20 10 200 PC 20 10 200 PC 20 10 200
NOTE: ANY OTHER REPAIR/RENEWAL TO BE EXTRA.
E016
ME SCAVENGE SPACE SAFETY VALVE TO BE OVERHAULED, CLEANED
AND PRESSURE TEST, IF NECESSARY PC 350 1 350 PC 150 1 150 PC 150 1 150 PC 180 1 180

E017 MAIN ENGINE TURBOCHARGERS COMPLETE OVERHAUL


M/E TURBOCHARGER OVERHAUL AS FOLLOW JOB WILL CARRRY OUT BY
KEMKLEN WORKSHOP IN SHIPYARD (TPL 85-B11)
REMOVAL & REASSEMBLY OF COMPLETE CARTRIDGE GROUP (ON SET 8660 1 8660 SET 6500 1 6500 SET 9076 1 9076 SET 5816 1 5816
BOARD)
IMPELLER WITH COMPRESSOR WHEEL DYNAMIC BALANCE TEST SET 4660 1 4660 SET 2500 1 2500 SET 3361 1 3361 SET 3361 1 3361
SAND BLASTING NOZZLE RING OR TURBINE BLADE PC 320 2 640 PC 1200 2 2400 PC 320 2 640 PC 1163 2 2326

CURRENCY: USD 9 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
MECHANICAL CLEANING AND MEASURING OF COVER RING / TURBINE
DIFFUSER PC 280 1 280 PC 500 1 500 PC 420 1 420 PC 537 1 537
DYE CHECK THE TURBINE BLADES / NOZZLE RING /COMPRESSOR PC 320 3 960 PC 350 3 1050 PC 320 3 960 PC 537 3 1611
WHEEL
EXTRACT& REFIT THE TURBIN DIFFUSER, REMOVE TO W/S FOR
CLEANING AND MEASURING, IF REQUIRED PC 1296 1 1296 PC 1296 1 1296 PC 1296 1 1296 PC 1296 1 1296

SILENCER CHEMICAL CLEANING, IF REQUIRED PC 1460 1 1460 PC 1500 1 1500 PC 1450 1 1450 PC 1619 1 1619
ALL SPARES SUPPLY BY OWNER
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E018 MAIN ENGINE AIR COOLER NO.1
M/E AIR COOLER CHEMICAL CLEANING AND PRESSURE TESTING SET 1680 1 1680 SET 1800 1 1800 SET 1800 1 1800 SET 1800 1 1800
END COVER PAINTED 2COATS. PC 50 2 100 PC 60 2 120 PC 100 2 200 PC 65 2 130
ZINC ANODES TO BE RENEWED WITH Y/S PC 20 6 120 PC 12 6 72 PC 20 6 120 PC 20 6 120
PLUGING OF LEAKING TUBE PC 25 5 125 PC 25 5 125 PC 25 5 125 PC 25 5 125
WATER MIST CATCHER,TO BE REMOVED & CLEANED SET 450 1 450 SET 250 1 250 SET 250 1 250 SET 300 1 300
AIR COOLING CASING DERUSTING / PAINT WITH O.S SET 350 1 350 SET 350 1 350 SET 350 1 350 SET 350 1 350
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E019 AUX.ENGINE OVERHAUL #2
AUXILIARY ENGINES (6L23) TO BE OVERHUALED WITH O/S SPARE
1 INCLUDE CYLINDER COVER/ PISTION/ CONNECT ROD/CYLINDER LINER. SET 4800 2 9600 SET 4500 2 9000 SET 5800 2 11600 SET 4500 2 9000
CLEANING AND CALIBRATION
2 THE FUEL VALVES OVERHUALED WITH O.S PC 180 6 1080 PC 180 6 1080 PC 180 6 1080 PC 180 6 1080
3 THE FUEL INJECTION PUMP OVERHUALED WITH O.S, IF REQUIRED PC 350 6 2100 PC 350 6 2100 PC 418 6 2508 PC 400 6 2400
4 MAIN BEARING TO BE OPEN.CLSOE WITH O.S SPARE, IF REQUIRED SET 180 5 900 SET 180 5 900 SET 180 5 900 SET 180 5 900
CYLINDER COVER OR PISTON BURINING SURFACE TO BE DYE CHECKED
5 PC 135 0 0 PC 135 0 0 PC 135 0 0 PC 135 0 0
INSPECTION
CAM SHAFT BEARING CLERANCE TO BE CHECKED AND RENEWED WITH
6 UNIT 80 6 480 UNIT 80 6 480 UNIT 80 6 480 UNIT 130 6 780
O.S
7 CRANK CASE CLEANING SET 350 0 0 SET 350 0 0 SET 350 0 0 SET 350 0 0
CRANKSHAFT DEFLECTIONS TO BE TAKEN AND RECORDED BEFORE
8 SET.TIME 220 2 440 SET.TIME 220 2 440 SET.TIME 220 2 440 SET.TIME 220 2 440
START OF OVERHAUL AND AGAIN AFTER COMPLETETION OF OVERHAUL
NOTE:ANY OTHER REPAIR OR ACCESORY WORK TO BE EXTRA
E020 ME STARTING AIR VALVE AND DISTRIBUTOR TO OVERHAUL
ME STARTING AIR VALVE TO BE OVERHAULED WITH O.S SET 850 1 850 SET 1600 1 1600 SET 1300 1 1300 SET 1800 1 1800
ME STARTING AIR DISTRIBUTOR TO BE OVEERHAUELD WITH O.S SET 1200 1 1200 SET 1500 1 1500 SET 1500 1 1500 SET 1650 1 1650
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E021 AUXILLIARY BOILER FD FAN OVERHAUL
PLS REFER TO ITEM:EL015
E022 MAIN ENGINE FRESH WATER COOLER CLEANING & PRESSURE TESTING
ALL COOLER PLATES TO BE REMOVED,AND SHIFT WORKSHOP FOR
CHEMICAL CLEANING AND REPALCE ALL GAKSET WITH O.S,AND
PLATE 30 0 3000 lumpsum 30 0 3000 lumpsum 30 0 3000 lumpsum 30 0 3000
PRESSURE TEST (NDT TEST AND END PLATE RECONDAITON TO BE
EXTRA)
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E023 MAIN ENGINE LUB OIL COOLER (PLATE TYPE COOLER)
ALL COOLER PLATES TO BE REMOVED,AND SHIFT WORKSHOP FOR
CHEMICAL CLEANING AND REPALCE ALL GAKSET WITH O.S,AND
PLATE 30 250 7500 lumpsum 30 85 2500 lumpsum 30 116 3480 lumpsum 39 116 4524
PRESSURE TEST (NDT TEST AND END PLATE RECONDAITON TO BE
EXTRA)
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E024 ATMOSPHERIC CONDENSOR
ATMOSPHERIC CONDENSER TO BE REMOVED TO W/S,CHEMICAL
CLEANED,PRESSURE TESTED SET 1680 1 1680 SET 850 1 850 SET 1800 1 1800 SET 680 1 680

YARD SUPPLY NEW END COVER GASKET PC 50 2 100 PC 40 2 80 PC 100 2 200 PC 45 2 90


CHOKED TUBES TO BE MADE THROUGH, PC 25 10 250 PC 20 10 200 PC 25 10 250 PC 25 10 250
DEMAGED TUBES (PLUGGED) TO BE RENEWED, PC 40 8 320 PC 20 8 160 PC 40 8 320 PC 40 8 320
ANODES TO BE RENEWED, PC 15 8 120 PC 15 8 120 PC 20 8 160 PC 20 8 160
YARD TO SUPPLY ABOVE ANODES, KG 8 16 128 KG 8 16 128 KG 8 16 128 KG 7.5 16 120
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
MAIN ENGINE FUEL OIL HEATER CLEANING & PRESSURE TESTING(2
E025
NOS),
HEATERS TO BE REMOVED TO WORKSHOP, CHEMICALLY CLEANED WITH
O/S GASKET AND REFITTED PC 749 2 1498 PC 750 2 1500 PC 950 2 1900 PC 780 2 1560

END COVER GASKET SUPPLY PC 20 4 80 PC 20 4 80 PC 100 4 400 PC 45 4 180


NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E026 HFO &LO PURIFIER (TUBE TYPE HEATER)
HEATERS TO BE REMOVED TO WORKSHOP, CHEMICALLY CLEANED WITH
O/S GASKET AND REFITTED PC 749 0 0 PC 749 0 0 PC 749 0 0 PC 749 0 0

END COVER GASKET SUPPLY PC 20 0 0 PC 20 0 0 PC 20 0 0 PC 20 0 0


NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E027 1 & 2 MAIN ENGINE LUB OIL PUMPS OVERHAUL
M/E LUBE OIL PUMP (TOM-250) TO BE OVERHAULED FOR INSPECTION,
AND REPLACE WASTED PARTS WITH O.S SET 1450 2 2900 SET 700 2 1400 SET 734 2 1468 SET 780 2 1560

IMPELLER BALANGE TEST / ALIGNMENT TIME 350 0 0 TIME 250 0 0 TIME 350 0 0 TIME 350 0 0
NOTE:ANY OTHER REPAIR OR ACSSORY WORK TO BE EXTRA.
AIR RESERVOIRS (MAIN AIR RESERVOIRS- 2 NOS, DECK AIR BOTTLE 1
E028
NO'S ,EMERGENCY AIR BOTTLE 1 NO'S.) CSM SURVEY
MAIN & EMERGENCY & DECK AIR RESERVOIRS INTERNAL TO BE
CLEANED AND COATED WITH CASTOR OIL WITH O/S--CSM SET 225 4 900 SET 300 4 1200 SET 450 4 1800 SET 350 4 1400

MANHOLE OPEN AND CLOSE WITH SHIP'S GASKET PC 54 4 216 PC 50 4 200 PC 54 4 216 PC 60 4 240
SAFETY VALVES TO BE REMOVED, TO WORKSHOP AND OVERHAULED
WITH O.S SPARES AND PRESSURE TESTED--CSM PC 176 4 704 PC 150 4 600 PC 280 4 1120 PC 156 4 624

NOTE:ANY OTHER REPAIR OR ACSSORY WORK TO BE EXTRA. 250 250 250 250
MAIN AIR COMPRESSOR AND TOP UP COMPRESSOR SAFETY VALVE TO
E029
PRESSURE TEST
SAFETY VALVES TO BE REMOVED, TO WORKSHOP AND OVERHAULED
WITH O.S SPARES AND PRESSURE TESTED PC 176 4 704 PC 150 4 600 PC 280 4 1120 PC 156 4 624

