Professional Documents
Culture Documents
CII Piping
CII Piping
CII Piping
Prepared by the
January 1997
CII members may reproduce and distribute this work internally in any medium at no cost to internal recipients.
CII members are permitted to revise and adapt this work for the internal use provided an informational copy is
furnished to CII.
Available to non-members by purchase; however, no copies may be made or distributed and no modifications
made without prior written permission from CII. Contact CII at http://construction-institute.org/catalog.htm to
purchase copies. Volume discounts may be available.
All CII members, current students, and faculty at a college or university are eligible to purchase CII products at
member prices. Faculty and students at a college or university may reproduce and distribute this work without
modification for educational use.
References .......................................................................................................... 69
77
Executive Summary
Several tools have been developed by the CII Piping Function Research Team
to improve the efficiency of the piping function. These tools, categorized into
policies, procedures, checklists, and roles, are described in this publication.
v
79
List of Figures
Figure 1.1: Flowchart for Industry Plant Engineering and Construction ........ 2
Figure 2.1: Tool #1-A: Procedure — Integrated Flowchart for P&ID
Development ................................................................................. 10
Figure 2.2: Tool #1-C: Procedure — The Process for Using the Integrated
P&ID Development Flowchart ..................................................... 13
Figure 2.3: Comparison of Project Effort Input for 1980s and 1990s .......... 15
Figure 2.4: An Example of a Traditional “Hold” on a P&ID ....................... 36
Figure 2.5: Tool #8-A: Procedure — Example of a Hold With Notes .......... 39
Figure 2.6: Tool #8-B: Procedure — Example of a Hold With an
Action Code .................................................................................. 40
Figure 3.1: Tool #9-A: Procedure — Supplier Data Request Form ............... 43
Figure 3.2: Tool #9-B: Procedure — Commentary on Supplier Data
Request Form ................................................................................ 44
Figure 3.3: Tool #10: Procedure — Supplier Data Coordination Meetings .. 49
Figure 3.4: Tool #11-A: Procedure — Supplier Pre-Qualification Procedure 52
Figure 3.5: Tool #11-B: Procedure — Commentary on Supplier Pre-Qualification
Procedure ...................................................................................... 53
Figure 4.1: Tool #12-A: Procedure — Packaged Unit Supplier Pre-Qualification
....................................................................................................... 56
Figure 4.2: Tool #12-B: Procedure — Commentary on Packaged Unit
Supplier Pre-Qualification ............................................................ 57
vii
81
List of Tables
ix
83
Chapter 1
Introduction
Since the early 1980s the construction industry has realized that the piping
function is the most costly and least efficient function within industrial projects.
The Business Roundtable has estimated that the potential savings from improving
the piping function are about $3.8 million for an average heavy industrial project
costing $190 million.
Previous research found that solving problems at the early stage of a project
can often be the most cost-effective approach for projects. However, enhancing
the engineering development processes of P&IDs, supplier data, and packaged
units in order to improve the piping function has largely been ignored.
The research team reached consensus on two issues: first, too many uncertainties
in the piping process are the key factor in the inefficiency of the piping function;
and second, the piping function can be greatly enhanced by minimizing uncertainties
during the engineering development processes of the P&IDs, supplier data, and
packaged units.
This section briefly discusses the three areas of uncertainty in the piping
function.
P&IDs are schematic drawings showing the arrangement of all process and
utility equipment, piping, and instrumentation. P&IDs are an extension of process
flow diagrams (PFDs) and are used as the basis for detailed engineering design.
P&IDs evolve with the development of a project; a finished P&ID carries complete
information for all equipment, piping, process control, and instrumentation, and
the interrelationships these elements have. P&IDs play a significant role in process
1
Chapter 1: Introduction
piping design, construction, and start-up. Figure 1.1 is a flowchart depicting the
role of P&IDs in industrial plant engineering and construction. The research team
determined that artificially frozen P&IDs and late P&ID changes are key symptoms
of the inefficient P&ID development process.
Supplier Data
Supplier data are major information sources for design documents (P&IDs and
isometrics). Unfortunately, supplier documents are often missing, late, or contain
inaccurate information when needed to support accelerated engineering design
programs. This causes non-certified (uncertain) data to be incorporated into the
design documents, which are then sent downstream into the process. Associated
delays and uncertainties affect the piping function in the following ways:
2
Chapter 1: Introduction
Packaged Units
Similar to supplier data, packaged units can become a source of delays and
uncertainties for the design effort. In addition to design issues, however, packaged
units present problems for on-site installation since they frequently cause piping
rework and/or rerouting.
