Professional Documents
Culture Documents
Sma SC Mvps RFQ Configurator Iec v3.41
Sma SC Mvps RFQ Configurator Iec v3.41
Storage Plant PV
t Control Stor
Genset / Load Plant Control
Needed for Commissioining G
SMA - Request for Quotation - Sunny Central PV Inverter, Sunny Centra
COMMERCIAL INFORMATION
Contact Information
Customer Company Name
Customer Commercial Contact - Name
Customer Commercial Contact - Email
Customer Technical Contact - Name
Customer Technical Contact - Email
Main technical contact in Commissioning phase (Decider)
Main technical contact in Commissioning phase (Engineer / Foreman)
SMA Commercial Contact - Name
SMA Technical Contact - Name
General Information
Project Name
Project Location / Ship-to location
Project Adress and/or GPS coordinates
Proximity to the sea, other aggressive environment
System Owner
Interconnect Utility
[For California only] Has a PWC 100 form been completed and the Project
has been registered with the Department of Industrial Relations?
Expected Schedule
Date of request
Quote Due Date / Needed Date of Answer
Other Information
Special Packing & Transportation Requirements
FAT Requirements & Scheduling
Service and /or Availibility Requirements
Spare Parts Requirement
Annual maintenance of SMA products by customers or by SMA
Miscellaneous
TECHNICAL INFORMATION
PV Plant Information
Active Power at POI
Required Power Factor at POI
Aux Power Factor Equipment
Voltage Level at POI
Tolerance of AC voltage at POI
Collector Voltage of Medium Voltage Transformer on MVPS
Medium Voltage Transformer Winding Configuration
Operating Temperature Range
Elevation
PV Information
Module Manufacturer
Module Model Number
Module Power Class
DC Array Size
Planned String Size
Tracker AC Power
Battery Information
DC Voltage Range
DC Voltage Range at Nominal Operation
Battery Rack Energy Content (kWh)
Battery Rack Power (kW)
Number of Racks connected per DC input / SLD available?
Battery Rack Prospective Peak Short Circuit Current (kA)
Fuse Pre-Arcing Integral I²t per DC input (A²s) / SLD available?
Battery Manufacturer and Model
Battery Management System and Model Number
Genset System
Fuel type
number of gensets
power rating per genset
genset control (manual / automatic)
Asynchronous or droop mode
Load profile
Annual energy consumption
Minimum load
maximum load
nnon lood
average load power factor
Load profile
Seasonal variable
Needed Information
IP address list including device IDs
Single Line Diagram whole plant
Communication Single Line Diagram
How is the local access to the system planned by the service
Access to Station
Local features to be considered
Which remote dial-in does the customer want to make available to us for
later support? Information about the possibilities.
Technical Information
Which MVSG protection settings should be used?
