FLS - Norville 15-11-2023

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 7

KEY PLAN

W N
S

Ma
kka
234.50

h
NORTH
6.55 221.40 6.55 E

15.00 m WIDE ROAD


8.80

8.80
DRIVEWAY
2.90

2.90
PROJECT NAME

MIXED OCCUPANCIES (SEPARATED)


RAMP UP RAMP UP
SEC 406.6E.P. GARAGE (S-2)

SEC 303.3 ASSEMBLY (A2)


SBC SEC 303.4 ASSEMBLY (A3)
ROOF TOP 201 SEC 304.1
OFFICES (B)
51.70

51.70
47.40

47.40
SEC 509 INCIDENTAL USES

TAB 601 TYPE I-B

BASIC DATA

RAMP UP
DOWN
RAMP

RAMP UP
17.24% SLOPE
RAMP DOWN
ENTRANCE

RAMP DN RAMP DN
RAMP 2

RAMP

RAMP 2
RAMP UP
DOWN

EXIT
1.40

1.40
OUTDOOR COURT OUTDOOR COURT
5.80

5.80
(TYPE I-B )

29.25
FIRE-RESISTANCE RATING - STRUCTURAL FRAME 2 Hrs
3.40

3.40
REQUIREMENTS FOR INCLUDING COLUMNS, GIRDERS, TRUSSES
STRUCTURE ELEMENTS - FLOOR CONSTRUCTION 2 Hrs
9.09% SLOPE
RAMP DOWN

10% SLOPE
RAMP UP
INCLUDING SUPPORTING BEAMS AND JOISTS
- ROOF CONSTRUCTION 1 Hr
OUTDOOR OUTDOOR INCLUDING SUPPORTING BEAMS AND JOISTS
131.20

131.20
RAMP UP
SEATING SEATING

67.35m WIDE ROAD


RAMP DN
m WIDE ROAD
160.00

160.00
FIRE APPARATUS ACCESS LEGEND
SYMBOL DESCRIPTION

RAMP UP RAMP UP RAMP UP RAMP DN FIRE APPARATUS MAIN


ACCESS ROAD

FIRE APPARATUS
CENTRAL

10% S
RAM
RAMP DOWN
10% SLOPE

FIRE APPARATUS PARKING SPACE


ROOF PARK FIRE APPARATUS HARDSTAND

86.50
TOP
15.0057.05

57.05
(_m) TRAVEL DISTANCE FROM
67.35

RAMP FROM BASEMENT 1


ROOF
RAMP TO BASEMENT 1

FIRE APPARATUS (Meter)

20.00
20% SLOPE
RAMP UP
TOP ASSEMBLY AREA
RAMP DOWN
5% SLOPE

FIRE HYDRANT

NOTES:
Fire apparatus is designed in accordance to section 503 of the SBC-801
64.95

and the NFPA 5000 7.1.5.2:


- Fire engine access road minimum width: 7.9m & 6m for private access.
- Unobstructed vertical clearance of not less than 4m (4.5 Recommended).
- Maximum Dead ends limit is 45m.

10% SLOPE
RAMP UP
- Imposed load: 34,050 kg.
RAMP DOWN
10% SLOPE

- Gradient not exceeding 10 percent.

Fire apparatus access road criteria


· Width ≥ 6 m
· Vertical clearance ≥ 4 m (4.5 m recommended by RCD)
· Inner turning radius ≥ 8.4 m
6.90

6.90
ROOF FLOOR OUTDOOR TERRACE ROOF FLOOR OUTDOOR TERRACE · Outer turning radius ≥ 14.4 m
· Maximum dead-end 45 m
· Slope 10%

FIRST FLOOR OUTDOOR TERRACE FIRST FLOOR OUTDOOR TERRACE


6.35

6.35
As detailed in the FLS Report for the project, the fire apparatus access
roads shall extend to within 45m (for non-sprinklered buildings) of all portions of
RAMP UP 7.69%
SLOPE

the building and all portions of the exterior walls of the first story (grade level) of
the building. The fire code official is authorized to increase the dimension of 45m
(if buildings are sprinklered) where the fire apparatus access roads cannot be
CANOPY CANOPY
7.70

7.70
met because of location on property, topography, waterways, nonnegotiable
MAIN ENTRY grades or other similar conditions, and an approved alternative means of fire
protection is provided (SBC 801 section 503.1.1 exception 1.2) This is proposed
to be increased to 137m since buildings are sprinkler protected per NFPA 5000.
20.00

20.00

20.00
SOUTH PARK SOUTH PARK
12.30

12.30

12.30
DROP OFF OWNER NAME
UP UP

UP
UP
UP
MP
RA

DN
MP

RA

PARKING PARKING
RA

MP

RAMP DN
RAMP UP

UP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

65.90 5.40 8.80 61.20 8.80 5.40 65.90


SAFETY CONSULTANT

6.55 71.30 78.80 71.30 6.55

60.00 m WIDE ROAD ARCH VIEW COMPANY


Address: 3321 Prince Mamduh Bin Abdulaziz st,
As Sulaymaniyah, Riyadh 12241
Kingdom of Saudi Arabia
SBC801 SEC 503.1.1 Buildings and facilities. Approved fire apparatus access roads shall be provided Tel: +966 11 279 0996 Email: info@arch-view.com
CR:1010749305 CSC: 674915 SCE: 5100001478
for every facility, building or portion of a building hereafter constructed or moved into or within the
jurisdiction. The fire apparatus access road shall comply with the requirements of this section and shall
TITLE
extend to within (45 m) of all portions of the facility and all portions of the exterior walls of the first story
of the building as measured by an approved route around the exterior of the building or facility.
Exceptions:
1:300 @ A0
1. The fire code official is authorized to increase the dimension of 45 m where any of the following
conditions occur: REV-2
1.1. The building is equipped throughout with an approved automatic sprinkler system installed in
15-11-2023
accordance with Section 903.3.1.1, 903.3.1.2 or 903.3.1.3.
KEY PLAN
N

4.35 .35 8.40 .40 9.70 .40 13.20 .45 6.50 .20 5.20 .20 5.20 .20 2.10 .60 3.40 .50 24.50 .45 30.65 .20 30.65 .45 24.50 .50 3.40 .60 2.10 .20 5.17 .23 5.20 .20 6.50 .45 13.20 .40 9.70 .40 8.35 .40 4.05 .30

Ma
kka
h
.20
.30
ACCESS ACCESS
STORAGE UNDER LPG HATCH HATCH STORAGE UNDER LPG
TANK (DESIGN SHOULD SHAFT FOR EXHAUST LOUVER SHAFT FOR EXHAUST LOUVER TANK (DESIGN SHOULD
COORDINATE WITH GAS STORAGE -9.40 m F.L. STORAGE STORAGE STORAGE PUMP LIFTING STATION STORAGE STORAGE STORAGE STORAGE LIFTING STATION PUMP STORAGE STORAGE STORAGE STORAGE COORDINATE WITH GAS

3.85
OPEN TO ABOVE OPEN TO ABOVE

3.95

3.95
SUMP PIT SUMP PIT
EARTH FILL COMPANY ROOM -9.40 m C.L. ROOM ROOM ROOM ROOM ROOM ROOM ROOM ROOM ROOM ROOM ROOM COMPANY EARTH FILL
(34.92 SQM.) ROOM 1 1 ROOM (34.92 SQM.)
-9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. (SEE PLUMBING -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. (SEE PLUMBING -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L.
DRAWINGS) DRAWINGS)
-9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. SAND TRAP -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. SAND TRAP -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
FD 45 FD 45

.35
.20

.20
S S S S S S S S S S S S S S S S S S S S

.30
CPoT = 18 M CPoT = 18 M

.30
47 46 46 47 47 38 46 47 46 47 46 47 46 47 39 46 46 47 47 46

9.30

9.30
EXHAUST FAN ROOM EXHAUST FAN ROOM
PD
3-A PD PD PD PD PD PD
3-B PD
(REFER TO EC . GS OF (REFER TO EC . GS OF FIRE

INT. EXIT STAIRWAY INT. EXIT STAIRWAY INT. EXIT STAIRWAY INT. EXIT STAIRWAY

3.50

3.50
FIRE A PERS ETAIL FOR A PERS ETAIL FOR
ARC ITECT APPRO AL) ARC ITECT APPRO AL)

-9.40 m F.L. -9.40 m F.L.


-9.40 m C.L.
1 2 3 -9.40 m C.L.
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58

7.80
FD 45
1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm FD 45

1.50 .20

1.50 .20
S S
36 36

4.00

4.00
.90

.90
.20 2.05 3.00 3.00 .60 3.00 11.65 3.00 3.00 .60 235 3.00 3.00 1.25198 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 4.10 4.10 1.25 3.48 235
3.47 .60 3.55 198 3.55 .60 3.55 3.55 .60 3.55 3.55 .60 3.55 3.55 .60 3.55 3.55 .60 235 3.55 3.55 198
.60 3.47 3.48 1.25 4.10 4.10 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 3.00 .60 3.00 235
3.00 1.25 3.00 198 3.00 .60 3.00 3.00 11.65 3.00 .60 3.00 3.00 2.05
.15

PLASTIC SPEED BUMP, AS -9.40 m F.L. -9.40 m F.L. -9.40 m F.L.

7.40

7.40

7.40
APPROVED -9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
.30 .30
.15 .15
.35 5.65 3.45 7.00 .60 6.00 .60 6.00 .60 6.00 1.80 5.45 .20 27.80 .20 .80 4.00 .60 4.10 .20 4.25 .60 6.95 .60 7.10 .60 7.10 .70 6.90 .80 6.90 .70 7.10 .60 7.10 .60 6.95 .60 4.25 .20 4.10 .60 4.00 .80 .20 27.80 .20 6.00 1.25 5.90 .70 6.00 .60 6.00 .60 7.45 .60 2.40 5.65 .35

.20

.20
VIP VIP
OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES

3.50

3.50

4.00
BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING

3.60

3.60
FD 45 S
39 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
FD 45 S
38

59 60 61 62 63 64 65 66 67 68 69 70 71 72

6.00

6.00
GS OF FIRE A PERS

GS OF FIRE A PERS
6.20

6.20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 .20 4.70 .30 1.20 3.80 .20 .35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

PROJECT NAME
.35 4.75 4.75

FRESH AIR FAN ROOM 3-A

FRESH AIR FAN ROOM 3-B


.30 1.90 .40 2.30 .30 2.40 .30 6.00 1.20 .30 1.85 .20 .20 1.85 1.50 6.00 .30 2.40 .30 2.30 .40

ETAIL FOR ARC ITECT APPRO AL)

ETAIL FOR ARC ITECT APPRO AL)


FD 90
S S
FD 90 PUMP ROOM S
FD 90
S
FD 90 FD 90S
FD 90
S
FD 90
S S
FD 90

.50

.50
49 49 49 49 49 49 49 49

OPEN TO ABOVE
.20

.80.20

.25.55.20

.20

.20
S S

OPEN TO ABOVE
47 -9.40 m C.L. 46
1.00

1.00
1.00
(30.00 SQM.)

(30.00 SQM.)
SHAFT SHAFT SHAFT SHAFT SHAFT SHAFT SHAFT S AFT S AFT SHAFT S AFT S AFT

.25
2
ACCESS
8 PUMP ROOM 8
ACCESS 2
A-401 A-511 A-511
RAMP 5% -9.25 m F.L. -9.40 m F.L. RAMP A-402

(REFER TO EC .

(REFER TO EC .
ELEC. ELEC.

2.50

2.50
-9.40 m C.L.