Table 1.1 shows the scope of this study. Industrial projects, excluding
commercial piping (plumbing), located in the U.S. were the major sources for this
investigation. The organizations involved in the research were CII owner companies
and CII contractor companies.
Research Scope
3
Chapter 1: Introduction
Types of Tools
The tools for enhancing the piping engineering development processes are
categorized and explained as follows:
Policy:
• A high-level overall plan embracing general goals and acceptable procedures.
Procedure:
• A particular way of accomplishing something or of acting.
• The means by which a policy can be accomplished. The procedure lays out
the steps usually followed in performing a recurring type of work. A
procedure establishes uniform methods for routine or repetitive matters.
Checklist:
• A complete list of necessary and/or desirable items with which engineers
perform a scrutinized cross-check in an effort to ensure these items are
properly addressed.
4
Chapter 1: Introduction
Role:
• Function; a socially expected behavior pattern usually determined by an
individual’s status.
• A norm that goes with a position or occupation. Roles and role pairs govern
the behavior of the person holding the position.
5
Chapter 2
Tools for Enhancing the P&ID Development Process
Research found that late P&ID changes are primarily the result of “artificially
frozen” P&IDs. Artificially frozen P&IDs are those containing information
elements that have not been finalized. Three key drivers that lead to artificially
frozen P&IDs and late P&ID changes are:
When P&ID development activities are not properly sequenced and prioritized,
projects can suffer from the following negative effects:
7
Chapter 2: Tools for Enhancing the P&ID Development Process
• Tool #2-A: Policy — Owner Project Team Formation for Early Input
8
Chapter 2: Tools for Enhancing the P&ID Development Process
The research team found the following six stages best describe the flow of the
P&ID development process:
Figure 2.1 depicts the six P&ID development stages and their activities. The
stages are shown in oval shapes at the bottom of the figure. The oval shapes on the
left are the predecessors to the ovals to their right. Above each stage are the
essential activities (shown vertically) for completing each stage. The arrows
indicate the sequence of the P&ID development. The shadowed blocks are P&ID
review activities. The double-lined blocks are P&ID development milestones.
9
Chapter 2: Tools for Enhancing the P&ID Development Process
10
Legend
O D D = P&ID Development = P&ID Information
Prepare Scope Receive Owner Develop AFO Stage Input
S Interm.
of Work AFP P&ID to Draft AFD
Supplier = P&ID Development = P&ID-Related
Input Milestone Activity
O D X
Process = P&ID Development O = Owner S = Supplier
Flow Develop P&ID Develop Draft O D = Designer C = Constructor
O/D Activity &
Diagram Schedule Reqt. AFM P&ID D
O S Multi-Disc. Reponsible Team O/D = Owner/Designer
Modify AFM Hazard/Safety Input
O Prelim. D to Draft AFO Revw • Piping/
• Control O
O Collect Prelim. Supplier O Mech.
Concept Conduct C
Input • Elect/ Issue AFD
• Interlock P&ID Input Owner Revw D D Receive Owner
Owner Instrum. P&ID for
Req’ts Collect AFC P&ID
Proj. Issue Draft • Struct. Detailed Design D
• Std. Dwgs. O Hazard/Safety
D Team AFO for • Geotech.
& Symbols Comments
Collect Prelim. Input Owner Revw D Detailed Disc.
Issue AFM P&ID
• Piping/Mech.
D
P&ID Internally Receive AFD
• Eqpt. List O • Equipment Engrg. D • Elect. & Modify AFC
• Piping Spec. Multi-Discip. O for Detailed
• Piping & Ducts Check- Instrum. to AFS
Revw Modify Draft Design
• Supplier • Instrument. lists Conduct • Struct.
• Owner AFD to Satisfy • Geotech.
