Professional Documents
Culture Documents
GGME - CX-393 - MS - RA - PHT - 01 Rev.1
GGME - CX-393 - MS - RA - PHT - 01 Rev.1
GGME - CX-393 - MS - RA - PHT - 01 Rev.1
: CX-393
14/06/2023
GGME JOB No
Mott MacDonald:
Mr. Alex Alexander – Resident Engineer
1E
Mr. Anup Sera – Engineering Manager
Petrochem:
1E
Mr. Cherian George – Chief Project Manager
Mr. Bright Thomas – Project Manager
Purpose of Issue
State the purpose of issue
Example: IN = For Information, FR = For Review, TR = For Tender, CN = For Construction, AB = As-Built AP
IM = For Implementation, FC = For Comments, AP = For Approval, RC = For Records, EN = For Enquiry,
FP = For Purchase,
SC = Site Confirmation, FP = For Processing
Issued by Siddiqui
Comment Document – Piping
Client: Petrochem Terminals FZE
Project: Petrochemical Terminal at Plot B052F02
However, detailed procedure for Low Voltage Holiday Testing, its equipment is specified
in the document. Sections that are not required shall not be included in the Method
Statement
2. The document shall be project and equipment specific and shall be revised.
5. Section 8.2.c calculations shall be included to demonstrate that the voltage selected and
required are firm.
The above comments and/or approval in no way relieve the Contractor from his obligations under the
Contract to ensure conformance to the Specification. Any deviations from the Specification found
subsequent to approval shall be corrected by the Contactor to the satisfaction of the Engineer.
______________________ _______________________
DUB - FT071
https://mottmac.sharepoint.com/teams/pj-f7567/do/Develop/CONSTRUCTION PHASE/02. M&P - GGME/03. COMMENT SHEETS/08.
PIPING/CT-8118-R00-GGME-DT0560_MSRA Holiday Testing R0.docx
COMMENTS RESOLUTION SHEET FOR CONSULTANT COMMENTS
GGME MOTT MAC DONALD / PETROCHEM
METHOD STATEMENT
The document title for ITI-NDT-CSP-0117 Rev 0 states that it is for High
Voltage Holiday Testing. A Low voltage holiday detector system is used only in applications where coating
1 However, detailed procedure for Low Voltage Holiday Testing, its thickness is less than 0.508 mm ( 20 mils) microns . Coating thickness above 0.508
equipment is specified in the document. Sections that are not required mm high voltage holiday detector shall be used . Jetty line coating is more than
shall not be included in the Method Statement specified limit of 0.508 mm - Not required sections are removed from MS.
The document shall be project and equipment specific and shall be Complied and Incorporated in the Method Statement.
2 revised.
There is no reference to the project, project documentation, drawings,
3 specifications etc and/or the Client, the Engineer, the Contractor, TPI etc in Complied & the mentioned details are incorporated in the Method statement.
the submitted document.
The basis for selection of High Voltage shall be established High voltage is selected on the basis that all the jetty pipes to be tested is having a
4 coating thickness above 0.508 mm
Voltage selection is dependent on the pipe coating thickness and the required
Section 8.2.c Calculations shall be included to demonstrate that the voltage is generated and displayed automatically once the coating thickness is
5 voltage selected and required are firm. entered in the holiday detector.
Prior to start the holiday test, the holiday test technician will demonstrate the same
to the client/consultant/TPI.
Reference to clearance by Contractor’s QA/QC, TPI and their Complied and Incorporated in the Method Statement.
6
involvement shall be provided.
Page 1 of 2
COMMENTS RESOLUTION SHEET FOR CONSULTANT COMMENTS
GGME MOTT MAC DONALD / PETROCHEM
For information
1 Nil
2 Nil
Page 2 of 2
GHANTOOT GENERAL MECHANICAL ENGINEERING L.L.C.
P.O. Box No. 5718, Dubai, U.A.E.
Tel. No. (04) 3472740
Fax. No. (04) 3473609
Doc. Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
METHOD STATEMENT Date: 13/06/2023
HOLIDAY TESTING OF JETTY PIPING Page 1 of 9
METHOD STATEMENT
Doc Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
Date: 13/06/2023
HOLIDAY TESTING OF
JETTY PIPING
1.0 SCOPE:
This document describes the procedure for detecting holidays in jetty pipeline coating in
accordance with Client’s Technical Specification (References given below in this
document) at Petrochem Petrochemical Terminal at Plot B052F02, Dubai, United Arab Emirates.
For holiday testing, High Voltage Holiday Detector is used to detect holidays such as pinholes and
voids in pipeline coatings; but because of the higher applied voltages, it can also be used to detect
thin spots in the coating. This method can be used on any thickness of pipeline coating and utilizes
applied voltages between 900 and 20 000 Vdc.
The purpose of this procedure is to ensure that the holiday testing is conducted in a safe manner
based on sound engineering practice and satisfies the requirements of relevant Technical
Specifications, International Codes and Site Requirements.
GGME
Cont. Cont.
Name Designation Name Designation
No. No.