STORAGE
ELEC. -9.40 m C.L. -9.25 m F.L.R ELEC.
2.80

2.80

2.80
.30 1.40 .20

.40 1.40 .20


21 20 19 18 17 16 15 14 13 21 20 19 18 17 16 15 14 13 13 14 15 16 17 18 19 20 21 13 14 15 16 17 18 19 20 21
-9.40 m C.L. STORAGE ROO

SE SE

-9.40 m C.L. STORAGE ROO


SUMP R . .
STORAGE

12 12 12 12

R
2 FD 90
1 2 3 4 5 6 7 8 9 10 11

OPEN TO
1 PIT
SAND TRAP

FD 90 S
12
1 2 3 4 5 6 7 8 9 10 11 11 10 9 8 7 6 5 4 3 2 1

FD13m
-9.40 S
90
C.L.
SAND TRAP SUMP PIT
1 11 10 9 8 7 6 5 4 3 2 1 R
2
6.90 .80 6.90
FD 90
6.10

6.10
A-511 TRENCH WITH GRATING TRENCH WITH GRATING TRENCH WITH GRATING TRENCH WITH GRATING A-511
A-421
P ABOVE P P P A-421
FD 45 FD 45

.30

.30
.30

.30

.30
S S S S
30 1 2 -9.40 m F.L. 2 2 31
A-403 S -9.40 m F.L. S A-404
FD 90 GREEN LAN SCAPE AR SCAPE GREEN LAN SCAPE AR SCAPE FD 45 FD 90LO

9.20
LANDSCAPE & 13
-9.40 m C.L. -9.40 m C.L. 12 LANDSCAPE &

2.50

2.50
-9.25 m F.L. LO .C. .C. -9.25 m F.L.
2.20

2.20

2.20
S S

-9.40 m C.L. E E HARDSCAPE AREA R . E E FD 45


36 36 E E R . HARDSCAPE AREA E E -9.40 m C.L.

MIXED OCCUPANCIES (SEPARATED)


S S

7.70

7.70
24 25

RAW WELL WATER DOMESTIC WATER COMBINED FIRE & COMBINED FIRE & FD 90 FD 90 DOMESTIC DOMESTIC
.30

.30

.30

.30

.30

.30

.30
S S S S S S
-9.40 m F.L.

-9.40 m F.L.
FD 45 31 46
TANK 1 TANK 1 IRRIGATION TANK 1 OPEN IRRIGATION TANK 2 OPEN
1 2
IRRIGATION TAN 1 RA ELL ATER 2
WATERTANK 2 OPEN WATERTANK 3 OPEN
47
FD 45 30
6.30

6.20
OPEN TO ABO E TAN OPEN TO ABO E
2
ELE ATOR
OPEN TO ABOVE OPEN TO ABOVE TO ABOVE TO ABOVE 2.50 .30 2.10 .30 2.40 .10 2.40 .30 4.25 .20
ACCESS ACCESS
.20 4.25 .30 2.40 .10 2.40
2 .30 2.10 .30 2.40 .30 TO ABOVE TO ABOVE ELE ATOR 2
2.80

2.80
LO C RRENT A-420 A-420 (620 m³ APPROX.) (300 m³ APPROX.) A-420 LO C RRENT
ROO
LOBBY -9.25 m F.L. (310m³ APPROX.) (300 m³ APPROX.) (300 m³ APPROX.) (620 m³ APPROX.) 2
ELE ATOR -9.25 m F.L. RAMP RAMP
ELE ATOR (300 m³ APPROX.) (310 m³ APPROX.) LOBBY ROO
A-420 5% 5% -9.25 m F.L.
SEC 406.6E.P. GARAGE (S-2)
4.60

4.60
-9.40 m C.L. LOBBY -9.40 m C.L. -9.40 m C.L. LOBBY -9.25 m F.L.
-9.40 m C.L.
.20

.20

.20
.40 6.40 .40 6.20 .40 6.20 .40 12.60 .40 .40 12.60 .40 6.20 .40 6.20 .40 6.40 .40
-9.40 m F.L. -9.40 m F.L.
TD = 76 M

1.50

1.50
S S
PAT AY PAT AY
.40

.40.40
47
-9.40 m C.L. -9.40 m C.L. 46
1.90 .20 5.20 .30 2.00 .30 2.40 .10 2.40 .30 1.85 .20 6.60 .80 5.90 .20 1.85 .30 2.40 .10 2.40 .30 2.00 .30 5.20 .20 1.90
SEC 303.3 ASSEMBLY (A2)
.40

3.40

TD = 108 M
CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL

TD = 76 M TD = 108 M SBC SEC 303.4

6.25
ASSEMBLY (A3)
201 SEC 304.1
E IP ENT
122 121 120 119 118 117 116 115 114 113 112 111 110 109 108 107 106 105 104 103 102 101 100 99 98 97 96 95 94 93 92 91 90 89 88 87 86 85 84 83 82 81 80 79 78 77 76 75 74 73 E IP ENT
6.00

6.00

6.00

6.00

6.00

6.00
STORAGE
-9.25 m F.L. STORAGE
-9.40 m C.L. OFFICES (B)
VIP VIP VIP VIP VIP VIP VIP VIP

.20
PD PD PD PD PD PD PD PD
7.14% SLOPE

7.14% SLOPE
RAMP DOWN

SEC 509 INCIDENTAL USES

RAMP UP
AIN ELECTRICAL ROO

AIN ELECTRICAL ROO


TAB 601 TYPE I-B
FRO BASE ENT 1

-9.40 m C.L.
ENTRANCE RA P 2

-9.40 m F.L.

-9.40 m C.L.
-9.40 m F.L.

E IT RA P 2 TO

9.55
BASE ENT 1
8.40

8.40
-9.40 m F.L. -9.40 m F.L. -9.40 m F.L.
-9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
S S
20 21
FD 45 FD 45

1.25
-9.40 mS F.L.
S
47 -9.40 m F.L.
-9.40 m C.L.
-9.40 m46
C.L. BASIC DATA
123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172

STORAGE ROO

-9.40 m C.L.
-9.40 m F.L.
STORAGE ROO

-9.40 m C.L.
-9.40 m F.L.

7.75
ACCESS ACCESS
RAMP RAMP

13.30

13.30
2.80 .30 .30 2.80

.60
.30
S S
.20

1 2

FD 90 222 221 220 STAIRWAY


INT. EXIT 219 218 217 216 215 214 213 212 211 210 209 208 207 206 205 204 203 202 201 200 199 198 197 196 195 194 193 192 191 190 189 188 187 186 185 184 183 182 181 180 179 178 176STAIRWAY
177 EXIT
INT. 175 174 173 FD 90

1.90
1.70

-9.25 m F.L. -9.25 m F.L.

2.60
2 2
A-405 A-406
-9.40 m C.L. -9.40 m C.L.

.20
PD SUMP PIT PD PD PD PD SUMP PIT PD

1100 mm / 5.1 mm 1100 mm / 5.1 mm


P P
E ERGENCY

E ERGENCY

-9.40 m C.L.
-9.40 m F.L.
1 1
4.70

4.70
E IT

2 2

E IT
-9.40 m C.L.
-9.40 m F.L.

TD = 120 M TD = 120 M
3 3

4 4

5 5

17
6

7
-9.40 m F.L. SAND TRAP
-9.40 m F.L. SAND TRAP
-9.40 m F.L. 6

7 17

16

15
8

9
-9.40 m C.L. -9.40 m C.L. -9.40 m C.L. 8

9
16

15

215 198 215 198


14 10 10 14

8.50
13 12 11 11 12 13
1.20

.40 1.20
7.60

7.60
(TYPE I-B )
.40
STORAGE

STORAGE
2 Hrs
S S
FIRE-RESISTANCE RATING - STRUCTURAL FRAME
ROO

ROO
47 46

ENCLOSED PARKING GARAGE GROUP (S-2) REQUIREMENTS FOR INCLUDING COLUMNS, GIRDERS, TRUSSES
STRUCTURE ELEMENTS - FLOOR CONSTRUCTION 2 Hrs

.45
INCLUDING SUPPORTING BEAMS AND JOISTS
LIFTING STATION .20 9.00 .20 .20 9.00 .20 LIFTING STATION - ROOF CONSTRUCTION 1 Hr
2ND242
BASEMENT Floor Gross Area= 37520.00 SQ.M246
ACCESS

ACCESS
2 FD 45 FD 45 2 INCLUDING SUPPORTING BEAMS AND JOISTS

HATCH
HATCH

.20

.20
S S

3.25
36 36
(SEE PLUMBING
DRAWINGS) 223 224 225 226 227 228 229 230 231 232 233 234 235 236 237 238 239 240 241 243 244 245 247 248 249 250 251 252 253 254 255 256 257 258 259 260 261 262 263 264 (SEE PLUMBING
DRAWINGS)

.60
OPEN TO ABO E IT

OPEN TO ABO E IT
STEEL GRATING

STEEL GRATING
S E A ST FAN E A ST FAN S

OCCUPANT LOAD FACTOR = 19.00 SQM / PERSON


LANDSCAPE / LANDSCAPE /
FD 45 21
ROO 2 A ROO 2 B FD 45 20
ELECTRICAL ROO

ELECTRICAL ROO
HARDSCAPE HARDSCAPE

12.10

12.10
-9.40 m C.L.
-9.40 m F.L.

(REFER TO EC . GS OF (REFER TO EC . GS OF

-9.40 m C.L.
AREA AREA

-9.40 m F.L.
8.60

8.60
FIRE A PERS ETAIL FOR FIRE A PERS ETAIL FOR
ARC ITECT APPRO AL) ARC ITECT APPRO AL)

5.50
-9.40 m F.L. -9.40 m F.L.
-9.40 m C.L. -9.40 m C.L.
LEGEND
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77
290 289 288 287 286 285 284 283 282 281 280 279 TOTAL
278 OCCUPANT LOAD = 1975 PERSON
LIFTING STATION

277 3
LIFTING STATION
3
276 275 274 273 272 271 270 269 268 267 266 265
78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100

FDXX
(SEE PLUMBING (SEE PLUMBING
OTORBI ES OTORBI ES OTORBI ES OTORBI ES

.30
2.90 6.10 6.10 2.90
FIRE DOOR RATING (IN MINUTES)

ACCESS

ACCESS
DRAWINGS) DRAWINGS)

HATCH

HATCH
BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING OTORBI ES OTORBI ES OTORBI ES OTORBI ES
.20

1.25 .20
.30 3.40 .30 4.50 1.75 .30 3.40 .30

2.00
BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING
PD PD PD PD PD PD

-9.40 m F.L.
EGRRSS CAPACITY FACTOR = 5.1 MM FOR EACH PERSON (STAIRS) -9.40 m F.L. -9.40 m F.L.
PHD
PANIC HARDWARE DOOR
-9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
FIRE BARRIER 2-HRs RESISTANCE RATING

6.50

6.50
6.88

6.87
.35
.15 5.65
.20
.30 1.80
.20
1.85 6.00 .80 5.90 .20 13.30 .30 9.85 .30 10.00 .30 6.00 .60 6.00 .60 6.00 .60 8.20 1.25 6.95
TOTAL REQUIRED EXIT STAIR WIDTH = 5.1 MM X 1975 PERSON =10100 MM
.60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 6.95 1.25 8.20 .60 6.00 .60 6.00 .60 6.00 .30 10.00 .30 9.85 .30 13.30 .20 5.90 .80 6.00 1.85
.20
1.80 .30 6.05
.30 FIRE BARRIER 1-HR RESISTANCE RATING
3.10 .30 2.40 .30 6.00 1.20 1.20 6.10 .30 2.40 2.40 .30 6.10 1.20 1.20 6.00 .30 2.40 .30 3.10

FIRE PARTITION 1-HR RESISTANCE RATING


S S S S
FD 90 FD 9049 FD 90
49 FD 90 FD 90 FD 90
49 FD 90
49 FD 90
AVAILABLE DIRECT EXIT STAIRS CLEAR WIDTH = 10 STAIRS With Total Clear Width = 11800 MM

1.03
.30 1.15 .20

.25 1.20 .20

.25 1.20 .20

.30 1.15 .20

.30 1.15 .20


.25 1.40

.25 1.40
ACCESS ACCESS

.60
1.00

S AFT S AFT S AFT RAMP S AFT S AFT S AFT S AFT S AFT S AFT RAMP S AFT S AFT S AFT
7.14% SLOPE

7.14% SLOPE
RAMP DOWN

RAMP UP
INTERIOR EXIT STAIRWAY CASE
VIP VIP VIP VIP

.)
.)