C
Packages • Elec. Req’ts Owner Revw
D (Optional) Hazard/Safety D * Field
• Eng’g Stds. • Special Req’ts • Dgn Team
O
- Piping Revw Changes
• Eqpt. & Mech. D Expert, Rvw Owner Modify AFD
- HVAC Supports D Draft to D O/D
• Prelim. Safety or
- Elect. P&ID
& Environ. P&ID Collect Owner O/D Match Detailed Material Pre-Start-Up
- Instrum. O Check- Comments Design Results Quantity Revw
• Construct. Revw Pre-Detailed
- Insul’n lists Takeoff
Issue Draft • Plant Op/Main Check- Design Revw
- Fire Prot. O/D D
P&ID Internal • Research lists • Plant Op/Main
D
Review • Construct. Pre-Construct. S Modify P&IDs
Modify Draft Final
D Revw to Incorporate
AFO to Supplier
O Comments
Collect Multi- Incorporate D Input
Collect Internal Discipline Owner D D
Modify Draft
Comments Comments Comments Complete
AFD to AFD Issue AFS
AFC P&ID
to Owner
O D
D D D
Modify Draft Modify Draft O
AFM to Match Reissue AFO Issue AFD
to Match Issue AFC Approval of
Comments for Approval to Owner
Comments to Owner AFS P&ID
O D O O O O
Approval for Approval of Approval of Approval of Approval of Start
AFP P&ID AFM P&ID AFO P&ID AFD P&ID AFC P&ID Operation
Approval for Approval for Approval for Approval for Approval for Approval for
Preliminary Multi-Discipline Owner Detailed Design Construction Start-Up &
Review Stage Review Stage Review Stage Stage Stage Operation Stage
Figure 2.1. Tool #1-A: Procedure — Integrated Flowchart for P&ID Development Process
Chapter 2: Tools for Enhancing the P&ID Development Process
• preparation of P&IDs
• issuance of P&IDs
• P&IDs reviews
• modification to P&IDs
• approval of P&IDs.
Tool #1-B: Procedure — Information and Decisions for P&ID Development Stages
The research team prepared Table 2.1 to describe the information and
decisions needed for each of the P&ID development stages. This table assists the
completion of Figure 2.1. Tool #1-B should be used in conjunction with Tools #1-
A and #1-C.
11
Chapter 2: Tools for Enhancing the P&ID Development Process
Table 2.1. Tool #1-B: Procedure — Information and Decisions Needed for
Each P&ID Development Stage
12
Chapter 2: Tools for Enhancing the P&ID Development Process
The Integrated
Compare your company’s P&ID flowchart to P&ID
Step 2
the Integrated P&ID Development Flowchart Development
Flowchart
Proceed
No
Step 6 with the
modification?
Yes
Figure 2.2. Tool #1-C — Procedure — The Process for Using the Integrated
P&ID Development Flowchart
13
Chapter 2: Tools for Enhancing the P&ID Development Process
Tool #2-A: Policy — Owner Project Team Formation for Early Input
To deal with untimely input to P&IDs, some owners have changed their
traditional approach of soliciting information input so as to maximize the chances
of their projects’ success. These owners are now not only obtaining early input into
the P&IDs from the process groups, but are soliciting input from design engineering
groups as well as construction and maintenance personnel (Figure 2.3).
In the 1990s many owners changed the conventional timing for incorporating
internal and external input into their P&ID development process. Figure 2.3,
which is composed of Figures 2.3.1 and 2.3.2, depicts that change. This figure is
adapted from a diagram of a project effort input concept provided by a CII owner
company. Figure 2.3.1 depicts that owners in the 1980s requested P&ID information
primarily from manufacturing/operations units and the process engineering group
at the early stages of P&ID reviews: AFP, AFM, and AFO. Other information
input, from the design engineering group, construction group, process control
group, and suppliers, generally took place in the later stages, i.e., AFD, AFC, and
AFS. However, this owner and several other experts interviewed have agreed that
late input often leads to P&ID changes. Typically, this late input includes
comments from the operations/maintenance group, construction group, and
package unit suppliers.
With both domestic and international markets getting more competitive and
leading to smaller profit margins, progressive owners are looking for approaches
where they can realize a cost-benefit ratio. Acquiring both external and internal
input earlier in the process is one key approach. Figure 2.3.2 demonstrates how
some owners organize task forces to better integrate P&ID information input. The
early inputs that begin in the AFM stage come not only from manufacturing units
and process engineering groups, but also from design engineering, process control,
construction/maintenance, and certain key suppliers.
14
Chapter 2: Tools for Enhancing the P&ID Development Process
1980s
100
Manuf./
Oper.
%
Effort 50 Process Design Constr./
Input Engr’g Engr’g Maint.
Process
Control
0
AFP AFM AFO AFD AFC AFS
1990s
100
Manuf./
Oper.
%
Effort 50 Process Design
Input Engr’g Engr’g Constr./
Maint.
Process
Control
0
AFP AFM AFO AFD AFC AFS
Figure 2.3. Comparison of Project Effort Input for 1980s and 1990s
• Final supplier input: AFC stage, for certifying the supplier information
provided.
15
Chapter 2: Tools for Enhancing the P&ID Development Process
The purpose of obtaining continuous supplier input from the AFM stage to
the AFC stage is to have as much supplier data frozen as possible by the time the
P&IDs reach the AFD stage. Readers can also refer to Chapter 3 for supplier data
process improvement and Chapter 4 for packaged unit process improvement.