NOTE:ANY OTHER REPAIR OR ACSSORY WORK TO BE EXTRA. 250 250 250 250
VARIOUS TANKS IN ER & BUNKER TANKS TO CLEAN & HEATING COILS
E030
PRESSURE TEST -
THE FOLLOWING ENGINE ROOM TANKS TO BE CLEANED
1 DIRTY BILGEWATER HOLDING TANK CAPACITY - 19.0 M3 TANK 225 1 225 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
2 CLEAN BILGEWATER HOLDING TANK CAPACITY - 41.1 M3 TANK 225 1 225 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
3 FUEL OIL SLUDGE TANK CAPACITY - 23 M3 TANK 225 1 225 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
4 FUEL OIL OVERFLOW TANK CAPACITY - 27.4 M3 TANK 225 0 0 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
5 LO DRAIN TANK CAPACITY -2.4 M3 TANK 225 0 0 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
6 HFO SETTLING TANK NO.1 CAPACITY - 60.9 M³ M3 4.5 60.9 274.05 M3 4.5 60.9 274.05 M3 4.5 60.9 274.05 M3 4.8 60.9 292.32
7 HFO SERVICE TANK NO.1 CAPACITY - 60.9 M³ M3 4.5 60.9 274.05 M3 4.5 60.9 274.05 M3 4.5 60.9 274.05 M3 4.8 60.9 292.32
8 DO SERVICE TANK CAPACITY - 37.9 M3 TANK 225 0 0 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
9 M/E LO SETTLING TANK CAPACITY - 48.4 M3 M3 4.5 0 0 M3 4.5 48.4 217.8 M3 4.5 48.4 217.8 M3 4.8 48.4 232.32
10 M/E LO STORAGE TANK CAPACITY - 67.1 M3 M3 4.5 0 0 M3 4.5 67.1 301.95 M3 4.5 67.1 301.95 M3 4.8 67.1 322.08
11 A/E LO STORAGE TANK CAPACITY - 14.5 M3 TANK 225 0 0 TANK 225 1 225 TANK 225 1 225 TANK 240 1 240
12 M/E LO SUMP TANK CAPACITY - 34.7 M TANK 450 1 450 TANK 450 1 450 TANK 450 1 450 TANK 450 1 450
13 DIESEL OIL TANK CAPACITY (P) - 72 M3 M3 4.5 0 0 M3 4.5 72 324 M3 4.5 72 324 M3 4.8 72 345.6
14 DIESEL OIL TANK CAPACITY (S) - 99.3 M3 M3 4.5 0 0 M3 4.5 99.3 446.85 M3 4.5 99.3 446.85 M3 4.8 99.3 476.64
15 NO.1 FO BUNKER TANK (STBD) CAPACITY -1616.7 M3, IF REQUIRED M3 4.5 1616 7272 M3 4.5 1616 7272 M3 4.5 1616 7272 M3 4.8 1616 7756.8
16 NO.2 LSMGO BUNKER TANK (P) CAPACITY -752.2 M3 , IF REQUIRED M3 4.5 752 3384 M3 4.5 752 3384 M3 4.5 752 3384 M3 4.8 752 3609.6
17 NO. FO BUNKER TANK (PORT) CAPACITY -809.1 M3 , IF REQUIRED M3 4.5 809 3640.5 M3 4.5 809 3640.5 M3 4.5 809 3640.5 M3 4.8 809 3883.2
OTHER REPAIR WORK FOR YOUR INFORMATION
MANHOLE COVER TO BE OPENED AND CLOSED WITH O/S PACKING PC 27 15 405 PC 27 34 918 PC 30 34 1020 PC 30 34 1020
SUPPLY NEW PACKING PC 20 15 300 PC 20 34 680 PC 20 34 680 PC 20 34 680
OILRESIDUE / SLUDGE DISPOSAL TON 800 10 8000 TON 650 10 6500 TON 600 10 6000 TON 850 10 8500
BILGE WATER DISPOSAL TON 45 150 6750 TON 36 150 5400 TON 36 150 5400 TON 36 150 5400
PROTALBE PUMP CONNECTION/DISCONNECT LINE.TIM LINE.TIM
36 5 180 36 5 180 LINE.TIME 36 5 180 LINE.TIME 36 5 180
E E
GAS FREE INSPECTION VISIT.TK 36 30 1080 VISIT.TK 24 30 720 VISIT.TK 32 30 960 VISIT.TK 32 30 960
VENTILATION INSTALLATION SET.LIN
18 17 306 SET.LINE 16 17 272 SET.LINE 18 17 306 SET.LINE 18 17 306
E
VENTILATION POWER USAGE 3500
VENTILATION USAGE (8HOURS. -PER SET.DAY) SET.DAY 40 51 2040 SET.DAY 16 51 816 SET.DAY 28 51 1428 SET.DAY 50 51 2550
TEMPORARY LIGHTING ON BOARD. CON. / DISCON. PC 9 17 153 PC 9 17 153 PC 9 17 153 PC 9 17 153
TEMPORARY LIGHTING ON BOARD. USAGE PC.DAY 10 25 250 PC.DAY 10 51 510 PC.DAY 10 51 510 PC.DAY 10 51 510
MSA CERTIFICATE ISSUED IF REQUIED PC 1200 1 1200 PC 1200 1 1200 PC 1200 1 1200 PC 1200 1 1200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E031 ER FUNNEL FRAME ARRESTORS MESH TO RENEW
ARRESTORS FRAME TO BE RENEWED
(SMALL PIECE MINIMUM CHARGEA AS MS, 15KG, PER PC) KG 2.5 100 250 KG 2.5 100 250 KG 2.5 100 250 KG 2.5 100 250

STAINLESS STEEL MESH TO BE RENEWED WITH Y/S M² 60 5 300 pc 100 5 500 pc 120 5 600 pc 350 5 1750
E032 MAIN ENGINE AND AUX. ENGINE FLOW METER TO RENEW.
MAIN ENGINE AND AUX. ENGINE FLOW METER TO BE REMOVED TO YARD
WORKSHOP AND OVERHAULED, CLEANED, REPALCE WITH O.S,AND SET 650 0 0 SET 400 0 0 SET 600 0 0 SET 600 0 0
CALIBRATION
L.O. BUNKER MANIFOLD AND SLUDGE SHORE CONNECTION MANIFOLD
E033
PIPE LINE RENEWAL (MAIN DECK PENETRATION)

CURRENCY: USD 10 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
AUX. ENGINE SYSTEM OIL BUNKER MANIFOLD (PORT AND STBD).
1 NO DIMENSION, PLS REFER TO YARD TARIFF
MAIN ENGINE SYSTEM OIL BUNKER MANIFOLD (PORT AND STBD).
2 NO DIMENSION, PLS REFER TO YARD TARIFF
MAIN ENGINE CYL OIL BUNKER MANIFOLD ( PORT AND STBD).
3 NO DIMENSION, PLS REFER TO YARD TARIFF
ENGINE ROOM SLUDGE SHORE DISPOSAL MANIFOLD (PORT SIDE).
4 NO DIMENSION, PLS REFER TO YARD TARIFF
SEWAGE SHORE DISCHARGE MANIFOLD (STBD SIDE).
5 NO DIMENSION, PLS REFER TO YARD TARIFF

ABOVE PIPE LINE NEED TO BE PRESSURE TEST. LINE.TIME 350 7 2450 LINE.TIME 250 7 1750 LINE.TIME 350 7 2450 LINE.TIME 200 7 1400
PIPE LINE PASS THROUGH SAVE OIL TRAY AND THEN MAIN DECK (MAIN
DECK PENETRATION) TO ENGINE ROOM. NO DIMENSION, PLS REFER TO
YARD TARIFF
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E034 ER BILGE WELL CLEANING & PAINTING
THE FOLLOWING ENGINE ROOM BILGE WELL TO BE CLEANED, CHEMICAL
CLEANING, AND APPLY PAINT WITH O.S--SHIPSTAFF
FORWARD STBD BILGE WELL - CAPACITY: APPROX- 4. CU. TRS., PC 250 1 250 PC 300 1 300 PC 350 1 350 PC 300 1 300
FORWARD PORT BILGE WELL- CAPACITY : APPOX : 4 CU.MTRS, PC 250 1 250 PC 300 1 300 PC 350 1 350 PC 300 1 300
AFT BILGE WELL -CAPACITY: APPROX: 5.5 CU. MTRS. PC 250 1 250 PC 300 1 300 PC 350 1 350 PC 300 1 300
BILGE WATER DISPOSAL TON 45 5 225 TON 24 5 120 TON 32 5 160 TON 36 5 180
YARD PUMP CONN/DISCONN LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E035 ECR AIR CONDITION OVERHAULING.
ER AIR CONDITION SYSTEM CLEANING,FLUSHING AND PRESSURE
SET 650 1 650 SET 650 1 650 SET 850 1 850 SET 650 1 650
TESTING BY N2,VACUUM TEST AND REFILL WITH SHIP'S SPARE
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E036 ER PUMPS OVERHAULING.
THE FOLLOWING PUMPS TO BE OVERHAULED WITH O.S
1) MAIN COOL SEA WATER PUMP # 1& 2. (FBWV-250)
MAIN COOL SEA WATER PUMP TO BE REMOVED TO WORKSHOP AND
SET 810 2 1620 SET 1200 2 2400 SET 1200 2 2400 SET 1200 2 2400
OVERHAULED, CALIBRATED AND REPLACE WASTED PARTS WITH O.S
2) #1 AND #2 BILGE BALLAST / FIRE PUMP.
BALLAST PUMP, PLS REFER TO DD 05
FIRE PUMP.
FIRE PUMP TO BE REMOVED TO WORKSHOP AND OVERHAULED,
SET 675 2 1350 SET 1500 1 1500 SET 1500 1 1500 SET 1500 1 1500
CALIBRATED AND REPLACE WASTED PARTS WITH O.S
3) ENGINE ROOM BILGE PUMP. NO DETAILED, CHECK ON SPOT
4) MAIN ENGINE LUB OIL PUMP #1 AND #2.(TOM-250-2)
PLS REFER TO ABOVE ITEM E 027
5) DECK SEAL PUMP #1 AND #2. NO DETAILED, CHECK ON SPOT
6) SCRUBBER SEA WATER PUMP. NO DETAILED, CHECK ON SPOT
AUX. BOILER FEED WATER PUMP #1 AND #2. NO DETAILED, CHECK ON
7)
SPOT
EXHAUST BOILER FEED WATER PUMP #1 AND #2. NO DETAILED, CHECK
8)
ON SPOT
FUEL OIL PURIFIER FEED PUMP #1 AND #2. NO DETAILED, CHECK ON
9)
SPOT
10) LUB OIL PURIFIER FEED PUMP #1 AND #2. NO DETAILED, CHECK ON SPOT
11) EMERGENCY FIRE PUMP. NO DETAILED, CHECK ON SPOT
12) ATMOS.COND.COOL SW PUMP (FBV-125)
ATMOS.COND.COOL SW PUMP TO BE REMOVED TO WORKSHOP AND
SET 390 1 390 SET 500 1 500 SET 390 1 390 SET 390 1 390
OVERHAULED, CALIBRATED AND REPLACE WASTED PARTS WITH O.S
13) LOW TEM COOL .S.W PUMP 1,2 & 3 (FBV-200)
LOW TEM COOL .S.W PUMP TO BE REMOVED TO WORKSHOP AND
SET 540 3 1620 SET 540 3 1620 SET 540 3 1620 SET 540 3 1620
OVERHAULED, CALIBRATED AND REPLACE WASTED PARTS WITH O.S
14) SLUDGE PUMP ( AE1E100-ID)
SLUDGE PUMPTO BE REMOVED TO WORKSHOP AND OVERHAULED,
SET 450 0 0 SET 450 0 0 SET 450 0 0 SET 450 0 0
CALIBRATED AND REPLACE WASTED PARTS WITH O.S
15) HFO TRANSFER PUMP (ALG-65)
SLUDGE PUMPTO BE REMOVED TO WORKSHOP AND OVERHAULED,
SET 450 0 0 SET 450 0 0 SET 450 0 0 SET 450 0 0
CALIBRATED AND REPLACE WASTED PARTS WITH O.S
16) NO-1 & 2 BOILER WATER CIRC PUMP (BBH-50DMW)
SLUDGE PUMPTO BE REMOVED TO WORKSHOP AND OVERHAULED,
SET 450 2 900 SET 650 2 1300 SET 550 2 1100 SET 550 2 1100
CALIBRATED AND REPLACE WASTED PARTS WITH O.S
17) NO 1&2 EGE FEED W PUMP EB2H-32
SLUDGE PUMPTO BE REMOVED TO WORKSHOP AND OVERHAULED,
SET 450 2 900 SET 650 2 1300 SET 550 2 1100 SET 550 2 1100
CALIBRATED AND REPLACE WASTED PARTS WITH O.S
EL DRIVE MOTOR REMOVE,REFIT IF REQUIRED
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
E037 VARIOUS TANKS IN ER TO CLEAN & PRESENT FOR CSM SURVEY
PLS REFER TO ABOVE ITEM E030
E038 INCINERATOR CHAMBER REFRACTORY
INCINERATOR REFRACTORY REBUILT UP TO 50MM
(MIN. CHARGE AS 1M2 FOR EACH SMALL PATCH) M² 243 4 972 M² 200 4 800 M² 45 4 180 M² 200 4 800