2 2 2
A-401 A-407 A-408 2
ETAIL FOR

ETAIL FOR
A-402

AIR FAN ROO 2 B (16.33 S


AIR FAN ROON 2 A (16.33 S

ELEC. ELEC. ELEC. ELEC.


2.80

2.80

2.80

2.80

2.80

2.80

2.80

2.80
21 20 19 18 17 16 15 14 13 13 14 15 16 17 18 19 20 21 21 20 19 18 17 16 15 14 13 13 14 15 16 17 18 19 20 21

R . SE 1 2 3 4 5 6 7 8 9 10
12

11
12

11 10 9 8 7 6 5 4 3 2 1 R . R . 1 2 3 4 5 6 7 8 9 10
12

11
12

11 10 9 8 7 6 5 4 3 2 1
SE R .

291 292 2
FD 90 293 294 295 296 297 298 299 300 301 302 303 304 305 306 307 308 309 310 311 312 313 314 315 316 317 318 319 320 FD 90 2
321 322 EXIT ACCESS CORRIDOR

E IT RA P 1 TO
P P P P
GS OF FIRE A PERS

GS OF FIRE A PERS
A-421
FD 90 FD 90 A-421
OPEN TO ABO E

OPEN TO ABO E
FD 45 FD 45 FD 45 FD 45
FRO BASE ENT 1
ENTRANCE RA P 1

BASE ENT 1
ARC ITECT APPRO AL)

ARC ITECT APPRO AL)


.30
.30

.30

.30

.30

.30

.30

.30
S S S S S S S S
30 1 2 31 30 1 2 31
GREEN GREEN
FD 45 LANSCAPE LANSCAPE -9.25 m F.L. FD 45

9.08
2.20

2.20

2.20

2.20

2.20

2.20

2.20

2.20
S S S S S S
E E SUMP PIT E E E E SUMP PIT E E

13.10
SAND TRAP SAND TRAP
36 24 25 24 25 -9.40 m C.L. 36

12.73

12.73
AR SCAPE AR SCAPE
TRAVEL DISTANCE (TD)
EC .

EC .
.30

.30

.30

.30

.30

.30

.30

.30
S S S S
FD 45 31
FD 45 30
FD 45
31
FD 45 30
(REFER TO

(REFER TO
2 2 2 2
2.67

2.67
ELE ATOR ELE ATOR
3.07

3.07
ELE ATOR ELE ATOR
FRES

A-420 A-420 A-420 A-420

FRES
3.37

3.37

3.37

3.38
LO .C. LO .C. LO .C. LO .C.
R . LOBBY LOBBY R . R . LOBBY LOBBY R .
354 353 -9.25 m F.L.
-9.40 m C.L.
-9.25 m F.L.
-9.40 m C.L.
352 351 350 349 348 347 346 345 344 343 342 341 340 339 338 337 336 335 334 333 332 331 330 329 328 327 326 325 -9.25 m F.L.
-9.40 m C.L.
-9.25 m F.L.
-9.40 m C.L.
324 323 COMMON PATH OF TRAVEL (CPoT)
1.00

1.00
PD PD
.60

.60

.60
.30

.30

.30

.30
VIP VIP ACCESS ACCESS
VIP VIP
1.80

1.80

1.80

1.80
RAMP RAMP

.20 5.80 .30 2.00 .30 2.40 .10 2.40 .30 9.85 .30 2.40 .10 2.40 .30 2.10 .30 2.40 .30 .30 2.40 .30 2.10 .30 2.35 .20 2.35 .30 9.85 .30 2.40 .10 2.40 .30 2.00 .30 5.80 .20
DEAD END DISTANCE (DED)
INT. EXIT STAIRWAY -9.40 m F.L.
-9.40 m C.L. INT. EXIT STAIRWAY -9.40 m F.L.
-9.40 m C.L. INT. EXIT STAIRWAY -9.40 m F.L.
-9.40 m C.L. INT. EXIT STAIRWAY

-9.40 m C.L.
-9.40 m F.L.
-9.40 m C.L.
-9.40 m F.L.

EXIT SIGN

7.50
7.60

7.60
1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm
EXIT SIGN DIRECTIONAL

STORAGE ROO
STORAGE ROO

235 198 235 198 235 198 235 198

19.40
S S
47 46

355 356 357 358 359 360 361 362 363 364 365 366 367 368 369 370 371 372 373 374 375 376 377 378 379 380 381 382 383 384 385 386 387 388 389 390 391 392 393 394 395 396 397 398 399 400 401 402 403 404 405 406 ASSEMBLY POINT
6.00

6.00
EXIT DISCHARGE

12.10
LANDSCAPE / LANDSCAPE /
HARDSCAPE
AREA
ACCESS
RAMP
ACCESS
RAMP
HARDSCAPE
AREA FIRE APPARATUS ACCESS ROUTES
6.00

6.00

458 457 456 455 454 453 452 451 PD


450 449 448 447 446 445 444 443 442 PD
441 440 439 438 437 436 435 434 PD
433 432 PD
431 430 429 428 427 426 425 424 423 PD
422 421 420 419 418 417 416 415 414
PD
413 412 411 410 409 408 407

.60
1.40
6.05 .30 3.40 .25 6.00 .80 9.10 .80 9.20 1.25 9.00 .80 9.20 .80 9.20 .80 9.20 .60 8.20 1.25 6.95 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 6.95 1.25 8.20 .60 9.20 .80 9.20 .80 9.20 .80 9.00 1.25 9.20 .80 9.15 .75 6.00 .25 3.40 .30 6.00
.20 .20

-9.40 m F.L. -9.40 m F.L. -9.40 m F.L.


-9.40 m C.L. -9.40 m C.L. -9.40 m C.L.

XXXX
7.60

7.60

7.60
TD = 122 M

STEEL LOUVER PARTITION STEEL LOUVER PARTITION


6.00 10.40 6.10 .60 6.10 10.40 6.00
XXXX / X

459 460 461 462 463 464 465 466 467 468 469 470 471 472 473 474 475 476 477 478 479 480 481 482 483 484
FRES
(REFER TO EC
AIR FAN ROO
GS FOR FIRE A PERS
1A
ETAIL)
FRES AIR FAN ROO
(REFER TO EC GS FOR FIRE A PERS
1B
ETAIL)

485 486 487 488 489 490 491 492 493 494 495 496 497 498 499 500 501 502 503 504 505 506 507 508 509 510 XXXX XXXX
6.00

OPEN TO ABOVE OPEN TO ABOVE

FD 45 FD 45
12.00

12.00

12.00
6.00

566 565 564 563 562 561 560 PD


559 558 557 556 555 554 553 552 551 PD
550 549 548 547 546 545 544 543 542 PD
541 540 539 538 537 536 PD
535 534 533 532 531 530 529 528 527 526 PD
525 524 523 522 521 520 519 518 517 PD
516 515 514 513 512 511
ACCESS ACCESS
RAMP RAMP

OWNER NAME
7.60

7.60

7.60
CPoT = 20.5 M

-9.40 m F.L. -9.40 m F.L. -9.40 m F.L.


-9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
.20.80

.20.80
DG S
S ACCESS 1 ACCESS 36
36 RAMP RAMP
FD 45 E A ST FAN GREEN FD 45 E A ST FAN
ROO 1 A ROO 1 B
567 568 569 570 571 572 573 574 575 576 577 578 579 580 581 582 583 584 585 586 587 588 589 590 591 592 593 LANSCAPE
594 595 596 597 598 599 600 601 602 603 604 605 606 607 608 609 610 611 612 613 614 615 616 617 618 619 620
6.00

6.00

6.00
(REFER TO EC . GS OF (REFER TO EC . GS OF
FIRE A PERS ETAIL FOR
AR SCAPE FIRE A PERS ETAIL FOR
5.60

5.60
ARC ITECT APPRO AL) 4 (ARTIFICIAL GREEN) ARC ITECT APPRO AL)
-9.40 m F.L. A-509 -9.40 m F.L.
-9.40 m C.L. -9.25 m F.L. -9.40 m C.L.
FD 45 FD 45 FD 45
-9.40 m C.L.
CW-1
FD 45 FD 45 FD 45 SAFETY CONSULTANT
9.55

9.55
.20

.20

.20
S S S S S S S S S S DG S S S S S S S S S S
47 47 47 47 21 21 47 47 47 47 4 10 3 46 46 46 46 20 20 46 46 46 46
LOC ER LOC ER
-9.40 m F.L. -9.25 m F.L. -9.40 m F.L.
AS AS
2.20

-9.40 m C.L.
.20 1.60

S AFT FOR E A ST LO ER STORAGE


SAND TRAP
-9.40 m C.L. 4
-9.40 m C.L. 3 STORAGE
SAND TRAP
S AFT FOR E A ST LO ER
LIFTING STATION ALE LOC ER FE ALE LOC ER LIFTING STATION
2.50

2.50
3
OPEN TO ABO E
ROO CLEANING ALE TOI. FE ALE TOI. RECEPTION
4
CLEANING ROO OPEN TO ABO E
4.20

STORAGE STORAGE STORAGE STORAGE LC. ELEC. STORAGE STORAGE STORAGE STORAGE ELEC. LC. STORAGE STORAGE STORAGE STORAGE

4.35
(24.25 S .) 4 E IP ENT ROO OFFICE ROO E IP ENT 4 (24.25 S .)
.20

ROO ROO ROO ROO


ROO ROO
ROO (SEE PLUMBING ROO -9.40 mPITF.L.
SUMP
SEWAGE 8 7
LOBBY OFFICE 5 5 5 5 5 5 SEWAGE -9.40 mPITF.L.
SUMP ROO (SEE PLUMBING ROO
ROO ROO
ROO ROO ROO ROO
DRAWINGS) -9.40 m C.L.
SUMP PIT
( ANITOR CLOSET) -9.25 m F.L. 6 6 6 6 6 6 -9.25 m F.L. -9.25 m F.L. (SUMP PIT
ANITOR CLOSET) -9.40 m C.L. DRAWINGS)
2.00

-9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m C.L. -9.40 m C.L. 7 8 -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L. -9.40 m F.L.
1.80

C C C C C C -9.40 m C.L.
1.45

1.45
-9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. ACCESS -9.40 m C.L. GULLY S O. S O. S O. S O. S O. S O. GULLY
-9.40 m C.L. ACCESS -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L. -9.40 m C.L.
HATCH SS MOP SINK LOC ER LOC ER
SS MOP SINK HATCH
.15

.15

.15

.35
1 1 1
ARCH VIEW COMPANY
A-444 A-445 A-446
Address: 3321 Prince Mamduh Bin Abdulaziz st,
As Sulaymaniyah, Riyadh 12241
Kingdom of Saudi Arabia
Tel: +966 11 279 0996 Email: info@arch-view.com
1.20 1.20 1.20 1.20 1.20 1.20 1.65 2.00 2.00 1.65 1.20 1.20 1.20 1.20 1.20 1.20 CR:1010749305 CSC: 674915 SCE: 5100001478
.35 6.50 .20 9.75 .20 9.70 .20 9.50 .20 10.55 .20 3.00 .20 3.00 .20 3.00 .60 3.40 .60 5.60 .20 9.70 .20 8.80 .65 6.85 .20 .20 .20 .20 .20 .20 .20 7.10 .20 .20 .20 .20 .20 7.50 .20 7.10 .20 .20 .20 .20 .20 .20 .20 6.85 .65 8.80 .20 9.70 .20 5.60 .60 3.40 .60 3.00 .20 3.00 .20 3.00 .20
INTERIOR FINISHES
10.55 .20 9.50 .20 9.70 .20 10.05 .20 6.20 .35

INTERIOR AND CEILING FINISHES (UL723) REQUIREMENTS SHALL COMPLIED AS PER SBC-2018 CH. 8 SEC. 803.11 TABLE 803.11 AS FOLLOWS:

SPRINKLERED TITLE
2 CLASSIFICATION OF OCCUPANCY MIXED USE OCCUPANCY - SEPARATED SECTION 508 EGRESS TRAVEL REQUIREMENTS OCCUPANCY
CLASSIFICATION EXIT ENCLOSURE AND CORRIDORS ROOMS AND ENCLOSED SPACES
WITH SPRINKLER SYSTEM AS PER-SBC801-2018-SEC1017.2
GROUP A2 B B C
SUMMARY OF CODE ANALYSIS REPORT FOR BASEMENT 3 TYPE OF CONSTRUCTION: TYPE I-B SECTION 601 TYPE OF EXIT TRAVEL DISTANCE
DEAD END (METER)
COMMON PATH OF EGRESS GROUP A3 B B C
OCCUPANCY (METER) TRAVEL (METER) CPET GROUP B B C C
ALLOWABLE ACTUAL ALLOWABLE ACTUAL
GROUP M B C C 1:250 @ A0
NO. CODE ANALYSIS SBC 2018 BUILDING LIMITATIONS
AREA AREA HEIGHT HEIGHT
AS PER CODE TABLE 1017.2 AS PER CODE SECTION 1020.4 AS PER CODE TABLE 1006.2.1

75 Meters 6 Meters 6 Meters ENCLOSED PARKING S-2 C C C


GROUP A2
xMAIN OCCUPANCY CATEGORY: ENCLOSED PARKING GARAGE SECTION 406.6 4 COMMERCIAL BUILDING
TABLE 503 CLASS OF FLAME SPREAD AND SMOKED DEVELOPED ON INTERIOR WALL AND CEILING FINISHES REV-2
1 -2 STORIES LEVEL BASEMENTS. UL 133386.00 SQ.M 54.00 M 14.70 M GROUP A3 75 Meters 6 Meters 6 Meters
CLASS FLAME SPREAD SMOKE DEVELOPED
DETAILD OCCUPANCY CATEGORY: INCEDENTAL USES SECTION 509 -3 STORIES LEVELS ABOVE GRADE PLANE. 90 Meters 15 Meters 30 Meters 15-11-2023
GROUP B A 0-25 0-450
SM: BUILDINGS MULTI STORIES ABOVE GRADE PLANE EQUIPPED THROUGHOUT WITH AN AUTOMATIC SPRINKLER SYSTEM
GROUP M 75 Meters 15 Meters 23 Meters B 26-75 0-450
2 CLASSIFICATION OF OCCUPANCY SINGLE USE OCCUPANCY SECTION 508 5 FIRE PROTECTION AUTOMATIC SPRINKLER AS PER SBC SECTION 903
GROUP S-2 120 Meters 15 Meters 30 Meters C 76-200 0-450
KEY PLAN
N

.30 4.05 .35 8.50 .30 9.70 .30 13.30 .45 6.50 .20 5.20 .23 5.17 .20 2.40 .30 3.40 .20 24.80 .45 30.65 .20 30.65 .45 24.80 .20 3.40 .30 2.40 .20 5.20 .20 5.20 .20 6.50 .45 13.30 .30 9.70 .30 8.50 .35 4.05 .30

Ma
kka
h
.20
.30
ACCESS ACCESS
STORAGE UNDER LPG TANK HATCH
Electric Buggy Wheelie Bin Trailer
Trolley (1 row) HATCH
(DESIGN SHOULD SHAFT FOR EXHAUST LOUVER Bin Washing
Basin / Area SHAFT FOR EXHAUST LOUVER STORAGE UNDER LPG TANK
COORDINATE WITH GAS OPEN TO ABOVE AND BELOW MDF UPS STC GSM LIFTING STORAGE Electric Buggy Water Jets for Bin
Washing Zone
STORAGE LIFTING GSM STC UPS MDF OPEN TO ABOVE AND BELOW (DESIGN SHOULD COORDINATE

3.50

3.50
for Waste Transfer Equipment
STORAGE -5.40 m F.L.

3.85
STORAGE

3.95

3.95
Wheelie Bin Trailer Trolley and Waste Transfer Equipment
EARTH FILL COMPANY STEEL GRATING FLOOR ROOM ROOM ROOM ROOM STORAGE STATION 1 ROOM (2 rows) Washing
ROOM STATION 1 ROOM ROOM ROOM ROOM STEEL GRATING FLOOR WITH GAS COMPANY EARTH FILL
(34.92 SQM.) STORAGE ROOM FOR Power Mover ROOM ROOM -5.40 m C.L. (34.92 SQM.)
ACCESS ROOM ACCESS ROOM
-5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. RECYCLABLES WASTE TRANSFER -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L.
-5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
240-lit / 360-lit Bins Power Mover -5.40 m F.L. EQUIPMENT ROOM
-5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
FD 45 -5.40 m C.L. FD 45

.35
.20

.20
S S S S S S S S S S S S S S S S S S S S S S

.30

.30
CPoT = 18 M CPoT = 18 M
47 20 20 21 21 46 39 46 47 42 43 46 47 46 47 38 47 20 20 21 21 46

FD 45
45 FD 45 FD 45 FD 45 FD 45

9.30

9.30
OPENING TO B2 FD 45 FD FD
FD 45
45 FD 45 FD 45 FD 45 OPENING TO B2

EXHAUST FAN ROOM 3-A E A ST FAN ROO 3B


(REFER TO EC . GS OF FIRE A PERS

INT. EXIT STAIRWAY INT. EXIT STAIRWAY INT. EXIT STAIRWAY INT. EXIT STAIRWAY (REFER TO EC . GS OF FIRE A PERS

5.80

5.80
ETAIL FOR ARC ITECT APPRO AL) ETAIL FOR ARC ITECT APPRO AL)

-5.40 m F.L. -5.40 m F.L.


1 2 3 -5.40 m C.L.
4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 -5.40 m C.L.
56 57 58

6.60

6.60
PD PD PD PD

7.80
FD 45
1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm FD 45

1.50 .20

1.50 .20
S S
36 36
PD PD PD PD

.90

.90

.90

.90
235 198 -5.40 m F.L.
-5.40 m C.L. 235 198 -5.40 m F.L.
-5.40 m C.L. 235 198 -5.40 m F.L.
-5.40 m C.L. 235 198
GENERATOR OPENING PLASTIC SPEED BUMP, AS GENERATOR OPENING

7.40

7.40

7.40
ABOVE ABOVE
1.0M x 0.45M APPROVED 1.0M x 0.45M

.35 5.35 2.40 .60 .45 7.00 .60 6.00 .60 6.00 .60 6.00 1.25 6.00 .80 6.00 .40 6.00 .80 6.00 .40 6.00 .80 1.80 4.00 .60 4.10 .60.30 3.20 1.25 6.95 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 6.95 1.25 3.20 .60.30 4.10 .60 6.00 .80 6.00 .40 6.00 .80 6.00 .40 6.00 .80 6.00 1.25 6.00 .60 6.00 .60 6.00 .60 7.00 3.75
.15

FD 45 FD 45

.20

.20

.60.20
MOTORBIKES & MOTORBIKES & OTORBI ES
BICYCLE PARKING BICYCLE PARKING BICYCLE PAR ING OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES

3.50

3.50

4.00
BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING
20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

80 79 78 77 76 75 74 73 72 71 70 69 68 67 66 65 64 63 62 61 60 59

OPEN TO ABO E AN BELO

6.00

6.00

OPEN TO ABO E AN BELO


6.20

STEEL GRATING FLOOR


.30 4.80 .40 4.80 .30 2.00

STEEL GRATING FLOOR


.40 4.80 .30
PROJECT NAME
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 2.00 .30 4.80 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54

S AFT FOR FRES AIR

S AFT FOR FRES AIR

5.40
S S .50 S S S S S S
FD 90 FD 90 FD 90 FD 90 FD 90 FD 90 FD 90 FD 45 FD 90 FD 90

.50
49 49 49 49 49 49 49 49

.20

.20

.20
S S

.)

.)
47 46
1.00

1.00
1.00

1.00

1.00

1.00
SHAFT SHAFT SHAFT SHAFT SHAFT SHAFT SHAFT S AFT S AFT S AFT S AFT S AFT
FD 90

10.10

10.10
(30.00 S
2

(30.00 S
FD 90 S
A-401 ACCESS S
49
S ACCESS 2 FD 90 S

-5.25Nm F.L. N
49 49 A-402 49
N RAMP 5% RAMP N
ELEC. ELEC. -5.25 m F.L.

2.50

2.50

STORAGE
-5.40 m C.L.
STORAGE ROO

-5.40 m C.L. STORAGE ROO


ELEC. ELEC.
2.80

2.80

2.80

2.80
.30 1.40 .20

.30 1.40 .20


24 23 22 47 46 45 44 43 42 41 24 23 22 47 46 45 44 43 42 41 41 42 43 44 45 46 47 22 23 24 41 42 43 44 45 46 47 22 23 24
STORAGE

SE 40

R . 40 40

R . 40
-5.40 m C.L.SE
R
2
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39
2
-5.40 m C.L. FD 90 S
12
25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25

FD 90
-5.25 Sm F.L.
13 -5.40 m F.L. 2 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 R
2
6.10

6.10
A-511 A-511
A-421
P P P -5.40 m C.L. -5.40 m C.L. P A-421
FD 45 FD 45

.30

.30
.30

.30

.30

.30
S S 7.10 .60 7.10 S S
30 1 2 2 2 31
A-403 S S A-404
FD 90 GREEN LAN SCAPE AR SCAPE GREEN LAN SCAPE AR SCAPE FD 90

9.20
LANDSCAPE & LO .C. 13
LO 12
.C. LANDSCAPE &

2.50

2.50
-5.25 m F.L. -5.25 m F.L.
2.20

2.20

2.20

2.20
S S

-5.40 m C.L. FD 90 E E HARDSCAPE AREA R . E E 36 36 E E R . HARDSCAPE AREA E E FD 90


MIXED OCCUPANCIES (SEPARATED)
S S
-5.40 m C.L.

7.70

7.70
24 (ARTIFICIAL GRASS) (ARTIFICIAL GRASS) 25
-5.40 m C.L.
-5.40 m F.L.

-5.40 m F.L.
FD 90 RAW WELL WATER DOMESTIC WATER COMBINED FIRE & COMBINED FIRE & FD 90 FD 90 DOMESTIC DOMESTIC FD 90
.30

.30

.30

.30

.30

.30

.30

.30

.30

.30
S S S S S S

FD 45 31 46
TANK 1 TANK 1 IRRIGATION TANK 1 OPEN IRRIGATION TANK 2 OPEN
1 2
IRRIGATION TAN 1 RA ELL ATER 2
WATERTANK 2 OPEN WATERTANK 3 OPEN
47
FD 45 30
6.40

6.40
OPEN TO BELO TAN OPEN TO BELO
2
ELE ATOR
OPEN TO BELOW OPEN TO BELOW TO BELOW TO BELOW .30 2.40 .30 2.10 .30 2.35 .20 2.35 .30 3.20 .20
ACCESS
24.00 24.00
ACCESS
.20 3.20 .30 2.35 .20 2.35
2 .30 2.10 .30 2.40 .30 TO BELOW TO BELOW ELE ATOR 2
2.80

2.80
LO C RRENT (620m³ APPROX.) (300 m³ APPROX.) LO C RRENT

3.10

3.10
A-420 A-420 A-420
ROO LOBBY -5.25 m F.L. (310 m³ APPROX.) (300 m³ APPROX.) (300 m³ APPROX.) (620 m³ APPROX.) 2 ELE ATOR -5.25 m F.L. RAMP RAMP
-5.25 m F.L. ELE ATOR (300 m³ APPROX.) (310 m³ APPROX.) LOBBY ROO .50
A-420 5% 5%
SEC 406.6E.P. GARAGE (S-2)
4.60

4.60
-5.40 m C.L. LOBBY -5.40 m C.L. -5.40 m C.L. LOBBY -5.25 m F.L. 5.05
-5.40 m C.L.