Table 2.2. Tool #2-A: Policy — Formation of the Owner Project Team
for Early Input
Formation Timing:
No later than the AFP or AFM stage
• Process engineer
• Piping/mechanical engineers
• Instrumentation/electrical engineers
• Construction experts
16
Chapter 2: Tools for Enhancing the P&ID Development Process
Tool #2-B: Policy — Tactics for Overcoming Barriers to Owner Project Team
Formation
There are two key barriers to owner project team formation. The first barrier
is related to the allocation and distribution of project resources. The second is
related to the owner organizational management and team member attitude. In
order to overcome these two barriers, four recommended tactics are listed in Table
2.3. The first two barrier breakers are recommended to resolve project resource
problems; the second two are intended to deal with the owner’s management issue.
17
Chapter 2: Tools for Enhancing the P&ID Development Process
Inefficient Procedures for P&ID Development & Reviews — Need for Tools
Because of the above two paradigms, many companies ignore the need for
P&ID development and review procedures. Research data show that 60 percent
(12/20) of the companies interviewed do not have P&ID development or review
procedures.
3. Standard items
18
Chapter 2: Tools for Enhancing the P&ID Development Process
P&ID procedures, the P&ID development and review documents that were
collected revealed the following key problems and their inter-relationships (Figure
2.1):
Tools for Improving Inefficient Procedures for P&ID Development and Reviews
19
Chapter 2: Tools for Enhancing the P&ID Development Process
20
Chapter 2: Tools for Enhancing the P&ID Development Process
Because these experience and preferences are rarely alike between owners and
their design counterparts, several months may be spent in the parties’ becoming
familiar with each other’s P&ID systems. To improve this situation, the industry
should establish standards for P&ID philosophies and P&ID physical components
as this will minimize time spent on coming to a mutual understanding.
Research found the top five items that have a high standardization potential
in P&ID philosophy and physical components. These are listed in Table 2.5 below:
The other potential needs for P&ID standardization are P&ID drafting
representations, P&ID terminology, and symbology. However, these are beyond
the scope of this research.
21
Chapter 2: Tools for Enhancing the P&ID Development Process
• to ensure that the information elements to be frozen during each stage are
accurate.
The contents of the seven reviews vary. The P&ID development technical
review checklist, shown in Table 2.6, identifies the technical contents for each
review and suggests a “freezing time” for each element. The “freezing time” is
defined as the milestone beyond which any further changes would result in
significant impacts on engineering and/or construction costs/schedules. The
research team interviewed 32 experts from 11 owner companies and nine contractor
companies to establish the “critical” time for freezing each P&ID information
element.
Although there was some agreement between owners and contractors on the
timing for freezing P&ID information elements, there was no established agreement
within the research sample. The research team has determined that a threshold
value of a cumulative 40 percent, starting from the AFP stage, is a reasonable
cutoff in determining the critical time for freezing each P&ID element. When an
overall cumulative response value (percent) was higher than 40 percent, that stage
was considered to be the critical one for freezing this P&ID element.
22
Table 2.6. Tool #5: Checklist — P&ID Development Technical Review Checklist (Page 1 of 6)
• 4. Drivers as required
• 5. Installed spares
• 6. Major internals including trays, packing, and demister pads
• 7. Specialty flanges
• 8. Arrangement of heat exchanger shells
Table 2.6. Tool #5: Checklist — P&ID Development Technical Review Checklist (Page 2 of 6)
• 3. Line numbers
• 4. Tie-in designations
• 5. Paint specification
C. Valves
• 1. Valve tags
• 2. Valve type
• 3. Valve size
Table 2.6. Tool #5: Checklist — P&ID Development Technical Review Checklist (Page 4 of 6)
• 5. Instrument numbers
• 7. Bridles/manifolds
• 4. Emergency interlocks
• 2. Jacketing
• 3. Tracing type
G. Specialty Items
• 1. Hoses
• 2. Steam traps
• 4. Sample systems
Table 2.6. Tool #5: Checklist — P&ID Development Technical Review Checklist (Page 6 of 6)
I. Interlocks
2. Reviewers should use the complete checklist (all six pages) to review each
P&ID.
3. Reviewers should circle one of the P&ID development stages on the checklist
to indicate the review stage; this checklist can be used during all six stages
of the P&ID development process.
29
Chapter 2: Tools for Enhancing the P&ID Development Process
6. Reviewers should identify the deviations for each P&ID element and then
make a note in the column for the number of deviations on the checklist.
7. Reviewers should accumulate the total number of deviations for each P&ID
and then determine the acceptance status.
