Professional Documents
Culture Documents
RE Q3 2022 Latest 3 6 1
RE Q3 2022 Latest 3 6 1
RE
UPDATE
Q3 2022
Lead Sponsors
Source: IHS Markit now a part of S&P Global
1. Executive Summary 7
2. Installation trends 8
8
• Cumulative installation trends
9
• Yearly installation trends and projections
10
• Yearly Projections
11
• Quarterly trends
3. Quarterly RE Generation 12
4. Market shares 13
13
• Inverter Suppliers
14
• Module Suppliers
5. Tenders 17
• New tenders 17
• Successful auctions 21
• Tariff trends 23
6. Financing deals 24
7. Price Trends 26
11. Annexure 31
Q3 2022 RE Updates
6
1 Executive Summary
In Q3 2022 (July-September 2022), about 2.82 GW of utility scale solar capacity was
added. This is about 25% higher than the previous quarter’s installation. In wind
segment, about 1.02 GW was added, which is 138% higher than the Q2 2022 installation.
In rooftop solar, more than 400 MW were added in this quarter.
During Jan-Sep 2022 period, about 9.3 GW of utility scale solar capacity was added,
which is about 1.7 times higher than last year installations in the same period. About
1.89 GW of new wind capacity was added in the first nine months of 2022, which is
about 46% higher than 1.3 GW capacity added during January to September 2021.
Gujarat led the installations with the commissioning of more than 700 MW of new
wind projects in this period. In the rooftop solar segment, about 1,334 MW of new
capacity was added during January to September 2022, which is 34% less than January
to September 2021 installations.
With respect to tender activity, in Q3 2022, 75 new tenders with a cumulative capacity
of 14.2 GW were issued across solar and wind segment, which is 25.7% higher than the
previous quarter.
In Q3 2022, India saw the lowest-winning solar tariff of INR 2.49/kWh under GUVNL’s
750 MW solar (Phase XVI) tender in Gujarat. The lowest-winning tariff in wind segment
was INR 2.84/kWh under GUVNL’s 500 MW Phase III wind tender. While the
lowest-winning tariff in wind solar hybrid segment was INR 3.03/kWh under RUMSL’s
750 MW Wind Solar Hybrid tender.
In Q3 2022, solar cells and modules exports increased by 57% and 524% respectively,
Q3 2022 RE Updates
compared to the previous quarter's figures. However, the solar cells imports increased
by 64% and solar modules imports decreased by 64% in Q3 2022. The significant
reduction in the import numbers is because of the imposition of 40% basic custom
duty (BCD) on solar modules.
The report also analyses module price trends in India, investments and deals, details of
which are elaborated in further sections.
7
2 Installation trends
As of September 30, 2022, about 60.8 GW of solar and 41.7 GW of wind capacity were
installed in India. The current pipeline of combined capacity of solar, wind and hybrid
projects are around 45 GW, which is likely to be commissioned in the next 4-5 years.
Another 28 GW of projects are under bidding phase i.e., where tenders have been
issued but auctions are not yet completed.
ll Hydro
r Sma4%
we 120
Po %
io 9
B
100 19
So
80
Capacity (GW)
la r (
30
5 2 %)
118.08 GW
87.7 GW 60
3
7
40
)
35%
20 Pipeline
in
W
6 Commissioned
8
0 1.3
Hybrid Wind Solar
Gujarat and Karnataka contributed around 51.3% of the total capacity. Whereas
in wind segment, Tamil Nadu, Gujarat, Karnataka and Maharashtra contributed
about 71.9% of the total wind capacity installed in India.
8
Utility Scale Solar: From Jan-Sep 2022, about 9.3 GW of new utility-scale solar
capacity was added in India. Compared to Jan-Sep 2021 period, installations are
about 1.7 times higher. Rajasthan, Gujarat and Tamil Nadu were the leading
states with most of the large-scale solar installations during this period.
Rooftop Solar: In the rooftop solar segment, about 1334 MW of new capacity
was added during January to September 2022, which is 34% less than 2068 MW
capacity added during January to September 2021. Gujarat, Maharashtra, and
Rajasthan were the leading states in the rooftop solar segment adding more
than 800 MW during the first nine months of 2022.
