The following table shows the tasks, dependencies, and estimated times a project manager might

input to a basic GANTT chart for a software development project.

Task Task Description Predecesso Duration(days)


Identifie r Task(s)
r
A Establish Project - 2
B Establish Customer Requirements A 3
C Produce Software Specification Documents B 4
D Write Test Plans C 1
E Write Code C 2
F Developer Testing E 2
G System Testing D, F 4
H Write Customer Documentation C, G 3

Develop a Gantt chart. When does the project end?