.20
.40 6.40 .40 6.20 .40 6.20 .40 12.60 .40 .40 12.60 .40 6.20 .40 6.20 .40 6.40 .40
-9.40 m F.L. -9.40 m F.L.
TD = 76 M TD = 108 M TD = 108 M TD = 76 M

1.50

1.50
PAT AY PAT AY

10% SLOPE
RAMP UP
-9.40 m C.L. -9.40 m C.L.
.40.30

.30
1.90 .20 2.50 .30 2.40 .30 2.00 .30 2.35 .20 2.35 .30 1.85 .20 6.60 6.60 .20 1.85 .30 2.35 .20 2.35 .30 2.00 .30 2.40 .30 2.50 .20 1.90
SEC 303.3 ASSEMBLY (A2)

.40
CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL CHARGING PEDESTAL

SBC SEC 303.4

7.00
LAN SCAPE LAN SCAPE
ASSEMBLY (A3)
AR SCAPE
81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 AR SCAPE
201 SEC 304.1
6.00

6.00

6.00

6.00

6.00

6.00
AREA AREA
-5.25 m F.L. -5.25 m F.L.
-5.40 m C.L. VERTICAL CABLE
TRAY OPENING
ABOVE
VERTICAL CABLE
TRAY OPENING
ABOVE
0.20 X 0.65
VERTICAL CABLE
TRAY OPENING
ABOVE
0.20 X 0.65
VERTICAL CABLE
TRAY OPENING
ABOVE
0.20 X 0.65
VERTICAL CABLE
TRAY OPENING
ABOVE
0.20 X 0.65
VERTICAL CABLE
TRAY OPENING
ABOVE
-5.40 m C.L. OFFICES (B)
OPENING TO B2 0.20 X 0.65 0.20 X 0.65 OPENING TO B2

.20
9.09% SLOPE
RAMP DOWN

VERTICAL CABLE
TRAY OPENING
ABOVE PD PD
VERTICAL CABLE
TRAY OPENING
ABOVE
SEC 509 INCIDENTAL USES
PD PD PD PD PD PD
0.20 X 0.65
VERTICAL CABLE
TRAY OPENING
ABOVE
VERTICAL CABLE
TRAY OPENING
ABOVE
VERTICAL CABLE
TRAY OPENING
ABOVE
VERTICAL CABLE
TRAY OPENING
ABOVE
0.20 X 0.65
E IT RA P 2
AIN ELECTRICAL ROO

AIN ELECTRICAL ROO


TO GRO N
TYPE I-B
0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65

TAB 601

-5.40 m C.L.
-5.40 m F.L.
FLOOR
-5.40 m C.L.
-5.40 m F.L.

OPEN TO ABO E

8.80
ENTRANCE

8.40

8.40
RA P 2
FRO GRO N -5.40 m F.L. -5.40 m F.L. -5.40 m F.L.
FLOOR -5.40 m C.L. -5.40 m C.L. -5.40 m C.L.

18.59% SLOPE
RAMP UP
OPEN TO ABO E S
20
S
21
FD 45 FD 45

1.25
-5.40 mS F.L.
S
47 -5.40 m F.L.
-5.40 m C.L.
-5.40 m46
C.L. BASIC DATA
STORAGE ROO

180 179 178 177 176 175 174 173 172 171 170 169 168 167 166 165 164 163 162 161 160 159 158 157 156 155 154 153 152 151 150 149 148 147 146 145 144 143 142 141 140 139 138 137 136 135 134 133 132 131
-5.40 m C.L.
-5.40 m F.L.

STORAGE ROO

-5.40 m C.L.
-5.40 m F.L.
ACCESS ACCESS
RAMP RAMP

13.30

13.30

10.95
14.
VERTICAL CABLE VERTICAL CABLE
TRAY OPENING TRAY OPENING
ABOVE ABOVE
2.80 .30 0.20 X 0.65 0.20 X 0.65 .30 2.80
.30

.30
S S
1 2

FD 90 181 182 183 STAIRWAY


INT. EXIT 184 185 186 187 VERTICAL CABLE
TRAY OPENING
ABOVE
188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221 222 223 224
VERTICAL CABLE
TRAY OPENING
ABOVE
225 226 EXIT
INT. 228 229
227STAIRWAY 230 FD 90
-5.25 m F.L. 0.20 X 0.65 0.20 X 0.65
-5.25 m F.L.
2.60

2.60
2 2
A-405 A-406
-5.40 m C.L. -5.40 m C.L.
P P
LINE OF GLASS FLOORING ABOVE

.20
N 25 25
N
ENTRANCE 26

27
26

27

1100 mm / 5.1 mm 1100 mm / 5.1 mm


PD PD
24 28 28 24

RA P 2 TO
-5.40 m C.L.

E ERGENCY

E ERGENCY
-5.40 m F.L.

23 29 29 23

-5.40 m C.L.
-5.40 m F.L.
22 30 30 22

E IT RA P 2
E IT

E IT
3.90

3.90
BASE ENT 2
TD = 120 M TD = 120 M
21 31 31 21

20 32 PD PD PD PD PD PD 32 20

FRO
19 33 33 19

34

35
-5.40 m F.L. -5.40 m F.L. -5.40 m F.L. 34

35

-5.40 m C.L. -5.40 m C.L. -5.40 m C.L.


BASE ENT 2
44 36 36 44

(SLAB OPENING FOR GLASS FLOORING)


43 37 37 43

215 198 215 198


42 38 38 42

LINE OF GLASS FLOORING ABOVE


LINE OF GLASS FLOORING ABOVE

8.50
41 40 39 39 40 41
1.30

1.30
7.60

7.60
(TYPE I-B )
.30

.30
STORAGE

STORAGE
2 Hrs
S S
7.14% SLOPE

7.14% SLOPE
RAMP DOWN

FIRE-RESISTANCE RATING - STRUCTURAL FRAME


ROO

47 46

RAMP UP
14.40

ROO
REQUIREMENTS FOR INCLUDING COLUMNS, GIRDERS, TRUSSES

ENCLOSED PARKING GARAGE GROUP (S-2) STRUCTURE ELEMENTS - FLOOR CONSTRUCTION 2 Hrs

6.90

.45
INCLUDING SUPPORTING BEAMS AND JOISTS
LIFTING
S
39
.20 9.00 .20 .20 9.00 .20
S
38 LIFTING
- ROOF CONSTRUCTION 1 Hr
ACCESS

ACCESS
FD 45 FD 45 INCLUDING SUPPORTING BEAMS AND JOISTS

HATCH
HATCH

.20

.20
S S

3.25
STATION 2 36 36 STATION 2

272 271 270 269 268 267 266 265 264 263 262 261 260 259 258 257 256 255 254 232 231
2ND253 252 251 250
SQ.M249 248 247 246 245 244 243 242 241 240 239 238 237 236 235 234 233
ACCESS ROOM OPENING TO B2 ACCESS ROOM

BASEMENT Floor Gross Area= 37520.00


OPENING TO B2 VERTICAL CABLE VERTICAL CABLE
TRAY OPENING TRAY OPENING
ABOVE ABOVE
S AFT FOR E A ST LO ER

S AFT FOR E A ST LO ER
0.20 X 0.65 0.20 X 0.65

.20

.20
OPEN TO ABO E AN BELO

OPEN TO ABO E AN BELO


STEEL GRATING FLOOR

STEEL GRATING FLOOR


EXHAUST FAN ROOM VERTICAL CABLE VERTICAL CABLE E A ST FAN
TRAY OPENING TRAY OPENING
ELECTRICAL ROO

S ABOVE
LINE OF GLASS FLOORING ABOVE ABOVE ROO 2 B S

ELECTRICAL ROO
FD 45 2-A FD 45
.)

.)
21 0.20 X 0.65 0.20 X 0.65 20
(REFER TO EC . GS OF
-5.40 m C.L.
-5.40 m F.L.

-5.40 m C.L.
-5.40 m F.L.
(REFER TO EC . GS OF

12.10

12.10
FIRE A PERS ETAIL FOR

OCCUPANT LOAD FACTOR = 19.00 SQM / PERSON


S S
(24.92 S
8.60

8.60
FIRE A PERS ETAIL FOR

(24.92 S
39 38 ARC ITECT APPRO AL)
ARC ITECT APPRO AL)

5.90

5.90
14.80
-5.40 m F.L. -5.40 m F.L.
LEGEND
(SLAB OPENING FOR GLASS FLOORING)
-5.40 m C.L. -5.40 m C.L.
LIFTING LIFTING
55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77
STATION 3 STATION 3 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100
273 274 275 276 277 278 279 280 281 282 283 284 285 286
ACCESS ROOM ACCESS ROOM 287 288 289 290 291 292 293 294 295 296 297 298
TOTAL OCCUPANT LOAD = 1975 PERSON FDXX

.30

.30
2.90 6.10

FIRE DOOR RATING (IN MINUTES)


OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES OTORBI ES 6.10 2.90

ACCESS

ACCESS

2.00
HATCH

HATCH
BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING BICYCLE PAR ING
.20

.20
.30 3.40 .30
.30 3.40 .30

PHD
VERTICAL CABLE
TRAY OPENING
VERTICAL CABLE
TRAY OPENING
PANIC HARDWARE DOOR
EGRRSS CAPACITY FACTOR = 5.1 MM FOR EACH PERSON (STAIRS)
ABOVE PD PD
ABOVE
PD PD PD PD
0.20 X 0.65 0.20 X 0.65

-5.40 m F.L. -5.40 m F.L. -5.40 m F.L.


-5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
FIRE BARRIER 2-HRs RESISTANCE RATING

6.50
6.87

6.87
.30

.50 5.05
.50
.30 1.80
.20
1.85 6.00 .80 5.90
.60
.20

2.50 .30 2.40 .30


12.70

7.20
.30 9.85 .30

4.80
10.00

.40 4.80
.30 6.00 .60 6.00 .60 6.00 .60 8.20 1.25 6.95

TOTAL REQUIRED EXIT STAIR WIDTH = 5.1 MM X 1975 PERSON =10100 MM


.60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 7.10 .60 6.95 1.25 8.20 .60 6.00 .60 6.00 .60 6.00 .20

4.80
10.10

.20 5.00
.30 9.85 .30

7.20
12.70

.30 2.40 .30 2.50


.20
.60
5.90 .80 6.00 1.85
.20
1.80 .30

.50
5.05 .50
.30 FIRE BARRIER 1-HR RESISTANCE RATING
FIRE PARTITION 1-HR RESISTANCE RATING
S S S S
FD 90 FD 90 FD 90 FD 90 FD 90 FD 90 FD 90 FD 90

1.25 .38
49 49 49 49

ACCESS ACCESS
1.65

1.65

1.65

1.65

1.65

1.65

1.65
AVAILABLE DIRECT EXIT STAIRS CLEAR WIDTH = 10 STAIRS With Total Clear Width = 11800 MM

1.00
S AFT S AFT S AFT RAMP RAMP S AFT S AFT S AFT

10% SLOPE
S AFT S AFT S AFT S AFT S AFT S AFT

RAMP UP
VERTICAL CABLE VERTICAL CABLE

INTERIOR EXIT STAIRWAY CASE


TRAY OPENING TRAY OPENING
2 ABOVE ABOVE
RAMP DOWN

S 2 S 2 S
10% SLOPE

GS OF FIRE A PERS ETAIL FOR

GS OF FIRE A PERS ETAIL FOR


0.20 X 0.65 0.20 X 0.65 S
2
OPEN TO ABO E AN BELO STEEL GRATING FLOOR

OPEN TO ABO E AN BELO STEEL GRATING FLOOR


49 A-401
.)

.)
N A-407 N 49 49 N A-408 N 49
A-402
ELEC. ELEC. ELEC. ELEC.
2.80

2.80

2.80

2.80

2.80

2.80

2.80

2.80
24 23 22 47 46 45 44 43 42 41 41 42 43 44 45 46 47 22 23 24 24 23 22 47 46 45 44 43 42 41 41 42 43 44 45 46 47 22 23 24

SE 40 40 40 40

SE
AIR (16.87 S

AIR (16.87 S
R . 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 R . R . 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 R .

330 329 FD 45
2
A-421
FD 90
P FD
P 90
FD 45 328 327 326 325 324 323 322 321 320 319 318 317 316 315 314 313 312 311 310 309 308 307 306 305 304 303 302 301 FD 45 FD 90
P FD
P 90 2
A-421
FD 45 300 299 EXIT ACCESS CORRIDOR
ARC ITECT APPRO AL)

ARC ITECT APPRO AL)


-5.40 m C.L.
-5.40 m C.L.

