Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROJECT LIST

Process
Locati Engineer Type- Growth
Sl. Dept. Project Title Discipline Queries from Piping Queries from Process Queries from Water & Utility Queries from Electrical Queries from I&C Queries from Civil & Structure (C&S)
on ing- (G)/ SDI(S))
involvement Lead from
CU,E&P
from TCE TCE
This is a brown field job which requires over head
lines to be routed through exisitng facilities like racks
across various areas. Our queries
1. It is mentioned that almost 7.5 KM portion of pipes are underground need to be laid on overground. Is it the length of all pipes OR length of
a) How many lines to be taken?
pipe route? Please clarify.
b) Diameter of these lines? 2. Furnish the route of pipe lines finalized in FEL1 along with number of pipe & dia of pipe.
c) Whether laser scan will be available for the whole 3. Are these pipes will be supported in new structure & foundation for over ground route? Please confirm.
route where the line is to be taken? 4. If the route is partly supported in new structure and partly supported on existing structure then please specify the percentage of support to
We feel without laser scan such a work is not be considered for new & existing structure?
possible. Secondly we feel since it means interfacing 5. Are the support system will be individual OR pipe gallery to be considered? Please soecify.
with various areas TSJ's various departments in COMMON FOR ALL PROJECTS:
Making the underground Water lines , to
1. Is detail Civil & Structural (C&S) engineering including complete analysis & design need to be carried out in this FEL-2 level? Please confirm.
Steel Overhead design , for ICW and DCW cooling charge of the respective areas need to be involved
1 TSJ LD#2 Sustenance Otherwise a preliminary analysis will be carried out AND/OR reference data will be used to estimate BOQ with (+/-) 25% variation. Please
making water lines , Fire water Old lines at RCPH of LD2 for discussing and taking concurrences.
feeding to Slab Casters , confirm.
d) Pipe length and route 2. If detail engineering for C&S need to be carried out in this stage then approved assignment need to be furnished to C&S team to carry out
the C&S engineering.
3. If DE need to be carried out then only single line Structural GA drawings without connection detail will be prepared in this stage. Preparation
of any fabrication drawings not considered in this FEL-2 stage. Please confirm.
4. If DE need to be carried out then only concrete out line diagram drawing will be prepared. Reinforcement detail will not be shown in this
stage. Please confirm.
5. Soil report will be shared by client. Please confirm.
6. All the existing "AS-BUILT" Civil & Structural drawings will be shared by client for the applicable area. Please confirm.
7. If only preliminary analysis is carried out then schematic drawings without any member sections will be prepared. Please confirm.
8. Overground survey data need to be shared by client. Otherwise 3D scanning is recomended. Please confirm.
Piping, C&S Piping 9. Underground mapping data need to be shared by client. Please confirm.
a) Which option i.e. option-1 or option - 2 is final. 1.We understand that the nos of pumps, their capacity, head
b) Pipe to be laid on above ground (from existing and type has been finalised by TSL and as indicated in the flow
structure or pedestal) or underground? scheme.
2.We understand that for installation of submersible pumps
inside existing CRM WWTP treated water tank is in the scope
of TCE.
1. We understand that CRM WWTP Treated Effluent
3.We presume that, the construction of Effluent Collection
Utilization in LD#2 Slag Quenching system shall be
Tank and adjacent Pump House will be RCC We understand that 415V Power
Operated, Control and Monitored by Stand alone PLC
4.We assume that there is no requirement for any Mechanical source from a existing switchboard
based Automation system. Please Confirm. 1.Is there any existing pit at existing CRM WWTP Treated water Tank to install new two number submersible pump OR new pit to be
Steel Handling arrangement/hoist in the CRM WWTP treated water spare feeder will be made available
3 TSJ LD#2 Improvement Utilization of CRM Effluent in LD2 Slag Quenching constructured for installation of new two nos. submersible pumps. Please clarify.
making tank. However, for the proposed effluent collection tank inside CRM WWTP plant. Study of
2. We understand that CRM WWTP Treated Effluent 2.Apart from the above, is there any civil & structural work need to be carried out at existing tank? If yes then please specify the same.
adjacent pump house hoisting facility is to be provided. existing Electrical system is not in our
Utilization in LD#2 Slag Quenching Automation system 3. Is this one DN 150 pipe will be supported in new structure & foundation at over ground? Please confirm.
scope of work. Please Confirm.
will be interfaced with CRM WWTP Automation System 4. If the route is partly supported in new structure and partly supported on existing structure then please specify the percentage of support to
Drawings requirement
for Data storage. Please Confirm.
be considered for new & existing structure?
I.Mechanical GA drawing for existing CRM WWTP treated 5. Please specify the material of construction (i.e RCC/STEEL) of new effluent Collection Tank.
water tank and Slag Quenching Water Tank showing minimum, 6. Is the new tank will be underground / overground tank? Please specify.
maximum & normal water level, Bottom level of the tank and 7. Is there any new pump house to be constructed? If yes then please specify the size along with MOC?
Water & top of tank COMMON FOR ALL PROJECTS:
Piping
Piping , C&S, Elect 1.PLEASE REFER ALL C&S QUERIES AS MENTIONED IN SL NO. 1 AND CLARIFY THE SAME.
a) Whether above ground and under ground survey
are required at this stage (FEL-2)? 1.Is there any PFD / P&ID available for this COG distribution
b) Whether stress analysis is required at this stage system for LCP?
(FEL-2)? 2.As per background information two (02 nos.) DN 900 lines
need to be considered, whereas in the Project scope there is a
mention of DN 700 COG line which may please be clarified by
client.
3.It is not clear from the scope whether insolation valves and
We understand that necessary operation, control and
U seal exist in the two (02) nos. DN 900 branch line which are
monitoring along with necessary instruments for DN700
tapped from the main header of DN 1500 (old & New). Please
Steel COG line from from the existing two DN 1500 COG (Old
4 TSJ LCP Safety Installation of New COG for Kiln 1 to 6 clarify.
making & New main) line from Coke Plant to Maerz kilns (MK) 1-
4.Existing layout / construction drawing of COG line with
6 of Lime Calcining Plant (LCP) will be required which will
support structure drawing may please be made available for 1. In scope it is specified that old COG line will be dismantled. Please clarify whether existing supporting structure to be dismantled or not.
be under scope of work. Please Confirm.
assessment of the quantum of the job. 2. From layout it is understood that new support structure along with new foundation will be constructed to support the new COG line between
5.Existing TOP conditions (Pressure, temperature & Flow) for point C &D. Please confirm.
Nitrogen services and its location. 3. Is the total route of new COG line limited to between point A to D? Please confirm.
6.As per Project scope clause no. 7 & 9 we presume that small 4. If the route between point A to point C is partly supported in new structure and partly supported on existing structure then please specify
pipe, fitting and valves are made for nitrogen purging. Please
the percentage of support to be considered for new & existing structure?
confirm.
5. Please share the health study report if any strengthening of existing structure is required.
COMMON FOR ALL PROJECTS:
Utility,C&S, INCUtility 1.PLEASE REFER ALL C&S QUERIES AS MENTIONED IN SL NO. 1 AND CLARIFY THE SAME.

You might also like