Mr. Anandaram Project Manager
Mr. Gopal Pitta Const. Manager
Mr. Shamim HSE Advisor
Mr. Sundar QA/QC Engineer
Mr. Ramakrishnan Piping Engineer
Mr. Aravind Site Engineer
I. For jetty pipe holiday testing inside the site plot limit – Consultant/Client approved
Site Permit to Work System shall be followed.
II. For jetty pipe holiday testing outside the site plot limit (i.e. jetty area outside tanker
berth) – Occupation of Work Site permit shall be obtained from DP World. Civil
contractor shall be responsible for obtaining the permit upon request by M & P
contractor.
III. For working inside Tanker Berth Area – Tanker Berth Safe Work Permit shall be
obtained from Trakhees. Trakhees certified Permit Issuer, performing authority and
Gas Inspector shall be responsible for issuing the permit.
GHANTOOT GENERAL MECHANICAL ENGINEERING L.L.C.
P.O. Box No. 5718, Dubai, U.A.E.
Tel. No. (04) 3472740
Fax. No. (04) 3473609
Doc. Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
METHOD STATEMENT Date: 13/06/2023
HOLIDAY TESTING OF JETTY PIPING Page 4 of 9
a. Dia.8” SS316L Pipelines (Piping Class DX1A) between New Berth and
Hose Exchange 1 for generic liquid chemicals including Monomers. 3 Nos.
b. Dia.8” SS316L pipeline (Piping Class DC1A) between New Berth and Hose
Exchange 1 for Acetic Acid. 1 No.
c. Dia.8” SS316L Pipelines (Piping Class DX1A) between PME Existing Berth and
Hose Exchange 1 for generic liquid chemicals including Monomers. 2 Nos.
d. Dia.3” SS316L (Piping Class DC1A) to transfer Nitrogen from the
Terminal to the New Berth for pigging operations 1 No.
e. Dia.3” SS316L (Piping Class DC1A) for vapor balancing between the
Terminal and New berth 1 No.
Steel pipes are coated with paint and wrapped with coating sleeve with the thickness up to 5000
microns. High voltage holiday detectors are used to inspect these coatings for pin holes,
scratches or other coating faults. The handle of the instrument generates a high DC voltage
which is applied to the surface of coating via a probe. An earth signal return cable is connected
between the instrument and the substrate. When the probe is passed over a coating flaw, the
electrical circuit is completed and current flows from the probe to the substrate.
As a result, the instrument gives audible, visual alarms and a spark may be produced at the
flaw, Spray equipment check.
The electric connection between Equipment and test specimen shall be as described in the
image below.
The coating under test can be electrically non-conductive or partially conductive (such as
coating which contain metallic or carbon particles). The coating must be at least 200 microns
(0.008”) thick, and preferably over 5000 microns thick.
The underlying substrate must be an electrically conductive material such as metal or concrete.
GHANTOOT GENERAL MECHANICAL ENGINEERING L.L.C.
P.O. Box No. 5718, Dubai, U.A.E.
Tel. No. (04) 3472740
Fax. No. (04) 3473609
Doc. Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
METHOD STATEMENT Date: 13/06/2023
HOLIDAY TESTING OF JETTY PIPING Page 6 of 9
Prior to making the inspection, ensure that the coated surface is dry. Dryness is critical
in a high voltage test. Take care to keep the electrode at least 12.7 mm (/2 in.) from any
bare sheared or slit edge.
11.0 SEQUENCE OF OPERATION
Connect the high voltage handle to the instrument.
Connect the clamp of the earth signal return cable to an exposed section of substrate and
plug the other end of the cable into the instrument.
Select the probe/electrode best suited for the work and attach it to the high voltage handle.
Check the cable connections, set test voltage and sensitivity etc. Voltage setting can be
done by manual or automatic. Automatic setting of voltage depends on the selection of test
standards and coating thickness.
Perform the verification before conducting the test.
Select the test voltage in kV according to the standards.
Holding the high voltage handle firmly, ensure that finger grasp and squeeze the black
rubberized grip on the underside of the handle.
With the probe in free air, press and release the button on the handle to switch on the high
voltage. The red light on the handle will illuminate and the instrument will emit a regular
clicking, indicating that the probe is at high voltage.
Place the probe on the test surface.
Keeping the probe in contact with the surface, move it over the work area at a speed of
approximately one meter in every four seconds, 0.25 m/s.
Any flaws in the coating will be indicated by one or more of the following;
A spark is seen between the probe and surface.
The blue light on the high voltage handle flashes.
The alarm sounds.
The alarm icon is shown on the display.
The display black light flashes.
If need to test in more than one location, always switch off the instrument before
disconnecting any cables, re attaching the cables in new test locations and before
recommencing testing repeat the steps.
12.0 PERMIT TO WORK SYSTEM: -
a. Proper “Permit to Work” system established by client / consultant shall be strictly followed.
b. Permits for Cold work/testing&commissioning shall be taken separately from the respective
permit authority of Client / Consultant whichever is applicable.
c. Permits from respective authority (DP World, Trakhees etc.) shall be obtained for working
in jetty/tanker berth area
d. Permit shall be taken Weekly/ every day before start the work and close upon the
completion and signed off by the respective authorities.
