II.

EARTHWORKS
A.1. EXCAVATION
A.1.1. FOOTING 1 (F1)
GIVEN:
L=1.6 m

W =1.6 m

D=2.0 m

N=19 sets

SOLUTION:
V exc =L× W × D × N

V exc =1.6 m× 1.6 m× 2.0 m×19 sets


3
V exc =97.28 m × 1.05
3
V exc =102.14 m

B.1. BACKFILL
B.1.1. FOOTING 1 (F1) & COLUMN (C1)
GIVEN:
L=1.6 m

W =1.6 m

D=2.0 m

T =0.35 m

N=19 sets

SOLUTION:
V =V exc−V con

V con=V con ( F 1 )+V con (C 1)

V con= ( 1.6 m×1.6 m×0.35 m ) +(0.3 m× 0.4 m+1.65 m)

V con=1.09 m³
V =V exc−V con

V =102.14 m3−( 1.09 m3 × 19 sets )


V =81.29× 1.20

V =97.55 m ³

B.1.2. ELEVATION & COLUMN (C1)


GIVEN:
Lelev =20.58 m

W elev =11.16 m

D2 (elev )=0.4 m

D1 (slab )=0.1 m

Lcolumn =0.3 m

W column=0.4 m

SOLUTION:
Delev =0.4 m−0.1 m

D(elev)=0.3 m

V (elev)=Lelev ×W elev × D elev

Total V (elev)= ( 20.58 m×11.16 m× 0.3 m )+ (1.3 × 2.10× 0.3 ) +(1.3 ×1.3 ×0.3)
3
Total V (elev)=84.01m

V (elev backfill)=V (elev)−V (column)


3
V (elev backfill)=84.01 m −(0.3 m× 0.4 m× 0.3 m× 19)

V (elev backfill)=83.32 m ³ ×1.20

V (elev backfill)=99.99 m ³
UNIT COST FOR EXCAVATION
GIVEN:
1.4 m ³ Manhours per one (1) cubic meters of
Man Rate= excavation (light dry soil)
8 hrs
Region II
Php .435 .00
Wage=
8 hrs

SOLUTION:
Wage
Unit Cost exc=
Man Rate
Php.435 .00
Unit Cost exc=
1.4 m ³
Unit Cost exc=Php .310 .71≈ 320 per cu . m

UNIT COST FOR BACKFILL


GIVEN:
0.625 day 5 hr 1 day
Man Rate= ×
1m³ 1m ³ 8 hr

Php .300 .00 Region II


Wage=
8 hrs

SOLUTION:
Php.300 .00 0.625 day
Unit Cost backfill= ×
1 day 1m³
Unit Cost backfill=Php .187 .50 ≈ Php .190 per cu . m

UNIT COST FOR BACKFILL ELEVATED


GIVEN:
Php .3500 .00
Price of Backfill=
1 truck
1truck
Capacity of Truck =
6m³

SOLUTION:
Unit Cost of Backfillelevated =Price of Backfill × Cap. of Truck

Php .3500 .00 1 truck


¿ ×
1 truck 6 m³
Unit Cost of Backfillelevated =Php .583.33 ≈ Php .584 per cu . m
III. REBARWORKS
A.1. FOOTING (F1)
GIVEN:
Footin Length Width Thicknes Depth Along X Along Y
g s
F1 1600mm 1600mm 350mm 2000mm 10-16mmØ 10-16mmØ

L=1.60 m
T =0.35 m

cc=0.075 m

SOLUTION:
F 1=2× [ T−2(cc ) ] + [ L−2(cc ) ]

F 1=2× [ 0.35−2(0.075) ] + [ 1.60−2(0.075) ]


F 1=1.90 m

Commerci Length No. of Scrap No. of No. of Total


al (m) Pieces (m) Pcs RSB Scrap
Length Require
(m) d
6 1.85 3 0.45 20 7 3.15
7.5 1.85 4 0.10 20 5 0.50
10.5 1.85 5 1.25 20 4 5
12 1.85 6 0.90 20 4 3.60
BILL OF MATERIALS & QUANTITIES
Work Quantity Unit Unit Total
Description Cost Cost
and Scope of
Works
`II. Earthworks
A. Excavation
Footing 1 103 cu.m 320.00 32,960.00
Direct Cost 32,960.00

B. Backfill
Footing 98 cu.m 190.00 18,620.00
Elevated 100 cu.m 584.00 58,400.00
Direct Cost 77,020.00

III. Rebarworks
A. Footing
16mmØ7.5 95 pcs 453.00 43,035.00
g.60
REFERENCES:

EXCAVATION & BACK FILL MAN HOUR – MANUAL LABOR


PhilConPrices (2021, January 24 ) Philippine Construction Productivity Rates
Philippine construction productivity rates Archives - PHILCON PRICES

MINIMUM WAGE FOR TUGUEGARAO CITY , REGION II

NewsToGov (2024, January 5) Minimum Wage Philippines 2024 in All Regions


https://newstogov.com/minimum-wage-philippines/

FOR BACKFILL MATERIALS


PhilConPrices (2023, October 19) Earthworks and Embankment Prices in the Philippines
Philippine construction productivity rates Archives - PHILCON PRICES

FOR REBARWORKS
WPFF: Philippine Material Price Tracker(2023, December 19) Rebar Price List and
Size Guide in the Philippines
Rebar Price List and Size Guide in the Philippines - WPFF

FOR GRADE 60 REBAR


Hammad Steel (2022) American Standard ASTM A615 Rebar Specification
ASTM A615 Steel Rebar | American Rebar Specifications | Grade 60 (hammadsteel.com)

You might also like