-5.40 m F.L.
.30

.30

.30

.30

.30

.30

.30

.30
S S S S S S S S
-5.40 m F.L.

30 1 2 31 30 1 2 31
GREEN GREEN
FD 45 -5.25 m F.L. LANSCAPE -5.25 m F.L. LANSCAPE -5.25 m F.L. FD 45 E IT RA P 1 TO

9.07
2.20

2.20

2.20

2.20

2.20

2.20

2.20

2.20
ENTRANCE S
36
S
E E E E S S
E E E E S
-5.40 m C.L.
S
36
S AFT FOR FRES

S AFT FOR FRES


24 25 24 25
-5.40 m C.L. -5.40 m C.L.

12.73

12.73
AR SCAPE AR SCAPE GRO N FLOOR
RA P 1 (ARTIFICIAL GRASS)
-5.25 m F.L.
-5.40 m C.L. (ARTIFICIAL GRASS)
OPEN TO ABO E TRAVEL DISTANCE (TD)
.30

.30

.30

.30

.30

.30

.30

.30
S S S S
FD 45
31
FD 45 30
FD 45
31
FD 45 30
FD 45
(REFER TO EC .

(REFER TO EC .
FRO GRO N
FLOOR 2
ELE ATOR
2
ELE ATOR ELE ATOR
2
ELE ATOR
2
3.07

3.07

A-420 A-420 A-420 A-420


3.37

3.37

3.37

3.37
LO .C. LO .C.

3.67

3.67
OPEN TO ABO E LO C RRENT LOBBY LOBBY R . R . LOBBY LOBBY LO C RRENT

331 332 ROO


-5.25 m F.L.
-5.40 m C.L.
-5.25 m F.L.
-5.40 m C.L.
333 334 335 336 337 338 339 340 341 342 343 344 345 346 347 348 349 350 351 352 353 354 355 356 357 358 359 360 -5.25 m F.L.
-5.40 m C.L.
-5.25 m F.L.
-5.40 m C.L.
ROO
361 362 COMMON PATH OF TRAVEL (CPoT)
.60

.60

.60
.30
.30

.30

.30
VERTICAL CABLE VERTICAL CABLE

20% SLOPE
RAMP UP
TRAY OPENING TRAY OPENING
ABOVE ABOVE
0.20 X 0.65
ACCESS ACCESS 0.20 X 0.65
1.80

1.80

1.80

1.80
PD RAMP PD PD PD PD RAMP PD

.20 2.50 .30 2.40 .30 2.00 .30 2.35 .20 2.35 .30 9.85 .30 2.35 .20 2.35 .30 2.10 .30 2.50 .20 .20 2.50 .30 2.10 .30 2.35 .20 2.35 .30 9.85 .30 2.35 .20 2.35 .30 2.00 .30 5.80 .20
DEAD END DISTANCE (DED)
INT. EXIT STAIRWAY -5.40 m F.L.
INT. EXIT STAIRWAY -5.40 m F.L.
INT. EXIT STAIRWAY -5.40 m F.L.
INT. EXIT STAIRWAY
-5.40 m C.L.
-5.40 m F.L.

-5.40 m C.L. -5.40 m C.L. -5.40 m C.L.

-5.40 m C.L.
-5.40 m F.L.
N

EXIT SIGN
VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE
TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING
7.60

7.60
ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE ABOVE
0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65

1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm 1200 mm / 5.1 mm

14.81% SLOPE
RAMP UP
14.81% SLOPE
RAMP DOWN

EXIT SIGN DIRECTIONAL

STORAGE ROO
STORAGE ROO

235 198 235 198 235 198 235 198

19.40
S S
47 46

LINE OF GLASS FLOORING ABOVE

ASSEMBLY POINT

E IT RA P 1 FRO
410 409 408 407 406 405 404 403 402 401 400 399 398 397 396 395 394 393 392 391 390 389 388 387 386 385 384 383 382 381 380 379 378 377 376 375 374 373 372 371 370 369 368 367 366 365 364 363

BASE ENT 2
ENTRANCE
RA P 1 TO
EXIT DISCHARGE

(SLAB OPENING FOR GLASS FLOORING)


BASE ENT 2

LINE OF GLASS FLOORING ABOVE


LINE OF GLASS FLOORING ABOVE

14.70
FIRE APPARATUS ACCESS ROUTES
7.14% SLOPE

7.14% SLOPE
RAMP DOWN

ACCESS ACCESS

RAMP UP
5.20

5.20
RAMP RAMP
PD PD PD PD PD PD

411 412 413 414 415 416 417 418 419 420 421 422 423 424 425 426 427 428 429 430 431 432 433 434 435 436 437 438 439 440 441 442 443 444 445 446 447 448 449 450

.60
1.40
-5.25 m F.L.
-5.40 m C.L. -5.25 m F.L.
6.05 .30 3.40 .25 6.00
-5.40 m C.L. 6.00 .25
.20
3.40 .30 6.05

TD = 120 M
.20
-5.40 m F.L. -5.40 m F.L. ( ARTIFICIAL GRASS) -5.40 m F.L.
GREEN
-5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
LAN SCAPE

FLOOR
XXXX
FLOOR

31.60

31.60

LINE OF GLASS FLOORING ABOVE

7.60
AREA

ESCALATOR REFERS TO MITSUBISHI


ESCALATOR REFER TO MITSUBISHI

GRO N
14.80
(SLAB OPENING FOR GLASS FLOORING)
P TO GRO N

XXXX / X
OPEN ABOVE

OPEN ABOVE
25.60

25.60
O N FRO
17.10

17.10
ESCALATOR GOING

ESCALATOR GOING

498 497 496 495 494 493 492 491 490 489 488 487 486 485 484 483 482 481 480 479 478 477 476 475
FRESH AIR SHAFT
OPEN TO BELOW
FRESH AIR SHAFT
OPEN TO BELOW 474 473 472 471 470 469 468 467 466 465 464 463 462 461 460 459 458 457 456 455 454 453 452 451 XXXX XXXX
4.00

4.00

(16.00 SQM.) (16.00 SQM.)


(REFER TO EC . GS OF FIRE A PERS (REFER TO EC . GS OF FIRE A PERS
ETAIL FOR ARC ITECT APPRO AL) ETAIL FOR ARC ITECT APPRO AL)
4.00 4.00
FD 45 FD 45

12.00
STEEL LOUVER PARTITION STEEL LOUVER PARTITION

499 500 501 502 503 504 505 506 507 508 509 510 511 512 513 514 515 516 517 518 519 520 521 522 523 524 525 526 527 528 529 530 531 532 533 534 535 536 537 538 539 540 541 542 543 544 545 546
3.30

3.30

ACCESS ACCESS
RAMP RAMP

A-422-A
1 1
A-422-A
OWNER NAME
1.71 2.70 2.69 2.69 2.70 1.71

17.00 6.10 .60 6.10 17.00


7.60

7.60

7.60
-5.40 m F.L. -5.40 m F.L. -5.40 m F.L.
-5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
.80

.80
.20.80

.20.80
PHD PHD PHD PHD
.20

.20

S DG DG S
36 ACCESS 1 2 ACCESS 36
OPENING TO B2 RAMP 1 2 RAMP OPENING TO B2
EMERGENCY EMERGENCY E A ST FAN
FD 45 E A ST FAN EXIT DOOR EXIT DOOR FD 45 ROO 1 B

584 583 582 581 580 579 578 577 576 575 ROO 1 A
574 573 572 571 570 569 568 567 566 565 564 563 562 561 560 559 558 557 (REFER TO EC . GS OF
556 555 554 553 552 551 550 549 548 547

6.00
-5.25 m F.L. FIRE A PERS ETAIL FOR
SHOW RACK

SHOW RACK

(REFER TO EC . GS OF
ARC ITECT APPRO AL)
5.60

5.60
FIRE A PERS ETAIL FOR
ARC ITECT APPRO AL)
-5.40 m C.L. LOBBY LOBBY
-5.40 m F.L. -5.40 m F.L.
-5.40 m C.L.
FD 45 FD 45
DG
MALE PRAYER HALL ADD EXIT DOORS FEMALE PRAYER HALL DG
FD 45 FD 45
-5.40 m C.L.
SAFETY CONSULTANT
9.55

9.55
9.60

9.60

3 4
DUMMY DUMMY DUMMY DUMMY

.20
S S S S S S S S DG DG S S S S S S S S
47 47 47 47 21 21 39 47 3
COLUMN COLUMN COLUMN
-5.25 m F.L. COLUMN
4 46 38 20 20 46 46 46 46
FD 45 ABL TION -5.25 m F.L.
-5.40 m C.L. FD 45
-5.40 m C.L.
SLOPE

SHAFT FOR EXHAUST LOUVER SHAFT FOR EXHAUST LOUVER


LO -5.25 m F.L. LO
OPEN TO ABOVE AND BELOW LIFTING TOILET 3 (MEN) TOILET 4 (WOMEN) LIFTING OPEN TO ABOVE AND BELOW
2.50

2.50
ELEC. -5.40 m C.L. ELEC.
HANDWASH

STORAGE STORAGE STORAGE STORAGE C RRENT C RRENT STORAGE STORAGE STORAGE STORAGE
STEEL GRATING FLOOR ROO ROO STEEL GRATING FLOOR

4.40
ROO STATION 4 STORAGE PUBLIC TOILET (MEN) PUBLIC TOILET (WOMEN) STORAGE STATION 4 ROO
ROO ROO ROO ROO (22.75 SQM.) (22.75 SQM.) ROO ROO ROO ROO
-5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L.
ACCESS ROOM ROO
-5.40 m F.L. JAN. WC WC WC WC
PWD
WC CPoT = 25 M ROO
-5.40 m F.L.
ACCESS ROOM
-5.40 m F.L.
-5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L. -5.40 m F.L.
1.45

1.45
-5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. ACCESS -5.40 m C.L. ACCESS -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L. -5.40 m C.L.
HATCH -5.40 m C.L. HATCH -5.40 m C.L.

.30
1 1 1 1 1
ARCH VIEW COMPANY
A-447 A-442 A-449 A-443 A-448
Address: 3321 Prince Mamduh Bin Abdulaziz st,
As Sulaymaniyah, Riyadh 12241
Kingdom of Saudi Arabia
Tel: +966 11 279 0996 Email: info@arch-view.com
CR:1010749305 CSC: 674915 SCE: 5100001478
.35 6.50 .20 9.75 .20 9.70 .20 9.50 .20 10.55 .20 3.00 .20 6.60 .20 3.40 .20 6.00 .20 18.30 1.25 1.25 1.20 1.20 1.20 1.20 1.70 2.40 .20 19.90 .20 19.94 .16 2.40 1.70 1.20 1.20 1.20 1.20 1.25 1.25 18.30 .20 6.00 .20 3.40 .20 6.60 .20 3.00 .20
INTERIOR FINISHES
10.55 .20 9.50 .20 9.70 .20 9.75 .20 6.55 .30

INTERIOR AND CEILING FINISHES (UL723) REQUIREMENTS SHALL COMPLIED AS PER SBC-2018 CH. 8 SEC. 803.11 TABLE 803.11 AS FOLLOWS:

SPRINKLERED TITLE
2 CLASSIFICATION OF OCCUPANCY MIXED USE OCCUPANCY - SEPARATED SECTION 508 EGRESS TRAVEL REQUIREMENTS OCCUPANCY
CLASSIFICATION EXIT ENCLOSURE AND CORRIDORS ROOMS AND ENCLOSED SPACES
WITH SPRINKLER SYSTEM AS PER-SBC801-2018-SEC1017.2
GROUP A2 B B C
SUMMARY OF CODE ANALYSIS REPORT FOR BASEMENT 3 TYPE OF CONSTRUCTION: TYPE I-B SECTION 601 TYPE OF EXIT TRAVEL DISTANCE
DEAD END (METER)
COMMON PATH OF EGRESS GROUP A3 B B C
OCCUPANCY (METER) TRAVEL (METER) CPET GROUP B B C C
ALLOWABLE ACTUAL ALLOWABLE ACTUAL
GROUP M B C C 1:250 @ A0
NO. CODE ANALYSIS SBC 2018 BUILDING LIMITATIONS
AREA AREA HEIGHT HEIGHT
AS PER CODE TABLE 1017.2 AS PER CODE SECTION 1020.4 AS PER CODE TABLE 1006.2.1