In order to achieve the rooftop solar capacity target of 40 GW, the government
has extended the timeline of the implementation of Rooftop Solar Programme
Phase-II from December 2022 to 31 March 2026 without any additional financial
support.
Wind: From Jan-Sep 2022, about 1.89 GW of new wind capacity was added,
which is 46% higher than 1.3 GW capacity added during January to September
2021. Gujarat led the installations with the commissioning of more than 700 MW
of new wind projects in this period.
Figure 2.2: State-wise solar and wind capacity addition in India from Jan- Sep 2022
5,000
Utility Scale Solar
Wind
4,000
Rooftop Solar
Capacity (MW)
2,000
1,000
Q3 2022 RE Updates
0
n
at
ra
la
s
er
ak
an
ad
ha
es
ra
ht
ar
th
ad
at
ng
Ke
N
st
uj
as
O
rn
ja
il
Pr
ar
la
m
Ra
Ka
Te
ah
ra
Ta
dh
An
9
200 60
5,000
12,000 50
150 40
4,000 30
Annual Growth (%)
100 20
3,000 10
50 0
6,000
-10
2,000
0 -20
-30
3,000
1,000 -40
-50
-50
0 -100 0 -60
e
e
20
18
19
17
21
20
18
19
17
21
22
22
20
20
20
20
20
20
20
20
20
20
20
20
10
In Q3 2022 (July- Sept 2022), about 2.82 GW of utility scale solar capacity was added.
This is about 25% higher than the previous quarter installations. In wind segment,
about 1.02 GW was added, which is 138% higher than the Q2 2022 installations
because of the peak wind season in the country. In rooftop solar segment, more
than 400 MW were added in the third quarter of 2022.
As per our estimates, the installation activity is likely to further pick up. In the next
two quarters, about 5.6 GW of solar, 2.5 GW of wind and 1.05 GW of hybrid
capacities are expected to get installed in the country.
6000
5000
Utility Scale Solar Wind Hybrid
4000
Capacity (MW)
3000
2000
1000
0
21
22
22
3e
9
19
19
19
20
20
20
21
21
02
02
22
01
02
20
20
20
20
20
20
20
20
02
20
20
20
12
12
20
12
12
12
2
4
2
3
2
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
Q
4
Q
Q
Q
Q
11
3 Quarterly RE Generation
The cumulative RE generation in Q3 2022 was 49,987 MU, down by 1.2% from
previous quarter’s generation data. In the third quarter of 2022, RE accounts for
12.2% of the total energy generated. Wind energy accounts for most of the
energy generation (49%) from renewable energy sources in Q3 2022 due to peak
wind season in the country, which is followed by solar at 42%, and other RES
(including biomass) at 9%.
60,000 20
Solar
Wind
Other REs
50,000 % RE share in total energy generation
17
16.0%
40,000
14
Million Units
%age share
13%
12.73%
12.20%
30,000
11.72%
11.7% 11
20,000 10.7%
9.6%
9.0%
8.67%
8.25% 8
10,000
0 5
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2020 2020 2020 2020 2021 2021 2021 2021 2022 2022 2022
Q3 2022 RE Updates
12
4 Market shares
For Q3 2022, we have received more than 2.9 GW of shipment data from 14 players
providing both central and string inverters in India. In Q3 2022, Sineng was the
leading inverter supplier followed by Sungrow and FIMER.