Customer
Example Customer
Customer
Example Project
Customer
Customer
Customer
Customer
- select -
- select -
Customer
Customer
- select -
- select -
- select -
Customer
- select -
- select -
Customer
Customer
- select -
- select -
- select -
- select -
- select -
Customer
- select -
- select -
- select -
- select -
- select -
- select -
- select -
Customer
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
- select -
Customer
- select -
- select -
Customer
- select -
- select -
Customer
- select -
- select -
- select -
- select -
- select -
- select -
- select -
Customer
Customer
SMA
ttery Inverter, MVPS Medium Voltage Power Station, Power Plant Manager
Comments
Comments
Comments
Explanation
Explanation
e.g. dirt road transportation
Explanation
e.g. 200MW - Total active power requirement at medium voltage level
Power Factor: e.g. 1 or 0.95
e.g. 1 MVAr
e.g. 20 kV
e.g. ±5 % at full power
if other:
select
e.g. -20°C to +40°C
e.g. <1000m
Explanation
e.g. 20 kW
Explanation
If already known, select the model
e.g 10
Medium Voltage Power Station (MVPS), with MV Switchgear
YES/NO - if yes, please provide detailed requirements
Explanation
select AC coupled for stand-alone or co-located storage projects, select DC coupled for PV + Storage
e.g. 20MW - Total active power requirement at medium voltage level
Power Factor: e.g. 1 or 0.95
e.g. 20 kV
e.g. ±5 % at full power
e.g. uk=12 %; eta=99.2 %
Explanation
Maximum voltage range of battery
"Usable" voltage range of battery
e.g. 200 kWh
e.g. 100 kW
e.g. 8
e.g. 10 kA
e.g. 4 MA²s, please refer to SMA PQ Tool
needed, if SMA integrates BMS into inverter control
needed, if SMA integrates BMS into inverter control, or via ext. Controller
Explanation
For DC coupled with Sunny Central PV inverter
1-6 per inverter possible
If already known, select the model, if not known select YES
e.g 10
Medium Voltage Power Station (MVPS), without MV Switchgear
Medium Voltage Power Station (MVPS), with MV Switchgear
YES/NO - if yes, please provide detailed requirements
Explanation
YES/NO
YES/NO - if yes, please provide information
YES/NO - if yes, please provide information
Communication network 1 is plant network: Communication diagram + IP adress list required
Explanation
YES/NO - if yes, please provide information
Please select all needed functions
if one is selected, please provide requirements-
if one is selected, please provide requirements-
if one is selected, please provide requirements-
Please describe requirments. (Ramp time fall and raise, dynamic requirements and filter times)
Please describe requirments. (Ramp time fall and raise, dynamic requirements and filter times)
if one is choosen, please provide requirements
Explanation
YES/NO - if yes, please provide detailed requirements
kVA
genset controller model / type
Explanation
kWh
kW
kW
kW
Explanation
standard SAT includes: open/closed loop P+Q control, basic function test, test for P+Q control mode
STANDARD/ADDITION tests: If additional , please specify
YES/NO - if yes, please provide detailed information
YES/NO - if yes, please provide detailed information
YES/NO - if yes, please provide detailed information
YES/NO
YES/NO
YES/NO
Explanation
Explanation
Standard or system specific? If system specific these must be checked for technical plausibility
T.01
T.02
T.03
T.04
T.04
T.05
T.06
T.07
T.08
T.09
T.10
T.10
L CLARIFICATION (Compliance Matrix/ Deviation List)
oject
S, SCS UP or SC UP…
omer
Description
SUPPLIER does not offer xxx
PURCHASER requests that xxx
Noted & Closed
CLOSED
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
OPEN
PV Configurator - SC-(UP) and MVPS-S2
Option Code* for SMA Sunny Central and 20ft. Medium Voltage Power Station (IEC)
*Not applicable for 20ft. UL MVPS-S2-US + SC (-UP) US versions