A: Accountable — The group is accountable for insuring that the result occurs.
30
Table 2.7. Tool #6: Procedure — Responsibility Assignment Chart for P&ID Development
Legend Process Project Piping Mech Instrum/ Safety Oper’ns Mainten Const’n Tech. Draft
A: Accountable, C: Consult, Engr. Mgr/ Engr. Engr. Elec. Engr. Engr. Engr. Engr. Expert
I: Inform, R: Responsible (1) Engr. (2) (3) (4) Engr (5) (6) (7) (8) (9) (10) (11)
Define P&ID Scope of Work R A C C C C C C I I C
Schedule P&ID Work R A C C C C C C C C C
Provide PFD R A
Provide Control Strategy R A R C
Integrate Control/ R A R C C C C
Interlocks Strategy
Std. Dwgs. and Symbols R A I I I I I I C
Incorporate Safety Concept R A C C
Operation Concept R A C C
Maintenance Concept R A C C
P&IDs can be truly frozen or “artificially” frozen. P&IDs are truly frozen
when information is certain and no future design changes or construction changes
will be necessary. Conversely, P&IDs that are frozen before some of their
information elements are truly certain are considered “artificially” frozen. Uncertain
P&ID information elements that have been artificially frozen often lead to late
P&ID changes, piping design changes, procurement/fabrication changes, and
construction changes.
Table 2.8 shows 10 conditions and the recommended solutions for each.
These conditions are listed in the order of agreement percentages that are shown
in the middle column. The higher the percentage, the more experts interviewed
agreed that the condition leads to artificially frozen P&IDs. These percentages
range from 83 percent (non-certified supplier data) to 46 percent (without
construction group’s review) and indicate that:
3. The third most common condition for artificially frozen P&IDs are:
• the information is waiting for further input from process engineers (67
percent)
• the information is frozen before it has been reviewed by all disciplines (63
percent).
32
Chapter 2: Tools for Enhancing the P&ID Development Process
4. The fourth most common condition for artificially frozen P&IDs is that the
information is hard to freeze in similar previous projects (58 percent).
• the information has not been reviewed by the construction group (46
percent). The research team found that this is because many of the CII
member companies interviewed have implemented constructability studies
at the early stage of projects.
The solutions shown in the far right column of Table 2.8 are compiled from
the suggestions collected from the experts interviewed in addition to the research
team’s opinions.
33
Chapter 2: Tools for Enhancing the P&ID Development Process
34
Table 2.8. Tool #7: Policy — Strategies for Avoiding Artificially Frozen P&IDs (Page 1 of 2)
3. The information has not been 79% • Cloud the uncertain information and mark it as “on hold.”
reviewed by owner maintenance • Responsible designers request an owner review within a specified
personnel. time frame.
4. The information has not been 75% • Brainstorming session, involving senior staff from operating units,
reviewed by owner hazard/safety/ should be held before the approval for owner review stage (AFO).
operations staff.
Table 2.8. Tool #7: Policy — Strategies for Avoiding Artificially Frozen P&IDs (Page 2 of 2)
8. The information is hard to freeze 58% • Document lessons learned from previous projects.
in similar previous projects. • Standardize P&ID information from lessons learned.
9. The information is designed by 50% • Extensive use of P&ID development guidelines, standards, and
inexperienced personnel. P&ID review checklists in order to train young engineers and to
maintain a consistent level of P&ID quality.
• Use experienced engineers to review the P&IDs designed by
inexperienced engineers.
10. The information has not been 46% • Bring the construction experts in early at the AFO stage to review
reviewed by the construction both P&IDs and plot plans.
group.
35
Chapter 2: Tools for Enhancing the P&ID Development Process
HOLD
P&ID K-18
Process engineers who design P&IDs with “holds” have different approaches
to take care of the areas in the clouds. Some process engineers show an indicative
layout of an on-hold process to P&ID users so as to give them a basic idea of this
process. Other engineers consider this approach as likely to mislead the readers to
use the uncertain information for their follow-on design. These engineers, therefore,
strongly recommend that the clouded area should show nothing but interface
information. This interface information is considered to be frozen in this approach.
Usually, engineers who encounter a “hold” take one of the following two
kinds of actions. The first is to leave the “hold” alone and wait for more
information to come. This often leads to an incomplete P&ID design submittal,
and is, therefore, not preferred by many design managers. The second kind of
action is for the engineers to proceed with a detailed design based on the
temporary information shown in the “hold.” This often results in rework in
design/manufacturing/ construction due to late information updates pertaining to
the “hold.” Because the current approach of communicating P&ID uncertain
information has the above drawbacks, improving such a method is necessary.