HOOK BAR INSTALLAITON PC 15 30 450 PC 15 30 450 PC 15 30 450 PC 15 30 450


E039 Accomodation AIR CONDITION SYSTEM- COMPRESSOR OVERHAULING.
AC COMPRESSOR TO BE REMOVED AND TRANSPORT TO YARD WORK
1&2
SHOP FOR OVERHAULED AND DEFECTIVE PARTS TO BE RENWED WITH SET 2800 1 2800 SET 2800 1 2800 SET 850 1 850 SET 2000 1 2000
)
VESSEL SUPPLY SPARES.
3) AC CONDENSER TO BE CLEANED &PRESSURE TESTED . SET 649 0 0 SET 649 0 0 SET 649 0 0 SET 649 0 0
EVAPORATOR COIL NEED TO CHEMICAL CLEANING & PRESSURE
4) SET 450 1 450 SET 450 1 450 SET 450 1 450 SET 650 1 650
TESTED.
BOTH COMPRESSOR HP &LP PIPE LINE TO BE PRESSURE TESTED BY
5) LINE.TIME 650 0 0 LINE.TIME 650 0 0 LINE.TIME 650 0 0 LINE.TIME 650 0 0
NITROGEN GAS .
AFTER COMPLETION OF JOB, SYSTEM SHOULD BE PRESSURE TESTED
6) SYSTEM 1800 0 0 SYSTEM 1200 0 0 SYSTEM 1600 0 0 SYSTEM 1500 0 0
AND GAS TO BE CHARGE WITH O.S
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
E040 PROVISION PLANT
PROVISION PLANT SYSTEM NITROGEN PRESSURE TEST TO BE CARRIED
SYSTEM 1800 1 1800 SYSTEM 1200 1 1200 SYSTEM 1300 1 1300 SYSTEM 1500 1 1500
OUT.
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
E041 FUNNAL FLOOR PLATE RENEWAL.NO DIMENSION, CHECK ON SPOT 500 500 500 500
E042 ME GOVERNOR INSPECTION & OVERHAUL
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA 3500 3500 3500 3500

E043 CASCADE TANK CLEANING & PAINTING


CASCADE TANK TO BE CLEANED FOR INSPECITON TANK 300 1 300 TANK 300 1 300 TANK 300 1 300 TANK 300 1 300
E044 STERNTUBE SEAL REPLACEMENT AND INSPECTION
STERN TUBE OIL DRAIN OUT BY SHIP STAFF
TAIL SHAFT WEAR DOWN TO BE MEASURED TIME 150 2 300 TIME 144 2 288 TIME 150 2 300 TIME 150 2 300
ROPE GUARD TO BE REMOVED AND REFITTED PC 180 1 180 PC 200 1 200 PC 180 1 180 PC 180 1 180
TOWER STAGING IN DRY DOCK M³ 2 200 400 M³ 2 200 400 M³ 2 200 400 M³ 2.5 200 500
STERN TUBE SEAL AFT SEAL SEAL LIPS BONDING OR REPALCEMENT
STERN TUBE SEAL OIL TO BE DRAINED, AND DISPOSAL TIME 220 1 220 TIME 220 1 220 TIME 220 1 220 TIME 220 1 220
TO ASSISTANCE SERVICE ENGINER FOR SEAL LIPS BONDING OR
REPALCEMENT IN SITU, MAKER SERVICE ENGINNER BY OWNER UNIT 675 2 1350 UNIT 550 2 1100 UNIT 700 2 1400 UNIT 850 2 1700
ARRANGED, SPARES WITH O/S
STERN TUBE SEAL LEAK TESTED TIME 280 1 280 TIME 280 1 280 TIME 280 1 280 TIME 200 1 200
SEAL LINER DEFLECTION INSPECTION/ADJUSTMENT TIME 180 1 180 TIME 180 1 180 TIME 180 1 180 TIME 180 1 180
SECURING LASHING WIRE BY YARD TIME 180 1 180 TIME 180 1 180 TIME 180 1 180 TIME 180 1 180
REMOVE.REFIT AFT SEAL LINNER WITH SEAL CASING TO WORKSHOP SET 350 1 350 SET 350 1 350 SET 350 1 350 SET 350 1 350
LINER MACHINING, IF NECESSARY PC 450 1 450 PC 500 1 500 PC 550 1 550 PC 550 1 550
SEAL CASING LEAKING TEST IN WROKSHOP SET.TIME 180 0 0 SET.TIME 180 0 0 SET.TIME 180 0 0 SET.TIME 180 0 0
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E045 AUXILLIARY BOILER MOUNTINGS OVERHAUL & CSM SURVEY
AUX. BOILER TO BE DRAINED BY SHIP'S STAFF
MANHOLE & ACCESS HOLE AND CLEANING
MANHOLE DOOR & BURNER REMOVE,REFIT FOR ACCESS
MANHOLES/HAND HOLES TO BE OPENED AND CLOSED. PC 54 2 108 PC 80 2 160 PC 54 2 108 PC 54 2 108
NEW PACKING SUPPLY PC 30 2 60 PC 30 2 60 PC 30 2 60 PC 30 2 60
GAS SIDE AUX BOILER TO BE HP FRESH WATER CLEANED. SET 2610 1 2610 SET 1500 1 1500 SET 950 1 950 SET 1400 1 1400
WATER SIDE OF AUX BOILER TO BE CLEANED BY HPFW SET 720 1 720 SET 1500 1 1500 SET 950 1 950 SET 1400 1 1400
WASHING SOOT WATER DISPOSAL TON 90 5 450 TON 36 2 72 TON 65 2 130 TON 90 2 180
PUMP LINE CON./DISCON. LINE.TIM LINE.TIM
36 2 72 36 1 36 LINE.TIME 36 1 36 LINE.TIME 36 1 36
E E
AUXILIARY BOILER FURNACE REFRACTORY TO BE RENEWED M² 243 5 1215 M² 180 5 900 M² 243 5 1215 M² 540 5 2700
SAFETY VALVES TO BE REMOVED, TO WORKSHOP AND OVERHAULED
PC 176 2 352 PC 150 2 300 PC 280 2 560 PC 156 2 312
WITH O.S SPARES AND PRESSURE TESTED
POPING TEST PC.TIME 180 2 360 PC.TIME 180 2 360 PC.TIME 180 2 360 PC.TIME 156 2 312
PRESSURE GAUGE CALIBRATION, IF REQURIED PC 80 6 480 PC 80 6 480 PC 80 6 480 PC 80 6 480
STANDARD RATES FOR STEAM VALVE / BOILER MOUNTINGS WORKS

CURRENCY: USD 11 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
VALVE TO BE OPENED INSITU, CLEANED, INSPECTED, GRINDED,
RENEWED DAMAGED PARTS / GASKET WITH O/S AND REASSEMBLED
25MM PC 19 2 38 PC 19 2 38 PC 19 2 38 PC 19 2 38
50MM PC 24 4 96 PC 24 4 96 PC 24 4 96 PC 24 4 96
80MM PC 41 2 82 PC 41 2 82 PC 41 2 82 PC 41 2 82
100MM PC 46 2 92 PC 46 2 92 PC 46 2 92 PC 46 2 92
125MM PC 62 2 124 PC 62 2 124 PC 62 2 124 PC 62 2 124
150MM PC 78 2 156 PC 78 2 156 PC 78 2 156 PC 78 2 156
200MM PC 100 3 300 PC 100 3 300 PC 100 3 300 PC 100 3 300
300MM PC 216 1 216 PC 216 1 216 PC 216 1 216 PC 216 1 216
COCK PC 36 2 72 PC 36 2 72 PC 36 2 72 PC 36 2 72
1) VALVE TRANSPORT TO WORKSHOP FOR REPAIR AND TEST 50% UP.
2) GOVERNOR V/VS / SAFETY VALVE / CONTRIL V/V CHARGE EXTRA.
3) HT GASKET SUPPPLY INCH 3.5 INCH 3.5 INCH 3.5 INCH 3.5
OTHER REPAIR, RENEWAL AND ACCESSORY WORKS SHALL BE
4)
CHARGED EXTRA.
E046 AUXILLIARY BOILER WATERTUBES CLEANING & PRESSURE TESTING
AUX BOILER WATERTUBES TO BE CLEANED BY CHEMICAL SET 1450 0 0 SET 1500 0 0 SET 950 0 0 SET 1800 0 0
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E047 EXHAUST GAS BOILER MOUNTINGS OVERHAUL
MANHOLE & ACCESS HOLE AND CLEANING
MANHOLES/HAND HOLES TO BE OPENED AND CLOSED. PC 54 0 0 PC 54 0 0 PC 54 0 0 PC 54 0 0
NEW PACKING SUPPLY, IF NECESSARY PC 30 0 0 PC 30 0 0 PC 30 0 0 PC 30 0 0
GAS SIDE OF EGE TO BE CLEANED BY HPFW SET 2610 1 2610 SET 1500 1 1500 SET 950 1 950 SET 1800 1 1800
WASHING SOOT WATER DISPOSAL TON 90 2 180 TON 36 2 72 TON 36 2 72 TON 90 2 180
PUMP LINE CON./DISCON. LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72 LINE.TIME 36 2 72
SAFETY VALVES TO BE REMOVED, TO WORKSHOP AND OVERHAULED
WITH O.S SPARES AND PRESSURE TESTED PC 280 1 280 PC 150 1 150 PC 280 1 280 PC 280 1 280

NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA


E048 TOPPING AIR COMPRESSOR
SAFETY VALVES TO BE REMOVED, TO WORKSHOP AND OVERHAULED
PC 176 1 176 PC 200 1 200 PC 280 1 280 PC 128 1 128
WITH O.S SPARES AND PRESSURE TESTED
E049 ENGINE ROOM VENT FAN MuSHROOM VENT COVER REPAIR.
STAINLESS STEEL MESH TO BE RENEWED WITH Y/S
M2 60 0 0 M2 60 0 0 M2 60 0 0 M2 60 0 0
(LESS THAN 0.5 M²,SMALL PIECE MINMUM CHARGE AS $30/PC)
WASTED & DAMAGED SOFT STEEL / OUTFITTINGS TO BE RENEWED IN
SITU KG 3 0 0 KG 3 0 0 KG 3 0 0 KG 3 0 0
(SMALL PIECE
SECURING MINIMUM
BOLTS CHARGEA
WITH NUTS AS MS,
SUPPLY/ 15KG, PERPC)
RENWEAL PC 3 0 0 PC 3 0 0 PC 3 0 0 PC 3 0 0
NOTE:FINAL CHARGE SUBJECT TO ACTUAL WORK DONE
E050 ENGINE ROOM BLOWER FLAP OPEN &CLOSING MACHANISM TO INSPECT
FAN MESH ROOM TO BE REMOVED AND SHIFT TO WORKSHOP FOR
SET 450 4 1800 SET 250 4 1000 SET 450 4 1800 SET 450 4 1800
OVERHAULED AND INSPECTION
FAN MUSHROOM & DAMPER DUCT BLASTING AND PAINTING SET 350 4 1400 SET 200 4 800 SET 250 4 1000 SET 250 4 1000
FIRE FLAPS DAMPER TO BE OVERHUALED WITH O/S CLEANING AND
SET 300 0 0 SET 300 0 0 SET 300 0 0 SET 300 0 0
INSPECITON
STAINLESS STEEL MESH TO BE RENEWED WITH Y/S
M2 60 9 540 M2 100 9 900 M2 120 9 1080 M2 120 9 1080
(LESS THAN 0.5 M²,SMALL PIECE MINMUM CHARGE AS $30/PC)
MESH FRAME FLAT BAR RENWAL PC.M 25 16 400 PC.M 20 16 320 PC.M 43.2 16 691.2 PC.M 43.2 16 691.2
FLANGE PACKING RENEW PC 50 4 200 PC 50 4 200 PC 50 4 200 PC 50 4 200
GALV.BOLT & NUT SUPPLY/ INSTALLED PC 3 36 108 PC 3 36 108 PC 3 36 108 PC 3 36 108
NOTE:FINAL CHARGE SUBJECT TO ACTUAL WORK DONE
E051 STEERING GEAR HYD PUMPS OVERHAUL
MAKER ENGINEER TO BE ARRANGE BY OWNER, YARD ASSIST WORK TO
Set 1800 1 1800 Set 850 1 850 Set 1800 1 1800 Set 850 1 850
BE EXTRA.
E052 MAIN ENGINE JACKET WATER HEATER CLEANING & PRESSURE TESTING
MAIN ENGINE JACKET WATER HEATER TO BE REMOVED TO WORKSHOP,
CHEMICALLY CLEANED WITH O/S GASKET AND REFITTED--Shipstaff PC 649 1 649 PC 650 1 650 PC 950 1 950 PC 780 1 780