Figure 4.1: Leading central and string inverter suppliers in solar sector in India in Q3 2022
1,200
1,000
Shipped Capacity (MW)
800
600
String inverter
Central inverter
400
200
0
ng
ER
lis
td
ls
VO
r
ire
la
dw
re
la
co
EI
el
ro
So
.L
o
ne
EV
So
iH
aa
av
TM
at
ng
rs
Co
oo
FI
Si
W
H
fa
St
ch
VT
Su
G
So
ita
s
IN
xe
H
Fo
Q3 2022 RE Updates
13
300
Chinese/ International suppliers
Shipped Capacity (MW)
Domestic manufacturers
200
100
ar
r
ns
s
r
r
on
e
er
r
r
la
gy
s
e
la
la
la
sy
la
ni
la
ie
in
ol
re
So
tio
ow
So
So
So
ks
So
er
ew
So
da
rg
sh
rS
aa
lu
Ja
En
e
P
ne
e
am
A
Zn
n
en
ha
di
W
nc
in
So
ve
zo
ta
ol
rE
en
R
irb
Tr
kr
de
m
Ta
ay
G
en
ie
re
Vi
Em
an
re
R
re
m
G
m
G
re
k
at
vi
s
P
ita
at
A
Sa
av
N
14
Figure 4.4: Top 15 project developers across utility-scale solar and wind segment as of September 30, 2022
Adani
ReNew Power
NTPC Limited
Azure
Solar Commissioned Solar Pipeline
Tata Power Wind Commissioned Wind Pipeline
Acme
Avaada
Mytrah
Sembcorp
Hero Future
Neyveli Lignite
Corporation
CLP Group
Engie
Q3 2022 RE Updates
0 5 10 15 20 25 30
Capacity (GW)
15
ˈˡ˩˘˜˟˜ˡ˚
ˉ˜˦˜˧˨˦˔˧
ʻ˔˟˟ʣʥʟʵˢˢ˧˛ˁˢʡʽʤʣʤ
ʻ˘˟˜ˣ˔˗ʸ˫˛˜˕˜˧˜ˢˡʶ˘ˡ˧˥˘
ʺ˔ˡ˗˛˜ˡ˔˚˔˥ʟʺ˨˝˔˥˔˧
ʪʠʬʷ˘˖˘ˠ˕˘˥ʥʣʥʥ
˪˔˔˥˘˘ʳ˪˔˔˥˘˘ʡ˖ˢˠ ˪˪˪ʡ˪˔˔˥˘˘ʡ˖ˢˠ
5 Tenders
Figure 5.1: Quarter-wise utility scale solar, wind and hybrid tender issuance and allocations
20,000
16,000
14,000
12,000
Capacity (MW)
10,000
8,000
6,000
4,000
2,000
0
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2020 2020 2020 2020 2021 2021 2021 2021 2022 2022 2022
600 MW solar power projects under Phase XVII with greenshoe option of
additional up to 600 MW.
17
Storage tenders issued in Q3 2022
• SECI floated a tender for supply of 2250 MW of Round-the-Clock (RTC) power
from RE power projects, complemented with power from any other source or
storage in India under RTC-III category.
• REMCL also issued a tender for supply of 1000 MW of RTC power from RE
power projects with or without storage across the country.
• GUVNL issued a tender for setting up of pilot projects of 500 MW/1000 MWh
under Phase I of standalone Battery Energy Storage Systems (BESS) scheme in
Gujarat.
Rooftop/Small Scale
EPC, 1932 MW, 14% Solar, 463 MW, 3%
Project Development
(Floating Solar), 300 MW,
2%
Project Development
(KUSUM Scheme), 1591
MW, 11%
100%=14.2 GW
Project Development
(Solar), 5663 MW, 40%
Project Development
(Hybrid), 4255 MW, 30%
18
Q3 2022 RE Updates
19
Capacity (MW)
0
500
1,000
1,500
2,000
2,500
SECI 2250 MW RE with ESS Storage
(RTC III) Pan India Sep 2022
2,250
REMCL 1548 MW Solar Pan
India Jul 2022
1,548
MSEDCL 1000 MW Solar Tranche
1,000
MSEDCL 1000 MW Solar (Tranche
1,000
V) Maharashtra Jun 2022
1,000
ESS Storage Pan India Jul 2022
750
Gujarat Jul 2022
600
2022
500
Maharashtra Sep 2022
Figure 5.3: Details of key Project Development tenders issued in Q3 2022
500
Storage (Phase-I) Gujarat Aug 2022
tenders were floated under solar and hybrid segment respectively.