13.0 HSE REQUIREMENTS FOR HOLIDAY TESTING: -
HSE requirements for holiday testing are as follows;
1. Trench should be inspected prior to start of holiday testing or after any adverse event
such as rain or sandstorm.
2. Do not work in trenches for holiday testing during adverse weather conditions. Evacuate
to safe area.
GHANTOOT GENERAL MECHANICAL ENGINEERING L.L.C.
P.O. Box No. 5718, Dubai, U.A.E.
Tel. No. (04) 3472740
Fax. No. (04) 3473609
Doc. Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
METHOD STATEMENT Date: 13/06/2023
HOLIDAY TESTING OF JETTY PIPING Page 8 of 9
Test Report: GGME QA/QC engineer shall prepare the test report and this will be
submitted to the TPI & Consultant Engineer for acceptance and signature. Test reports
shall include;
a) Reference P&ID, Piping GAs
b) Pipeline number & MOC
c) Pipeline size
d) Details of the wrapping (brand, technical information, thickness) provided including
details of primer coat.
Also, report shall be prepared for individual pipelines.
(Holiday Testing Report Format is attached in Annexure – 1)
15.0 DOCUMENTATION: -
GHANTOOT GENERAL MECHANICAL ENGINEERING L.L.C.
P.O. Box No. 5718, Dubai, U.A.E.
Tel. No. (04) 3472740
Fax. No. (04) 3473609
Doc. Ref: GGME/CX-393/MSRA/PHT/01- Rev. 0
METHOD STATEMENT Date: 13/06/2023
HOLIDAY TESTING OF JETTY PIPING Page 9 of 9
The full documentation/QC Dossier pertaining to the jetty piping holiday test shall be
submitted to consultant as per provisions of the contract.
ANNEXURE-1
CLIENT: CONSULTANT:
PROJECT PETROCHEMICAL TERMINAL AT PLOT B052F02 IN JAFZA NORTH,
TITLE: DUBAI, UAE
RISK MATRIX
SEVERITY LIKELIHOOD
COMPANY EXTREMELY
PEOPLE ASSET DAMAGE ENVIRONMENT VERY UNLIKELY UNLIKELY PROBABLE REGULAR
REPUTATION UNLIKELY
1 2 3 4 5
Fatalities GLOBAL
INTERNATIONAL/
(or multiple severe Extensive (media interest,
MASSIVE IMPACT
5 5 10 15 20 25
permanent disablement) significant recovery work)
Major injury NATIONAL
NATIONAL/ MAJOR
(or severe permanent Major (on site impact, regional
IMPACT
4 4 8 12 16 20
disablement) media interest)
Disability
SERIOUS
(Electrical Shock, CONSIDERABLE
Broken Bone, Third
Localized (considerable recovery
IMPACT
3 3 6 9 12 15
works)
Degree Burn)
L.T.I. LIMITED
(Bruises, Stitches)
Minor
(small recovery work)
MINOR IMPACT 2 2 4 6 8 10
MINOR VERY SLIGHT
First aid Slight
(negligible recovery work) IMPACT 1 1 2 3 4 5
3. Use of all steel Unstable ground. Fall of 3 3 9 Conduct Tool box talk prior start of 2 2 4 All activities Low Permit
tubular A-frame Damaged tubular A- materials work. shall be issuer,
with Chain block for Load failure strictly Permit
frame. Position the A-frame on a stable and monitored by
lifting and No TPI certification. Physical levelled ground. Ensure its stability reviewer,
site
positioning of jetty injuries prior lifting the load. Performing
Lack of inspection. supervisors/E
pipe for holiday
Unattended load in Trench All steel A-frame and lifting gears ngineers. authority.
testing. collapse shall be certified by Trakhees Holiday test
lifted position.
Property approved TPI agency. Technician
Overloading.
damage. Daily lifting gear inspection to be
Corroded or defective done by lifting supervisor and
chain block. Lifting gear
verified by HSE.
Chain vibration or jerk damage. Never leave the load unattended in
during lifting. lifted position.
Side pulling. Do not stand or work under the lifted
Pulling the chain too load unless it is properly secured.
hard. Only load the A-frame and lifting
Lack of supervision. gears within its rated capacity.
Lack of PPE. Use the chain block only for vertical
lifting.
No side pulling of Chain block shall
be allowed.
While lifting or lowering load using
chain block, keep your feet clear.
Load shall be lifted gradually only
using chain block.
Only competent workers shall do the
lifting activity.
6. Heat stress Lack of training Sweating Heat stress training to be given to all Air Permit issuer,
High humidity Dehydration 4 4 16 workforce. 2 3 6 conditioners Medium Permit
Working directly under Dizziness Provision of cold drinking water in the reviewer,
sunlight for long time. Provide rest shelters and frequent workers rest Performing
Fainting
area shall be
People working/ Tiredness
breaks for workers to rest authority.
No person shall work/ walk under maintained
walking under direct
Penalty from properly in
Holiday test
sunlight during mid-day direct sunlight during the summer Technician
Trakhees advance to
break. Mid-day break
avoid
Dust suppression to be done
frequently.
breakdown.