Note: Graph shows max. power for SC/MVPS combination (Vdc limit, PF=1, nominal AC voltage), for detailed sizing according to SC/MVPS Power
project specifications, please refer to data sheets and SMA Application Enginnering. 12
Power/ kVA
8
40°C: n/a
2
45°C: n/a Grid-Feed
50°C: n/a 0
15 20 25 30 35 40 45 50 55
55°C: n/a
Temperature / °C
1. DC Grounding - select -
2. DC Connection - select -
Check
SC/MVPS Power
12
10
Power/ kVA
2
Grid-Feed
0
15 20 25 30 35 40 45 50 55
Temperature / °C
Explanation Check
Explanation Check
Note:***Reduced Inrush Current option available for 20kV or 21kV/50Hz
(Other applications can be handled as customized solution)***
- select -
n/a
- select -
without MVPS
MVPS-2200-S2-11
MVPS-2475-S2-11
SC 2660 UP
MVPS-2660-S2-10
MVPS-2800-S2-10
MVPS-2930-S2-10
MVPS-3060-S2-10
MVPS-4000-S2-10
MVPS-4200-S2-10
MVPS-4400-S2-10
###
###
###
###
###
###
unevenly distributed
et of 6
- select -
ts of 3
- select -
32 fused inputs
36 x 1-pol PV + 6 battery inputs
UPSys DC-Fuse
- select -
- select -
internal (tOVP)
Select "Inverter Aux power supply" first
Single busbar
- select -
No
Yes
Inverter with reactive power provision during feed-in operation and non-feed-in operation (night). Mandatory for -40C temperature option (No. 20)
- select -
2-Winding Transformer
4-Winding Transformer
Yes
###
(optional)
Yes
Yes
- select -
Yes, for all devices
@1200Vdc
###
- select -
-40 … 60°C (35°C)
- select -
0 to 1000m
1001 to 2000m
- select -
- select -
-25 … 60°C (35°C)
n/a
- select -
50 Hz
- select -
Dy11 (Standard)
- select -
Without
- select -
Without
- select -
12 hours
- select -
Standard
n/a
Standard
Strongly Reduced
Without
n/a
Without
n/a
Without
n/a
Without
Auxiliary Contacts (recommended)
Remote Control
- select -
- select -
n/a
Without
- select -
Without
n/a
Without
- select -
Without
-25°C to +45°C
-25°C to +55°C
-35°C to +55°C
Harsh
- select -
Without
- select -
Road transport
- select -
DE: German
EN: English
FR: French
ES: Spanish
STORAGE Configurator - SCS-(UP) and MVPS-S2
Option Code* for SMA Sunny Central Storage and 20ft. Medium Voltage Power Station (IEC)
*Not applicable for 20ft. UL MVPS-S2-US + SCS (-UP) US versions
Note: Graph shows max. power for SCS/MVPS combination (SCS UP (-XT) @1200Vdc, PF=1, nominal AC voltage), for detailed sizing
according to project specifications, please refer to SMA PQ-Tool!
- select -
- select -
Check
SCS/MVPS Power
12
10
Power/ kVA
2
Charging Grid-Feed
0
15 20 25 30 35 40 45 50 55
Temperature / °C
Explanation Check
(optional)
(optional)
(optional)
Explanation Check
- select -
n/a
- select -
without MVPS
MVPS-2200-S2-11
MVPS-2475-S2-11
MVPS-2900-S2-11
MVPS-2660-S2-10
MVPS-2800-S2-10
MVPS-2930-S2-10
MVPS-3060-S2-10
MVPS-4000-S2-10
MVPS-4200-S2-10
MVPS-4400-S2-10
###
50 55 ###
###
n1
n1
Last cell changed
$H$35
No - Grid Following only
internal
internal (tOVP)
Select "Inverter Aux power supply" first
none
none
Managed Switch MMF Backbone
(optional)
Without
16 DI
###
n/a
2-Winding Transformer
4-Winding Transformer
Yes
(optional)
N
o
Yes
- select -
Yes, for all devices
- select -
Standard, Lockable
- select -
-25 … 60°C (25°C)
-40 … 60°C (25°C)
- select -
- select -
-25 … 60°C (25°C)
n/a
- select -
50 Hz
- select -
Dy11 (Standard)
- select -
Without
- select -
Without
- select -
12 hours
- select -
Standard
n/a
Standard
Strongly Reduced
Without
n/a
Without
n/a
Without
n/a
Without
Auxiliary Contacts (recommended)
Remote Control
- select -
- select -
n/a
Without
- select -
Without
n/a
Without
- select -
Without
-25°C to +45°C
-25°C to +55°C
-35°C to +55°C
Harsh
- select -
Without
- select -
Road transport
- select -
DE: German
EN: English
FR: French
ES: Spanish
Configurator - PPM-10
Option Codes for SMA Power Plant Manager
Quantity of PPM: 30
Is controller redundancy needed? - select - if "Yes", also enter "Quantity of PPM" = 2 (per POC/POI)
Additional Comments
POC/POI)
Customer comments