75 Meters 6 Meters 6 Meters ENCLOSED PARKING S-2 C C C


GROUP A2
xMAIN OCCUPANCY CATEGORY: ENCLOSED PARKING GARAGE SECTION 406.6 4 COMMERCIAL BUILDING
TABLE 503 CLASS OF FLAME SPREAD AND SMOKED DEVELOPED ON INTERIOR WALL AND CEILING FINISHES REV-2
1 -2 STORIES LEVEL BASEMENTS. UL 133386.00 SQ.M 54.00 M 14.70 M GROUP A3 75 Meters 6 Meters 6 Meters
CLASS FLAME SPREAD SMOKE DEVELOPED
DETAILD OCCUPANCY CATEGORY: INCEDENTAL USES SECTION 509 -3 STORIES LEVELS ABOVE GRADE PLANE. 90 Meters 15 Meters 30 Meters 15-11-2023
GROUP B A 0-25 0-450
SM: BUILDINGS MULTI STORIES ABOVE GRADE PLANE EQUIPPED THROUGHOUT WITH AN AUTOMATIC SPRINKLER SYSTEM
GROUP M 75 Meters 15 Meters 23 Meters B 26-75 0-450
2 CLASSIFICATION OF OCCUPANCY SINGLE USE OCCUPANCY SECTION 508 5 FIRE PROTECTION AUTOMATIC SPRINKLER AS PER SBC SECTION 903
GROUP S-2 120 Meters 15 Meters 30 Meters C 76-200 0-450
Y ELEV. 632.973 .20 23.80 12.60 161.30 12.60 23.80 .20 REF. ELEV. +1.716 ROAD
LEV. +0.659 ROAD SURVEY ELEV. 633.974 SURVEY ELEV. 634.030
4.50 .20 8.60 .20 9.70 .60 9.70 .20 8.60 .30 4.40
KEY PLAN
.60

.20
.20

.30
1.10

1.10

Ma
S AFT FOR E A ST
S AFT FOR E A ST

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)

(4000 Ltrs.)
LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G

LPG STORAGE TANK-A/G


LO ER

kka
LO ER

3.60

3.60
4.30

DEEP WELL (34.92 S .) DEEP WELL

4.00
4.20

4.20
CONTROL LPG TAN S (34.92 S .) LPG TAN S CONTROL
RE O ABLE STEEL DRIVEWAY DRIVEWAY DRIVEWAY DRIVEWAY DRIVEWAY RE O ABLE STEEL GRATING
GRATING

h
REMOVABLE GRATING REMOVABLE GRATING
.20

.20
1.20

1.20
S S
19 9.70 x 3.50 (33.95 m²) 9.70 x 3.50 (33.95 m²) 18

7.50

7.50

11.70
+0.30 FL +0.30 FL +0.30 FL +0.30 FL +0.30 FL
+0.20 CL +0.20 CL +0.20 CL +0.20 CL +0.20 CL
PAT AY
+0.50 FL
+0.20 CL

3.00

3.00
+0.50 FL

4.30

4.30
58 59 +0.20 CL
6.00 6.60 .20 .20 41.90 1.20 .30 3.20 .20 8.20 .20 7.50 .20 7.50 .20 7.50 .20 7.50 .20 7.50 .20 7.50 .20 8.20 .20 3.20 .30 1.20 41.90 .20 .20 6.60 6.00
2.05 2.05
3.30 5.25 .30 5.10 .30 3.55 6.60 .30 4.45 .20 3.50 .20
FD 45 FD 45
PHD PHD PHD PHD PHD PHD PHD PHD

.20

.20
9.00

9.00
.20
S S

.20
.30

.30

.30

.30
9 10 10 10 9 9 9 10 18 19
2.20

3.00

3.00
57 60

2.70

2.70
3.70

3.70
GAR EN AREA GAR EN AREA
F EL F EL

4.40

4.40
S
STORAGE FD 45
22
STORAGE

1.20
PHD PHD

.20

.20

.20

.20
DG DG
ROO 5 6
ROO
+0.50 FL CW-23 CW-19 CW-19 CW-19 CW-19 CW-19 CW-18 CW-18 CW-19 CW-19 CW-19 CW-19 CW-19 CW-24 .30 5.25 3.30
+0.20 CL
.20

.20

.20

.20
56 53 61

10.80

10.80
PHD
PHD EXIT DOOR OPENING EXIT DOOR OPENING

8.20
8.80
GENERATOR OPENING GENERATOR OPENING

4.70
(35.50 S .) (35.50 S .)

7.60

7.60

7.60
ABOVE ABOVE R ROO

14.70
O.L 2 1.0M x 0.45M
O.L 2 1.0M x 0.45M
6.00

O.L 1 1700 mm / 3.8 mm 1700 mm / 3.8 mm


6.00
O.L 1

11.80

11.80
R ROO
GENERATOR
55 52 ELECTRO EC ANICAL AREA ELECTRO EC ANICAL AREA 62 E I +1.67 FL
ABO E
OPEN TO
GENERATOR

.20
10.00

10.00

10.00
OPEN TO ABO E ROO OLTAGE +1.57 CL
ROO
2.35
447 425 447 425 ROO
.20

.20

.20
S S

.60

.60

.60

.60
37 37
+0.50 FL
O.L +0.50
1 FL S
FD 45
22 FD 45
S
23 +0.50 FL O.L 1
PHD

4.80
PHD +0.50 FL
54 O.L 66 O.L 62 O.L 60 O.L 60 O.L 60 O.L 60 O.L 62 O.L 66 +0.20 CL

2.80
+0.20 CL 51

3.20
32.80 10.30 10.30 32.80 63 +0.20 CL +0.50 FL
+0.20 CL +1.67 FL
RAMP UP O.L 3 FD 90
S S
FD 90 FD 90
S S
FD 90
S
FD 90 FD 90
S
FD 90
S
FD 90
S S
FD 90
S
FD 90
S
FD 90
S
FD 90 O.L 3 +1.57 CL RAMP UP

.40
50 50 50 50 50 50 50 50 50 50 50 50
+0.50 FL
AREA 1060 2 RESTA RANT RESTA RANT RESTA RANT RESTA RANT RESTA RANT RESTA RANT RESTA RANT RESTA RANT AREA 1060 2

1.00

1.00
1.00

1.00

1.00

1.00
S AFT S AFT S AFT S AFT S AFT S AFT S AFT S AFT S AFT S AFT S AFT S AFT
RAMP UP

31.80

31.80
RAMP UP 3

9.90

9.90
50

9.20

9.20
3
O.L 231 O.L 231 64

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE

SHAFT ABOVE
A-401
A-402

RES-21
RES-15

RES-16

RES-17

RES-18

RES-19

RES-20

RES-22
2.50

2.50
ELEC. ELEC. ELEC. ELEC.
2.80

2.80
2.80

2.80
28.60

28.60
57 56 55 54 53 52 51 80 79 78 77 76 75 74 73 57 56 55 54 53 52 51 80 79 78 77 76 75 74 73 73 74 75 76 77 78 79 80 51 52 53 54 55 56 57 73 74 75 76 77 78 79 80 51 52 53 54 55 56 57

N 72

ROO N
72 72

N ROO 72

N
FD 90 S

15 16 17 18 19 20 21 22 FD 90
S

5.00
R R
PHD GY LTI P RPOSE S O ROO
58 59 60 61 62 63 64 65 66 67 68 69 70 71 58 59 60 61 62 63 64 65 66 67 68 69 70 71 71 70 69 68 67 66 65 64 63 62 61 60 59 58 71 70 69 68 67 66 65 64 63 62 61 60 59 58
ARC ITECT APPRO AL) ARC ITECT APPRO AL)
2
14 15
GY LTIP RPOSE S O ROO 2
6.60

6.60
P P P P

17.30
A-421 A-421
FD 45 FD 45

.30

.30
OPEN TO ABO E
.30

.30

.30

.30
S S S S

( ALE)
16.00

OPEN TO BELO STEEL GRATING FLOOR OPEN TO BELO STEEL GRATING FLOOR

OPEN TO ABO E
32

FD 90
3
49
3
A-403
.C.FD 90
S
15
272.39 SQ.M.
S AFT FOR FRES AIR (32.32 S .)
256.13 SQ.M. 255.74 SQ.M. 255.74 SQ.M. 255.74 SQ.M. 255.74 SQ.M. 256.13 SQ.M. 272.39 SQ.M. S AFT FOR FRES AIR (32.32 S .)
S
FD 90LO
14
3
A-404
(FE ALE) 65 FD 90
3 33
TRANSFOR ER ROO

2.50

2.50
+0.50 FL GAR EN AREA LO .C. GAR EN AREA
2.20

2.20

2.20

2.20
PROJECT NAME
(REFER TO EC . GS OF FIRE A PERS ETAIL FOR (REFER TO EC . GS OF FIRE A PERS ETAIL FOR
S R . R . S
TRANSFOR ER ROO
+0.20 CL 26 27

.60

.60
.30

.30

.30

.30

.30

.30

.30

.30
S S S S

FD 45 33 3 3
FD 45 32

2.00 .30 4.90 .30 2.05


FD 90 ELE ATOR ELE ATOR2 FD 90 .30 4.90 2.00
2.40

2.40
PHD LO C RRENT .30 LO C RRENT
+0.50 FL LOBBY LOBBY A-420 +0.50 FL PHD
3.00

3.00
ELE ATOR 2 ELE ATOR

16.80

16.80
ROO 2 2 ROO
LOBBY A-420 48 +0.30 CL A-420 +0.30 CL 66 A-420
LOBBY
.20

.20
DRIVEWAY

DRIVEWAY
+0.20 CL

+0.20 CL
+0.30 FL

+0.30 FL
2.40 .30 2.10 .30 4.90 .30 2.00
2.00 .30 4.90 .30 2.10 .30 2.40

10.60
3.00

3.00
S S
E B ROO LOADING & LOADING & E B ROO
.30 8.25 FD 45 22
UNLOADING UNLOADING FD 45 23
10.00

10.00
10.20

10.20
47
MIXED OCCUPANCIES (SEPARATED)
DELIVERY 2 DG DG
PHD PHD 67 DELIVERY 3

10.60

10.60
11 11

PHD S
PHD S
.30

.30
6.00

6.00
19 18

+0.50 FL
13.65 +0.20 CL CW-14 CW-14

ETER
LOADING &
UNLOADING
TD = 59 M EXIT DOOR OPENING EXIT DOOR OPENING TD = 59 M LOADING &
UNLOADING ETER
3.90

3.90
ROO
DELIVERY 1
46 68
DELIVERY 4 +0.50 FL
+0.20 CL
ROO
+1.67 FL
SEC 406.6E.P. GARAGE (S-2)
+0.50 FL VERTICAL CABLE
VERTICAL CABLE
TRAY OPENING
VERTICAL CABLE
TRAY OPENING
VERTICAL CABLE
TRAY OPENING
VERTICAL CABLE
TRAY OPENING VERTICAL CABLE
DG TRAY OPENING ABOVE ABOVE ABOVE ABOVE TRAY OPENING DG
6 ABOVE 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 ABOVE 5
1.60

1.60
0.20 X 0.65 0.20 X 0.65
.20

.30
CW-15 CW-15

1700 mm / 3.8 mm 1700 mm / 3.8 mm SEC 303.3 ASSEMBLY (A2)


.60

.20

.20

.20

.20

.60
DG DG

.40
11 11

SBC SEC 303.4


VERTICAL CABLE VERTICAL CABLE
TRAY OPENING TRAY OPENING
ABOVE ABOVE
PHD O.L 101 PHD PHD O.L 101 PHD

2.40
9 0.20 X 0.65 0.20 X 0.65 10
2.60

2.60
VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE VERTICAL CABLE
1 TRAY OPENING TRAY OPENING TRAY OPENING TRAY OPENING 58
CW-16 CW-17 CW-17 CW-17 CW-17 CW-16