END COVER GASKET SUPPLY PC 30 2 60 PC 40 1 40 PC 100 1 100 PC 45 1 45


NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E053 MAIN ENGINE JACKET WATER COOLER CLEANING & PRESSURE TESTING
ALL COOLER PLATES TO BE REMOVED,AND SHIFT WORKSHOP FOR
CHEMICAL CLEANING AND REPALCE ALL GAKSET WITH O.S,AND
PLATE 30 PLATE 30 PLATE 30 PLATE 30
PRESSURE TEST (NDT TEST AND END PLATE RECONDAITON TO BE
EXTRA)
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
E054 TANK CLEANING SW HEATER (OVERHAUL AND SURVEY)
PLS REFER TO ITEM DD 48--SHIPSTAFF
E055 SEA CHEST CLEANING, SEA SUCTION AND SHIP SIDE VALVES OVERHAUL
SEA CHEST, PLS REFER TO ITEM:DD 02
THE FOLLOWING VALVES TO BE OPENED INSITU, CLEANED, INSPECTED,
GRINDED, RENEWED DAMAGED PARTS / GASKET WITH O/S AND
REASSEMBLED
1) 10 K 250, 90° ANGLE SDNR VALVE (BILGE & FIRE OVBD V/V)X 1 NO. PC 94 1 94 PC 48 1 48 PC 86.4 1 86.4 PC 86.4 1 86.4
2) 10 K 65, ANGLE STORM VALVE , (SEWAGE OVBD V/V) X 1 NO. PC 43 1 43 PC 18 1 18 PC 69.12 1 69.12 PC 69.12 1 69.12
3) 10 K 65, STRAIGHT STORM VALVE (SEWAGE OVBD V/V) X 1 NO. PC 43 1 43 PC 18 1 18 PC 69.12 1 69.12 PC 69.12 1 69.12
4) 10 K 150, ANGLE STORM VALVE ( GREY WATER OVBD V/V)X 1 NO. PC 94 1 94 PC 32 1 32 PC 92.16 1 92.16 PC 92.16 1 92.16
5) 10 K 150, STRAIGHT STORM VALVE (GREY WATER OVBD V/V) X 1 NO. PC 94 1 94 PC 32 1 32 PC 92.16 1 92.16 PC 92.16 1 92.16
10 K 150, STRAIGHT GOLBE SDNR VALVE, (ATOM COND OVBD V/V) X 1
6) PC 64 1 64 PC 32 1 32 PC 46.08 1 46.08 PC 46.08 1 46.08
NO.
7) 10 K 50,STRAIGHT GOLBE SDNR VALVE (OWS OVBD V/V) X 1NO PC 26 1 26 PC 14 1 14 PC 23.04 1 23.04 PC 23.04 1 23.04
8) 10 K 200,FLANGE TYPE BFLY VALVE, ( SCRUBBER OVBD V/V) X 1NO. PC 146 1 146 PC 108 1 108 PC 114.048 1 114.048 PC 104 1 104
9) 20 K 65,STRAIGHT GOLBE SDNR VALVE, ( BLR BLOW DOWN V/V) X 1NO. PC 32 1 32 PC 18 1 18 PC 34.56 1 34.56 PC 34.56 1 34.56
10 K 300, FLANGE TYPE BFLY VALVE, ( CENTRE COOLER OVBD V/V) X
10) PC 205 1 205 PC 151.2 1 151.2 PC 164.736 1 164.736 PC 161 1 161
1NO.
11) 10 K 100, STRAIGHT GLOBE SDNR VALVE, (FWG OVBD V/V) X 1NO. PC 40 1 40 PC 22 1 22 PC 34.56 1 34.56 PC 34.56 1 34.56
12) 10 K 400, FLANGE TYPE BFLY VALVE,( VAC COND OVBD V/V) X 1NO. PC 272 1 272 PC 201.6 1 201.6 PC 221.76 1 221.76 PC 161 1 161
10 K 500, FLANGE TYPE BFLY VALVE, MANUAL AND HYD OPERATED
13) PC 350 1 350 PC 259.2 1 259.2 PC 285.12 1 285.12 PC 207.5 1 207.5
( PORT SIDE LOW SEA CHEST V/V) X 1 NO.
10 K 500, FLANGE TYPE BFLY VALVE, MANUAL AND HYD OPERATED
14) PC 350 2 700 PC 259.2 2 518.4 PC 285.12 2 570.24 PC 207.5 2 415
( STBD SIDE LOW SEA CHEST V/V) X 1 NO.
20 K 40,STRAIGHT GLOBE SDNR V/V,STEAM BLOW LINE VALVE FOR LOW
15) PC 26 1 26 PC 14 1 14 PC 23.04 1 23.04 PC 23.04 1 23.04
SEA CHEST.
20 K 40, STRAIGHT GLOBE SDNR V/V,STEAM BLOW LINE VALVE FOR HIGH
16) PC 26 1 26 PC 14 1 14 PC 23.04 1 23.04 PC 23.04 1 23.04
SEA CHEST.
17) 10 K 125, STRAIGHT GLOBE SDNR V/V, EMERGENCY FIRE P/P SUC V/V. PC 52 1 52 PC 26 1 26 PC 46.08 1 46.08 PC 46.08 1 46.08
WHEN VALVE IS SENT TO WORKSHOP FOR REPAIR AND TEST,PRICE TO
BE CHARGED WITH EXTRA BY 50%.
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA
E056 ULTRASONIC TESTING OF STUB PC
ULTRASONIC THICKNESS MEASUREMENTS ARRANGE BY YARD FOR ALL
OVERBOARD LINE STUB PIPECES UP TO 300POINTS LOT 800 1 800 LOT 500 1 500 LOT 350 1 350 LOT 500 1 500

E057 INERT GAS FAN # A & B TO OVERHAUL


PLS REFER TO ITEM:EL012
NEW PIPELINE FABRICATION FROM SEWAGE OVERBOARD LINE TO AFT
E058
PEAK TANK
STRAIGHT PIPE 65A,MS,SCH80,NON GALVANIZED M 51 40 2040 M 29 40 1160 M 45 40 1800 M 45 40 1872
ELBOW 65A PC 61 8 488 PC 61 8 488 PC 61 8 488 PC 61 8 488
FLANGE 65A PC 45 16 720 PC 45 16 720 PC 45 16 720 PC 45 16 720
NOTE:
1) ANY OTHER REPAIR OR ACCESSORY WORKS CHARGE EXTRA.
2) FINAL CHARGE SUBJECT TO ACTUAL WORK DONE ON SPOT AND
CALCULATED FOLLOWING ABOVE STEEL / PIPE WORK TARIFF & NOTES
E059 FRESH WATER GENERATOR EVAPORATER TUBES CLEANING
FWG CONDENSER (TOP SECTION)
FWG CONDENSER BOTH END COVER TO BE OPENED AND TO BE
PC 849 0 0 PC 849 0 0 PC 950 0 0 PC 950 0 0
CLEANED IN SITU, REPALCE WITH O/S GASKET AND REFITTED
CHOKED TUBES TO BE MADE THROUGH IF NECESSARY PC 25 0 0 PC 35 PC 25 PC 25
END FLANGE GASKET SUPPLY PC 20 4 80 PC 20 2 40 PC 20 2 40 PC 20 2 40
FWG HEATER ( BOTTOM SECTION)
HEATERS TO BE REMOVED TO WORKSHOP, CHEMICALLY CLEANED WITH
PC 1260 1 1260 PC 850 1 850 PC 950 1 950 PC 950 1 950
O/S GASKET AND REFITTED
CHOKED TUBES TO BE MADE THROUGH IF NECESSARY PC 25 15 375 PC 35 15 525 PC 25 15 375 PC 25 15 375
END FLANGE GASKET SUPPLY PC 20 4 80 PC 20 4 80 PC 20 4 80 PC 20 4 80
WHOLE UNIT TO BE SHIFTO WORKSHOP FOR REPAIR WORK, CASE BY
CASE
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
E060 PROPELLER & INTERMEDIATE SHAFT BEARING SURVEY
PROPELLER CLEANING AND POLISHING
PROPELLER NORMAL POLISHING 5 BLADE TIME 610 1 610 TIME 610 1 610 TIME 610 1 610 TIME 950 1 950
PROPELLER BLADE ROOT (0.3R) DYE CHECK INSPECTION TIME 800 1 800 TIME 500 1 500 TIME 650 1 650 TIME 1000 1 1000
PROPELLER BLADE EDGE(W<200MM) M 60 M 60 M 60 M 60
TOWER STAGING IN DRY DOCK M3 2 200 400 M3 2 200 400 M3 2 200 400 M3 2.5 200 500
PROPELLER TO REMOVE,REFIT

CURRENCY: USD 12 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
PROPELLER TO BE REMOVED AND REFITTED FOR INSEPCTION AND
TIME 1392 1 1392 TIME 2000 1 2000 TIME 2500 1 2500 TIME 1500 1 1500
REPALCE GREASE, GASKET WITH O.S
MAGNAFLUX TEST ON TAILSHAFT CONE, IF NECESSARY TIME 350 1 350 TIME 350 1 350 TIME 350 1 350 TIME 350 1 350
CAP TALLOW TO BE REFILLED WITH O/S TIME 320 0 0 TIME 320 0 0 TIME 320 0 0 TIME 320 0 0
LIFTING EYE TO BE INTATALLED SWL15~20TON PC 260 1 260 PC 260 1 260 PC 260 1 260 PC 260 1 260
LIFTING EYE TO BE INTATALLED UP TO 5TON PC 50 1 50 PC 50 1 50 PC 50 1 50 PC 50 1 50
ADD TOWER STAGING IN DRY DOCK FOR REMOVE,REFIT M3 2 200 400 M3 2 200 400 M3 2 200 400 M3 2.5 200 500
TAILSHAFT TO BE WIDTHDRAWN, INCLUDING 1 PC INTERMEDIATE SHAFT
SET 3150 1 3150 SET 2200 1 2200 SET 3600 1 3600 SET 3520 1 3520
REMOVE REASSEMBLED AFTERWARD.
ONE PLUMMER BLOCK FOR INTERMEDIATE SHAFT BEARING TO BE
SET 320 1 320 SET 250 1 250 SET 320 1 320 SET 350 1 350
DISCONN/CONN FROM FOUNDATION
STERN TUBE FWD/ AFT BEARING AND CASING CLEANING AND
TIME 450 1 450 TIME 350 1 350 TIME 450 1 450 TIME 450 1 450
CALIBRATION
TAILSHAFT BEARING CLEARANCE TO BE CHECK TIME 180 2 360 TIME 100 2 200 TIME 180 2 360 TIME 180 2 360
INTERMEDIATE BEARING LOAD TEST TIME 650 0 0 TIME 650 0 0 TIME 650 0 0 TIME 650 0 0
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA.
E061 WINDLASS & MOORING HYD PUMP OVERHAUL
HYDRAULIC MOTOR OVERHAULE WITH O.S SEAL KIT PC 1800 4 7200 PC 1200 4 4800 PC 2000 4 8000 PC 1800 4 7200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA.
ATMOSPHERIC STEAM CONDENSER SEA WATER COOLING OUTLET LINE
E062
RENEWAL.
STRAIGHT PIPE 250A,MS,SCH80,NON GALVANIZED M 156 M 156 M 156 M 156
ELBOW 250A PC 167 PC 167 PC 167 PC 167
FLANGE 250A PC 42 PC 42 PC 42 PC 42
GALV BOLTS & NUTS WITH WASHER PC 3 PC 3 PC 3 PC 3
NON ASBESTOS GASKET 250A 5K~10K THK = 1.5~3MM PC 10 PC 10 PC 10 PC 10
E063 DECK SEAL SEA WATER PIPE LINE SECTION TO RENEW.
STRAIGHT PIPE 50A, MS, SCH40, NO.GALV. L≤MTR M 30 25 750 M 19 25 475 M 29 25 725 M 26.92 25 673
ELBOW 50A PC 13 12 156 PC 13 12 156 PC 13 12 156 PC 13 12 156
FLANGE 50A PC 11 24 264 PC 11 24 264 PC 11 24 264 PC 11 24 264
GALV BOLTS & NUTS M16X70 PC 3 48 144 PC 3 48 144 PC 3 48 144 PC 3 48 144
NON ASBESTOS GASKET 50A 5K~10K THK=1.5~3MM PC 5 12 60 PC 5 12 60 PC 5 12 60 PC 5 12 60
RUBBER COATING EXTRA.
E064 BUNKER LINE PRESSURE TESTING
BUNKER LINE (FO & DO) PRESSURE TEST LINE.TIME 420 2 840 LINE.TIME 400 2 800 LINE.TIME 320 2 640 LINE.TIME 450 2 900
FW WATER SUPPLY TON 3 50 150 TON 1.5 50 75 TON 2.5 50 125 TON 2.5 50 125
OIL WATER DISPOSAL IF ANY TON 45 50 2250 TON 36 50 1800 TON 36 50 1800 TON 36 50 1800
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
SUBTOTAL 245,522 215,908 240,583 245,611