36
Chapter 2: Tools for Enhancing the P&ID Development Process
The research team found four causes leading to the inefficiency in current
P&ID communication. These causes are:
• No contact point for P&ID users to clarify the information pertaining to the
“hold.” Under schedule pressure, engineers often try to do something with
the “hold” in order to make some detailed design progress. However, they
are troubled by the lack of a person to contact so as to clear up the vagueness
of the hold.
• No time of reference for when the information will become firm. Without
knowing when the “holds” will be discharged, engineers often assume that
the information shown in the on-hold area is likely to be certain and proceed
with their design. This leads to design and construction rework when the
“holds” are clarified by new information.
37
Chapter 2: Tools for Enhancing the P&ID Development Process
The following sections discuss two tools that can improve the efficiency of
P&ID communication. The first communication tool can include specific on-hold
information needed, a contact point for clarification, and a time reference for
releasing the “hold.” The second tool provides a recommended action for engineer
follow-up.
The first tool, adding detailed notes to P&ID “hold” clouds, can provide
additional information to engineers and can help establish a clearer design
direction. This tool has two purposes. The first is to respond to the interviewees’
comment that the “hold” should specify what information items remain uncertain.
The second is to eliminate three of the four causes. This tool recommends that the
following three pieces of information (as a minimum) be included in the notes by
the engineers who prepare P&IDs with “hold” clouds:
1. What are the specific reasons for the “hold”? (What item is uncertain?)
In item 1, the specific area of uncertainty, such as the size or material for a
piece of equipment, can be identified in the notes to assist engineers in deciding
their future actions. If the engineers are not sure what action to take, they can
consult the responsible person or discipline, identified in item 2, for additional
information. The engineers can also schedule their design activity based on the
release time indicated in item 3. According to some interviewees, this tool is
particularly useful for large projects, where communication between engineers is
sometimes more difficult. For smaller projects, having weekly meetings to discuss
this information is a viable alternative. An example of this tool is illustrated in
Figure 2.5.
38
Chapter 2: Tools for Enhancing the P&ID Development Process
HOLD #2
HOLD #2:
(1) Line size and material are on hold.
HOLD #2 (2) Contact John Smith/Process
(512) 555-5555
(3) The hold will be released on 05/30/96
P&ID K-18
Table 2.9 shows the relationship between the level of certainty of a “hold”
and the three corresponding suggested actions. In this table, both the level of
certainty of a “hold” and the corresponding suggested actions should be assigned
by the engineers who place the P&ID “on hold.” The percentages in the column
“Level of Certainty” are not significant in themselves, but could be established for
a company or a project. The percentages shown in Table 2.9 are only examples
that the research team considers adequate for this application.
39
Chapter 2: Tools for Enhancing the P&ID Development Process
HOLD #2
HOLD #2:
(1) Line size and material are on hold.
HOLD #2 (2) Contact John Smith/Process
(512) 555-5555
(3) Action Code: B
(4) The hold will be released on 05/30/96
P&ID K-18
Figure 2.6: Tool #8-B: Procedure — Example of a Hold With an Action Code
40
Chapter 3:
Tools for Enhancing the Supplier Data Process
Research indicates that the following items directly influence supplier data
timeliness and quality:
Research also indicates three major classes of problems with the above factors
of supplier data:
• Supplier selection problems, which stem mostly from using the classical bid
approach.
41
Chapter 3: Tools for Enhancing the Supplier Data Process
The main cause of such communication problems centers around the supplier
data requests themselves. Some designers assume that suppliers know the “standard”
set of drawings that are required to support the design effort and that their
definitions of information to be included on each type of drawing (i.e., general
arrangement drawings or detail drawings) are the same. In addition, suppliers are
not always fully informed as to when designers need supplier drawings. The
resulting effects include:
42
Chapter 3: Tools for Enhancing the Supplier Data Process
The supplier is to furnish the following data for each equipment item furnished in the
quantities, packages and schedules established below. All documentation must be
identified with the following information: Plant - Project - Order # - Equipment/Tag #
43
Chapter 3: Tools for Enhancing the Supplier Data Process
1. Final payment will not be made until all documentation agreed upon in the
supplier data request has been submitted to the Supplier Data Coordinator.
3. Each resubmittal should retain the original document number and should
include a new revision number.
44
Chapter 3: Tools for Enhancing the Supplier Data Process
45
Chapter 3: Tools for Enhancing the Supplier Data Process
46
Chapter 3: Tools for Enhancing the Supplier Data Process
Certified Material Test Reports: These reports shall include all chemical,
physical, mechanical, and electrical property test data required by the
specification and/or applicable codes.
