Professional Documents
Culture Documents
Automated Estimate - Structural
Automated Estimate - Structural
Automated Estimate - Structural
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 44 bags
Sand 1.8 cu.m
Gravel 3.6 cu.m
Tie Wire 6.00 kg
F-1 16mm Ø X 12m 12.00 pcs
F-1 12mm Ø X 9m 16.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
EXCAVATION COST =
BACKFILL COST =
TOTAL COST =
ING ESTIMATE
FOOTING DETAILS
ERIALS
PRICE TOTAL COST
₱ 220.00 ₱ 9,680.00
₱ 875.00 ₱ 1,575.00
₱ 1,875.00 ₱ 6,750.00
₱ 95.00 ₱ 570.00
#N/A #N/A
#N/A #N/A
MATERIAL COST = #N/A
35% #N/A
Bottom
Bar
(pcs)
8
12mm Ø
16mm Ø
20mm Ø
25mm Ø
28mm Ø
32mm Ø
###
###
Tie Wire
Sand
Gravel
WALL FOOTING ESTIM
WALL FOOTING DETAILS
Concrete Mix Class
Concrete B
Reinforcement
WALL
Quantity
FOOTING Length Width Thickness Concrete
Depth (m)
(m) (m) (m) Cover (mm) Bar Size
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 45 bags
Sand 2.8125 cu.m
Gravel 5.625 cu.m
Tie Wire 2.50 kg
WF-1 12mm Ø X 6m 22.00 pcs
WF-1 10mm Ø X 6m 10.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
EXCAVATION COST =
BACKFILL COST =
TOTAL COST =
NG ESTIMATE
NG DETAILS
Economical Main
Steel Bars Temperature Bars
Bar Length Bars
Length (spacing) (mm)
(m) (pcs)
MATERIALS
COLUMN ITEM QUANTITY UNIT
Cement 31 bags
Sand 1.28 cu.m
Gravel 2.56 cu.m
Tie Wire 7.00 kg
2x3x8 Good Lumber 46.00 pcs
2x2x8 Good Lumber 46.00 pcs
3/4" Phenolic Board 9.00 pcs
Common Nail 2" 6.00 kg
Common Nail 3" 6.00 kg
C-1 16mm Ø X 6m 24.00 pcs
C-1 10mm Ø X 12m 15.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
TOTAL COST =
N ESTIMATE
OLUMN DETAILS
MAIN
Economical Top Economical
Steel Bars Bottom Cutting TIES
Bar Length Bar Bar Size Bar
Length Bar (pcs) Length SPACING
(m) (pcs) Length (m)
(mm)
MAIN RE
BEAM Quantity
FTB-1
FTB-2
B-1 1.00 0.30 0.90 8.40 40 0.2 16mm Ø
B-2
B-3
B-4
B-5
RB-1
RB-2
RB-3
MATERIALS
COLUMN ITEM QUANTITY UNIT
Cement 28 bags
Sand 1.134 cu.m
Gravel 2.268 cu.m
Tie Wire 3.50 kg
2x3x8 Good Lumber 54.00 pcs
2x2x8 Good Lumber 54.00 pcs
3/4" Phenolic Board 7.00 pcs
Common Nail 2" 5.00 kg
Common Nail 3" 5.00 kg
B-1 16mm Ø X 6m 5.00 pcs
B-1 10mm Ø X 12m 10.00 pcs
SHORING JACK
Area = 2.52 sq.m
Required Qty. = 5.00 pcs
TOTAL COST =
ATE BEAM ESTIMATE
BEAM DETAILS
MAIN
Economical Economical
Steel Bars At At Cutting TIES
Bar Length Bar Size Bar
Length Support Midspan Length SPACING
(m) Length (m)
(mm)
- -
- -
6.00 6.00 4 4 10mm Ø 12 2.34 200
- -
- -
- -
- -
- -
- -
- -
IALS
PRICE TOTAL COST
₱ 220.00 ₱ 6,160.00
₱ 875.00 ₱ 992.25
₱ 1,875.00 ₱ 4,252.50
₱ 95.00 ₱ 332.50
₱ 275.00 ₱ 14,850.00
₱ 210.00 ₱ 11,340.00
₱ 1,200.00 ₱ 8,400.00
₱ 90.00 ₱ 450.00
₱ 90.00 ₱ 450.00
₱ 419.47 ₱ 2,097.36
₱ 328.84 ₱ 3,288.38
JACK
₱ 300.00 per pc. Rental
rate
-
-
-
-
-
-
-
-
-
-
###
###
Tie Wire
###
###
###
###
###
SLAB EST
SLAB DET
Concrete Mix Class
Concrete AA
R
SLAB Quantity
Length Width Thickness Concrete Cover Ground or
(m) (m) (m) (mm) Suspended Bar Size
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement 50 bags
Sand 2.072925 cu.m
Gravel 4.14585 cu.m
Tie Wire 6.00 kg
3/4" Phenolic Board 12.00 pcs
2x2x12 Good Lumbe 51.00 pcs
Common Nail 3" 4.00 kg
Common Nail 2" 2.00 kg
S-1 10mm Ø X 10.5m 22.00 pcs
S-1 10mm Ø X 10.5m 13.00 pcs
S-2 10mm Ø X 10.5m 22.00 pcs
S-2 10mm Ø X 10.5m 13.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
SHORING JACK
Area = 33.17 sq.m
Required Qty. = 56.00 pcs
TOTAL COST =
AB ESTIMATE
SLAB DETAILS
Bottom
Economical Top Bar Economical
Bar Cutting
Bar Length Cutting Length (spacing) Bar Size Bar
(spacing) Length
(m) (mm) Length (m)
(mm)
10.5 3.42 200 200 10mm Ø 10.5 2.58
10.5 3.42 200 200 10mm Ø 10.5 2.58
- -
- -
- -
- -
- -
- -
- -
- -
RIALS
PRICE TOTAL COST
₱ 220.00 ₱ 11,000.00
₱ 875.00 ₱ 1,813.81
₱ 1,875.00 ₱ 7,773.47
₱ 95.00 ₱ 570.00
₱ 1,200.00 ₱ 14,400.00
₱ 320.00 ₱ 16,320.00
₱ 90.00 ₱ 360.00
₱ 90.00 ₱ 180.00
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
MATERIAL COST = #N/A
35% #N/A
G JACK
₱ 300.00 per pc. Rental
rate
Bottom
Top Bar
Bar
(spacing)
(spacing)
(mm)
(mm)
200 200
200 200
###
20mm Ø
25mm Ø
28mm Ø
32mm Ø
###
###
Tie Wire
Sand
Gravel
WALL ESTIMATE
WALL DETAILS
Mortar Mix Class
Concrete B
Reinforcemen
Deductible
WALL Quantity Areas (ex.
Length Height Plaster Thickness
Thickness Doors &
(m) (m) Sides (1 or 2) Bar Size
Windows)
(sq.m)
MATERIALS
FOOTING ITEM QUANTITY UNIT
Cement Err:508 bags
Sand 2.90 cu.m
Tie Wire 1.00 kg
100mm CHB - pcs
150mm CHB 270.00 pcs
200mm CHB - pcs
W-1 12mm Ø X 9m 7.00 pcs
TOTAL MATERIAL COST =
LABOR COST (% of Materials) =
TOTAL COST =
TIMATE
TAILS
Vertical
Economical
Bars Horizontal Bars
Bar Length Steel Bars Length ###
Spacing Spacing (mm)
(m)
(mm)