******END OF THE ENGINE SECTION QUOTATION******

CURRENCY: USD 13 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

IMCY SHIPYARD HAUFENG SHIPYARD XINYA SHIPYARD COSCO SHIPYARD


ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT
# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
MT "PHOENIX I "
IMO No.:9236248
CRUDE OIL TANKER / YEAR OF BUILD 2002-04-29, CLASS: LR
LOA / BM / DM=248 / 43.03 / 21.0 M
GRT / NET / DWT=59,693 / 31,164 / 105,851 MT

EL DD ELECTRICAL WORKS
EL001 MAIN SWITCH BOARD BUS BAR CLEANING & TESTS
MSB & STARTER PANELS TO BE CLEANED AND CONNECTIONS TO BE
RETIGHTENED PANEL 100 13 1300 PANEL 120 13 1560 PANEL 100 13 1300 PANEL 120 13 1560

MSB,PANEL BUS BARS THERMOGRAPHIC INSPECTION, IF REQUIRED PANEL 100 3 300 PANEL 100 3 300 PANEL 100 3 300 PANEL 150 3 450
EL002 EMERGENCY SWITCH BOARD BUS BAR CLEANING & TESTS
ESB & STARTER PANELS TO BE CLEANED AND CONNECTIONS TO BE
RETIGHTENED PANEL 100 3 300 PANEL 120 3 360 PANEL 100 3 300 PANEL 120 3 360

ESB PANEL BUS BARS THERMOGRAPHIC INSPECTION, IF REQUIRED PANEL 100 1 100 PANEL 100 1 100 PANEL 100 1 100 PANEL 150 1 150
MSB & ESB VOLTMETERS, AMMETERS, KW METERS, FREQUENCY
EL003 METERS & EARTH RESISTANCE METERS CALIBRATION
THE FOLLOWING METERS TO BE CALBRCATED
MAIN SWITCH BOARD:
1 AC VOLTMETERS 3 NOS(RANGE 0-600 VOLTS) PC 80 3 240 PC 35 3 105 PC 45 3 135 PC 40 3 120
2 AC AMMETERS 3 NOS (RANGE 0-2000 AMPS). PC 45 3 135 PC 35 3 105 PC 45 3 135 PC 40 3 120
3 WATT METERS 3 NOS (RANGE -150 KW TO 2000 KW) . PC 80 3 240 PC 55 3 165 PC 45 3 135 PC 60 3 180
4 FREQUENCY METERS -1 NO (55 TO 65 HZ) PC 80 3 240 PC 55 3 165 PC 45 3 135 PC 60 3 180
5 GROUND RESISTANCE METERS 2 NOS (0-INFINITY MEGA OHMS) PC 120 2 240 PC 55 2 110 PC 45 2 90 PC 60 2 120
EMERGENCY SWITCH BOARD:
1 AC VOLTMETERS -1 NO (RANGE 0-600 VOLTS) PC 80 1 80 PC 35 1 35 PC 45 1 45 PC 40 1 40
2 AC AMMETERS 1 NO (RANGE 0-300 AMPS) PC 45 1 45 PC 35 1 35 PC 45 1 45 PC 40 1 40
3 WATT METERS 1 NO (RANGE 0 KW TO 250 KW) . PC 80 1 80 PC 55 1 55 PC 45 1 45 PC 60 1 60
4 FREQUENCY METERS -1 NO (55 TO 65 HZ) PC 80 1 80 PC 55 1 55 PC 45 1 45 PC 60 1 60
5 GROUND RESISTANCE METERS 2 NO(0-INFINITY MEGA OHMS) PC 120 2 240 PC 55 2 110 PC 45 2 90 PC 60 2 120
EL004 GENERATORS ACB NO. 1, 2 & 3 SERVICING & FUNCTION TESTING
CIRCUIT BREAKER TO BE DRAWOUT AND SERVICE SET 300 3 900 SET 200 3 600 SET 300 3 900 SET 220 3 660
ACB TO BE FUNCTION TESTED SET 750 3 2250 SET 750 3 2250 SET 350 3 1050 SET 950 3 2850
MISC Repairs as per inspection & function test 5000 5000 5000 5000
EL005 EMCY GENERATOR AIR CIRCUIT BREAKER
CIRCUIT BREAKER TO BE DRAWOUT AND SERVICE SET 300 1 300 SET 300 1 300 SET 300 1 300 SET 220 1 220
ACB TO BE FUNCTION TESTED SET 750 1 750 SET 750 1 750 SET 350 1 350 SET 950 1 950
EL006 AUXILLIARY ENGINES ALTERNATORS CLEANING
GENERATOR (≤1000KVA TO BE OPENED, AIR GAP TO BE CHECKED
OUT. GENERATORS TO BE CLEANED BY ELECTRICAL SOLVENT IN
PLACE AND DRIED. INSULATION TO BE CHECKED. CLOSED UP ON SET 1820 3 5460 SET 2000 3 6000 SET 2500 3 7500 SET 1800 3 5400
COMPLETION IN SITU

BEARING OR BUSH RENEWAL WITH O/S PC 650 0 0 PC 650 0 0 PC 650 0 0 PC 300 0 0


LOAD TEST ASSISTACNE AND INSPECTION TIME 800 0 0 TIME 800 0 0 TIME 800 0 0 TIME 800 0 0
SHAT ALIGNMENT TIME 800 0 0 TIME 800 0 0 TIME 800 0 0 TIME 800 0 0
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
EL007 EMERGENCY GENERATOR ALTERNATOR CLEANING
EMERGENCY ALTERNATOR TO BE, CLEANED, OVERHAULED WITH
O/S, GAP ALIGNMENT AND CLOSED UP ON COMPLETION IN PLACE SET 800 1 800 SET 900 1 900 SET 1500 1 1500 SET 1800 1 1800

BEARING OR BUSH RENEWAL WITH O/S PC 300 0 0 PC 300 PC 300 PC 300


EL008 MGPS & ICCP INSPECTION AND MAINTENANCE
A ICCP
MAKER SERVICE ENGINEER TO BE ARRANGED BY OWNER.YARD
ASSISTANCE WORK AS FOLLOW. 6500 6500 6500 6500

CHEERY PICKER ASSISTANCE SET.HR 36 36 1296 SET.HR 36 36 1296 SET.HR 40 36 1440 SET.HR 40 36 1440
COFERDAM COVER PLATE TO BE OPENED / CLOSED PC 27 0 0 PC 27 0 0 PC 27 0 0 PC 27 0 0
RUBBER GASKET RENEWAL PC 15 4 60 PC 15 4 60 PC 15 4 60 PC 15 4 60
ICCP ANODE REPLACEMENT
ICCP ANODE TO BE RENEWED WITH O/S PC 400 2 800 PC 400 2 800 PC 350 2 700 PC 350 2 700
ICCP REFERENCE CELLS TO BE RENEWED WITH O/S PC 300 1 300 PC 300 1 300 PC 350 1 350 PC 300 1 300
ICCP SYSTEM DIELECTRIC SHIELD REPAIRS
DIELECTRIC SHIELD TO BE BLASTED WA2.5, AND COATED WITH O/S LOCATI LOCATIO
400 0 0 400 0 0 LOCATION 400 0 0 LOCATION 400 0 0
ON N
SUPPLY EPOXY PUTTY (5L+5L) SET 750 1 750 SET 750 1 750 SET 750 1 750 SET 750 1 750
B MGPS
MGPS ANODES TO BE REPALCED WITH O.S PC 250 0 0 PC 200 4 800 PC 350 4 1400 PC 350 4 1400
MGPS TO BE SERVICED BY IMC YY VIKING ENGINEERS , IF REQUIRED SET 800 1 800 SET 500 1 500 SET 650 1 650 SET 1180 1 1180
NOTE:ANY OTHER REPAIR / ACCESSORY WORK TO BE EXTRA.
EL009 ROUTINE MAINTENANCE OF MARINE TRANSFORMERS
MAIN TRANSFORMER VACCUM CLEANING IN SITU (380V~440V) SET 450 1 450 SET 500 1 500 SET 656 1 656 SET 550 1 550
SECONDARY TRANSFORMER VACCUM CLEANING IN SITU (36V-230V) SET 300 1 300 SET 300 1 300 SET 300 1 300 SET 300 1 300
EL010 MAIN ENGINE AUX BLOWER # 1 & 2 MOTORS TO OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S (83.25KW) PC 775 2 1550 PC 620 2 1240 PC 620 2 1240 PC 620 2 1240

FAN IMPELLER & EL DRIVE MOTOR ROTOR


FAN IMPELLER CLEANED, INSPECTED, SPARES RENEWED WITH O/S,
SET 180 0 0 SET 180 0 0 SET 180 0 0 SET 350 0 0
REFITTED AND TESTED
IMPELLER DYNAMIC BALANCE TEST SET 659 2 1318 SET 500 2 1000 SET 600 2 1200 SET 600 2 1200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA. 500 500 500 500
EL011 MAIN L.O. PUMP # 1 & 2 MOTORS TO OVERHAUL
ELECTRIC MOTORS TO BE REMOVED TO SHORE WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 100KW PC 620 2 1240 PC 496 2 992 PC 496 2 992 PC 496 2 992

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 2 360 SET 120 2 240 SET 160 2 320 SET 200 2 400
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA. 500 500 500 500
EL012 IG BLOWER MOTORS # 1 & 2 OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 65KW PC 600 2 1200 PC 820 2 1640 PC 820 2 1640 PC 635 2 1270

IGS BLOWER FAN CASING SIDE COVER AND INLET SUCTION TO BE


1 REMOVED AND REFIT AFTER REPAIR WORK SET 350 2 700 SET 350 1 350 SET 350 1 350 SET 350 1 350

IMPELLER TO BE SHIFT TO WORKSHOP & CHEMICAL CLEAN & ASH


2 BLASTING FOR INSPECTION SET 300 2 600 SET 300 2 600 SET 300 2 600 SET 300 2 600

3 FAN IMPELLER TO BE DYNAMICALLY BALANCED PC 510 2 1020 PC 510 2 1020 PC 510 2 1020 PC 200 2 400
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA
EL013 ALL VENT FAN MOTOR
1 PUMP ROOM(5.5KW), PLS REFER TO DD 28 pc 500 1 500 pc 120 1 120 pc 500 1 500 pc 220 1 220
2 STEERING GEAR ROOM(1.5KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 120 1 120 SET 120 1 120 SET 120 1 120 SET 120 1 120