300
II Madhya Pradesh Jul 2022
255
the total issued capacity, about 5.96 GW and 4.01 GW of project development
Madhya Pradesh (1,258 MW), Maharashtra (298 MW) and Gujarat (60 MW) have
issued the majority of these tenders in this quarter.
1,400
1,250 MW
1,200
1,000 Component A
Component C
Capacity (MW)
800
600
400
298 MW
200
53.69 MW 42.8 MW 26 MW 17 MW 8 MW
0
MPUVNL 1250 MW Solar (Under
KUSUM scheme Component C)
Madhya Pradesh Jul 2022
20
Out of the total auctioned capacity, 1,750 MW has been allocated to various
developers under solar segment, 1260 MW to hybrid segment and 500 MW to
wind segment.
1000 3.5
900
Capacity Tendered (MW)
Capacity Allotted (MW)
800 Lowest Tariff (INR/kWh)
3.03
700
Tariff (INR/kWh)
2.9 3.0
Capacity (MW)
500
400
2.5
300 2.49
200
100
0 2.0
GUVNL 750 MW Solar
(Phase XVI) Gujarat Jul
2022
21
Of the auctioned capacity, Tata Power won the maximum solar capacity of 450
MW followed by Avaada (325 MW), Engie ,NTPC and SJVN (200 MW each). In wind
segment, Ayana Renewables won the maximum capacity of 140 MW followed by
Blupine Energy (100 MW), O2 Power and GSECL (70 MW each). ReNew Power (300
MW), Tata Power (200 MW) and Sprng Energy (160 MW) were awarded the highest
capacities under wind solar hybrid segment.
In addition, JSW Energy was awarded 500 MW under SECI’s pilot projects of 500
MW/1000 MWh Standalone BESS Systems at INR 1.08 million/MW/month in Q3
2022.
700
Solar Tenders
Wind Tenders
600
Hybrid Tenders
500
Capacity (MW)
400
300
200
100
0
Tata Power
JSW Energy
Avaada
ReNew Power
Blupine Energy
Engie
NTPC
SJVN
Sprng Energy
O2 Power
Ayana Renewables
UPC Renewables
Juniper Green
GSECL
Sukhbir Agro
Acme
EDF
22
In Q3 2022, India saw the lowest-winning solar tariff of INR 2.49/kWh under
GUVNL’s 750 MW solar (Phase XVI) tender in Gujarat. This is about 25% higher
than the lowest solar tariff, INR 1.99/kWh that was discovered under GUVNL’s 500
MW solar Phase XI tender auctioned in 2020. The lowest-winning tariff in wind
segment was INR 2.84/kWh under GUVNL’s 500 MW Phase III wind tender.
While the lowest-winning tariff in wind solar hybrid segment was INR 3.03/kWh
under RUMSL’s 750 MW Wind Solar Hybrid tender in Q3 2022.
3.5
Solar 3.26 3.26
3.11
3.05
2.97
3.0 2.91
2.81
2.69
2.61
Tariff (INR/kWh)
2.55 2.58
2.5 2.51
2.5 2.49
2.43
2.36
2.29 2.30
2.2 2.17
2.14
2.0
1.99
1.5
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2020 2020 2020 2020 2021 2021 2021 2021 2022 2022 2022
3.11
3.04
3.05 3.05 2.99
2.95
3.0 3.03
Tariff (INR/kWh)
2.83 2.83
Tariff (INR/kWh)
2.78 2.89
2.82 2.70 2.84
2.79 2.77
2.70 2.76 2.70 2.62
2.69
Q3 2022 RE Updates
2.54
2.42 2.53
2.00 2.00
22
22
19
20
19
21
20
22
22
9
21
02
01
20
20
20
20
20
20
20
20
20
20
12
12
3
3
3
4
3
3
Q
Q
Q
Q
Q
Q
Q
Q
Q
The investment flow in RE sector in Q3 2022 was more than $6,627 million. About
8,737 MW RE assets were acquired in this quarter with total investment of more
than $4600 million. Another $1358 million equity investments were also raised by
various players.
• JSW Neo Energy, a wholly owned subsidiary of JSW Energy, has agreed to
acquire a portfolio of 1,753 MW of renewable energy generation capacity from
Mytrah Energy (India) for $1320 million.