47
Chapter 3: Tools for Enhancing the Supplier Data Process
• Requisitioning Engineer
• Expediters
• Provide a forum for the engineers to identify any drawing needs or highlight
time requirements.
48
Chapter 3: Tools for Enhancing the Supplier Data Process
Participants
Requisitioning Sales
Expediter
engineer engineer
Designer
team Supplier’s
Engineering Supplier
team
disciplines drawing (if necessary)
representativer coordinator
Issues Addressed
Prioritization of
Purchase orders status Reviews status
Purchase Orders
Expected Outcome
49
Chapter 3: Tools for Enhancing the Supplier Data Process
The supplier data cycle process includes responsibilities and requests from the
designer team, the owner team, and the supplier team.
One reason for the length of this process is the supplier selection process. If
a competitive bidding process is utilized, chances are that the bidder may differ
from job to job due to fluctuations in pricing and performance levels. Engineering
must then wait until the procurement cycle is complete before it can utilize any
supplier drawing information. As a result, supplier data receipt time is extended
and frequently behind schedule. The design team then spends additional time and
resources expediting the data or utilizing incomplete/preliminary documentation
in order to maintain the engineering schedule.
50
Chapter 3: Tools for Enhancing the Supplier Data Process
51
Chapter 3: Tools for Enhancing the Supplier Data Process
Establish a committee
to administer the program
Specialty
Electrical
piping
Communicate goals
and objectives Shop fab.
Valves
pipe
Distributive
Instruments
control
Rotating Structural
Sub-committee creates a set equipment steel
of criteria for establishing a
perferred supplier list Supplier data
cycle time
Equipment
quality
Owner
A/E Solicit information from Documentation
Contractor various sources quality
Supplier
Documentation
Sub-committee evaluates timeliness
suppliers
Price (market)
competitiveness
Final negotiations are conducted
with the preferred suppliers
Periodic performance
Committee aggregates all evaluation update
information into one master
preferred-suppliers list Update criteria
Sub-committee maintains
list of preferred suppliers
52
Chapter 3: Tools for Enhancing the Supplier Data Process
53
Chapter 4:
Tools for Enhancing the Packaged Unit Process
Packaged unit process is the third major problem in the piping function.
Research has identified seven main issues concerning packaged units. The research
team has developed four recommendations that will address most of these issues.
Best practices have been identified for two of the issues.
The research shows that packaged unit supplier quality suffers due to the
following problems:
Because packaged units are more complex than most plant equipment,
supplier engineering should be carefully monitored over and above the typical
review of product data and the final product. This program consists of establishing
a committee that develops evaluation criteria, and then evaluates packaged unit
suppliers based on those criteria.
55
Chapter 4: Tools for Enhancing the Packaged Unit Process
Establish a committee
to administer the program
Communicate goals
and objectives
Refrigeration Lube oil
Owner Equipment
A/E Solicit information from quality
Contractor various sources Documentation
PU Supplier
quality
Sub-committee evaluates Documentation
PU suppliers timeliness
Price (market)
competitiveness
Periodic performance
Committee aggregates all evaluation update
information into one master
preferred PU suppliers list Update criteria
56
Chapter 4: Tools for Enhancing the Packaged Unit Process
57
Chapter 4: Tools for Enhancing the Packaged Unit Process
The following major problems and solution tools relate to packaged unit
design:
After identifying the problems associated with packaged unit design, the
following tools can be used to improve the packaged unit design:
58
Chapter 4: Tools for Enhancing the Packaged Unit Process
Participants
Specification Specification
package package
developers developers
Designer’s
Owner team
team
Process O&M Engineering
engineer personnel disciplines
representatives
Issues Addressed
Necessity of Redundancy of
customization specifications
Clarity of
specifications
Use of Unnecessary length
supplier standards of specifications
Expected Outcome
59
Chapter 4: Tools for Enhancing the Packaged Unit Process
• Review the specifications package with the supplier and ensure full
understanding.
• Review all the clarifications and come to an agreement for every exception.
• Explain to the packaged unit supplier what the supplier data requirements
are and when they are needed.
