DATE: February 29, 2024

Attention: SANTECO CONSTRUCTION SUPPLIES AND SERVICES

Thru: Anthony C. Basa

Sales and Project Coordinator

Project: MENGAL WOMEN CENTER (OLYMPIC POOL)

Location: Echague, Isabela

Subject: Cost proposal (Labor only)

DESCRIPTION OF WORK QTY UNI LABOR AMOUNT


T

GENERAL REQUIRMENTS
MOBILIZATION/ 1 LOT 60,000
DEMOBILIZATION
SITE 1 LOT 100,000
SUPERVISION/MANAGEMEN
T
SUB TOTAL 160,000
(A)

SITE WORKS
TRIMMING/GRAVEL 1 LOT 50,000
BEDDING
SUB TOTAL 50,000
(B)

CIVIL/STRUCTURAL
REBARS 33,702.36 KGS 15.00 505,535,40
.
STEEL MATTING 260 M² 120 31,200
REINSFORCEMENT
WIRE MESH 200 LM 20 4,000
CONCRETING (RMC) 280 M² 700 196,000
FORM WORKS 540 M² 300 162,000
MASONRY
CHB WALL 334 M² 350 116,900
PLASTER 284 M² 250 71,000
WATER PROOFING
FAST SETTING CEMENT 130 LM 60 7,800
PLUG
CRYSTALLINE WATER 1,044 M² 150 156,600
PROOFING
POLYURENTHANE 1,044 M² 150 156,600
FLEXIBLE MEMBRANE
WATER BASED FLEXIBLE 1,044 M² 150 156,600
MEMBRANE
FIBER MESH 1,044 M² 15 15,660

SUB TOTAL 1,579,895.40


(C)

TILE WORKS
TILE INSTALLATION 1,099 M² 400 439,600
SUB TOTAL 439,600
(D)

GRAND TOTAL 2,229,495.40

PREPAIRED BY:

HERRIE P. UBAS JR.

0975-677-8864