• KKR and Hero Future Energies, the renewable energy arm of the Hero Group,
has signed the definitive agreements under which KKR and the Hero Group
will invest $450 million in the Company.
• Continuum Green Energy has raised $350 million in debt through a bond issue
to expand its solar, hybrid and wind projects.
5,000
Equity
Bonds
M&A
4,000 Other
Investments (US$ Million)
3,000
2,000
Q3 2022 RE Updates
1,000
0
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2020 2020 2020 2020 2021 2021 2021 2021 2022 2022 2022
25
0
500
1,000
1,500
2,000
Sprng Energy (Acquirer : Shell)
0
Figure 6.2: Investments by deal type in Q3 2022
1,000
3,000
5,000
2,000
4,000
MW
0
100
200
300
400
500
Tata power
Serentica Renewables
O2 Power
7 Price Trends
In the overseas market, the prices of solar cells have increased by 5.6% while the prices
of mono-PERC solar modules have decreased marginally by 0.8% on QoQ basis.
Figure 7.1: Global price trends of solar cells and modules in Q3 2022
0.30 Mono PERC solar modules
0.27 0.27 0.27 0.26
Prices (USD/Wp)
0.25 0.24
0.23
0.21
0.20 Cells
0.17
0.16 0.16 0.16
0.15 0.14
0.13
0.12
0.10
Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022
In the Indian market, the landed price for Chinese multi crystalline module
suppliers (excluding GST and BCD), was about 23-26 cents/Wp in Q3 2022 while
prices for mono PERC modules was in the range between 25-27 US cents/Wp.
30
Mono PERC solar modules Multi crystalline modules
27.2 27.2 27.2 27
27 26 26
Prices (US cents/ Wp)
25.3
24.5 26
24 25.6
24 23 23
22 23.7 23.4
21.5 22.8
21 22.2
20.5
21 20 20 20
19
19.5
18 18.5 18.5
18.0
17.5
Q3 2022 RE Updates
15
Q4 2020
Q2 2020
Q3 2020
Q2 2022
Q3 2022
Q4 2018
Q4 2019
Q1 2020
Q4 2021
Q2 2018
Q3 2018
Q2 2019
Q3 2019
Q2 2021
Q1 2022
Q3 2021
Q1 2018
Q1 2019
Q1 2021
26
8 Quarterly
Import-Export Statistics
In Q3 2022, solar cells and modules exports increased by 57% and 524%
respectively, compared to the previous quarter's figures. However, the solar cells
imports increased by 64% and solar modules imports decreased by 64% in Q3
2022. The significant reduction in the import numbers is because of the
imposition of 40% basic custom duty (BCD) on solar modules.
Exports Imports
Q2 2021
Q3 2021
Q4 2021
Q1 2022
Q2 2022
Q3 2022
solar module (exports) solar cell (exports) solar cell (Import) solar module (Import)
27
10 Financials
Leading Players
During Jul-Sept 2022, among the private players, the highest revenue was
incurred by ReNew Power with INR 2,168 crore followed by Tata Power (INR 1,826
crore), Adani Green Energy (INR 1,686 crore) and Suzlon Energy (INR 1,438 crore)
while maximum profit was generated by Tata Power and Adani Green Energy of
INR 171 crore and INR 146 crore respectively.
Figure 10.1: Revenue of Leading RE Players during past four quarters, Quarter wise
5000
Q3 2021
Q4 2021
4000 Q1 2022
Revenue (in INR Crore)
Q2 2022
Q3 2022
3000
2000
1000
0
Tata Power Suzlon ReNew Power Adani Green Energy
In Q3 2022, Adani’s revenue and PAT has decreased by 1% and 33% respectively
as compared with the previous quarter because their solar and wind CUF has
decreased by 4.4% and 20.3% respectively in this quarter. The reason behind the
reduction in wind CUF is primarily due to a one-off disruption in the transmission
line of 150 MW wind power plant in Gujarat.