60
Chapter 4: Tools for Enhancing the Packaged Unit Process
Participants
Specification
package
Process developers Sales
engineer engineer
Expediter
Requisitioning
and/or
engineer
Owners inspector Designer Packaged team
team team supplier team
O&M
Engineering Supplier Engineer(s)
personnel
disciplines drawing
representativers coordinator
Issues Addressed
Performance testing
O&M needs Inspection specifications
requirements
Expected Outcome
Supplier agreement on
Full incorporation
documentation
of O&M needs
procedures and deadlines
Supplier’s full
understanding of
specifications package
Supplier understanding
Clarification of
of testing and inspection
all exceptions
procedures
61
Chapter 4: Tools for Enhancing the Packaged Unit Process
Note:
The customization and pre-award meetings are not intended to take the place
of the kick-off meeting. This meeting is important because it introduces the owner
and designer teams to shop personnel, who will be responsible for the actual
packaged unit design and fabrication.
From 17 packaged unit case studies reviewed in detail by the research team,
the average direct field and engineering rework percentage was found to be 7.3
percent of the initial cost. It is thus cost effective to have a designated packaged
unit coordinator for all projects. Table 4.1 describes detailed information of this
new role.
62
Chapter 4: Tools for Enhancing the Packaged Unit Process
Qualifications:
• Familiarity with all the disciplines involved (enough to be able to ask the
right questions)
• Ability to ask questions to all disciplines about the need for consistency
between the many reviews
Key Tasks:
• Coordinate between designers and packaged unit suppliers (requirements,
timing, etc.)
- Customization review
- Pre-award meeting
Prerequisite Policy:
The packaged unit coordinator needs to be given enough clout and
authority to impose a task or a deadline on all disciplines of engineering
involved in the packaged unit.
63
Chapter 5:
Conclusions
The piping function is the most costly and least efficient function within
industrial projects. Although research has shown that taking care of problems at
the early stage of the projects can be the most cost-effective approach, limited
research has been conducted related to the improvement of the piping function.
The CII Piping Function Research Team recognizes that too much uncertainty in
the piping engineering process is the primary reason for the inefficiency. The team
first identified 14 problematic piping issues, and then proceeded to develop
solutions. The following conclusions are offered by the research team:
1. Three areas that involve recurring uncertainty in the piping function are
P&IDs, supplier data, and packaged units.
2. The drivers leading to inefficient P&ID development are (1) lack of sequencing
and prioritization in the P&ID development process, (2) inefficient P&ID
development procedures and review checklists, and (3) inefficient
communication of P&ID uncertainty.
4. Supplier quality issues and design issues are two big problems in the
packaged units process.
6. Research indicates that early input can greatly improve the performance of
projects. Lack of input from construction and operation/maintenance at the
early stage of projects is a main contributor to project uncertainty. Leading
companies are encouraging such input in order to minimize uncertainty in
the piping process.
65
Chapter 5: Conclusions
66
Table 5.1. Summary Listing of Solution Tools for Inefficient Piping Function (Page 1 of 2)
- (Tool #1-C):
Use of the Integrated P&ID
Development Flowchart
- (Tool #3): - (Tool #5):
• Inefficient P&ID - (Tool #6):
****
Pre-P&ID Information List P&ID
Development and Responsibility Assignment Chart Review
- (Tool #4): for P&ID Development
Review Procedure Checklist
P&ID Standardization List
and its Use
- (Tool #7):
Strategies for Avoiding
Artificially Frozen P&IDs
Table 5.1. Summary Listing of Solution Tools for Inefficient Piping Function (Page 2 of 2)
- (Tool #10):
• Coordination Problems Supplier Data Coordination
Meetings
Chapter 5: Conclusions
67
References
Gibson, G. E., Kaczmarowski, Jerome H., and Lore, H. Edgar, Jr. Modeling
Pre-Project Planning for the Construction of Capital Facilities. The
University of Texas at Austin. Construction Industry Institute Source
Document 94. July 1993.
Hartman, W., Williams, F. Pipe Drafting. McGraw Hill Book Company. New
York, N.Y., 1981
69
References
Nayyar, Mohinder L. Piping Handbook. McGraw Hill, Inc. New York, N.Y.,
1992.
70
References
Piping: Improving P&IDs, Supplier Data, and Packaged Units. The University
of Texas at Austin, Construction Industry Institute Research Summary
47-1. December 1996.
“Total Effort Graphs.” Dow Chemical Company. Research mail from Bill
Olmsted to Shih-Jen Liao, February, 15, 1995.
Voeller, J. G. Special Reprint from the Nov. ’94 issue of The A-E-C Automation
Newsletter highlighting the efforts of PlantSTEP Inc., Technology
Publications Inc., Atlanta, Georgia, 1994, p. 3.
Weaver, Rip. Process Piping Design. Gulf Publishing Company, Book Division,
Houston, Texas, 1986.
71
Notes
72
Notes
73
Piping Function Research Team
* Principal Author