DISCUSSION REGARDING OPTIONS FOR MITIGATION OF OVERLOADING OF

220KV SARFARAZ NAGAR GRID STATION


Sr. # Option/ Situation Responsibility Action
NPCC (SO) to confirm the requirement at 220kV Sarfaraz
Nagar G/S keeping in view evolving situations below:

Situation 1: 3rd 220/132kV 160 MVA Transformer added


1. General NPCC in 220kV Okara G/S.
Situation2: LESCO is diverting load to 220kV WAPDA
Town G/S (about 50 to 100 MW to be diverted) by
constructing Chanar Bagh G/S.

NPCC  Confirmation of loading of 220 kV Transmission Lines


 Confirmation of availability of material
 Confirmation of scope of work (Dismantling of
Design existing buildings, capacity of trenches, space in CHB,
etc.)
Addition of 160  Impedance matching for parallel operation
2.
MVA Auto T/F  Identification of Grid Stations from where material
GSO
can be sourced if not available in inventory.
 Confirmation of Timelines for implementation of
PD/ GSC
option
 Estimation of Cost for Civil Works (including tentative
Civil
shifting of Metering Room)
 Confirmation of loading of 220 kV Transmission Lines
NPCC  Confirmation of loading of Grid Stations from where
transformer will be shifted.
Design  Impedance matching for parallel operation
Augmentation of
 Identification of Grid Stations and transformers that
one 160 MVA T/F GSO
3. will be likely underloaded in upcoming summer.
with 250 MVA
 Checking and confirmation of suitability of existing
T/F (installed)
foundations for 250 MVA T/F.
Civil
 Estimation of Cost for foundation strengthening, if
required
 Confirmation of Timelines for implementation of
PD/ GSC
option
 Confirmation of loading of 220 kV Transmission Lines
NPCC
 Confirmation of loading of QABP Grid Station.
 Confirmation of timelines of shipment/ arrival of 250
MP&M
Augmentation of MVA transformers.
two 160 MVA  Confirmation of Timelines for implementation of
4. PD/ GSC
T/Fs with 250 option
MVA T/Fs (QABP)  Checking and confirmation of suitability of existing
foundations for 250 MVA T/F.
Civil
 Estimation of Cost for foundation strengthening, if
required