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 131 1 131 SET 84 1 84 SET 105 1 105 SET 105 1 105

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 1 125 SET 125 1 125 SET 300 1 300 SET 300 1 300
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
3 CO2 ROOM(0.75KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 80 1 80 SET 80 1 80 SET 80 1 80 SET 80 1 80

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 131 1 131 SET 150 1 150 SET 246 1 246 SET 59 1 59

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 1 125 SET 250 1 250 SET 300 1 300 SET 300 1 300
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
4 SANITORY FAN(0.75KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 80 1 80 SET 80 1 80 SET 80 1 80 SET 80 1 80

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 131 1 131 SET 131 1 131 SET 131 1 131 SET 131 1 131

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 1 125 SET 125 1 125 SET 125 1 125 SET 125 1 125
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
5 GALLEY SUPPLY (1.2KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 80 1 80 SET 80 1 80 SET 80 1 80 SET 80 1 80

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 131 1 131 SET 84 1 84 SET 105 1 105 SET 105 1 105

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 1 125 SET 300 1 300 SET 250 1 250 SET 250 1 250
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
6 GALLEY EXHAUST FAN(2.2 KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 120 1 120 SET 120 1 120 SET 120 1 120 SET 120 1 120

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 183 1 183 SET 84 1 84 SET 105 1 105 SET 105 1 105

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 150 1 150 SET 300 1 300 SET 250 1 250 SET 200 1 200
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
7 AIR CONDITIO ROOM FAN(0.75KW),
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 80 2 160 SET 80 1 80 SET 80 1 80 SET 80 1 80

CURRENCY: USD 14 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND
OVERHAUL WITH O/S SET 131 2 262 SET 58 1 58 SET 59 1 59 SET 59 1 59

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 2 250 SET 300 1 300 SET 250 1 250 SET 250 1 250
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
8 SUNDRY EXH FAN (0.75KW).
MUSH ROOM TO BE DISCONNECTD FOR TAKE OUT EL MOTOR AND
REFIT WITH O.S SET 80 1 80 SET 80 1 80 SET 80 1 80 SET 80 1 80

FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND


OVERHAUL WITH O/S SET 131 1 131 SET 131 1 131 SET 131 1 131 SET 131 1 131

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 125 1 125 SET 125 1 125 SET 125 1 125 SET 125 1 125
FAN DUCT RUBBER PACKING RENEWAL PC 20 2 40 PC 20 2 40 PC 20 2 40 PC 20 2 40
NOTE:ANY OTHER REPAIR OR ACCESSORY WORK TO BE EXTRA.
STAINLESS STEEL MESH TO BE RENEWED WITH Y/S
M2 60 M2 60 M2 60 M2 60
(LESS THAN 0.5 M²,SMALL PIECE MINMUM CHARGE AS $30/PC)
MESH FRAME FLAT BAR RENWAL PC.M 25 PC.M 25 PC.M 25 PC.M 25
SECURING BOLTS WITH NUTS SUPPLY/ RENWEAL PC 3 PC 3 PC 3 PC 3
NOTE:
1) ANY OTHER REPAIR OR ACCESSORY WORKS CHARGE EXTRA.
2) FINAL CHARGE SUBJECT TO ACTUAL WORK DONE ON SPOT AND
CALCULATED FOLLOWING ABOVE TARIFF & NOTES
EL014 LT COOLER FW PUMP MOTORS # 1 ,2& 3 OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 26KW PC 328 3 984 PC 261 3 783 PC 261 3 783 PC 262 3 786

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 3 360 SET 180 3 540 SET 100 3 300 SET 100 3 300
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 1500 1500 1500 1500
EL015 BOILER FD FAN MOTOR
FAN AIR INLET SUCTION TO BE REMOVED, REFIT SET 450 2 900 SET 200 2 400 SET 250 2 500 SET 250 2 500
IMPELLER TO BE SHIFT TO WORKSHOP & CHEMICAL CLEAN FOR
SET 350 2 700 SET 350 2 700 SET 350 2 700 SET 350 2 700
INSPECTION
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 90KW PC 775 2 1550 PC 620 2 1240 PC 620 2 1240 PC 620 2 1240

FAN IMPELLER DYNAMIC BALANCING SET 650 2 1300 SET 450 2 900 SET 400 2 800 SET 360 2 720
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 2000 2000 2000 2000
EL016 EMERGENCY FIRE PUMP MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 30KW PC 328 1 328 PC 261 1 261 PC 262 1 262 PC 262 1 262

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 1 120 SET 120 1 120 SET 120 1 120 SET 120 1 120
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 500 500 200 200
EL017 ALL ER VENT FAN MOTORS TO OVERHAUL
EL MOTOR CASING SIDE DOOR TO BE OPNED AND CLOSED FOR
PC 120 4 480 PC 120 4 480 PC 120 4 480 PC 350 4 1400
TAKE OUT THE EL MOTOR
FAN MOTORS TO BE REMOVED TO WORKSHOP CLEANING AND
OVERHAUL WITH O/S 18.5KW SET 343 4 1372 SET 273 4 1092 SET 250 4 1000 SET 275 4 1100

FAN IMPELLER TO BE DYNAMICALLY BALANCED SET 350 4 1400 SET 300 4 1200 SET 300 4 1200 SET 300 4 1200
NOTE:ANY OTHER REPAIR OR ACCESSORY WORKS TO BE EXTRA 3500 3500 3500 3500
EL018 AIR CON COMPRESSOR MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 26KW PC 620 2 1240 PC 496 1 496 PC 496 1 496 PC 496 1 496

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 2 360 SET 200 1 200 SET 200 1 200 SET 200 1 200
EL019 MAC AND WORKING AIR COMPRESSOR MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 45KW PC 383 3 1149 PC 306 1 306 PC 306 1 306 PC 306 1 306

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 3 360 SET 120 1 120 SET 120 1 120 SET 120 1 120
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 36KW PC 351 3 1053 PC 280 1 280 PC 281 1 281 PC 281 1 281

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 3 360 SET 120 1 120 SET 120 1 120 SET 120 1 120
1000 1000 1000 1000
EL020 FIRE & G.S PUMP MOTOR # 1 & 2
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 110KW PC 777 2 1554 PC 656 2 1312 PC 656 2 1312 PC 632 2 1264

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 2 360 SET 180 2 360 SET 180 2 360 SET 180 2 360
2500 2500 2500 2500
EL021 STEERING GEAR 1 & 2 MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 67KW PC 480 2 960 PC 384 2 768 PC 384 2 768 PC 384 2 768

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 2 360 SET 180 2 360 SET 180 2 360 SET 180 2 360
EL022 MAIN FEED PUMP MOTOR # 1 & 2 OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 75KW PC 480 2 960 PC 384 2 768 PC 384 2 768 PC 384 2 768

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 2 360 SET 180 2 360 SET 180 2 360 SET 180 2 360
1200 1200 1200 1200
EL023 SCRUBBER COOLING SW PUMP MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 45KW PC 383 1 383 PC 306 1 306 PC 306 1 306 PC 306 1 306

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 1 120 SET 120 1 120 SET 120 1 120 SET 120 1 120
650 650 650 650
EL024 BALLAST PUMP MOTOR OVERHAUL
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 160KW PC 1042 2 2084 PC 768 2 1536 PC 768 2 1536 PC 768 2 1536

5000 5000 5000 5000


EL025 MAIN COOLING SEA WATER PP NO. 1 & 2 OVERHAULING
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 33KW PC 351 2 702 PC 281 2 562 PC 281 2 562 PC 281 2 562

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 120 2 240 SET 120 2 240 SET 120 2 240 SET 120 2 240
1500 1500 1500 1500
EL026 ATM COND PP MOTOR OVERHAULING
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 15KW PC 274 1 274 PC 176 1 176 PC 169 1 169 PC 169 1 169

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 100 1 100 SET 100 1 100 SET 100 1 100 SET 100 1 100
500 500 500 500
CONDENSATE PP NO. 1 & 2 FOR COPT VACCUUM COND. MOTOR
EL027 OVERHAULING
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 15KW PC 274 2 548 PC 169 2 338 PC 169 2 338 PC 169 2 338

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 100 2 200 SET 100 2 200 SET 100 2 200 SET 100 2 200
EL028 VISCOSITY CONTROL UNIT OVERHAUL
M/E & A/E F.O SYSTERM VISCOSITY CONTROLLER UNIT AT ECR &
LOCAL CALIBERATION SET 850 2 1700 SET 1000 2 2000 SET 950 2 1900 SET 950 2 1900

NOTE:ANY OTHER REPAIR OR SPARES SUPPLY TO BE EXTRA


EL029 AUX BOILER CONTROL PANEL
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA 5500 5500 5500 5500

EL030 ENGINE ROOM OVER HEAD CRANE


FUNCTION OF UPPER HOIST LIMIT SWITCH (HOOK STOP), END
SWITCHES FOR THE TRANSVERSE TROLLEY AND END OF RAIL SET.TI
450 1 450 SET.TIME 450 1 450 SET.TIME 450 1 450 SET.TIME 450 1 450
SWITCHES FOR THE GANTRY TO BE CHECKED. ME

ENGINE ROOM CRANE LOAD TEST, SWL=5TON SET.TI


168 2 336 SET.TIME 650 2 1300 SET.TIME 300 2 600 SET.TIME 350 2 700
ME
ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 3.7KW PC 223 1 223 PC 400 1 400 PC 450 1 450 PC 450 1 450

ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR


CLEANING AND OVERHAUL WITH O/S 0.75KW PC 180 2 360 PC 180 2 360 PC 180 2 360 PC 180 2 360

NOTE:ANY OTHER REPAIR OR SPARES SUPPLY TO BE EXTRA


EL031 INERT GAS CONTROL SYSTEM
MAKER ENGINEER TO BE ARRANGED BY OWNER.YARD ASSISTANCE
WORK TO BE EXTRA 4500 4500 4500 4500

EL032 MOORING & WINDLASS WINCH PUMP MOTOR OVERHAUL


ELECTRIC MOTORS TO BE REMOVED, SHIFT TO WORKSHOP FOR
CLEANING AND OVERHAUL WITH O/S 45KW PC 620 4 2480 PC 850 4 3400 PC 496 4 1984 PC 496 4 1984

SHAFT / EL MOTOR ALIGNMENT TO BE CHECKED AND ADJUST SET 180 4 720 SET 120 4 480 SET 150 4 600 SET 150 4 600
2500
Provision Crane : Macgregor Type -Gp 160 514-S ; Ele Motor 289
EL033
1591-801, 440V 60Hz 3 Phase , 32Kw ,1765Rpm
1. Check All Condition Of Hoses And Damage Hose To Be
pc 10 10 100 pc 10 10 100 pc 10 10 100 pc 10 10 100
Renewed.
2. Check Safety Device And Defective Parts To Be Renewed.
3. Check Remote Control And Defective Parts To Be Renewed. set 850 1 850 set 850 1 850 set 850 1 850 set 850 1 850
4. Load Test To Be Carried Out And Certificate To Be Issued. set 650 1 650 set 650 1 650 set 450 1 450 set 450 1 450

EL034 Hose Handling Crane ; P & S


1. Check All Condition Of Hoses And Damage Hose To Be
pc 10 60 600 pc 10 60 600 pc 10 60 600 pc 10 60 600
Renewed.
2. Check Safety Device And Defective Parts To Be Renewed.
3. Check Remote Control And Defective Parts To Be Renewed. set 800 1 800 set 800 1 800 set 800 1 800 set 800 1 800
4. Load Test To Be Carried Out And Certificate To Be Issued. set 650 1 650 set 650 1 650 set 450 1 450 set 450 1 450

CURRENCY: USD 15 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT


# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
SUBTOTAL 108,439 100,869 100,121 101,003