ASSEMBLY (A3)
ABOVE ABOVE ABOVE ABOVE

45 447 425 447 425


0.20 X 0.65 0.20 X 0.65 0.20 X 0.65 0.20 X 0.65

RESTA RANT DG
11
DG
11
DG
11
DG
11
DG
11
DG
11
RESTA RANT 69
201
.80

.80
1 1

9.00
A1.01
SLOPE 4% PHD PHD PHD PHD PHD PHD SLOPE 4% A1.01

ASTE ANAGE ENT


14 23 ASTE ANAGE ENT
SEC 304.1 OFFICES (B)
9.30

9.30

9.30

9.30
2 10 50 59
8.60

8.60

8.60
S 18 34 S
8.40

8.80

8.40
44
ONE 1
DG
11 PHD PHD DG
11 ONE 2 44
AREA AREA
-0.10 FL 19 +0.50 FL 35 +1.35 FL
SHAFT ABOVE

SHAFT ABOVE
ROP OFF
282.11 SQ.M. .20 9.20 .20 7.70 .20 7.50 .20 7.50
+0.30 CL
.20 7.50 .20 7.50 .20 7.70 .20 9.20 .20
282.11 SQ.M. ROP OFF
RES-14

RES-23
CW-13 CW-13
5.00

5.00
20 36

3.00 .30 10.85


3 11 44 70 51 60
10.85 .30 3.00
SEC 509 INCIDENTAL USES
21 37
65.60

22 38

TYPE I-B

1.25
FD 45 FD 45
TAB 601
.20

.20

.20
12.80

12.80

.20
.30

.30
S S
1.25

1.25

1.25

1.25
45 4 12 52 61 45

-0.10 FL 23 39 +1.35 FL
3.15

3.15
PHD 9
PHD
10 RAMP UP 7% RAMP UP 4%
O.L 114 O.L 114
SHAFT ABOVE

SHAFT ABOVE
24 40 SLOPE SLOPE
5 13 53 62
RES-13

RES-24
2.50 .20 4.60
43 +0.50 FL 71
4.60 .20 2.50
.20

.20
25 41
RESTA RANT -1.30 CL RESTA RANT
RAMP DOWN 7%

CLEANING CLEANING

7.75
RAMP UP 7%
9.00

9.00

9.00
53.60
7.00

7.00
8.80
E IP ENT 26 42 E IP ENT
SLOPE

SLOPE
2.35

2.35
7.75

7.75
S DG
PHD PHD DG S
17.24% SLOPE

13
RAMP DOWN

STORAGE
24
SHAFT ABOVE

SHAFT ABOVE
48 11 11 48
6 14 4.80 2.80 4.00 5.50 1.50 2.20 12.00 2.20 1.50 5.50 2.40 1.60 2.80 4.80 54 63 STORAGE
RES-12

RES-25
+0.50 FL OTORBI ES27 43
OTORBI ES +0.50 FL
BICYCLE PAR ING BICYCLE PAR ING

30.90
1 +0.50 FL +0.50 FL +0.50
RAMP FL 1
.20

.20
CW-12 CW-12
A-413
RAMP DN N DN DN A-417
28 44

ENTRANCE RA P 3%2 42 317.27 SQ.M. 317.27 SQ.M. 72

1.60

1.60
2.50

2.50
RAMP DOWN RAMP DOWN 7% RAMP UP 7% RAMP UP 4%
STEEL
7 GATE
29 +0.45 SL +0.45 SL +0.45 SL +0.45 SL 45
SLOPE SLOPE
+0.50 FL BARRIER
15 VERTICAL CABLE
TRAY OPENING
ABOVE
+0.20 FL +0.20 FL
VERTICAL CABLE
TRAY OPENING
ABOVE
55
STEEL GATE
64
+0.50 FL
SLOPE SLOPE
E IT RA P 2 BASIC DATA
1.35

1.35
0.20 X 0.65 0.20 X 0.65
BARRIER

4.80

4.80
.60

.60

.20

.20

.20

.20

.60

.60
3.20

3.20
+0.50 FL VERTICAL CABLE VERTICAL CABLE

3.70
30 TRAY OPENING TRAY OPENING 46 2.35
+0.20 CL S FD 90 8 16
PHD
ABOVE
1.60 2.40 7.55 7.55 15.40 7.55 7.55 2.40 1.60 ABOVE
PHD 56 65 FD 90 S

O.L 111 O.L 111


9 0.20 X 0.65 0.20 X 0.65 10
3 3 3 3
A-405 31 47 A-406
41
4.00

4.00
DN DN
73

10.00
N P
57

57
P N
56

56
32
RESTA RANT RESTA RANT 48
55

58

58

55
54

59

59

54
2.40

2.40
FOOD KIOSK

FOOD KIOSK
53

60

60

53
9 17 57 66
7.20

7.60

7.60

7.60

7.60

7.20
33 DG
PHD PHD DG 49
52

61

61

52
7.60

7.60
12 25
11 11
51

62

62

51
E IT E IT
50

63

63

50
.60

.60

4.10
+0.50 FL +0.15 SL +0.15 SL +0.50 FL
49

64

64

49
E ERGENCY E ERGENCY
48

65

65

48
+0.20 CL +0.20 CL
66

66
310.45 SQ.M. 310.45 SQ.M.

2.00

2.00
CW-11 CW-11
40
67

67
74
78

68

68

78
1 1
2.60

2.60
77

69

69

77
1 A1.01 7% SLOPE 7% SLOPE A1.01 1
76

70

70

76
A1.01 A1.01
75

71

71

75
2.00 .20 5.55 .20 3.20 .20 .20 3.20 .20 5.55 .20 2.00
PLANTED COLUMN
74

73

72

72

73

74
PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED COLUMN PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED PLANTED

1.80

1.80
.60

.60

.20

.20

.20

.20

.60

.60
.30

COLUMN COLUMN COLUMN COLUMN COLUMN COLUMN COLUMN COLUMN COLUMN P COLUMN COLUMN COLUMN COLUMN COLUMN COLUMN
O.L 2
.30

WALL

4.10
WALL
BOOKSHELF BOOKSHELF BOOKSHELF BOOKSHELF

3.00
NICHE NICHE

FD 45
S PHD 9
PHD
10
FD 45
S
41
O.L 111 O.L 111 40
9.09% SLOPE

15.00
RAMP DOWN

10% SLOPE
O.L 20 39 O.L 20

RAMP UP
GLASS FLOORING
75

DRIVEWAY
DRIVEWAY

FRES AIR FRES AIR


CL

+0.20 CL
+0.30 FL

+0.30 FL
TOILET FAN ROO
RESTA RANT RESTA RANT FAN ROO TOILET
4.90

PRAYER CW-70 CW-70 PRAYER


+0.20

(SEE SHEET A-440) 2A +0.45 SL +0.45 SL 2B (SEE SHEET A-441)


ROO PHD ROO
DG
PHD DG
7.20

7.60

7.60

7.60

7.60

7.20
11 11
(SEE SHEET A-450)
O.L 18 11 26 O.L 18
(SEE SHEET A-451)

3.70
3.20 CW-11 CW-11
3.20

310.45 SQ.M. 310.45 SQ.M.

10.00

10.00
.20

DG DG
38 +0.15 SL +0.15 SL
9
76 8
SHAFT ABOVE

SHAFT ABOVE
.50 .50
(TYPE I-B )
RES-11

RES-26
ENTRY ATER FEAT RE ATER FEAT RE
1.80

S DG VERTICAL CABLE VERTICAL CABLE DG S


JANITOR 48 7 12 TRAY OPENING TRAY OPENING 12 7 48
JANITOR
PWD ABOVE ABOVE PWD
2.00 .50 5.05 .50 WC 0.20 X 0.65 0.20 X 0.65
WC 5.05 .50 2.00
2 Hrs
.20

S DG
FIRE-RESISTANCE RATING - STRUCTURAL FRAME
14.70

.60

.20

.20

.20

.20

.60
40 9
FD 45
RAMP UP VERTICAL CABLE VERTICAL CABLE
RAMP DN REQUIREMENTS FOR INCLUDING COLUMNS, GIRDERS, TRUSSES

7.70
TRAY OPENING TRAY OPENING
SHAFT ABOVE

SHAFT ABOVE
ABOVE ABOVE

O.L 4 PHD PHD O.L 4 2 Hrs

+0.20 CL
RES-10

RES-27
9 0.20 X 0.65 0.20 X 0.65 10
STRUCTURE ELEMENTS - FLOOR CONSTRUCTION

+0.50 FL
E IT

13.70
+0.20 CL
+0.50 FL

+0.98 FL
-0.70 FL CONTROL ROO FIRE
ABL TION
FD 45 37 O.L 111 DN

+0.65 TS +0.65 TS
DN
O.L 111 77 FD 45 ABL TION
E FOR
IT RAOFFICE
P INCLUDING SUPPORTING BEAMS AND JOISTS
FOR OFFICE

7.80
CO AN CENTER

ENTRANCE RA P
SEC RITY ROO RESTA RANT RESTA RANT E TRA
- ROOF CONSTRUCTION 1 Hr
7.60

DG
PHD PHD DG
7.20

7.60

7.60

7.60

7.60

7.20
(
ARC ITECT APPRO AL 11 11 ARC ITECT APPRO AL
A IN ROO INCLUDING SUPPORTING BEAMS AND JOISTS
CI IL
EFENSE)
WASTE
BASKET
10 CW-10
+0.50 FL +0.05 FL +0.50 FL CW-10 27 WASTE
BASKET

O.LRI ER12 O.LRI ER12

4.90

4.90
S +0.30 CL +0.65 WL -1.30 CL +0.30 CL S
DG
8
AITING ROO OPEN TO BELO
REFER TO EC RE
. OG.ABLE STEEL
OF FIRE A GRATING FLOOR
PERS ETAIL FOR
36 310.45 SQ.M. 310.45 SQ.M. 78 OPEN TO BELO
REFER TO EC RE
. OG.ABLE STEEL
OF FIRE AITING ROO
A GRATING FLOOR
PERS ETAIL FOR
DG
9

3.30
+0.20 FL
WATER
DISPENSER S AFT FOR E A ST LO ER (24.92 S .) S AFT FOR E A ST LO ER (24.92 S WATER
DISPENSER .)
.20

.60

.60

.20

.20

.20

.20

.60
.40

VERTICAL CABLE +0.15 SL +0.15 SL VERTICAL CABLE

ENTRY
TRAY OPENING TRAY OPENING
ABOVE ABOVE

FOOD KIOSK

FOOD KIOSK
8.55 .30 17.15 6.00 6.00
PHD
.60 9 0.20 X 0.65 2.75 0.20 X 0.65
PHD
10.60 6.00 6.00 17.15 .30 8.55
35 79
LEGEND

4.00
PLASTIC SPEED BUMP, AS

3.00
APPROVED RESTA RANT RESTA RANT

7.48
RAMP UP RAMP UP RAMP UP RAMP DN
6.00

6.00

6.00

6.00
DRIVEWAY 9 28 DRIVEWAY
7.72

7.72
7.73

7.73
PHD PHD E IT FDXX
DG DG
E IT RA P
FIRE DOOR RATING (IN MINUTES)
11 11
1 +0.45 SL +0.45 SL 3
A-419
34 2.40
80 A-419 FOR SER ICE
FOR SER ICE
.20 .30
1.80
.20
.60
.30 .30
377.45 SQ.M. CW-9 CW-9 377.45 SQ.M. .30 .30
.20 .30 +0.83 FL .20

+0.30 FL +0.30
6.00 FL
ENTRANCE.30 RA P 6.05 1.95 6.00 .60 6.00 .20 2.50 2.40 2.00 .40 4.80 9.85 .30 4.80 .40
O.L 135 4.90 .20
O.L 135 .30 2.40 .30 2.10 5.20 .30 9.85 4.80 .40 2.00 2.40 2.50 .60 .60 6.00 1.95 1.80 6.05 .30
PHD
+0.20 CL S
FD 90 FD 90
S S
FD 90
.30
+0.60 SL +0.60 SL .30
FD 90
S
FD 90
S S

You might also like