Id Modo de Nombre de tarea Duración Comienzo Fin tri 2, 2023 tri 3, 2023 tri 4, 2023 tri 1, 2024 tri

tri 2, 2023 tri 3, 2023 tri 4, 2023 tri 1, 2024 tri 2, 2024
tarea abr may jun jul ago sep oct nov dic ene feb mar abr may
1 REMODELING EMBASSY OF 228 días mar 2/05/23 mié 6/03/24
CANADA
2 CIVIL WORKS 197 días mar 2/05/23 jue 25/01/24
3 PERIMETER WALL 32 días mar 2/05/23 mar 13/06/23
4 PRELIMINARY WORKS 5 días mar 2/05/23 lun 8/05/23
5 INSTALLATION OF WORK BOOTH 5 días mar 2/05/23 lun 8/05/23
6 DIGGING FOR FOUNDATION FOR WALL 5 días mar 2/05/23 lun 8/05/23
IN THE CORNER
7 STRUCTURAL STEEL FOR WALL IN THE 4 días lun 8/05/23 vie 12/05/23
CORNER
8 FORMWORK FOR WALL IN THE 4 días vie 12/05/23 jue 18/05/23
CORNER
9 CONCRETE FOR WALL IN THE CORNER 1 día jue 18/05/23 vie 19/05/23

10 DEMOLITION OF METAL PIPES BASES 10 días lun 8/05/23 lun 22/05/23


IN THE WALLS
11 STRUCTURAL STEEL FOR CONCRETE 5 días lun 22/05/23 vie 26/05/23
WALL REPLACING METAL PIPES
12 FORMWORK FOR CONCRETE WALL 6 días vie 26/05/23 lun 5/06/23
REPLACING METAL PIPES
13 CONCRETE FOR WALL REPLACING 1 día lun 5/06/23 mar 6/06/23
METAL PIPES
14 STRUCTURAL STEEL FOR 0.40M WALL 5 días vie 26/05/23 vie 2/06/23
(SIKADUR 31)
15 FORMWORK FOR 0.40M WALL 5 días vie 2/06/23 vie 9/06/23
16 CONCRETE FOR 0.40M WALL 2 días vie 9/06/23 mar 13/06/23
(SIKADUR 32)
17 GUARD BOOTH 145 días lun 10/07/23 jue 25/01/24
18 REMOVAL OF EXISTING WINDOWS 7 días lun 10/07/23 mié 19/07/23
AND DOORS
19 DEMOLITION OF WALLS AND ROOF 15 días lun 10/07/23 mar 1/08/23
SECTION OF EXISTING SHED
20 EXCAVATION FOR WALLS 10 días vie 14/07/23 lun 31/07/23
FOUNDATIONS
21 STRUCTURAL STEEL FOR GUARD 12 días lun 31/07/23 mar 15/08/23
BOOTH FOUNDATION AND WALLS
22 CONCRETE FOR GUARD BOOTH WALL 1 día vie 18/08/23 lun 21/08/23
FOUNDATION
23 TEST SOIL 7 días lun 21/08/23 mar 29/08/23
24 STRUCTURAL STEEL FOR NEW 7 días mar 29/08/23 vie 8/09/23
FOUNDATION AND NEW WALL
25 CONCRETE FOR NEW WALL 1 día vie 8/09/23 lun 11/09/23
FOUNDATION
26 FORMWORK FOR GUARD BOOTH 96 días lun 21/08/23 lun 1/01/24
WALLS
27 CONCRETE FOR GUARD BOOTH WALL 1 día lun 1/01/24 mar 2/01/24

28 STRUCTURAL STEEL FOR NEW SLAB 5 días mar 2/01/24 mar 9/01/24
29 ELECTRICAL PIPES 90 días lun 21/08/23 mié 20/12/23
30 SANITARY PIPES 90 días lun 21/08/23 mié 20/12/23
31 FORMWORK FOR NEW SLAB 5 días mar 9/01/24 lun 15/01/24
32 CONCRETE FOR NEW SLAB 1 día lun 15/01/24 mar 16/01/24

Schedule of activities Embassy Tarea Resumen Hito inactivo solo duración solo el comienzo Hito externo División crítica
73DSTUDIO S.A.C. División Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha límite Progreso

Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas críticas Progreso manual

Página 1
Id Modo de Nombre de tarea Duración Comienzo Fin tri 2, 2023 tri 3, 2023 tri 4, 2023 tri 1, 2024 tri 2, 2024
tarea abr may jun jul ago sep oct nov dic ene feb mar abr may
33 RENDERING OF WALLS AND CEILING 7 días mar 16/01/24 jue 25/01/24
OF SECURITY BOOTH
34 END OF CIVIL WORKS 0 días jue 25/01/24 jue 25/01/24 25/01

35 FINISHING WORK 228 días mar 2/05/23 mié 6/03/24


36 FLOOR 162 días lun 26/06/23 vie 2/02/24
37 INDOOR 162 días lun 26/06/23 vie 2/02/24
38 SHIPPING 50 días lun 26/06/23 lun 4/09/23
39 ROOM FLOOR SIZE: 0.60m x 50 días lun 26/06/23 lun 4/09/23
0.60m PORCELAIN TILE SERIE:
OTTAWA

40 TYPICAL FLOOR SIZE: 0.60m X 50 días lun 26/06/23 lun 4/09/23


0.60m PORCELAIN TILE SERIE: FS
VENECIA COLOR: NATURAL

41 WALL SIZE: 0.10m X 0.30m 50 días lun 26/06/23 lun 4/09/23


PORCELAIN TILE SERIE: GALLERY
COLOR: GREY SHINNY

42 SKIRTING BOARD 0.10m x 2.00m 50 días lun 26/06/23 lun 4/09/23


FOAM THICKNESS=20mm SERIE:
FL5 WALL

43 VENEER INSTALLATION 7 días jue 25/01/24 vie 2/02/24


44 SKIRTING BOARD INSTALLATION 7 días jue 25/01/24 vie 2/02/24
45 OUTDOOR 105 días lun 26/06/23 jue 16/11/23
46 SHIPPING 80 días lun 26/06/23 jue 12/10/23
47 TYPICAL FLOOR SIZE: 0.60m X 80 días lun 26/06/23 jue 12/10/23
0.60m PORCELAIN TILE SERIE: FS
VENECIA COLOR: NATURAL

48 VENEER INSTALLATION 25 días jue 12/10/23 jue 16/11/23


49 SANITARY 7 días jue 25/01/24 vie 2/02/24
50 INSTALLATION OF SANITARY 7 días jue 25/01/24 vie 2/02/24
EQUIPMENT
51 METALWORK 182.88 días mar 13/06/23 lun 19/02/24
52 MANUFACTURING OF TOPPERS 5 días mar 13/06/23 lun 19/06/23
53 SUPPLY AND INSTALLATION OF 32 días lun 19/06/23 mié 2/08/23
TOPPERS
54 EXTENSION OF 2 FRONT GATES 5 días mar 13/06/23 lun 19/06/23
55 MANUFACTURE AND INSTALLATION 15 días jue 11/01/24 mié 31/01/24
OF LETTERS WITH GALVANIZED PLATE
OF 2MM AND PAINTED WITH
POLYURETHANE PAINT

56 SUPPLY AND INSTALLATION OF 14 15 días mar 30/01/24 lun 19/02/24


POLES (PEDESTALS) FOR LUMINAIRES
TYPE L OF 4.11X1.10M

57 INSTALLATION OF FIXED BOLLARDS 20 días jue 12/10/23 jue 9/11/23


58 RETRACTABLE BOLLARDS SHIPPING 65 días mar 13/06/23 lun 11/09/23
59 PREPARATION OF WORK ZONE 37 días lun 11/09/23 lun 30/10/23
60 PROTECTION OF HIGH/MEDIUM 10 días lun 30/10/23 lun 13/11/23
VOLTAGE LINES
61 SHOPDRAWING OF BOLLARDS' 15 días lun 13/11/23 vie 1/12/23
INSTALLATION
62 INSTALLATION OF BOLLARDS' CASE 5 días vie 1/12/23 lun 11/12/23
63 POURING OF FIRST LAYER OF 2 días lun 11/12/23 mié 13/12/23
CONCRETE FOR BOLLARD
FOUNDATION

Schedule of activities Embassy Tarea Resumen Hito inactivo solo duración solo el comienzo Hito externo División crítica
73DSTUDIO S.A.C. División Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha límite Progreso

Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas críticas Progreso manual

Página 2
Id Modo de Nombre de tarea Duración Comienzo Fin tri 2, 2023 tri 3, 2023 tri 4, 2023 tri 1, 2024 tri 2, 2024
tarea abr may jun jul ago sep oct nov dic ene feb mar abr may
64 FORMWORK FOR BOLLARDS' CASE 2 días mié 13/12/23 vie 15/12/23
65 PIT FILLING WITH AFIRMADO AND 1 día vie 15/12/23 lun 18/12/23
LAYER OF CONCRETE
66 HOLIDAYS BREAK 20 días lun 18/12/23 lun 15/01/24
67 POURING OF SECOND LAYER OF 1 día lun 15/01/24 mar 16/01/24
CONCRETE FOR BOLLARD
FOUNDATION

68 INSTALLATION OF RETRACTABLE 20 días mar 16/01/24 lun 12/02/24


BOLLARDS
69 INSTALLATION OF METAL DOORS IN 10 días lun 5/02/24 vie 16/02/24
SECURITY BOOTH
70 FACADE 186 días mar 2/05/23 jue 11/01/24
71 DEKTON'S SHIPPING 115 días mar 2/05/23 mié 4/10/23
72 SURFACE PREPARATION 31 días mié 4/10/23 mié 15/11/23
73 SUPPLY AND INSTALLATION OF 40 días mié 15/11/23 jue 11/01/24
VENEER WITH DEKTON
74 ELECTRICAL 22 días jue 25/01/24 vie 23/02/24
75 ELECTRICAL WIRING FOR SECURITY 15 días jue 25/01/24 mié 14/02/24
BOOTH AND PERIMETER FENCE
76 SUPPLY AND INSTALLATION OF 7 días mié 14/02/24 vie 23/02/24
SWITCHES
77 FORNITURE INSTALLATION 10 días jue 25/01/24 mié 7/02/24
78 REINFORCED DRYWALL PARTITION 5 días jue 25/01/24 jue 1/02/24
79 LOCKER INSTALLATION 5 días jue 25/01/24 jue 1/02/24
80 MELAMINE INSTALLATION 10 días jue 25/01/24 mié 7/02/24
81 BEVELLED MIRROR 1 día jue 25/01/24 vie 26/01/24
82 THERMA 3 días jue 25/01/24 mar 30/01/24
83 AIR CONDITIONING 30 días lun 15/01/24 vie 23/02/24
84 CIVIL WORKS 15 días lun 15/01/24 vie 2/02/24
85 EQUIPMENT INSTALLATION 15 días lun 5/02/24 vie 23/02/24
86 FIRE ALARM SYSTEM 122.13 días jue 14/09/23 mar 27/02/24
87 WIRING 10 días jue 25/01/24 mié 7/02/24
88 TESTS 5 días mié 7/02/24 mié 14/02/24
89 LUMINAIRES 88.94 días jue 14/09/23 lun 15/01/24
90 SECURITY BOOTH 122.13 días jue 14/09/23 mar 27/02/24
91 SHIPPING 80 días jue 14/09/23 mié 3/01/24
92 LUMINAIRE INSTALLATION 10 días mié 14/02/24 mar 27/02/24
93 PERIMETER WALL 110 días jue 14/09/23 lun 12/02/24
94 SHIPPING 100 días jue 14/09/23 mar 30/01/24
95 LUMINAIRE INSTALLATION 10 días mar 30/01/24 lun 12/02/24
96 PAINTING 31 días jue 25/01/24 mié 6/03/24
97 FIRST LAYER SECURITY BOOTH 10 días jue 25/01/24 mié 7/02/24
PAINTING
98 PASTING OF EXTERIOR WALLS 20 días jue 25/01/24 mié 21/02/24
99 PAINTING OF EXTERIOR PLANTERS 7 días jue 25/01/24 vie 2/02/24
100 SECOND LAYER SECURITY BOOTH 6 días mar 27/02/24 mié 6/03/24
PAINTING
101 END OF PROJECT 0 días mié 6/03/24 mié 6/03/24 6/03

Schedule of activities Embassy Tarea Resumen Hito inactivo solo duración solo el comienzo Hito externo División crítica
73DSTUDIO S.A.C. División Resumen del proyecto Resumen inactivo Informe de resumen manual solo fin Fecha límite Progreso

Hito Tarea inactiva Tarea manual Resumen manual Tareas externas Tareas críticas Progreso manual