******END OF THE Electrial SECTION QUOTATION******

CURRENCY: USD 16 736091635.xlsx


QUOTATION FOR R15-2
IMC SHIPYARD (ZHOUSHAN) CO., LTD. MT "PHOENIX I" 03/18/2024

IMCY SHIPYARD HAUFENG SHIPYARD XINYA SHIPYARD COSCO SHIPYARD


ITEM UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT UNIT PAYMENT
# QUOTATION DESCRIPTION UNIT QTY UNIT QTY UNIT QTY UNIT QTY
No. PRICE US$ PRICE US$ PRICE US$ PRICE US$
MT "PHOENIX I "
IMO No.:9236248
CRUDE OIL TANKER / YEAR OF BUILD 2002-04-29, CLASS: LR
LOA / BM / DM=248 / 43.03 / 21.0 M
GRT / NET / DWT=59,693 / 31,164 / 105,851 MT

N001 MAGNETIC COMPASS SERVICING


MAGNETIC COMPASS DEVATION TO BE CHECKED DURING SEA TRAIL TIME 880 1 880 TIME 1000 1 1000 TIME 880 1 880 TIME 1100 1 1100
N002 AUTO PILOT
FOLLOW-UP STEERING CONTROL SYSTEM ANNUAL INSPECTION SET 860 1 860 SET 625 1 625 SET 860 1 860 SET 1400 1 1400
AUTO STEERING GEAR CONTROL SYSTEM ANNUAL INSPECTION SET 860 1 860 SET 625 1 625 SET 860 1 860 SET 1400 1 1400
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
N003 ECHO SOUNDER
ANNUAL INSPECTION SERVICE SET 860 1 860 SET 1000 1 1000 SET 860 1 860 SET 1100 1 1100
N004 VHF 1&2
ANNUAL SERVICING FOR VHF SET 860 2 1720 SET 550 2 1100 SET 860 2 1720 SET 580 2 1160
N005 AIS
AIS SERVICE SET 860 1 860 SET 700 1 700 SET 860 1 860 SET 720 1 720
N006 COURSE RECORDER
CHECK ON SPOT 800 800 800 800
N007 RADAR X BAND & SBAND
ANNUAL INSPECTION SERVICE SET 880 2 1760 SET 900 2 1800 SET 900 2 1800 SET 1100 2 2200
N008 SERVICING OF MASTER ECDIS
ANNUAL SERVICING FOR ECDIS. SET 880 1 880 SET 950 1 950 SET 880 1 880 SET 1000 1 1000
N009 SERVICING OF MASTER ECDIS -
ANNUAL SERVICING FOR ECDIS. SET 880 1 880 SET 950 1 950 SET 880 1 880 SET 1000 1 1000
N010 BRIDGE CLOCK RPTR
MAIN CLOCK SYSTEM SERVICE SET 980 0 0 SET 980 0 0 SET 980 1 980 SET 1080 1 1080
SINGLE SUB CLOCK SERVICE PC 180 PC 180 PC 180 PC 180
N011 BRIDGE WEATHER FACIMILE 800 800 800 800
CHECK ON SPOT
N012 DOPPLER SPEED LOG SERVICING
ANNUAL INSPECTION SERVICE SET 880 1 880 SET 1850 1 1850 SET 1500 1 1500 SET 850 1 850
N013 GYRO NO. 1
ANNUAL INSPECTION SERVICE FOR GYRO COMPASS SET 1200 1 1200 SET 1000 1 1000 SET 1500 1 1500 SET 1500 1 1500
ONE SET OF SUPPORT LIQUID PRICE, IF NECESSARY SET 920 1 920 SET 920 1 920 SET 920 1 920 SET 850 1 850
N014 GYRO NO. 2
ANNUAL INSPECTION SERVICE FOR GYRO COMPASS SET 1200 1 1200 SET 100 1 100 SET 1500 1 1500 SET 1500 1 1500
ONE SET OF SUPPORT LIQUID PRICE, IF NECESSARY SET 920 1 920 SET 920 1 920 SET 920 1 920 SET 850 1 850
NOTE:ANY OTHER REPAIR AND ACCESSORY WORK TO BE EXTRA.
SUBTOTAL 16,280 14,340 17,720 18,510

******END OF THE BRIDGE SECTION QUOTATION******

CURRENCY: USD 17 736091635.xlsx


SERVICE ENGINEER ATTENDANCE & MISC REPAIRS
SNO SERVICE ENGINEER ATTENDANCE & MISC REPAIRS COSTS
1 LSA /FFA ANNUAL SERVICES 9,500
2 CARGO GUAGING SYSTEM- SERVICE ENGINEER CHARGES 7,000
3 SERVICE ENGINEER FOR STERN TUBE SEAL RENEWAL 7,500
4 ME TURBOCHARGER OVERHAULING 5,000
5 SERVICE ENGINEER FOR IGG AUTOMATION 5,000
6 ME PNEUMATIC VALVES OVERHAULING 6,000
7 FIRE DETETCION SYSTEM HEALTH CHECK UP 4,500
8 MAIN BOILER COMBUSTION CONTROL HEALTH CHECK UP 5,000
9 BRIDGE EQUIPMENT HEALT CHECK UP 2,500
10 ICCP SERVICE ENGINEER 5,000.00

TOTAL ESTIMATED REPAIR AND SE COST IN USD 57,000.00


MT PHOENIX I DD SPARES

ESTIMATED
S.No. Requisition No. Title Req.Catregory
COST

1 PHO/V-0165/REQ22 Requisition for 815 - Fixed CO2 System

SPARES 5000

2 PHO/V-0164/REQ22 Requisition for 434.07 - Windlass and Mooring Winch


Control Valve
SPARES 4500

3 PHO/V-0161/REQ22 Requisition for 434.01.01 - Mooring Winch No 01


Hydraulic Motor
SPARES 5000

4 PHO/V-0159/REQ22 SEWAGE OVER BOARD STORM VALVES

SPARES 850

5 PHO/V-0158/REQ22 Requisition for 601.01.14.05 - ME Stays and Top


Bracings
SPARES 3000

6 PHO/V-0157/REQ22 Requisition for 381.01 - Cargo Valve Hydraulic Unit

SPARES 5000

7 PHO/V-0152/REQ22 Requisition for 755.03 - Vacuum Condenser for COPT

SPARES 951

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 19 of 32
8 PHO/V-0149/REQ22 Requisition for 571.01.01.01 - Air Conditioning Plant
Compressor
SPARES 6500

9 PHO/V-0148/REQ22 Requisition for 354.01 - Cargo Pumps

SPARES 2500

10 PHO/V-0134/REQ22 Requisition for 630.01.02 - Stern Tube Seal FWD

SPARES 23000

11 PHO/V-0133/REQ22 Requisition for 801.01.01.01 - Ballast Pump No 01


SPARES 2500

12 PHO/V-0130/REQ22 Requisition for 800.03 - Level Switch

SPARES 260

13 PHO/V-0129/REQ22 Requisition for 380.01.07 - Cargo Tank Overfill Level


Alarm System
SPARES 0

14 PHO/V-0124/REQ22 Requisition for 651.01 - Auxiliary Engine Complete No


01
SPARES 2825

15 PHO/V-0123/REQ22 Requisition for 651.01 - Auxiliary Engine Complete No


01
SPARES 14500

16 PHO/V-0115/REQ22 Requisition for 703.01.01.01 - ME FO Circulating Pump


No 01
SPARES 1500

17 PHO/V-0111/REQ22 Requisition for 554.01.01 - Provision Refrigeration


Compressors
SPARES 1800

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 20 of 32
18 PHO/V-0110/REQ22 Requisition for 403.01 - Steering Gear System

SPARES 1634

19 PHO/V-0109/REQ22 Requisition for 721.02 - MGPS

SPARES 5500

20 PHO/V-0108/REQ22 LT COOLER INLET AND OUTLET VALVES


SPARES 650

21 PHO/V-0107/REQ22 Requisition for 713.01.03.01 - ME LO Cooler

SPARES 4643

22 PHO/V-0106/REQ22 Requisition for 722.02.01.01 - LT Central Fresh Water


Cooler No 01
SPARES 2990

23 PHO/V-0104/REQ22 BOILER F.O SUPPLY PUMP


SPARES 3500

24 PHO/V-0103/REQ22 FWG DISTILATE PUMP

SPARES 550

25 PHO/V-0102/REQ22 Requisition for 761.01.03 - Fresh Water Generator


Ejector Pump
SPARES 1850

26 PHO/V-0101/REQ22 Requisition for 703.01.02.01 - AE FO Circulating Pump


No 01
SPARES 750

27 PHO/V-0100/REQ22 Requisition for 703.02.02.01 - AE FO Supply Pump No


01
SPARES 750

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 21 of 32
28 PHO/V-0099/REQ22 Requisition for 703.02.01.01 - ME FO Supply Pump No
01
SPARES 1050

29 PHO/V-0098/REQ22 BOILER WATER CIRCULATING PUMP (BBH-50DMW)

SPARES 1450

30 PHO/V-0097/REQ22 BOILER FEED WATER PUMP (EB4H-100)

SPARES 3250

31 PHO/V-0096/REQ22 INERT GAS SYSTEM

SPARES 3500

32 PHO/V-0094/REQ22 CARGO HOSE HANDLING CRANE

SPARES 1606

33 PHO/V-0091/REQ22 GASKTES FOR BOILER MOUNTINGS

SPARES 600

34 PHO/V-0090/REQ22 BILGE ALARM LEVEL SWITCH


SPARES 2094

35 PHO/V-0088/REQ22 Requisition for 651.01.07.01 - AE No 01 Turbocharger

SPARES 3889

36 PHO/V-0087/REQ22 ICCP SYSTEM


SPARES 8400

37 PHO/V-0085/REQ22 INCINERATOR TYPE -100 SL-1WS

SPARES 3000

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 22 of 32
38 PHO/V-0079/REQ22 IG DECK SEAL PUMP

SPARES 300

39 PHO/V-0075/REQ22 I.G SCRUBBER PUMP

SPARES 300

40 PHO/V-0063/REQ22 Requisition for 501 - Lifeboat with Equipments

SPARES 16000

41 PHO/V-0062/REQ22 MAIN COOL S.W.PUMP MODEL - FBWV-250

SPARES 2000

42 PHO/V-0061/REQ22 EMERGENCY FIRE PUMP MODEL -FFV-100D

SPARES 250

43 PHO/V-0059/REQ22 FIRE AND GS PUMP MODEL FE2V-250E

SPARES 1500

44 PHO/V-0053/REQ22 Requisition for 417.02 - Weather Facsimile Receiver

SPARES 1000

45 PHO/V-0047/REQ22 NON ASBESTOS BRAKE LINING

STORES 1700

46 PHO/V-0040/REQ22 MAIN ENGINE EXHAUST VALVE

SPARES 1600

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 23 of 32
47 PHO/V-0039/REQ22 GASKETS FOR BOILER MOUNTINGS

SPARES 350

48 PHO/V-0038/REQ22 NAVIGATION EQUIPMENT SPARE & STORE

SPARES 1500

49 PHO/V-0037/REQ22 MAIN ENGINE FUEL INECTOR

SPARES 1200

50 PHO/V-0034/REQ22 MAIN ENGINE FUEL PUMP

SPARES 12000

51 PHO/V-0032/REQ22 MAIN ENGINE PNEUMATIC VALVES REPAIR KIT

SPARES 7500

52 PHO/V-0018/REQ22 Requisition for 601 - Main Engines

SPARES 600

53 PHO/V-0009/REQ22 Requisition for 646.05 - Boiler Feed Water Pump

SPARES 1500

54 PHO/V-0005/REQ22 ELECTRICAL MOTOR BEARING

SPARES 5000

55 PHO/V-0084/REQ21 Requisition for 731.01.03.01 - Topping Up Air


Compressor
SPARES 3719

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 24 of 32
56 PHO/V-0082/REQ21 Requisition for 403.01.02.02 - Steering Gear Hydraulic
Pump No 02
SPARES 581

57 PHO/V-0081/REQ21 Requisition for 580.01.02 - Sewage Vacuum System

SPARES 3664

58 PHO/V-0078/REQ21 Requisition for 651.03.07.01 - AE No 03 Turbocharger

SPARES 5000

60 PHO/V-0058/REQ21 Requisition for 644.01 - Oil Fired Boiler No 01

SPARES 2500

61 PHO/V-0057/REQ21 Requisition for 601.01 - Main Engine

SPARES 9000

62 Requisition for ME T/C spares

SPARES 15000

TOTAL
225106

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 25 of 32
EQUIPMENT DETAILS COMMENTS

CO2 FIXED SYSTEM Co2 system Flexible hoses renewal


FLEXIBLE HOSE due as per class requirements for
MAKER: NK CO., LTD. LSA/FFA maintenance
TYPE: STRAIGH 2A

WINDLASS AND MOORING WINCH CONTROL VALVE Quotation awaited . Cost input basis
MAKER: FUKUSHIMA LTD. experience of other vessels docking .
TYPE: E12 AXOAAB
TOTAL NUMBER OF CONTROL VALVE: EIGHT(08)

WINDLASS AND MOORING WINCH HYDRAULIC Awaiting quotation of spares .