Q3 2022 RE Updates
Suzlon Energy’s Revenue has increased by 4.2% and PAT performance has also
increased significantly by 255% in Q3 2022 as compared to last quarter due to
new orders of nearly 193 MW.
In Q3 2022, Tata Power’s revenue and PAT have decreased by 16.1% and 10.5%
respectively. Additionally, the sales of Tata Power’s Solar Pumps have decreased
by 54% as compared to the previous quarter Q2.
28
Figure 10.2: Profit After Tax (PAT) of Leading RE Players during past four quarters, Quarter wise
350
300
250
200
150
Profit (in INR Crore)
100
50
0
-50
-100
-150
-200
-250
-300
-350
-400
Tata Power Adani Green Energy Suzlon ReNew Power
29
11 GTAM Traded Volume
The IEX and PXIL together traded a total of 517.2 MU in GTAM in Q3 2022, which is
49% lower than the volume traded in the second quarter of 2022. The average
trade price in IEX-GTAM for Q3 2022 was INR 5.57/kWh, while for PXIL it was INR
4.92/kWh. This is approximately 31% and 46% less than the respective previous
quarter’s prices.
Figure 11.1: Quarter wise GTAM Traded volume and Price Trend
2,000 10
1,800 1682 9
1,600 8
Million Units/ GWH
1,400 7
INR/kWh
1,200 6
955
1,000 5
862
800 724.40 4
586 555.45
600 3
459
374.93 384
400 2
237
200 233.20 1
89.72
0.39 33.86
0 0
Q1 2021 Q2 2021 Q3 2021 Q4 2021 Q1 2022 Q2 2022 Q3 2022
30
12 Annexure
Tendered Capacity
Tender Name Date of issue State Technology Tender Scope
(MW)
MPUVNL 1250 MW
Solar (Under KUSUM
Rooftop/Small Project
scheme Component Jul-22 1250 Madhya Pradesh
Scale Solar Development
C) Madhya Pradesh Jul
2022
REMCL 1000 MW RE
with or without ESS Project
Jul-22 1000 Pan India RE with ESS
Storage Pan India Jul Development
2022
GUVNL 750 MW Solar
Project
(Phase XVI) Gujarat Jul Jul-22 750 Gujarat Utility Scale Solar
Development
2022
NLC 500 MW Solar
(EPC) Pan India Jul Jul-22 500 Pan India Utility Scale Solar EPC
2022
RUMSL 300 MW
Floating Solar Phase Project
Jul-22 300 Madhya Pradesh Floating Solar
II Madhya Pradesh Jul Development
2022
JAKEDA 200 MW
Rooftop/Small Rooftop/Small Scale
Rooftop Solar J&K Jul Jul-22 200 Jammu & Kashmir
Scale Solar Solar
2022
MSEDCL 1000 MW
Solar Tranche VIII Aug-22 1000 Maharashtra Utility Scale Solar Project Development
Maharashtra Aug 2022
IRCON 500 MW Solar
(EPC) Karnataka Aug-22 500 Karnataka Utility Scale Solar EPC
August 2022
GUVNL 500 MW with
1000 MWh BESS
Aug-22 500 Gujarat Hybrid Project Development
Storage (Phase-I)
Gujarat Aug 2022
MSEDCL 298 MW
Solar (Under KUSUM
Rooftop/Small
Scheme Component Aug-22 298 Maharashtra Project Development
Scale Solar
A) Maharashtra Aug
2022
31
Tendered Capacity
Tender Name Date of issue State Technology Tender Scope
(MW)
32
Capacity Capacity
Minimum Commissioning
Tender Name Tendered Allotted Winner details
CUF Timeline
(MW) (MW)
KSEBL 10 MW with
20 MWh BESS 10 10 - 15 months • Hero Future Energies – 10 MW
Solar Kerala
MSEDCL, 500
MW, Solar Phase
• NTPC – 200 MW (INR 2.82/kWh)
VIII Tranche VI, 500 500 19% 15 months
• Avaada – 300 MW (INR 2.83/kWh)
Maharashtra, Jun
2022
Asset
Deal Value Stake
Date Company name Deal type Sector acquired Acquirer/ Investor
(US$ mn) acquired
(MW)
Continuum Green
Jul-22 Bond Renewable - - $350 million -
Energy
Tata Power
Greenforest New
Jul-22 Renewable Equity Renewable - $245 million 11%
Energies Bidco
Energy
Wind Two