MOTOR
MAKER: FUKUSHIMA LTD.
TYPE: M2703
TOTAL NUMBER OF EIGHT(08)
ONE VERTICAL TYPE WITH HANDLE STORM VALVE Valves to be renewed in every
150Ø docking .
ONE ANGLE TYPE WITH HANDLE STORM VALVE 150Ø
ONE VERTICAL TYPE WITH HANDLE STORM VALVE
65Ø
ONE
MAINANGLE TYPE
ENGINE TOPWITH HANDLE STORM VALVE 65Ø 3 out of 4 units are leaking . It is for
BRACING
TOTAL QUANTITY FOUR (04) dampening the main engine
MAKER: BY CONTROL INC. vibrations
TYPE: HY 300

CARGO AND BALLAST HYDRAULIC VALVE ACTUATOR Awaiting quotation of spares . Case by
MAKER: NAKAKITA SEISAKUSHO CO LTD. case will plan the overhauling of
TYPE: PAC-80U-01,PAC-80U-02,PAC-80U-03 Cargo tanks valves actuators if leaking
TYPE: PAC-80U-04,PAC-80U-05 or not working properly .

VACUUM CONDENSER Gaskets & anodes


MAKER: DONGHWA ENTEC
TYPE: SHELL AND TUBE TYPE
SURFACE AREA: 250 M2
DWG: DHCC- 007850

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 26 of 32
AIR CONDITION COMPRESSOR Accomodation AC compressor
MAKER: YORK REFRIGERATION (SABROE) overhauling spares
TYPE: SMC 106 S
REFRIGERANT: 404A
WORKING PRESSURE: 24 BAR
VOLUME SWEPT:
CARGO OIL PUMP339 M3/H Mechanical seals to keep as spare
MAKER: SHINKO IND. LTD. onboard . Presently pumps
MODEL: 450-3 performance are satisfctory

FWD AND AFT STERN TUBE SEAL Stern tubes seals renewal . Tailshaft
MAKER: KOBELCO MARINE ENGINEERING COMPANY withdrawl will be done during this
TYPE: DX-670 special survey
FWD SEAL DWG: DX670004-1
AFT SEAL DWG: CX670001-1
BALLAST PUMP Mechanical seals to keep as spare
MAKER: SHINKO IND.LTD onboard . Presently pumps
MODEL: CV350 performance are satisfctory

H.T F.W EXPANSION TANK Level switch malfunctioing


MAKER: DAEHWA ENGINEERING
TYPE: LS-FS-3
TITLE: LEVEL SWITCH
DWG NO. DX005S-L
SPECS: AC125 15A/DC 30V 6A
LEVEL SWITCH Cargo tanks gauging system fault
finding is in progress . Kongsberg are
MODEL-TMR-702T not supporting . Awaiting quotation of
TOP MOUNTING spares from other vendors
ENCL-IP 56
CONN SIZE-ENGINE
AUXILIARY 5K 100 #3
A Big end bearings for two generators

ENGINE NO- SB6L23-2489


GEN NO-246689
MODEL NO- 6L23/30H
AUXILIARY ENGINE NO#2 Decarb spares for two generators .
Cylinder liners & connecting rods not
ENGINE NO-SB6L23-2488 included
GEN NO- 246688
MODEL NO-6L23/30H
ME F.O CIRCULATING PUMP Pumps ovrehauling basic spares
MAKER: IMO PUMP
MODEL: ACE 038K3 NQBP T4E Q182

PROVISION REFRIGERATION COMPRESSOR Refer compressor overhauling spares


MAAKER:HI PRESS KOREA YORK REFRIGERATION
MODEL: BFO 3

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 27 of 32
YOWOON MITUBISHI ELECTRO HYDRAULIC STEERING Ram Seals
GEER
YOWOON INDUSTRIES LTD.
MODEL: YDFT-170-2

MARINE GROWTH PREVENTING SYSTEM MGPS system , anodes cost


MAKER: KOREA CATHELCO LTD.
TYPE:
MG (COPPER) ANODES KSMG 800 (ONE PIECE
REQUIRED)
TC (ALUMINIUM) ANODES KSTC 800 (TWO PIECES LT cooler two valves
REQUIRED)

MAIN L.O COOLER ME LO cooler gaskets


MAKER: DONGHWA
TYPE: PLATE TYPE HEAT EXCHANGER
DWG NO: DHPHE-007903

CENTRAL F.W COOLER LT cooler gaskets


MAKER: DONGHWA ENTEC
TYPE: PLATE TYPE HEAT EXCHANGER
DWG NO: DHPHE-007902

BOILER F.O SUPPLY PUMP Two Boiler fuel oil supply pump
MAKER: KANGIRAM overhauling spares
MODEL: DCS7/5000.11 CLD 42

FWG DISTILATE PUMP Pumps ovrehauling basic spares


MAKER: DONGHWA ENTEC
MODEL: HQ2B-4020-SC
TYPE: CENTRIFUGAL PUMP

FWG EJECTOR PUMP Pumps ovrehauling basic spares


MAKER: SHIN SHIN HAMWORTHY
MODEL: C125 CID1

AE FO CIRCULATING PUMP Pumps ovrehauling basic spares


MAKER: IMO AB PUMP
MODEL: ACE 032N3 NQBP T4E Q182

AE FO SUPPLY PUMP Pumps ovrehauling basic spares


MAKER : IMO AB PUMP
MODEL: ACE 025N3 NQBP T4E Q162

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 28 of 32
ME F.O SUPPLY PUMP Pumps ovrehauling basic spares
MAKER: IMO PUMP
MODEL: ACE 032L3 NQBP T4E Q162

BOILER WATER CIRCULATING PUMP Pumps ovrehauling basic spares


HORIZONTAL CENTRIFUGAL
MAKER: NANIWA PUMP MFG.CO.,LTD.
MODEL: BBH-50DMW
BORE: 50
BOILER MAIN FEED WATER PUMP Pumps ovrehauling basic spares
HORIZONTAL CENTRIFUGAL
MAKER: NANIWA PUMP MFG.CO.,LTD.
MODEL : (EB4H-100)
BORE : 100
DAEWOO HEAVY INDUSTRIES LTD. Demister , nozzles cost
HULL NOS. H-5178-5179
Maker : Air Blowers
Air Products Order no: 14616-14617.

MAKER: Mac-GREGOR Spares already supplied onboard .


TYPE : HH 400-1519 Renewal done by shipstaff.

METAL FOIL INSERTED STEAM GASKETS (HIGH Boiler mountings gaskets


TEMPERATURE)

Bilge alarm body not in good


condition

FOR STX MAN B&W ENGINE AE two turbocharger overhauling


TURBOCHARGER MAKE: SS MAN B&W spares

Cathodic protection spares , putty


cost

WASTE OIL INCINERATOR Incinerator spares


TYPE-100SL-1WS
MAKE : HYUNDAI – ATLAS
TYPE : MAXI 100SL -1 W/S

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 29 of 32
CENTRIFUGAL PUMP Pumps ovrehauling basic spares
NANIWA PUMP
DRAWING NO- 99DS0336
BHR-40 (2SET)

NANIWA PUMP Pumps ovrehauling basic spares


VERTICAL CENTRIFUGAL
FEV-200E
DRAWING NO- 99DS0330

LIFE BOAT AIR CYLINDER // NOS - 6 // TYPE - AIR // Lifeboat 5 yearly service , load test ,
CAPACITY 40 LTRS . PLEASE FIND CETIFICATE wire renewal & davit shevaes
renewed during class annuals in
March 2022

NANIWA PUMP Pumps ovrehauling basic spares


VERTICAL CENTRIFUGAL
MODEL -FBWV-250
DRW NO-A0DS0432

NANIWA PUMP Pumps ovrehauling basic spares


VERTICAL CENTRIFUGAL PUMP
MODEL -FFV-100D
DRW NO- 99DS0333

NANIWA PUMP Pumps ovrehauling basic spares


2NOS ,
VERTI,CENTRI SELF PRIMING SYSTEM
MODEL -FE2V-250E

NOT WORKING, RECOMMENDED TO REPLACE Awaiting quotation

NON ASBESTOS BRAKE LINING FOR WINCHES Brake lining 20 mtr length
THICKNESS - 16mm
WIDTH - 140mm

MAN B&W Five units exhaust valves overhauling


basic spares

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 30 of 32
( FROM IMPA) GASKETS , WOUND, SPIRAL, ROUND
SHAPE WITH INNER AND OUTER RINGS (IOR)
TEMPERATURE: -250 DEG C to 500 DEG C
PRESSURE: 29.4 MPA
FLUID : WATER, STEAM OIL, SOLVENT, GAS
THICKNESS: 3 MM Radar scanner bearings , carbon
bushes

MAKE : HSD MAN B&W Five units fuel injectors valves


TYPE : 5S70MC overhauling basic spares
ENGINE NO. : ML1072
RATING : 19,100 BHP @ 91 RPM.

MAKE : HSD MAN B&W ME fuel pump overhauling spares .


TYPE : 5S70MC
ENGINE NO. : ML1072
RATING : 19,100 BHP @ 91 RPM.

Maker: HSD- MAN B&W Diesel Engines S70 MC ME Pneumatic valves overhauling kits
Ship Nos: Daewoo-5179
Engine Type: HSD-MAN B&W, 5S70MC.

Make: JUNG A Marine Equipment Manufacturing ME revolution spare counter not


Co., Ltd working .
Model: WSI-H-2-T-PI
Type: Straight Line Type
Drawing No.: WP-SDT-WWAY-12
AUX BOILER FEED WATER PUMP Pumps ovrehauling basic spares
MAKE: NANIWA PUMP
TYPE: HORIZONTAL CENTRIFUGAL PUMP
MODEL: EB2H-32
BORE: 32
ELCTRICAL MOTORS BEARINGS

BEFORE SEND REQUISTION (PH-E-24-2021) TOPPING UP AIR compressor block


TOPPING UP AIR COMPRESSOR MODEL NO- (H-63) supplied & successfully installed by
shipstaff

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 31 of 32
STEERING GEAR P/P NO-2
TYPE- 1V-FH2B-MK-RFBLA20D11
SERIAL NO-01520
MITSUBISHI
HEAVY INDUSTRIES LTD
TOKOYO JAPAN.900 SYSTEM
EVAC VACUUM Cabin vacuum toilets spares for
maintenance

Make: SSANGYONG - MAN B&W AE no 1 T/C cartridge damaged which


was beyond repair so reconditioned
one supplied

AALBORG Boiler basic burner routines spares

MAN B&W Main engine spares for decarb -4


UNITS ARE DUE

ABB TURBOCHARGER BEARINGS

© 2020 MariApps Marine Solutions Pte Ltd. All rights reserved. Page 32 of 32