Jul-22 Renergy Private Acquisition Wind 50 Torrent Power $4.10 million 100%
Ltd
Fourth Partner
Jul-22 Equity Solar - Filatex india $1.29 million 26%
Energy
$1550
Aug-22 Sprng Energy Acquisition Renewable 2100 Shell 100%
million
$263.97
Aug-22 Atha Group Acquisition Solar 400 Actis 26%
million
BlackRock-backed
Aug-22 Tata Power Equity Renewable - GreenForest New $251 million 5.27%
Energies Bidco
Wind Syngene
Aug-22 O2 Power Equity - $0.38 million 26%
(Open access) International
34
Asset
Deal Value Stake
Date Company name Deal type Sector acquired Acquirer/ Investor
(US$ mn) acquired
(MW)
Ontario Teacher's
Sep-22 Mahindra Susten Equity Renewable - Pension Plan $300 million 30%
Board
CDPQ
Sep-22 Apraava Energy Equity Renewable - $82.6 million 10%
Infrastructures
Reliance
Sep-22 SenseHawk Acquisition Solar 79 $32 million -
Industries
Serentica
$18.79
Sep-22 Renewables (SPV Equity Renewable Hindustan Zinc 26%
million
of Sterlite Power)
$4.96
Sep-22 Clean Max Kratos Equity Renewable UPL Limited 26%
million
Niveshaay with
the participation
of Action
Navitas Alpha
Tesa Group, $0.87
Sep-22 Renewables Equity Solar -
Madhusudan million
Private Limited
Sarda, IVY Growth
Associates and
others
35
OptiMOS™ power MOSFETs in TOLT
Optimized for superior thermal performance
lnfineon's OptiMOS™ power MOSFET family expands its high performance package offerings with the introduction of
the TO-Leaded top-side cooling (TOLT) package to its portfolio. The TOLT package offers the same high current low
profile benefits as the TO-Leadless (TOLL) package with the additional advantage of top-side cooling for optimum
thermal performance.
This innovative package combined with the key features of OptiMOS™ 5 power MOSFET technology enables best-in
class products in 80V and lO0V as well as high current rating >300A for high power density designs.
With top-side cooling, the drain is exposed at the surface of the package allowing for 95% of the heat to be dissipated
directly to the heatsink, achieving 20% better RthJA and 50% improved RthJC compared to the TOLL package.
Benefits
2.5
> Reduce size with high power density, ease of manufacturing with FR4 PCB
> High power density with Best in Class performance (very low RDS(on) 1.5
�
and high current capability) ?
> Superior thermal performance which improves the overall system
1
reliability with longer end product life time
0.5
==
,.......=. =rm1M (Thermal
Interface Material) 0
TOLL TOLT
Rth (j-heatsink) @360um TM 5000s35
Toll on FR4 board without solder stop mask
https://www.infineon.com/optimos-tolt
.�
Infineon
RE ONLINE
DASHBOARD
Research & Analytics
OLAR
Capacity addition, Developers, Module suppliers,
Tariff trends, Inverter suppliers, Turbine
Leading players suppliers
market share etc. Installation trends, Projects,
E
T SHAR
ES
MA
FIL
MARKE
FTO
RO
EP
ES
I CI
POL
Landed cost, Cross-subsidy
surcharge, State-wise player-wise
corporate PPA market size etc.
ES S
ACC
OPEN ET
K
MAR
TE
ND (350+ tenders with status of all ongoing
ER
S tenders, amendments and auctions
across the solar,wind, rooftop, hybrid and
storage tenders in India)
PV NU
MA
DS
PLAYER
PROFIL
REN
FA
CT
CE T
RIU
ES
NG
INCLUSIONS CONTACT US
• Online access for 12 months For online demo of the dashboard
• Weekly RE Newsletter (48 in a year) please contact us at: