Download as pdf or txt
Download as pdf or txt
You are on page 1of 55

MAHARASHTRA INDUSTRIAL DEVELOPMENT CORPORATION

Item Specification

Work Name: M & R to wss in MIA.. Replacement of old existing AC pressure water supply
pipeline with D.I. pipeline at D-zone in MIA.

Sub Estimate:M & R to wss in MIA.. Replacement of old existing AC pressure water supply
pipeline with D.I. pipeline at D-zone in MIA.
1 Excavation for foundation in earth, soil of all types, sand, gravel and soft murum,
including removing the excavated material up to a distance of 50 m. beyond the
building area and stacking and spreading as directed, dewatering, preparing the bed
for the foundation and necessary back filling, ramming, watering including shoring and
strutting etc. complete. (Lift upto 1.5 m.) By Mechanical Means
Specification:
Specification-

1.1 General - The excavation refers to excavation for foundation, wet or dry, in earth, soils of all
types, sand, gravel, soft murum and similar other soft or loose material and shall comply with
specification subject to the following:
1.2 Disposal of excavated materials - Unsuitable materials obtained from clearing the site and
excavation shall be disposed off with all lead beyond the building area as directed by the Engineer.
Useful materials obtained from clearing site and excavation, shall be stacked with all lead beyond
the building area as directed by the Engineer. Materials suitable for back-filling or other use shall
be stacked at a convenient place with all beyond the structure for rouse. Surplus materials shall be
used for leveling the ground around the structure within a lead of 50metres(about 164') if directed
by the Engineer.
1.3 Item to include
(1) Clearing site.
(2) Setting out works, profiles, etc., according to sanctioned plan or as ordered and setting up
Bench marks and other reference mark.
(3) Providing and subsequently removing shoring and strutting or cutting slopes except when,
separately provided for in the tender.
(4) Bailing and pumping out water when separate provision does not exist for it in the tender.
(5) Excavation and removal of all materials of whatever nature wet or dry and necessary for the
construction of foundation including materials like explosives, removal of blows and slipsand use
of tools, plant and equipment necessary for satisfactory completion of the item and preparing bed
for foundation.
(6) Sorting out of useful excavated materials, conveying them up to the specified lead clear
beyond the structure and stacking them neatly for backfilling or reuse and wasting useless

Page 100 Tender ID - 31688


materials as directed by the Engineer.
(7) Backfilling the trenches alongside masonry or concrete with approved material up to the
natural ground level.
(8) Necessary protection including labour, materials and equipment to ensure safety and
protection against risk or accident.
(9) Supply of facilities for inspection and measurements at any time by the concerned Government
officials.
(10) Compensation for injury to life and damage to property if any caused by the contractor’s
operations concerned with this item.
(11) Small drill holes to explore the nature of substratum if necessary. The lead for stacking or
disposal of materials obtained from excavation or clearing site shall be limited to 50 meters beyond
the building on all sides.
Mode of Measurement and payment - The quantity to be measured in Cubic meter and paid
accordingly.

2 Excavation for foundation in Soft rock and old cement or lime masonry foundations
including removing the excavated material upto a distance of 50 metres beyond the
building area and stacking as directed, including dewatering, preparing the bed for the
foundation and necessary back filling with available earth /murum, ramming, watering
including shoring and strutting etc. complete (lift upto 1.5m) By Mechanical Means
Specification:
Specification:
General - Specification:
General – This shall include all material which is rock or hard conglomerate ,all decomposed and
weathered rock, highly fissured rock, old masonry and also soft rock , Boulders bigger than ½
cubic metre and other varieties of rock which would normally be removed with pick, crow bars,
wedges and hammer with some difficulty.
Excavation- Foundation excavation shall include removal of all materials ofwhatever nature and
whether wet or dry, necessary for the construction of the foundation and substructure exactly in
accordance with the lines, levels, grades and curves shown on the plans or as directed by the
Engineer. It shall be taken to the exact width of the lowest step of the footing and the sides shall be
left plumb where the nature of soil admits it. Unless there is a specific extra provision in the
contract for shoring or for cutting side slopes, contractor shall at his own cost do the necessary
shoring or cutting of slopes to a safe angle or both as approved by the Engineer when the strata
need such treatment. The contractor shall notify the Engineer before starting excavation to enable
him to take cross sectional levels for purposes of measurements before the ground is disturbed.
Disposal of excavated materials- No materials excavated from the foundation trenches of
whatever kind they may be, are to placed even temporarily nearer than 1.5 m. or greater distance
prescribed by the Engineer from the outer edge of the excavation. All materials excavated will
remain the property of Government. Rate for excavation, includes sorting of useful materials and
stacking them separately as directed within the specified lead. Materials suitable and useful for

Page 101 Tender ID - 31688


backfilling or other use shall be stacked on convenient places but not in such a way as to obstruct
free movement of men, animals and vehicles or encroach on the area required for constructional
purposes. It shall be used to the extent required to completely backfill the structure to original
ground level or the elevation shown on the plans or as directed by the Engineer. For backfilling, the
materials shall be placed in 15 cm. to 20 cm. layers, moistened and well compacted. Materials not
useful in any way shall be wasted as directed by the Engineer. If useful excavated rubble is
required by the contractor for use in other items, it shall be paid for at the rate fixed in the tender
and if not so provided, at the rate in the Divisional schedule current at the time of tendering or at
mutually agreed rate if there is no rate in the Divisional schedule. The site shall be left clean of all
debris on completion.

The rate for the item of excavation will include :-


(1) Clearing site.
(2) Setting out works, profiles, etc., according to sanctioned plan or as ordered and setting
up Bench marks and other reference mark.
(3) Providing and subsequently removing shoring and strutting or cutting slopes except
when, separately provided for in the tender.
(4) Bailing and pumping out water when separate provision does not exist for it in the tender.
(5) Excavation and removal of all materials of whatever nature wet or dry and necessary for
the construction of foundation including materials like explosives, removal of blows and slipsand
use of tools, plant and equipment necessary for satisfactory completion of the item and preparing
bed for foundation.
(6) Sorting out of useful excavated materials, conveying them up to the specified lead clear beyond
the structure and stacking them neatly for backfilling or reuse and wasting useless materials as
directed by the Engineer.
(7) Backfilling the trenches alongside masonry or concrete with approved material up to the natural
ground level.
(8) Necessary protection including labour, materials and equipment to ensure safety and protection
against risk or accident.
(9) Supply of facilities for inspection and measurements at any time by the concerned Government
officials.
(10) Compensation for injury to life and damage to property if any caused by the
contractor’s operations concerned with this item.Small drill holes to explore the nature of
substratum if necessary. The lead for stacking or disposal of materials obtained from excavation or
clearing site shall be limited to 50 meters beyond the building on all sides.
Mode of measurement and payment –
The quantity to be measured in Cubic meter and paid accordingly.

3 Excavation for foundation in Hard rock by chiselling, wedging, line drilling, etc.
including trimming and levelling the bed, removing the excavated material upto a distance

Page 102 Tender ID - 31688


of 50 metres beyond the building area stacking as directed, dewatering and back
filling with available earth/ murum watering, ramming etc. complete. (Lift upto 1.5 m). By
Mechanical Means
Specification:
Specification:
General - When local conditions preclude the use of blasting, excavation shall be done by
chiseling, wedging or line drilling as specified or ordered by the Engineer. The excavation refers to
excavation generally for foundation, wet or dry, in hard rock by chiseling, wedging or line drilling.
Excavation- excavation shall be done by chiseling, wedging or line drilling as specified or ordered
by the Engineer, During excavation in rock the lowest 15 cm. of the strata shall be blasted with
light charges so as not to shatter or weaken the underlying rock on which the foundation will be
actually laid. If excavation in rock is done to larger widths and lengths than those shown on the
drawings or as directed by the Engineer, no payment shall be made for such over break. If
excavation is done to depths greater than those shown on the drawings or directed by the
Engineer, excess depth shall be made up with foundation grade concrete or masonry as directed
by the Engineer at the contractor's cost.
Disposal of excavated materials- No materials excavated from the foundation trenches of
whatever kind they may be, are to placed even temporarily nearer than 1.5m. or greater distance
prescribed by the Engineer from the outer edge of the excavation. All materials excavated will
remain the property of Government. Rate for excavation, includes sorting of useful materials and
stacking them separately as directed within the specified lead. Materials suitable and useful for
backfilling or other use shall be stacked on convenient places but not in such a way as to obstruct
free movement of men, animals and vehicles or encroach on the area required for constructional
purposes. It shall be used to the extent required to completely backfill the structure to original
ground level or the elevation shown on the plans or as directed by the Engineer. For backfilling,
the materials shall be placed in 15 cm. to 20 cm. layers, moistened and well compacted. Materials
not useful in any way shall be wasted as directed by the Engineer. If useful excavated rubble is
required by the contractor for use in other items, it shall be paid for at the rate fixed in the tender
and if not so provided, at the rate in the Divisional schedule current at the time of tendering or at
mutually agreed rate if there is no rate in the Divisional schedule. The site shall be left clean of all
debris on completion. Unsuitable materials obtained from clearing site and excavation shall be
disposed off within a lead of 50 meters as directed by the Engineer. Useful materials obtained
from clearing site and excavation shall be stacked within a lead of 50 meters beyond the building
area as directed by the Engineer. Materials suitable for back-filling shall be stacked at convenient
places within a lead of 50 meters from the structure for reuse. Useful stones from rock excavation
shall be stacked neatly within a lead of 50 meters and will be allowed to be used by the contractor
on payment at rates laid down in the contract or if not so laid down, at scheduled rates of the
Division or at a mutually agreed rates if there are no such rates in the schedule..
The rate for the item of excavation will include :-
(1) Clearing site.

Page 103 Tender ID - 31688


(2) Setting out works, profiles, etc., according to sanctioned plan or as ordered and setting up
Bench marks and other reference mark.
(3) Providing and subsequently removing shoring and strutting or cutting slopes except when,
separately provided for in the tender.
(4) Bailing and pumping out water when separate provision does not exist for it in the tender.
(5) Excavation and removal of all materials of whatever nature wet or dry and necessary for the
construction of foundation including materials like explosives, removal of blows and slipsand use
of tools, plant and equipment necessary for satisfactory completion of the item and preparing bed
for foundation.
(6) Sorting out of useful excavated materials, conveying them up to the specified lead clear
beyond the structure and stacking them neatly for backfilling or reuse and wasting useless
materials as directed by the Engineer.
(7) Backfilling the trenches alongside masonry or concrete with approved material up to the
natural ground level.
(8) Necessary protection including labour, materials and equipment to ensure safety and
protection against risk or accident.
(9) Supply of facilities for inspection and measurements at any time by the concerned Government
officials.
(10) Compensation for injury to life and damage to property if any caused by the contractor’s
operations concerned with this item.Small drill holes to explore the nature of substratum if
necessary. The lead for stacking or disposal of materials obtained from excavation or clearing site
shall be limited to 50 meters beyond the building on all sides.
Mode of measurement and payment -The quantity to be measured in Cubic meter and paid
accordingly.

4 DI PIPES
4.1 Providing D.I. pipes (push on joints pressure pipes of D. I. of following class
and diameters confirming to the I. S. specification inclusive cost of jointing materials
(Rubber gasket of EPDM Quality ) excluding GST levied by GOI & GOM in all respect
including Third party inspection charges of TPI Agency approved by MJP
including Transit insurance, Railway Freight, Unloading from railway wagon,
Loading into Truck, Transportation to departmental store, unloading, stacking etc.
completed as directed by Engineer in charges (IS 1536/2001 for pipes and IS 158/1969 and
IS 12820/1989 or latest edi- tion/revision with amendments for Rubber Gaskets.
Note: For DI pipe supply from MJP 18% GST would be applicable. Same should be
considered for estimation purpose.
4.1.1 ( IS:8329-2000 Latest Version) D.I. K-9
4.1.1.1 200mm
Specification:

Specification:

Page 104 Tender ID - 31688


The tender item includes supply of DI pipes of required class k-9 & dia as specified in BOQ & as
per the requirement for the site including carting of the pipes to site of work as specified with due
supply of required rubber gaskets as per IS -1536/2001,IS158/1969&IS- 12820/1989 of best
quality of approved make suitable for minimum work test pressure of 40 kg/cm^2 as required for
distribution pipeline network. The agency should clearly mention this specific requirement in his
supply order to the manufacturer of DI pipes.The DI pipes shall be suitable for flexible push on joint
suitably chamfered or rounded off for smooth entry of pipes in the socket fitted with rubber gasket.
Pipes should be lowered into the trench with tackle suitable for the weight of pipes. For smaller
sizes, up to 200 mm nominal bore, the pipe may be lowered by the use of ropes but for heavier
pipes suitable mechanical equipment have to be used. All construction debris should be cleared
from the inside of the pipe either before or just after a joint is made. This is done by passing a pull-
through in the pipe, or by hand, depending on the size of the pipe. All persons should vacate any
section of trench into which the pipe is being lowered On gradients of 1:15 or steeper, precautions
should be taken to ensure that the spigot of the pipe being laid does not move into or out of the
socket of the laid pipe during the jointing operations. As soon as the joint assembly has been
completed, the pipe should be held firmly in position while the trench is back filled over the barrel
of the pipe.
Rubber gasket for push-on, mechanical & flanged joint shall compatible with water to be conveyed
for materials pressure and temperature. while conveying the potable water Gasket should not
deteriorate the quality of water or should not impart any test or odour.

The DI pipes to be supplied of various diameters &class shall be confirming to specifications as per
I.S. IS -1536/2001,IS158/1969 & IS-12820/1989.
Raw Material –
Raw material used to manufacture the DI pipes shall be as per relevant IS.
Pressure Rating &Dimensions.
The pressure rating of DI pipes and specials shall be confirming to I.S. IS -1536/2001,IS158/1969
& IS-12820/1989 Table-1and 2 respectively. Each pipe shall be of uniform thickness throughout its
length. The dimension to tolerances shall be as per specified I.S. standards.

Colour of pipes-
The Colour of the DI pipe shall be as specified in IS code is black Performance requirements.
The pipe supplied should have passed the acceptance tests as per clause given in specified IS-
8329 standards. The manufacturer should provide the test certificates for the tests conducted, as
required in specified standards along with the supply of pipes & rubber gasket. Third party
inspection of pipes& Rubber gasket shall be carried out by MIDC approved agency. The supply of
pipe at site, then only it can be measured and recommended for further payment.
Marking-
As per the provisions of clause given in specified standards each straight length of the pipe shall
be clearly marked in inedible ink/paint the following information shall be marked. ISI stamping with
marking of IS 8329-1994 &IS-1536-2001.

Page 105 Tender ID - 31688


The manufacturer’s name and /trade mark. Lot number /Batch number
The Supply of pipes shall be in available lengths as per I.S. 8329-1994 &IS-1536-2001.Quantities
of pipes in tender shall be got verified Engineer in charge before placing supply order is necessary
& binding for the contractor.
Damages to supplied materials due to carelessness of the contractor during loading, unloading,
transport, lowering, laying, cutting to required size, jointing, testing, etc. shall be at contractor's
accounts and no payment on this quantity is admissible .final quantity payable under this item of
pipe supply shall be restricted to the total laid length &successfully tested for that diameter &class
of pipes.
Mode of Measurement :-
a) On supply of DI pipes - 70%
b) after laying and jointing - 20%
c) On satisfactory hydraulic testing - 10%

5 Hydraulic testing of C.I./D.I. pipe line to specified pressure including cost of


all materials and labour and water for testing for specified length including cutting,
placing end cap making arrangement for filling safe water using reciprocating type
pumps which should be able to provide specified test pressure gauges and other necessary
equipments, labour, operation charges, etc. required for testing. The rate under this
item shall also include cost of retesting, if necessary and reinstating to original
position using water supplied by the contractor.
5.1 Without Rubber Rings 200 mm.
Specification:
Specification:
General :
The arrangements made by the contractor for hydraulic testing of pipes shall be subject to the
approval by the Engineer. The contractor shall paint inside the serial number of pipe, the diameter
and the plate thickness and letters MIDC as well as the date of the test etc. as directed by the
Engineer. The pipes shall be inspected thoroughly before testing for any apparent defect in
welding and the contractor shall repair such defects Such pipes will be laid only on approval of the
Engineer-in-Charge. Necessary provisions for storage tank for water for testing water pumping
arrangements, if necessary and making available the required water shall be made by the
contractor Accurate pressure gauge of approved make shall be mounted on one end of the pipe to
indicate the pressure inside the pipe being tested. The pressure shall be applied gradually by
approved means and shall be maintained at least for 10 minutes or till inspection by EIL and
Engineer-in-Charge.

HYDRAULIC TESTING OF PIPE LINE –the working pressure shall be not less than 8 kg/cm2.
The drop in pressure shall not exceed 0.7 kg/cm2 within a period of 2 hours after the full test
pressure is built-up Under this pressure no leak or sweating shall be visible at the joints. The entire
cost of testing, retesting including cost of water taken together shall be paid under relevant item or
Bill of Quantities. The contractor shall make all the arrangements for all labour, pumps, pressure

Page 106 Tender ID - 31688


gauge equipment etc. The gauges should be got tested if insisted by the Engineer-in-Charge.

MODE OF PAYMENT AND UNIT OF MEASUREMENT –The payment shall be on KM basis

6 Providing and laying in situ Ready Mix Cement Concrete grade of trap / granite /
quartzite / gneiss metal for RCC works in foundation like raft, grillage, strip
foundation and footing of RCC column and steel stanchions including normal
dewatering, form work, compaction, finishing and curing including
transporting from mixing plant upto distance of 25 km., pouring the concrete at work
site for 1.5 M lift above G.L. and 5.0 M lift below G.L., etc. complete.
(Excluding reinforcement and structural steel)
6.1 For Foundation
6.1.1 In RCC M-150
Specification:
Specification:
General -
The item refers to the cement concrete required for R.C.C.footings of columns and steel
stanchions, grillage and raft and strip foundation in building construction. Providing and casting in
situ cement concrete 1:2:4 for R.C.C. columns as per detailed designs and drawings or as directed
including dewatering centering from- work, compacting, finishing the formed surface with cement
mortar 1:3 of sufficient minimum thickness to give a smooth and even surface or roughening if
special finish is to be provided and curing (excluding steel reinforcement).
Materials –
A) Workability : The following procedure is adopted for testing workability;
(i) There should be mentioned of specified workability as per grade requirement and site
requirement in the tender document
(ii) After making sure that the concrete has been uniformly mixed, take a sample from the first 0.5
cum. of concrete discharge and do a sump (of compacting factor) test on the sample. If the result
complies with the specified requirements, then the load should be accepted. If the results are
beyond limit, a further sample should be taken from the second 0.5 cum. of the discharge and if
this is satisfactory, the load should be accepted, if not the concrete load should be rejected, as the
same is not as per the specification range. Permissible variation in sump shall be 10 mm as per IS:
4926-1976.
B) Cement Content : Cement content for cubic meter of Ready Mix Concrete shall be mentioned
for each grade of concrete. The minimum cement content in the various grades of concrete shall
be as per design mix for a particular grade of concrete. The mix design shall confirm to one of the
methods specified in IS: 10262 or IRC 44. However preferable the mix design should be done as
per details given in IRC-44 of 1976- “Tentative guidelines cement concrete mix design”. The mix
design shall be approved from Govt. laboratory. The grade of cement shall be mentioned in the
contract documents. Cement shall have to be got tested at the Govt. laboratory or the laboratory
approved by the Engineer in Charge.

Page 107 Tender ID - 31688


C) Water : The contractor/ manufacturer shall have to make their own arrangements of potable
water for using in mixing of concrete and for curing purpose. It shall meet the requirement as per
IS: 456-2000.

D) Sand : Sand shall be of approved quality with fineness modulus between 2.4 to 3.5 as per
approved mix design. The sand will have to be screened to remove the oversize particles and
washed to reduce the silt contents below 5% by volume after one hour & to bring it within
the permissible range of fineness modulus. Blending of sand of fine and coarse quality may be
permitted at mix design stage to achieve the required fineness modulus, if it is found necessary to
give desired results. The fine aggregates will be tested as directed by Engineer in Charge.

E) Coarse Aggregate : Specified sizes of aggregates mentioned in design mix shall be used by
manufacturer of RMC plant. Client shall confirm the quality of sand used for concrete. If coarse
aggregate are found having white spots, the same shall be got tested from approved testing
laboratory to eliminate possibility of potential aggregate alkali reactivity before accepting or using
spotted aggregates. The manufacturer should make the necessary arrangements to stock the
aggregates separately so that they do not get mixed up with each other and/or with the foreign
materials and do not get segregated. The screening of the aggregates shall be done if found
necessary as directed by the Engineer in Charge.

F) Compressive Strength : Compressive Strength testing shall be carried out on site for 7 days,
14 days and 28 days strength. The water content shall be the minimum required to provide the
specified workability for full compaction of the concrete to the required compaction of the concrete
to the required density. The maximum water cement ratio shall be 0.40. At least three sets
consisting of 4 cubes from different loads for testing the compressive strength for each days work.
One cube from each set shall be tested for 7 days, 14 days and 28 days strength in presence
of Engineer in Charge in accordance with testing procedure. In case of failure of 28 days strength
at site laboratory, remaining three cubes shall be sent to approved laboratory immediately for
testing for 28 days strength.

G) Density : The density of the compacted concrete shall be such that the total air voids are not
more than 3%. Core density test shall be carried out in accordance with the relevant IS codes
H) Admixtures : The admixture shall be used with consent with the purchaser/ client. The
admixture used shall confirm to IS: 9103-1979 reaffirmed on 1990 or ASTMC-494 of 92. The
following admixtures to be used in concrete: (i) Accelerating Admixtures, (ii) Retarding
Admixtures, (iii) Water Reducing Admixtures, (iv) Air Entraining Admixtures,

Proportioning Mix - In ordinary concrete, although proportion of cement to fine and coarse
aggregate is specified by volume, the quantity of cement shall be determined by weight assuming
one bag of cement weighing 50 Kg. nett to be equivalent to 35 litres. Fine and coarse aggregates

Page 108 Tender ID - 31688


shall be measured by dry volumes in suitable wooden boxes. Due allowance shall be made for
bulking in the fine aggregate due to moisture if any, at the time of mixing.

Ingredients required for concrete containing 50 Kg. bag of cement for different proportions of mix
will be as under :-

Mix Cement Fine Coarse Water

aggregate aggregate

1 2 3 4 5

1:1:2 50Kg 50Kg 100Kg 23-27 litres

1:1.5:3 50Kg 75Kg 150Kg 23-30 litres

1:2:4 50Kg 100Kg 200Kg 27-32 litres

1:3:6 50Kg 150Kg 300kg 37.5-45 litres

1:4:8 50Kg 200Kg 400kg 47.5-57 litres

1:5:10 50Kg 250Kg 500Kg 56-68 litres

In case of slabs special mixes with smaller size aggregates shall be taken out and placed below
bottom steel to obtain dense cover. The ratio of the volumes of the fine and coarse aggregates
may be varied within limits of 1:1.5 to 1:2.5 as directed by the Engineer to suit the maximum size of
coarse aggregate, the grading, density, workability and strength without extra cost. But the sum of
the volumes of the fine and coarse aggregates so adjusted shall however be equal to the sum of

Page 109 Tender ID - 31688


the volumes of fine and coarse aggregates given above for a particular mix. The quantity of water
shall be just sufficient, but not more than sufficient, to produce a dense concrete of required
workability for its purpose. An accurate control shall be kept on the quantity of mixing water.
An allowance shall be made for surface moisture present in the aggregates when computing water
content as indicated in I.S. 456-1978. In the case of reinforced concrete work, the workability shall
be such that the concrete will surround and properly grip all the reinforcement. Water cement ratio
will such as will give concrete just sufficiently weight to be placed and compacted without difficulty.
For vibrated concrete, water content may be reduced by 15% to 20% to give the required reduced
slump.

Mixing -
For all important works concrete shall be mixed in mechanical mixer at the site of work. Care shall
be taken to see that the mixer and other accessories are in first class working condition especially
the blades which have to extend right up to the bottom of the drum. Trial mix shall be taken out to
ensure good mixing. Mixing shall be continued till there is uniform distribution of the materials and
a uniform colour is obtained and each individual particle of the coarse aggregate shall show a
complete coating of mortar containing its proportionate amount of cement. In no case mixing shall
be done for less than 1.5 minutes. The water cement ratio shall range between 0.55 to 0.64 for
1:2:4 mix. When hand mixing is permitted by the Engineer it shall be done on a smooth water tight
platform large enough to allow efficient turning over of the ingredients of concrete before and after
adding water. Mixing platform shall be so arranged that no foreign matter shall get mixed with
concrete nor the mixing water shall flow out. The cement in required number of bags shall be
placed in a uniform layer on top of the measured quantity to fine aggregate required, also spread in
a layer of uniform depth in the mixing platform. Dry sand and cement then shall be mixed
thoroughly by turning over to get a mixture of uniform Colour. Enough water shall then be added
gradually through a rose and the mass turned over till a mortar of required consistency is obtained.
The measured quantity of coarse aggregate shall then be placed on a mixing platform and wetted
and the mortar added and the entire mass turned and returned until all the particle of the coarse
aggregate are fully covered with mortar and mixture is of a uniform colour and required
consistency. In hand mixing, quantity of cement shall be increased by 5% above that specified in
para. B.5.3 without any extra cost. Concrete shall have a consistency such that it will be workable
in the required position and in the case of R.C.C., flow around reinforcing steel also. For vibrated
concrete, slump shall range between 2.5 cm. to 5 cm. For hand tamped concrete, slump shall
range between 8 cm. to 13cm.according to the type and nature of the concrete item. The slump
shall be least permitted by workability and maintained throughout the concreting operation of a
member. The concrete shall be placed in its final position and rammed, vibrated and finished within
30 minutes of adding water to cement. Re-tempering or remixing of partially hardened concrete
shall not be permitted.
Scaffolding -
All scaffolding, hoisting arrangements and ladders, etc., required for the facility of concreting shall
be provided by the contractor at his own expense and removed on the completion of work. The

Page 110 Tender ID - 31688


scaffolding, hoisting arrangements and ladders, etc., shall be strong enough to withstand all live,
dead and impact load expected to act and shall be subjected to the approval of the Engineer.
However the contractor shall be solely responsible for the safety of scaffolding,
hoisting arrangement, ladders, work and workmen. The contractor shall pay the necessary
compensations arising out of the use of the scaffolding hoisting arrangements and ladders and for
damages to work, properties and injuries to persons. The scaffolding, hoisting arrangements and
ladders shall allow easy approach to work spot and afford easy inspection.

Forms - Forms shall generally comply with I.S.456-1964,para.7.2.

Materials -
The forms and false work shall be made of wood or metal. The timber from which the forms are
prepared should preferably be partially seasoned as too dry a timber will swell for absorption of
moisture while green timber will dry and shrink. It shall be free from sap, shakes, loose knots,
wormholes or other defects. The plants and scantlings shall be sawn straight and all edges and
planes shall be straight and free from warps. Partially seasoned soft wood is generally preferable
for formwork as it is difficult to drive nails in hard wood. The dimensions of scantlings should
conform to the design. The strength of the wood shall not be less than that assumed in the design.
In metal form, steel sheets of designed gauge strengthened with framing of angle or other sections
shall be used. Wooden forms may also be lined with thin steel sheets or plywood to give the
required surface or finish.

Fabrication -
The timber plans and scantlings of designed dimensions shall be used in the formwork with
appropriate spacing of studs, yokes, joists, girders, etc., as provided in the design. All timber in
contact with concrete shall be wrought on one face and two edges, the unwrought face being on
the outside. The joints should be made mortar tight. This may be done either by providing tongued
and prooved or rebated. joints or by caulking or nailing metal strips or applying adhesive tape on
the joints. The forms shall be built with sufficient strength and rigidity and held in shape by bolts,
clamps, ties, nails, wales or other contrivance to prevent distortion or collapse due to pressure of
concrete and other loads incidental to the construction operations. The nuts and bolt heads inside
the formwork adjoining the concrete should be countersunk. The formwork should allow finish
concrete to have a smooth surface and conforms to the shapes, lines and dimensions shown on
the plans and true to line and grades. The effect of vibration shall be taken into account in the
design and fabrication of forms and falsework. Forms shall be so designed and constructed as to
be removable in sections without damaging the surface of the concrete and with facilities of
removal in the ascending order of removal time, without disturbing the remaining forms required to
be removed later.

Treatment of inside of forms - Before placing concrete, the inside of the forms which comes in
contract with concrete shall coated with mineral oil or any other suitable material approved by the

Page 111 Tender ID - 31688


Engineer which will prevent adhesion to concrete to the forms but will not discolour the concrete.
When oil is used, it shall be applied before reinforcement is placed. Care shall be taken to see that
reinforcement does not came in contact with the coating. All chipping, saw dust and other rubbish
shall be removed from the interior of the forms before concrete.
False work - Falsework shall be built on foundation or base of sufficient strength to carry the loads
without settlement. Falsework which can not be founded on solid footing must be supported by
piles or other similar devices. Falsework shall be designed to carry the full loads including that due
to construction operations coming upon it.
Erection - Falsework and formwork shall be erected with an eye for absolute safety of the
formwork and concrete work before, during and after pouring concrete. Watch must be kept to see
that the behaviour of centering and formwork is satisfactory during concreting. Erection should also
be such that it would allow removal of forms in proper sequence without damaging either the
concrete or the forms to be removed later. If there is failure of falsework and/or formwork the
contractor shall be responsible for all the consequent damages to work, injury to life and damage
to property.
Inspection - The forms and falsework will be inspected, checked and approved by the Engineer
before concreting is commenced. But this will not relieve the contractor of his responsibilities for
strength, adequacy and safety of the formwork and falsework.
Removal of forms - Formwork shall be removed carefully without damaging the concrete or giving
sudden shocks. It should be ascertained from the exposed sides of concrete that it has gained
adequate strength before the bottoms and supports of the formwork are removed Unless otherwise
specified in the special provisions, forms of concrete work using ordinary Portland cement may be
struck after expiry of the following periods in normal circumstances :-

1) Vertical faces of all structural 28 hrs. to 48 hrs. members,

wall

(2) Slabs (props left under) 3 days

(3) Beam soffits (props left under) 7 days

(4) Slabs spanning upto 4.5 m. 7 days

Page 112 Tender ID - 31688


(5) Slabs spanning over 4.5 m. 14 days

(6) Beams spanning upto 6 m. 14 days

(7) Beams spanning over 6 m. 21 days

For Pozzolana Grade 43 or Grade 53 and other types of cements the striking period may be
suitably modified. In important structures, the sequence of striking formwork shall be approved by
the Engineer.
Reuse - Before reuse, all forms shall be thoroughly scraped and cleaned, joints gone over and
repaired and the insides retreated to prevent adhesion, all to the entire satisfaction of the Engineer.
The shape, strength, rigidity, mortar tightness and surface smoothness of reused forms shall be
maintained at all times.
Transporting - The concrete shall be handled from the place of mixing to the final position as
quickly as practicable by methods which will prevent segregation and loss of ingredients. In no
case shall the operation take more than 15 minutes.
Placing -
The concrete shall be placed into its final position, compacted and finished within 30 minutes of
mixing the water and before setting commences. The method of placing shall be such as to avoid
segregation. Placing shall be done in a balanced manner to avoid eccentric loads on formwork. As
far as practicable the concrete for a particular portion shall be done in one continuous operation.
The construction joints when required shall be made only where located on the plans or shown in
the pouring schedule unless otherwise approved by the Engineer. The joint shall be regular and
vertical and shall be made by placing a bulk head at the joint. Before commencing subsequent
concreting, all loose particles, laitance, etc., shall be removed and the surface shall then be
covered by thick cement slurry as part of placement. Care shall be taken during the placing not to
disturb the forms or the reinforce-ment. Concrete compacted manually, shall preferably be laid in
layers of 15 cm. to 20 cm. the layers being decided by the time lapse between the successive
layers. The time of laying one layer shall not exceed 30 minutes. The successive layers shall
commence within 30 minutes. When work is to be resumed on a surface which has hardened,
such a surface shall be roughened and scrubbed with brushes to remove laitance, care being
taken to avoid dislodgement of coarse aggregate, swept clean, thoroughly wetted and covered with
6mm. thick mortar layer composed of cement and sand in the same proportion as the cement and
sand in the concrete, immediately before the commencement of concrete, for securing good bond.
The concrete shall be normally laid in the dry. If the area is under water, it shall be pumped dry and
kept so while placing concrete and till it sets. Where it is necessary to deposit concrete under
water, it shall be done as per I.S. 456-1964* para. 13.2. No extra payment will be made for the

Page 113 Tender ID - 31688


special arrangements, plant, etc., need for the purpose or for the additional 10% cement required
to be added.
Compacting -
The concrete shall be thoroughly compacted during depositing to get a dense concrete and
thoroughly worked into the edges and corners of the formwork as also along its faces and around
reinforcement in the case of R.C.C., by means of suitable tools such as spades and rods to get a
good cast finish without honey combing. Concrete shall not be disturbed once it is set. For
important or big works where stiffer mix with less slump is adopted, use of mechanical vibrators is
essential. The vibrators shall have not less than 3600 and preferably about 5000 impulses per
minute and shall be worked at an interval of about 60cm. It shall be worked in one place for only
such time as will allow formation of dense concrete without sinking and segregation of the coarse
aggregate. Over vibration shall be avoided. Vibration shall be aided by spading and rodding.
Curing -
The concrete shall be initially protected from damage on account of impact, undue pressure,
excessive heat of sun, rain, etc., and covered with wet sacking, hessian or similar absorbent
material soon after the initial set. After the final set the concrete shall be kept continuously wet
preferably by pounding water for a period of not less than 14 days from the date of placement. On
Sundays, holidays and days of cessation of work, arrangement shall be made to keep the concrete
continuously watered. Should the contractor fail to water the concrete continuously, the Engineer
may provide labour, materials and equipment required for watering and recover the cost from the
contractor.
When atmospheric temperature exceeds 40oC (104oF) following precautions should be taken:-
(1) Stacking aggregates under shades and keeping them moist.
(2) Using cold water.
(3) Reduce the time between mixing and placing to the minimum.
(4) Cooling formwork by sprinkling water.
(5) Starting curing before concrete dries out.
(6) Restricting concreting to mornings and evenings.
Finishing - Immediately after the removal of forms, any undulations, depressions, cavities,
honeycombing, broken edges or corners, high spots and other defects shall be made good and
finished with cement mortar 1:2 But the necessity of such finishing must be exceptional and the
total surface requiring finishing shall not exceed 1 per cent. on an average. If the initial experience
shows that this percentage is exceeded the method of working itself should be changed to get the
required cast finish. Where the concrete surface is to receive plaster, the surface shall roughened
immediately after removal of forms and within a day thereof to secure a hold for the plaster. The
rate for concrete is inclusive of this roughening and finishing. Concrete after finishing shall be
cured for thefull period.
Retempering - Concrete shall be mixed only in such quantities as are required for immediate use
and any concrete which has developed initial set shall not be used. Concrete which is partially
hardened shall not be retempered or re-mixed but shall be destroyed or thrown away.

Page 114 Tender ID - 31688


Sampling and Testing -
Sampling of materials and concrete shall be done carefully by the contractor under the direct
supervision of the Departmental staff as per I. S. 456-1978 at the cost of contractor. All necessary
labour, materials, equipments, etc., for sampling, preparing test cubes, curing, etc., shall be
provided by the contractor. Testing of the materials and concrete will be arranged by the
Department in an approved laboratory at the cost of the contractor. No plea will be entertained
later on the ground that casting of the test specimen was faulty and that the result of the test
specimen did not give a correct indication of the actual quality of concrete. Compressive strength
of ordinary concrete shall not be less than those specified below

No. Mix Works test on

15cm. cubes

Kg./sq.cm. at 7 Kg./sq.cm. at 28

days days

1 1:1:2 160 250

2 1:1.5:3 130 200

3 1:2:4 100 150

4 1:3:6 66 100

5 1:4:8 48 70

One set of six 15cm. cubes shall be prepared from the concrete to be used in the work for
compression test on each of the three days operation and thereafter for every 60 cu. m. of
concrete or three days’ work whichever is less, by the contractor in the presence of a responsible
officer of the Department of a rank not less than that of an overseer. If the source of aggregate or
grading is changed, one set of six test cubes shall be taken for each changed batch. Three cubes

Page 115 Tender ID - 31688


shall be used for test at 7 days’ age and three at 28 days. After the relation between strength at 7
days and 28 days is reliably established for the particular set of materials for the same sources,
subsequent tests may be carried out only on three cubes at 7 days and above. 20% of the tests
results may be less than the average strength given above. If the average strength of the cubes
show ultimate compressive strength less than the above the Engineer shall have right to order a
change in the mix or water content for the remaining concrete without extra cost. Defective
concrete having strength below 80 % of the required strength is liable to be rejected. Concrete of
strength up to 80% of the required strength may be accepted as substandard work at a reduced
rate provided such weak concrete is restricted to such members and in such quantities as will not
endanger the safety of the structure.

Keeping record -
A day to day record authenticated by a responsible officer of the department and the
representative of the contractor, in the proforma approved by the Engineer shall be maintained by
the contractor on the work site and kept open for inspection. This shall contain important
information such as receipt of cement on the work site, daily use with details of use on various
items, time of starting concreting and closer, number of batches through the mixer, source of
water, water cement ratio of concrete, slump, dates of erection of formwork, passing of formwork
by the competent authority, dates of striking of forms, periods, and method of curing and other
events worthy of note. On completion of the work, the record shall be handed over to the
Department.
Item to include –
(1) All labour, materials, use of equipment, tools and plant, installing and removal of scaffolding,
falsework and forms and bracing necessary for the satisfactory completion of the item except the
reinforcement steel.
(2) Providing cement concrete of specified proportion including transporting, placing and
compacting, curing, finishing to the dimensions and shapes shown on the plans or as ordered by
the Engineer.
(3) Necessary sampling and tests for material and concrete.
(4) Compensation for injury to persons and damages to work or property.
Mode of measurement and payment -
The contract rate shall be for a unit of one cubic metre of concrete. The concrete shall be
measured for its length, breadth and depth. No deduction shall be made for reinforcement in
concrete in R.C.C. work. Individual dimension shall be measured correct to one cm. and quantities
shall be worked out correct upto three places of decimals of a cubic metre.

7 Providing and casting in situ Ready Mix Cement Concrete grade of trap / granite /
quartzite / gneiss metal of approved quality for RCC works as per detailed drawings and
designs or as directed by Engineer-in- charge including normal dewatering, centering,
form work, compaction, finishing the formed surfaces with CM 1:3 of sufficient
minimum thickness to give a smooth and even surface wherever necessary or

Page 116 Tender ID - 31688


roughening if special finish is to be provided and curing including transporting
from mixing plant upto distance of 25 km., pouring the concrete at work site for 1.5 M
lift above G.L. and 5.0 M lift below G.L., etc. complete.
(Excluding reinforcement and structural steel)
7.1 For Beams / Braces / Lintels
7.1.1 In RCC M-200
Specification:
Specification:
General - The item refers to the cement concrete required for R.C.C.footings of columns and steel
stanchions, grillage and raft and strip foundation in building construction. Providing and casting in
situ cement concrete 1:1.5:3 for R.C.C. columns as per detailed designs and drawings or as
directed including dewatering centering from- work, compacting, finishing the formed surface with
cement mortar 1:3 of sufficient minimum thickness to give a smooth and even surface or
roughening if special finish is to be provided and curing (excluding steel reinforcement).
Materials –
A) Workability : The following procedure is adopted for testing workability;
(i) There should be mentioned of specified workability as per grade requirement and site
requirement in the tender document
(ii) After making sure that the concrete has been uniformly mixed, take a sample from the first 0.5
cum. of concrete discharge and do a sump (of compacting factor) test on the sample. If the result
complies with the specified requirements, then the load should be accepted. If the results are
beyond limit, a further sample should be taken from the second 0.5 cum. of the discharge and if
this is satisfactory, the load should be accepted, if not the concrete load should be rejected, as the
same is not as per the specification range. Permissible variation in sump shall be 10 mm as per IS:
4926-1976.
B) Cement Content : Cement content for cubic meter of Ready Mix Concrete shall be mentioned
for each grade of concrete. The minimum cement content in the various grades of concrete shall
be as per design mix for a particular grade of concrete. The mix design shall confirm to one of the
methods specified in IS: 10262 or IRC 44. However preferable the mix design should be done as
per details given in IRC-44 of 1976- “Tentative guidelines cement concrete mix design”. The mix
design shall be approved from Govt. laboratory. The grade of cement shall be mentioned in the
contract documents. Cement shall have to be got tested at the Govt. laboratory or the laboratory
approved by the Engineer in Charge.

C) Water : The contractor/ manufacturer shall have to make their own arrangements of potable
water for using in mixing of concrete and for curing purpose. It shall meet the requirement as per
IS: 456-2000.

D) Sand : Sand shall be of approved quality with fineness modulus between 2.4 to 3.5 as per
approved mix design. The sand will have to be screened to remove the oversize particles and
washed to reduce the silt contents below 5% by volume after one hour & to bring it within

Page 117 Tender ID - 31688


the permissible range of fineness modulus. Blending of sand of fine and coarse quality may be
permitted at mix design stage to achieve the required fineness modulus, if it is found necessary to
give desired results. The fine aggregates will be tested as directed by Engineer in Charge.

E) Coarse Aggregate : Specified sizes of aggregates mentioned in design mix shall be used by
manufacturer of RMC plant. Client shall confirm the quality of sand used for concrete. If coarse
aggregate are found having white spots, the same shall be got tested from approved testing
laboratory to eliminate possibility of potential aggregate alkali reactivity before accepting or using
spotted aggregates. The manufacturer should make the necessary arrangements to stock the
aggregates separately so that they do not get mixed up with each other and/or with the foreign
materials and do not get segregated. The screening of the aggregates shall be done if found
necessary as directed by the Engineer in Charge.

F) Compressive Strength : Compressive Strength testing shall be carried out on site for 7 days,
14 days and 28 days strength. The water content shall be the minimum required to provide the
specified workability for full compaction of the concrete to the required compaction of the concrete
to the required density. The maximum water cement ratio shall be 0.40. At least three sets
consisting of 4 cubes from different loads for testing the compressive strength for each days work.
One cube from each set shall be tested for 7 days, 14 days and 28 days strength in presence
of Engineer in Charge in accordance with testing procedure. In case of failure of 28 days strength
at site laboratory, remaining three cubes shall be sent to approved laboratory immediately for
testing for 28 days strength.

G) Density : The density of the compacted concrete shall be such that the total air voids are not
more than 3%. Core density test shall be carried out in accordance with the relevant IS codes
H) Admixtures : The admixture shall be used with consent with the purchaser/ client. The
admixture used shall confirm to IS: 9103-1979 reaffirmed on 1990 or ASTMC-494 of 92. The
following admixtures to be used in concrete: (i) Accelerating Admixtures, (ii) Retarding
Admixtures, (iii) Water Reducing Admixtures, (iv) Air Entraining Admixtures,

Proportioning Mix - In ordinary concrete, although proportion of cement to fine and coarse
aggregate is specified by volume, the quantity of cement shall be determined by weight assuming
one bag of cement weighing 50 Kg. nett to be equivalent to 35 litres. Fine and coarse aggregates
shall be measured by dry volumes in suitable wooden boxes. Due allowance shall be made for
bulking in the fine aggregate due to moisture if any, at the time of mixing.
Ingredients required for concrete containing 50 Kg. bag of cement for different proportions of mix
will be as under :-

Page 118 Tender ID - 31688


Mix Cement Fine Coarse Water

aggregate aggregate

1 2 3 4 5

1:1:2 50Kg 50Kg 100Kg 23-27 litres

1:1.5:3 50Kg 75Kg 150Kg 23-30 litres

1:2:4 50Kg 100Kg 200Kg 27-32 litres

1:3:6 50Kg 150Kg 300kg 37.5-45 litres

1:4:8 50Kg 200Kg 400kg 47.5-57 litres

1:5:10 50Kg 250Kg 500Kg 56-68 litres

In case of slabs special mixes with smaller size aggregates shall be taken out and placed below
bottom steel to obtain dense cover. The ratio of the volumes of the fine and coarse aggregates
may be varied within limits of 1:1.5 to 1:2.5 as directed by the Engineer to suit the maximum size of
coarse aggregate, the grading, density, workability and strength without extra cost. But the sum of
the volumes of the fine and coarse aggregates so adjusted shall however be equal to the sum of
the volumes of fine and coarse aggregates given above for a particular mix. The quantity of water
shall be just sufficient, but not more than sufficient, to produce a dense concrete of required
workability for its purpose. An accurate control shall be kept on the quantity of mixing water.
An allowance shall be made for surface moisture present in the aggregates when computing water
content as indicated in I.S. 456-1978. In the case of reinforced concrete work, the workability shall
be such that the concrete will surround and properly grip all the reinforcement. Water cement ratio

Page 119 Tender ID - 31688


will such as will give concrete just sufficiently weight to be placed and compacted without difficulty.
For vibrated concrete, water content may be reduced by 15% to 20% to give the required reduced
slump.

Mixing -
For all important works concrete shall be mixed in mechanical mixer at the site of work. Care shall
be taken to see that the mixer and other accessories are in first class working condition especially
the blades which have to extend right up to the bottom of the drum. Trial mix shall be taken out to
ensure good mixing. Mixing shall be continued till there is uniform distribution of the materials and
a uniform colour is obtained and each individual particle of the coarse aggregate shall show a
complete coating of mortar containing its proportionate amount of cement. In no case mixing shall
be done for less than 1.5 minutes. The water cement ratio shall range between 0.55 to 0.64 for
1:2:4 mix. When hand mixing is permitted by the Engineer it shall be done on a smooth water tight
platform large enough to allow efficient turning over of the ingredients of concrete before and after
adding water. Mixing platform shall be so arranged that no foreign matter shall get mixed with
concrete nor the mixing water shall flow out. The cement in required number of bags shall be
placed in a uniform layer on top of the measured quantity to fine aggregate required, also spread in
a layer of uniform depth in the mixing platform. Dry sand and cement then shall be mixed
thoroughly by turning over to get a mixture of uniform Colour. Enough water shall then be added
gradually through a rose and the mass turned over till a mortar of required consistency is obtained.
The measured quantity of coarse aggregate shall then be placed on a mixing platform and wetted
and the mortar added and the entire mass turned and returned until all the particle of the coarse
aggregate are fully covered with mortar and mixture is of a uniform colour and required
consistency. In hand mixing, quantity of cement shall be increased by 5% above that specified in
para. B.5.3 without any extra cost. Concrete shall have a consistency such that it will be workable
in the required position and in the case of R.C.C., flow around reinforcing steel also. For vibrated
concrete, slump shall range between 2.5 cm. to 5 cm. For hand tamped concrete, slump shall
range between 8 cm. to 13cm.according to the type and nature of the concrete item. The slump
shall be least permitted by workability and maintained throughout the concreting operation of a
member. The concrete shall be placed in its final position and rammed, vibrated and finished within
30 minutes of adding water to cement. Re-tempering or remixing of partially hardened concrete
shall not be permitted.
Scaffolding -
All scaffolding, hoisting arrangements and ladders, etc., required for the facility of concreting shall
be provided by the contractor at his own expense and removed on the completion of work. The
scaffolding, hoisting arrangements and ladders, etc., shall be strong enough to withstand all live,
dead and impact load expected to act and shall be subjected to the approval of the Engineer.
However the contractor shall be solely responsible for the safety of scaffolding,
hoisting arrangement, ladders, work and workmen. The contractor shall pay the necessary
compensations arising out of the use of the scaffolding hoisting arrangements and ladders and for
damages to work, properties and injuries to persons. The scaffolding, hoisting arrangements and

Page 120 Tender ID - 31688


ladders shall allow easy approach to work spot and afford easy inspection.

Forms - Forms shall generally comply with I.S.456-1964,para.7.2.

Materials -
The forms and false work shall be made of wood or metal. The timber from which the forms are
prepared should preferably be partially seasoned as too dry a timber will swell for absorption of
moisture while green timber will dry and shrink. It shall be free from sap, shakes, loose knots,
wormholes or other defects. The plants and scantlings shall be sawn straight and all edges and
planes shall be straight and free from warps. Partially seasoned soft wood is generally preferable
for formwork as it is difficult to drive nails in hard wood. The dimensions of scantlings should
conform to the design. The strength of the wood shall not be less than that assumed in the design.
In metal form, steel sheets of designed gauge strengthened with framing of angle or other sections
shall be used. Wooden forms may also be lined with thin steel sheets or plywood to give the
required surface or finish.

Fabrication -
The timber plans and scantlings of designed dimensions shall be used in the formwork with
appropriate spacing of studs, yokes, joists, girders, etc., as provided in the design. All timber in
contact with concrete shall be wrought on one face and two edges, the unwrought face being on
the outside. The joints should be made mortar tight. This may be done either by providing tongued
and prooved or rebated. joints or by caulking or nailing metal strips or applying adhesive tape on
the joints. The forms shall be built with sufficient strength and rigidity and held in shape by bolts,
clamps, ties, nails, wales or other contrivance to prevent distortion or collapse due to pressure of
concrete and other loads incidental to the construction operations. The nuts and bolt heads inside
the formwwork adjoining the concrete should be countersunk. The formwork should allow finish
concrete to have a smooth surface and conforms to the shapes, lines and dimensions shown on
the plans and true to line and grades. The effect of vibration shall be taken into account in the
design and fabrication of forms and falsework. Forms shall be so designed and constructed as to
be removable in sections without damaging the surface of the concrete and with facilities of
removal in the ascending order of removal time, without disturbing the remaining forms required to
be removed later.

Treatment of inside of forms -


Before placing concrete, the inside of the forms which comes in contract with concrete shall coated
with mineral oil or any other suitable material approved by the Engineer which will prevent
adhesion to concrete to the forms but will not discolour the concrete. When oil is used, it shall be
applied before reinforcement is placed. Care shall be taken to see that reinforcement does not
came in contact with the coating. All chipping, saw dust and other rubbish shall be removed from
the interior of the forms before concrete.

Page 121 Tender ID - 31688


False work -
Falsework shall be built on foundation or base of sufficient strength to carry the loads without
settlement. Falsework which can not be founded on solid footing must be supported by piles or
other similar devices. Falsework shall be designed to carry the full loads including that due to
construction operations coming upon it.
Erection -
Falsework and formwork shall be erected with an eye for absolute safety of the formwork and
concrete work before, during and after pouring concrete. Watch must be kept to see that the
behaviour of centering and formwork is satisfactory during concreting. Erection should also be
such that it would allow removal of forms in proper sequence without damaging either the concrete
or the forms to be removed later. If there is failure of falsework and/or formwork the contractor shall
be responsible for all the consequent damages to work, injury to life and damage to property.
Inspection - The forms and falsework will be inspected, checked and approved by the Engineer
before concreting is commenced. But this will not relieve the contractor of his responsibilities for
strength, adequacy and safety of the formwork and falsework.
Removal of forms - Formwork shall be removed carefully without damaging the concrete or giving
sudden shocks. It should be ascertained from the exposed sides of concrete that it has gained
adequate strength before the bottoms and supports of the formwork are removed Unless otherwise
specified in the special provisions, forms of concrete work using ordinary Portland cement may be
struck after expiry of the
following periods in normal circumstances :-

1) Vertical faces of all structural 28 hrs. to 48 hrs. members,

wall

(2) Slabs (props left under) 3 days

(3) Beam soffits (props left under) 7 days

(4) Slabs spanning upto 4.5 m. 7 days

(5) Slabs spanning over 4.5 m. 14 days

Page 122 Tender ID - 31688


(6) Beams spanning upto 6 m. 14 days

(7) Beams spanning over 6 m. 21 days

For Pozzolana Grade 43 or Grade 53 and other types of cements the striking period may be
suitably modified. In important structures, the sequence of striking formwork shall be approved by
the Engineer.
Reuse - Before reuse, all forms shall be thoroughly scraped and cleaned, joints gone over and
repaired and the insides retreated to prevent adhesion, all to the entire satisfaction of the Engineer.
The shape, strength, rigidity, mortar tightness and surface smoothness of reused forms shall be
maintained at all times.
Transporting - The concrete shall be handled from the place of mixing to the final position as
quickly as practicable by methods which will prevent segregation and loss of ingredients. In no
case shall the operation take more than 15 minutes.
Placing -
The concrete shall be placed into its final position, compacted and finished within 30 minutes of
mixing the water and before setting commences. The method of placing shall be such as to avoid
segregation. Placing shall be done in a balanced manner to avoid eccentric loads on formwork. As
far as practicable the concrete for a particular portion shall be done in one continuous operation.
The construction joints when required shall be made only where located on the plans or shown in
the pouring schedule unless otherwise approved by the Engineer. The joint shall be regular and
vertical and shall be made by placing a bulk head at the joint. Before commencing subsequent
concreting, all loose particles, laitance, etc., shall be removed and the surface shall then be
covered by thick cement slurry as part of placement. Care shall be taken during the placing not to
disturb the forms or the reinforce-ment. Concrete compacted manually, shall preferably be laid in
layers of 15 cm. to 20 cm. the layers being decided by the time lapse between the successive
layers. The time of laying one layer shall not exceed 30 minutes. The successive layers shall
commence within 30 minutes.
When work is to be resumed on a surface which has hardened, such a surface shall be roughened
and scrubbed with brushes to remove laitance, care being taken to avoid dislodgement of coarse
aggregate, swept clean, thoroughly wetted and covered with 6mm. thick mortar layer composed of
cement and sand in the same proportion as the cement and sand in the concrete, immediately
before the commencement of concrete, for securing good bond. The concrete shall be normally
laid in the dry. If the area is under water, it shall be pumped dry and kept so while placing concrete
and till it sets. Where it is necessary to deposit concrete under water, it shall be done as per I.S.
456-1964* para. 13.2. No extra payment will be made for the special arrangements, plant, etc.,
need for the purpose or for the additional 10% cement required to be added.

Page 123 Tender ID - 31688


Compacting -
The concrete shall be thoroughly compacted during depositing to get a dense concrete and
thoroughly worked into the edges and corners of the formwork as also along its faces and around
reinforcement in the case of R.C.C., by means of suitable tools such as spades and rods to get a
good cast finish without honey combing. Concrete shall not be disturbed once it is set. For
important or big works where stiffer mix with less slump is adopted, use of mechanical vibrators is
essential. The vibrators shall have not less than 3600 and preferably about 5000 impulses per
minute and shall be worked at an interval of about 60cm. It shall be worked in one place for only
such time as will allow formation of dense concrete without sinking and segregation of the coarse
aggregate. Over vibration shall be avoided. Vibration shall be aided by spading and rodding.
Curing -
The concrete shall be initially protected from damage on account of impact, undue pressure,
excessive heat of sun, rain, etc., and covered with wet sacking, hessian or similar absorbent
material soon after the initial set. After the final set the concrete shall be kept continuously wet
preferably by pounding water for a period of not less than 14 days from the date of placement. On
Sundays, holidays and days of cessation of work, arrangement shall be made to keep the concrete
continuously watered. Should the contractor fail to water the concrete continuously, the Engineer
may provide labour, materials and equipment required for watering and recover the cost from the
contractor. When atmospheric temperature exceeds 40oC (104oF) following precautions should be
taken:-
(1) Stacking aggregates under shades and keeping them moist.
(2) Using cold water.
(3) Reduce the time between mixing and placing to the minimum.
(4) Cooling formwork by sprinkling water.
(5) Starting curing before concrete dries out.
(6) Restricting concreting to mornings and evenings.
Finishing -
Immediately after the removal of forms, any undulations, depressions, cavities, honeycombing,
broken edges or corners, high spots and other defects shall be made good and finished with
cement mortar 1:2 But the necessity of such finishing must be exceptional and the total surface
requiring finishing shall not exceed 1 per cent. on an average. If the initial experience shows that
this percentage is exceeded the method of working itself should be changed to get the required
cast finish. Where the concrete surface is to receive plaster, the surface shall roughened
immediately after removal of forms and within a day thereof to secure a hold for the plaster. The
rate for concrete is inclusive of this roughening and finishing. Concrete after finishing shall be
cured for the full period.
Retempering -
Concrete shall be mixed only in such quantities as are required for immediate use and any
concrete which has developed initial set shall not be used. Concrete which is partially hardened
shall not be retempered or re-mixed but shall be destroyed or thrown away.

Page 124 Tender ID - 31688


Sampling and Testing -
Sampling of materials and concrete shall be done carefully by the contractor under the direct
supervision of the Departmental staff as per I. S. 456-1978 at the cost of contractor. All necessary
labour, materials, equipments, etc., for sampling, preparing test cubes, curing, etc., shall be
provided by the contractor. Testing of the materials and concrete will be arranged by the
Department in an approved laboratory at the cost of the contractor. No plea will be entertained
later on the ground that casting of the test specimen was faulty and that the result of the test
specimen did not give a correct indication of the actual quality of concrete. Compressive strength
of ordinary concrete shall not be less than those specified below

No. Mix Works test on

15cm. cubes

Kg./sq.cm. at 7 Kg./sq.cm. at 28

days days

1 1:1:2 160 250

2 1:1.5:3 130 200

3 1:2:4 100 150

4 1:3:6 66 100

5 1:4:8 48 70

One set of six 15cm. cubes shall be prepared from the concrete to be used in the work for
compression test on each of the three days operation and thereafter for every 60 cu. m. of
concrete or three days’ work whichever is less, by the contractor in the presence of a responsible
officer of the Department of a rank not less than that of an overseer. If the source of aggregate or
grading is changed, one set of six test cubes shall be taken for each changed batch. Three cubes

Page 125 Tender ID - 31688


shall be used for test at 7 days’ age and three at 28 days. After the relation between strength at 7
days and 28 days is reliably established for the particular set of materials for the same sources,
subsequent tests may be carried out only on three cubes at 7 days and above. 20% of the tests
results may be less than the average strength given above. If the average strength of the cubes
show ultimate compressive strength less than the above the Engineer shall have right to order a
change in the mix or water content for the remaining concrete without extra cost. Defective
concrete having strength below 80 % of the required strength is liable to be rejected. Concrete of
strength up to 80% of the required strength may be accepted as substandard work at a reduced
rate provided such weak concrete is restricted to such members and in such quantities as will not
endanger the safety of the structure.

Keeping record -
A day to day record authenticated by a responsible officer of the department and the
representative of the contractor, in the proforma approved by the Engineer shall be maintained by
the contractor on the work site and kept open for inspection. This shall contain important
information such as receipt of cement on the work site, daily use with details of use on various
items, time of starting concreting and closer, number of batches through the mixer, source of
water, water cement ratio of concrete, slump, dates of erection of formwork, passing of formwork
by the competent authority, dates of striking of forms, periods, and method of curing and other
events worthy of note. On completion of the work, the record shall be handed over to the
Department.
Item to include –
(1) All labour, materials, use of equipment, tools and plant, installing and removal of scaffolding,
falsework and forms and bracing necessary for the satisfactory completion of the item except the
reinforcement steel.
(2) Providing cement concrete of specified proportion including transporting, placing and
compacting, curing, finishing to the dimensions and shapes shown on the plans or as ordered by
the Engineer.
(3) Necessary sampling and tests for material and concrete.
(4) Compensation for injury to persons and damages to work or property.
Mode of measurement and payment -
The contract rate shall be for a unit of one cubic metre of concrete. The concrete shall be
measured for its length, breadth and depth. No deduction shall be made for reinforcement in
concrete in R.C.C. work. Individual dimension shall be measured correct to one cm. and quantities
shall be worked out correct upto three places of decimals of a cubic metre.

8 Providing and fixing in position TMT - FE - 500 bar reinforcement of various diameters
for R.C.C. pile caps, footings, foundations, slabs, beams columns, canopies, staircase,
newels, chajjas, lintels pardis, copings, fins, arches etc. as per detailed designs,
drawings and schedules. including cutting, bending, hooking the bars, binding with wires
or tack welding and supporting as required complete.

Page 126 Tender ID - 31688


Specification:
General - The item provides for the supply of mild steel bars, cutting, bending, binding
with galvanized iron wire and erecting in position for reinforcement in R.C.C.

Materials -
1) TMT bar
2)The binding wire
Supply - When the supply is made by the Department, the contractor shall convey the mild steel
bars from the place of delivery mentioned in schedule `A’ of the tender to the site of work. The
contractor shall be solely responsible for any damage during the conveyance and till it is used.
When the contractor supplied mild steel reinforcement bars obtained from the market they shall be
supplied to the site of work without damage.

Fabrication - Reinforcing steel shall be thoroughly cleaned of all coatings of any characters that
would destroy or reduce the bond. Bending reinforcement shall conform accurately to the
dimensions and shapes shown on the plans or as directed by the Engineer. Bars shall not be bent
or straightened in a manner that will injure
the material. Bars with kinks, bends or cracks shall not be used. Bars shall be bent cold to the
shapes and dimensions shown on the drawings or as directed by the Engineer in writing. Bar
bender may be used to attain proper radii of bends and shapes. Bars which may be bend in
transport or handling shall be properly straightened before being placed in work without heating
them. Bending bar by heating to cherry red heat not exceeding 815øc may be allowed for only
M.S. bars larger than 25mm. diameter except for bars which depend for their strength on cold
working . Hot bars shall not be cooled by quenching. HYSD bars shall not be heated for bending.
Details of length, sizes, laps and bending diagrams shall be got approved by the Engineer. This is
to secure additional precautions against errors.

Splicing and Lapping - All reinforcement shall be furnished in full lengths indicated on the plans
as far as possible. splicing bars except as shown on the plans will not available, bars shall be
spliced. spliced of tensile reinforcement at points of maximum stress and of adjacent bars at the
same place shall be avoided. Splices shall be staggered as far as possible and located at suitable
points. A welded or mechanical connection if adopted, shall develop the full strength of the bars .
Welding of HYSD bars shall not be done. However welding of HYSD bars may be done with
written permission of the Engineer in charge by special methods as may be suitable. Unless
otherwise shown on the plans, bars shall be lapped as specified in I.S. 456-1964* with due regard
to the grade of concrete. In lap-splices, bars shall be placed in contact and just wired together to
keep in place.

Coupling - Whenever plans and specifications call for the use of coupling-boxes or bottle nuts to
join bars, they shall have sufficient cross section to transmit the full strength of the bars. The ends
of the bars which are jointed by coupling shall be upset for a sufficient length so that effective cross

Page 127 Tender ID - 31688


section after cutting the screw threads shall not be less than the normal cross section of the bars.
Screw threads shall be standard Whitworth threads. Coupled joints will be paid for separately.

Welding - Whenever plans and specifications call for the welding of joints in reinforcement bars in
lieu of lapping them, the bars shall be butt-welded so as to transmit their full strength. Welding
shall generally conform to specification No.B- 18 and I.S. 456-1964* except as modified below and
when otherwise directed by the Engineer. Welded joints shall be so staggered that in any one
section equal to the lap length of the bars, not more than 33% of the bar are welded. Electric arc
welding or oxyacetylene process of welding, using a process which will exclude air from the molten
metal and conforming to any special provisions for the welding as laid down by the Engineer in
writing will be accepted. Suitable means shall be provided for holding the bars securely in position
during the process of welding. The ends of the
bars shall be cleaned of all loose scale, rust, grease, paint, and other foreign matter and clean
original metal exposed before welding. Only competent and experienced welder shall be employed
on the work. Preliminary test of the weld shall be carried out at the contractor’s cost to see that the
actual field welding method is satisfactory and gives the required strength. Two welds in 100 welds
or a minimum of 2 welds shall be made on the site on the test pieces under conditions exactly
similar to the field welding of actual reinforcement bars and tested for their tensile strength. The
strength of the welded joint shall not be less than that of the original bar. If the tests are not
satisfactory, change of welding procedure and further tests may be ordered by the Engineer. Bars
welded along with the welded samples, found unsatisfactory on tests shall be cut and rewelded.
Additional welds if required on this account shall not be paid for. All the tests shall be at the cost of
the contractor. When welded joints are required they will be paid for separately. No part of the
reinforcement embedded in concrete shall be used for conducting electric current.

Substitution - Substitution of size of bars different from those specified will be permitted at the
request of the contractor only if authorised by the Engineer. The steel substituted shall have area
not less than the designed area provided further that the safe bond stress is not exceeded. If such
substituted steel has larger area than that originally specified, such excess weight due to larger
area will not paid for.

Placing and Fastening - All reinforcement shall be accurately placed in position with spacing and
cover shown on the plan and firmly held so during the placing and setting of concrete. Bars shall
be tied at all intersections. Binding wire of 1.63m. or 1.22mm diameter shall be used. Alternatively
the Engineer may permit spot welding instead of tying wire. Spacing of bars shall be maintained by
means of stays, blocks, ties, spacers, hangers or other approved supports at sufficiently close
interval so that bars will not sags between supports nor be displaced during placing, vibrating or
compacting concrete or by any other operation. Metal supports which extends
to the surface of the concrete except where shown in the plans and wooden supports shall not be
allowed. Placing bars for reinforcement on a layer of fresh concrete as the work progress, will not
be permitted. The use of pieces of broken stones or bricks or wooden blocks for maintaining

Page 128 Tender ID - 31688


spacing or cover shall not be permitted. Layers of bars shall be separated by pre cast cement
mortar blocks, spacer bars or other approved devices. Special care shall be taken to prevent any
disturbance of the reinforcement in concrete that has already been placed. Reinforcement after
being placed in position shall be maintained in a clean condition till it is completely embedded in
the concrete. All bars protruding from concrete to which other bars are to be spliced and which are
likely to be exposed for an indefinite period shall be protected from rusting from rusting by a thin
coat of cement wash.
Inspection - Full details of the numbers, sizes, lengths, weights, laps, welds, spacing of the bars
placed in position in different parts of the work shall be recorded, certified and signed by the
Engineer to show that all reinforcement has been placed correctly as per the sanctioned drawings
or as ordered by the Engineer in writing before placing concrete. No concrete shall be deposited
until the Engineer has inspected and certified the correctness of reinforcement, recorded the steel
measurements and given permission to place the concrete in writing. After the approval of
reinforcement by the Engineer it will be the contractor’s responsibility to see that the reinforcement
spacing and arrangements are not tempered with in any way before or during concreting.
Tests - When the contractor supplies his own steel, he shall produce the test certificate. If there is
any doubt about the quality, tensile and cold bend tests shall be carried out according to I.S. 432 -
1978 in an approved laboratory and the cost of the tests shall be borne by the contractor if the
results are unsatisfactory and by the Department if the results are satisfactory.

Item to include -
1) Cost of labour, material, use of tools, plant and tackle and other incidental items to complete the
work included under the item satisfactorily.
2) Supplying, conveying, cleaning, cutting, bending, binding with 1.63 mm. or 1.22 mm. (16 or 18
gauge) wire or spot-welding and placing reinforcement in position and maintaining it clean and in
position till the concrete is laid.
3) Cost of sampling and testing.

Measurement and Payment - No measurements will be taken of the wire used for tying reinforcement bars. The rate
for reinforcement steel and its fabrication shall include the cost of the binding wire.
Measurement - When required to be measured, measurement shall be by weight with quintal or tonne as the unit.
The wire shall be weighed correct up to 0.10 Kg.

Measurement and Payment - The item will be measured on Metric tonne basis & paid accordingly.

9 Providing and supplying D.I. fittings with ISI mark Mechanical joint
confirming to tables 12 to table 31 of IS 9523/2000 upto latest amendments including
cost of SBR/ EDPM gaskets, Nuts, Bolts, Washers and Ductile iron follower glands.
Fittings should be with internally Ordinary portland cement mortor lined and
externally metallic zinc coating/zinc rich paint with finishing layer of black bitumen
coating including transportation and excluding all statutary duties and taxes such as
GST levied by Gol and GoM in all respect etc. complete. D.I. FITTINGS (Mechanical Joints)

Page 129 Tender ID - 31688


9.1 Double Socket Bend 90 degree (200 mm Dia)
9.1.1 200mm Dia
9.2 MJ Collar/Coupling
9.2.1 200 mm dia
9.3 All Socket Tee
9.3.1 200 x 100 mm dia
9.3.2 200 x 150 mm dia
9.4 Double Socket Tee with Flange branch-PN-10
9.4.1 200 x 80 mm dia
9.5 Flange Socket-PN-10
9.5.1 80 mm dia
9.5.2 200 mm dia
Specification:
The items include providing ,supplying DI/CI/MS Double flanged specials suitable for diameter as
required and of required thickness and including all materials labour charges with including all
taxes. if necessary, inspection charges, transportation to stores/ sites & stacking etc complete.

Scope: The item cover supply of DI/CI/MS double socket and flanged specials of various
diameters including conveyance of specials form manufacture's works to site stores, stacking them
properly and protecting till commissioning of work.

General: The specials shall confirm to relevant I.S.S.

Tests: The specials shall be tested at factory for 15 kg/sq/cm/ Pressure.

Flanges: The flanges shall be drilled to IS-1538.

Tolerance: The tolerance in weight and dimensions shall be as per ISS. Only the specials fitting
within tolerance limit shall be accepted.

PERMANENT TEST POINTS –


Providing permanent test points on the pipe line as per drawing and as directed by Engineer In
Charge directed.

ALL CAST IRON SPECIALS – Material –


All Cast iron specials such as C.I. detachable joints shall confirm to I.S. 1538- 1993 (Part 1 to
24).The Supply at departmental stores shall be of various diameters as specified. The specials
shall befree from any defects. It should be possible to cut/drill the special to suit site condition to fit
in the position. The hardness of the external surface shall not exceed 210 HBS. Rings shall
confirm to IS 5382- 1985. Ring shall be homogeneous and free from porosity, grit and surface

Page 130 Tender ID - 31688


defects ,such as pitting, irregularities. Dimension of rings shall be as per IS 10292-1988.

MANUFACTURE –
The dimensions of flanged sockets and flanged spigots shall be as per Tables 7 & 8 of IS 1538-
1993, respectively. Supply and Stacking at Departmental Store or Work Site : As specified under
the agreement.
Markings –
Each fitting shall have cast stamped or indelibly painted on it the following markings :
1.Manufacturer’s Name or trademark or identification mark.
2.The nominal diameter,
3.Mass of fitting,
4.Last 2 digits of year of manufacture,
5.Any other mark required by the purchaser.

Item to Include –
The item includes the supply of DI detachable joints, including all taxes, levies excluding GST,
transporting, loading, unloading and stacking at departmental store or work site as directed. The
necessary test certificate also shall be provided along with the supply. .

9.1 Specification
Double Socket bend 90 degree

General : The item provides to supply at departmental store the D.I easy link mechanical joint of
double socket bends suitable for use in pipes of D.I. with suitable D.I. follower gland sealing rubber
gasket and nut bolts etc. complete as per the specified diameter of pipe / pipes. (Dia. between 80
mm & 900 mm). The bends shall conform the provisions of IS: 1538-1993 and IS 5382-1985.
Material : All Ductile iron specials such as D.I. mechanical joints shall confirm to I.S. 1538- 1993
(Part 1 to 24). The Supply at departmental stores or work site shall be of various diameters and
degree bends as specified. The specials shall be free from any defects. It should be possible to
cut/drill the special to suit site conditions to fit in the position etc. The hardness of the external
surface shall not exceed 210 HBS. Sealing Rings shall confirm to IS 5382-1985. Ring shall be
homogeneous and free from porosity, grit and surface defects, such as pitting, irregularities.
Dimension of rings shall be as per IS 10292- 1988.
Manufacture : The dimensions of easy link mechanical joint of double socket bends shall be as per
Tables 10, 11 & 12 of IS 1538- 1993, for 900, 450& 22.50 bends, respectively.
Supply and Stacking at Departmental Store : As specified under agreement of supply order.
Testing : The fittings shall be tested for:
Tensile Test : Minimum Tensile strength of 150 MPa. 2. Brinell Hardness Test : shall not exceed
210 HBS

Page 131 Tender ID - 31688


3. Hydrostatic Test : As per IS: 1538-1993, which shall be: For Dia. upto and including 300 mm -
2.5 MPa. Dia over 300 mm & up to & include 600 mm - 2.0 MPa. Dia over 600 mm - 1.5 MPa. 6.6
Markings : Each special fitting shall have cast stamped or indelibly painted on it the following
markings:
1. Manufacturer’s Name or trademark or identification mark.
2. The nominal diameter,
3. Mass of fitting,
4. Last
2 digits of year of manufacture,
5. Any other mark required by the purchaser.
Item to Include : The item includes the supply of Cast Iron easy link mechanical joint of double
socket bends suitable for use in pipes of D.I with suitable D.I. follower gland sealing rubber gasket
and nut bolts etc.,coated with anti corrosive paint including all taxes, levies except octroi,
transporting, loading, unloading and stacking at work site as directed. The necessary test
certificate also shall be provided along with the supply. Octroi paid shall be reimbursed on
producing documentary evidence for the payment made.
Mode of Measurement and Payment : The item shall be measured as number of bends including
gaskets, nuts & bolts etc. for the specified diameter of pipe. The measurement and payment shall
be per No

9.2 Specification
MJ COLLAR COUPLING –

The item provides to supply at departmental store the Ductile Iron jiffy collar coupling with rings
etc. complete as per the specified diameter of pipe / pipes. (Dia. between 80 mm &800 mm). The
joints shall conform the provisions of IS: 1538-1993 and IS 5382-1985.
MATERIAL –
All Cast iron specials such as D.I. mechanical compression collar coupling shall confirm to I.S.
1538- 1993 (Part 1 to 24). The Supply at departmental stores shall be of various diameters as
specified in supply order. The specials shall be free from any defects. It should be possible to cut it
drill the special to suit the site condition and fit in position etc. The hardness of the external surface
shall not exceed 210 HBS. Sealing Rings shall confirm to IS 5382-1985. Ring shall be
homogeneous and free from porosity, grit and surface defects, such as pitting, irregularities.
Dimension of rings shall be as per IS 10292- 1988.
Item to Include –
The item includes the supply of MJ collar coupling, including all taxes, levies excluding GST,
transporting, loading, unloading and stacking at departmental store or work site as directed .The
necessary test certificate also shall be provided along with the supply.
2.7.4 Flat rubber gaskets –

Page 132 Tender ID - 31688


The item provides to supply at departmental store the flat rubber gaskets for flanged joints.
Following two types of rubber gaskets, depending upon the hardness of rubber ay be supplied as
specified in the supply order:
1.Type A: 50 to 65 Hardness in IRHD and
2.Type B: 65 to 80 Hardness in IRHD.
In each of two types, 2 Grades, Grade 1 & 2 are again prescribed.
Material –
The rubber gaskets shall be manufactured from either a) Sheet Rubber or b) Sheet Rubber
reinforced with fabric (Rubber insertion jointing). For manufacturing rubber gaskets, natural rubber
or synthetic rubber or a blend thereof, shall be used, with suitable composition and vulcanization to
attain the required degree of hardness.The fabric for rubber insertion jointing shall have a minimum
breaking strength of 120N/mm2,under test conditions according to IS: 1969- 1968.
Manufacture –
The rubber gaskets shall be free from porosity, grit and surface defects such as pitting and
irregularities. The rubber shall be homogeneous. The manufacturing of sheet rubber and rubber
insertion jointing shall be in accordance with the IS: 638-1979. The thickness and number of fabric
plies shall be as per the IS. Unless mentioned in the supply order the size of each rubber sheet
shall have suitable bolt holes conforming to IS 1538-1993, for the pipe diameter specified in the
order.
Supply and Stacking at Departmental Store:As specified under agreement.
Markings –
Each piece of rubber sheet jointing or rubber insertion jointing shall be marked with the following:
1.The name of manufacturer or the Trade Mark,
2.Type, Grade and Thickness,
3.Month and Year of manufacture,
Any other Marking as specified in the purchase order Item to Include:
The item includes the supply of flat rubber gasket at departmental store, suitable for flanged
joints(3/6 mm thick) with bolt holes and nominal bore, pitch circle diameter as per IS: 1538- 1993
and gasket as per IS: 638-1979, including all taxes, levies except octroi, transporting, loading,
unloading and stacking at departmental store as directed. The necessary test certificate also shall
be provided along with the supply. Octroi paid shall be reimbursed on producing documentary
evidence for the payment made. Mode of Measurement and Payment:
General–
This section covers the general requirements for Ductile Iron (DI) fittings suitable for Tyton joints to
be used with Ductile Iron pipes with flanged and Tyton jointing system.
Supply–
All the DI fittings shall be supplied with one rubber ring for each socket. The rubber ring shall
conform to IS: 12820 and IS: 5382 as described in the preceding chapter. Flanged fittings shall be
supplied with one rubber gasket per flange and the required number of nuts and bolts.
General–

Page 133 Tender ID - 31688


This section covers the requirements for lubricant for the assembly of Ductile Iron pipes and
specials suitable for Tyton push-in rubber ring joints
Specification–
The lubricant has to have the following characteristics:
• must have a paste like consistency and be ready for use
• has to adhere to wet and dry surfaces of DI pipes and rubber rings
• to be applied in hot and cold weather; ambient temperature 0 – 50 °C, temperature of
exposed
• pipes up to 70 °C
• must be non toxic
• must be water soluble
• must not affect the properties of the drinking water carried in the pipes
• must not have an objectionable odour
• has to inhibit bacterial growth
• must not be harmful to the skin
• must have a shelf live not less than 2 years
Acceptance tests –
They shall be conducted in line with the provisions of the IS9523
Packing–
All the DI fittings shall be properly packed with jute cloth. Rubber rings shall be packed in
polyethylene bags. Rubber rings in PE bags and nuts, bolts etc. shall be supplied in separate jute
bags. The fittings should also be supplied by the manufacturer of the pipes. They should preferably
be
manufactured by the manufacturer of the pipes. In case they are not, it will be the responsibility
ofthe manufacturer of the pipes to have them manufactured from a suitable manufacturer under it’s
own supervision and have it tested at his/sub contractors premises as per the contract. The pipe
manufacturer will however be responsible for the compatibility and quality of the products.
Mode of Measurement –
Payment shall be made on number basis.

9.3 Specification
9.4 specification

All Socket Tee-


Double socket Tee with Flange Branch -PN-10-

General : The item provides to supply at departmental store the Cast Iron easy link mechanical
joint of D.I. tees suitable for use in D.I. pipe lines with suitable D.I. gland, sealing rubber gasket
(IS:5382/1985) and nut bolts with rings etc. complete as per the specified diameter of pipe / pipes.
(Dia. between 80 mm & 400 mm).

Page 134 Tender ID - 31688


The Tees may be with-
1) with all sockets and
2) with Double socket Tees with Flanged branch and they shall conform the provisions of IS: 1538-
1993 and IS 5382-1982
Material : All Ductile iron specials such as D.I. easy link mechanical joint of D.I. tees shall confirm
to I.S. 1538- 1993 (Part 1 to 24). The Supply at departmental stores shall be of various diameters
as specified. The specials shall be free from any defects. It should be possible to cut/drill the
special to suit site conditions to fit in the position etc. The hardness of the external surface shall not
exceed 210 HBS. Sealing Rings shall confirm to IS 5382-1985. Ring shall be homogeneous and
free from porosity, grit and surface defects, such as pitting, irregularities. Dimension of rings shall
be as per IS 10292- 1988.
Manufacture : The dimensions of easy link mechanical joint of D.I. tees shall be as per Tables 14 &
15 of IS 1538-1993, for Tees with all sockets and Double socket Tees with Flanged branch,
respectively.
Mode of Measurement –Payment shall be made on number basis.

9.5 Specification
Flange Socket-

General : The item provides to supply at departmental store the DI easy Flange Socket piece
suitable for D.I. pipes including suitable D.I. gland, sealing rubber gasket etc. complete as per the
specified diameter of pipe / pipes. (Dia. between 80 mm & 750 mm). The joints shall conform the
provisions of IS: 1538-1993 and IS 5382-1985
Material : All Ductile Iron specials such as D.I. easy link mechanical joint of Flange Socket piece
shall confirm to I.S. 1538- 1993 (Part 1 to 24). The Supply at departmental stores shall be of
various diameters as specified. The specials shall be free from any defects. It should be possible
to cut/drill the special to suit site conditions to fit in the position etc. The hardness of the external
surface shall not exceed 210 HBS. Sealing Rings shall confirm to IS 5382-1985. Ring shall be
homogeneous and free from porosity, grit and surface defects, such as pitting, irregularities.
Dimension of rings shall be as per IS 10292- 1988.
Manufacture : The dimensions of sockets, flanges, drilling holes and nut & bolts shall be as per
Tables 2, 3, 4, 5 & 6 of IS 1538-1993. 8.4 Supply and Stacking at Departmental Store : As
specified under agreement.
Testing : The fittings shall be tested for:
1. Tensile Test : Minimum Tensile strength of 150 MPa.
2. Brinell Hardness Test : shall not exceed 210 HBS.
3. Hydrostatic Test : As per IS: 1538-1993, which shall be: For Dia. upto and including 300 mm -
2.5 MPa. Dia over 300 mm & up to & include 600 mm - 2.0 MPa. Dia over 600 mm - 1.5 MPa.

Page 135 Tender ID - 31688


Markings : Each fitting shall have cast stamped or indelibly painted on it the following markings:
1. Manufacturer’s Name or trademark or identification mark.
2. The nominal diameter,
3. Mass of fitting,
4. Last 2 digits of year of manufacture,
5. Any other mark required by the purchaser.
Item to Include : The item includes the supply of Cast Iron easy link mechanical joint of socket and
flanged tail piece suitable for D.I pipes including cost of suitable D.I. gland, sealing rubber gasket,
including all taxes, levies except octroi, transporting, loading, unloading and stacking at
departmental store as directed. The necessary test certificate also shall be provided along with the
supply.
Mode of Measurement and Payment : The measurement and payment shall be made per No.

10 Providing erecting Cast Steel/ Spheroidal Graphite (S.G) Iron D/F Sluice Valves
/ Butterfly Valves with jointing to pipe work (including all hardware and packing)
water works quality, having non-rising spindle with hand wheel and without bypass
arrangement, spindle of stainless steel as per requirement, inspection charges,
transportation upto departmental store, unloading, stacking, excluding GST levied
by GOI & GOM in all respect etc. excluding C. C. foundation / structural steel
support.
10.1 A) For Rating Class 150 (Working Pressure 20 kg/cm2 and Test Pressure 30
kg/cm2)
10.1.1 Sluice Valves. CS-150
10.1.1.1 200 mm dia.
Specification:
Specification:
These specifications cover general provisions and requirements and are supplementary to the
General conditions of contract.

GENERAL –
The Sluice Valves proposed to be procured through this tender are to be used for drinking water
supply schemes under execution.

WORK UNDER THIS CONTRACT –


The work entitled manufacture, supply and delivery of Sluice valves for transmission mains shall
comprise the manufacture, supply and delivery of the goods as mentioned in the Bill of Quantities.
The manufacturer of sluice valves should be from MIDCs approved list

NOTE –
The above goods to be used for conveyance of potable water at temperatures varying from 10
degree centigrade to 40 degree centigrade.

Page 136 Tender ID - 31688


The tender price shall include all labour and machinery and all materials necessary for the proper,
manufacture of the goods, for tests at the contractor’s works for the insurance and for delivery to
works for the proper maintenance and for discharging every obligations and requirement of the
contract, in accordance with the intent of the contract documents, as stated in the General
Conditions of Contract.
a) Sluice Valves PN 1.0 of IS: 2906 /14846
(Latest version) of various sizes,
ranging from 150 mm to 800 mm.
As per schedule B of the item

STANDARDS –
Where reference is made to a particular standard, it shall be the latest revision of the Indian
Standard Institution. Unless otherwise specified, the sluice valves shall be in accordance with the
provisions of IS:780:1980 and IS:2906:1984 or sizes of the sluice valves covered under relevant
standards.

MARKING OF SLUICE VALVES –


Each sluice valve shall be marked as per IS:780:1980, Para-II for sizes and IS:2906:1984, (Latest
version) of various sizes, ranging from 150 mm to 800 mm.

PACKING AND HANDLING –


The contractor shall dispatch from the manufacturer’s works goods adequately protected to
prevent damage and deterioration during transportation and storage, etc. The packing is to be
quite robust to withstanding rough handling during the transit by road/ rail/ sea and storage. Each
package / create will contain sluice valve of one size only in relevant class. The packing procedure
followed shall be in accordance with para 12 of IS:780:1980 and para 12.1 of IS:2906:1984
The contractor shall use proper handling equipment or follow suitable handling method as
approved by the Engineer to unload the materials at the delivery site to prevent damage to the
goods and equipments.Third party inspection from agency approved by MIDC should be carried
out at contractor’s cost
only. The contractor should produce manufacturer’s test certificate conforming that the valves have
been tested in accordance with I.S. specifications, stating the actual pressure and the medium
used in the test. The design workmanship, material, strength and dimensions of all parts shall be
as per I.S.S. The product shall be of proven quality rendering reliable service during maintenance
and requirement.

THIRD PARTY INSPECTION –


Third party inspection shall be carried from MIDC approved agencies.
The valve shall be tested in factory by third party in presence of MIDC representative.
1.1.Review of martial of construction

Page 137 Tender ID - 31688


2.b Overall dimension of all component
3.c. Hydraulic testing.
The cost of valves should be including all taxes (Central & Local) railway freight, transportation
upto site of work or departmental store including loading unloading etc.

MODE OF MEASUREMENT – This item will be measured and paid as per Number basis. 80%
payment shall be payable after supply, 20% payment shall be payable after lowering, laying and
jointing.

11 Providing double flange sluice valve confirming for IS- 14846 including worn
gear arrangements as per test pressure, stainless steel spindle, caps, including
inspection charges, transportation upto departmental store, unloading, stacking
excluding GST levied by GOI & GOM in all respect etc. complete.
11.1 Sluice valve - PN - 1.6 (With by pass arrangement)
11.1.1 80 mm.
Specification:
Specification: The item provides for supplying, fixing in position and jointing C.I. Sluice Valves,
Class-I type both end flanged (without hand wheel). The Sluice valves are designated according to
Nominal Pressures ( PN ) for the maximum working pressure in MPa.

A] CI Sluice valves confirming to IS:2906-1969, PN-0.6 (Suitable for working pressure of 6


kg/cm2)

B] CI Sluice valves confirming to IS:14846-2000, PN-1.0 (Suitable for working pressure of 10


kg/cm2)
i) Conforming to I.S. 14846-2000 for 50 to 300 mm dia. CI Sluice valves confirming to IS:2906-
1969 - PN-1.0 (Suitable for working pressure of 10kg/cm2)
ii) Conforming to I.S. 2906-1969 for 350 to 900 mm dia.

C] CI Sluice valves confirming to IS:14846-2000 - PN-1.6 (Suitable for working pressure of


16kg/cm2)
Material : Sluice Valves The material for different components of sluice valves shall be according
to Table No.1 of respective IS codes referred above.

Manufacturing : The sluice valves are used in a pipe line for controlling or stopping flow of water.
These shall be of specified size and class and shall be of inside non-raising screw type up to
300mm size and raising or non-raising screw type above 300mm with eitherdouble flange. The
manufacturing shall in all respects comply with the Indian Standard Specifications IS : 780 and IS
14846. The body, domes covers, wedge gate and stuffing box shall be of good quality cast iron,
the spindle of chrome steel, the nut and valve seats of leaded tin bronze. The bodies, spindles and
other parts shall be truly machined with surface smoothly finished. The area of the water-way of
the fittings shall be not less than the area equal to the nominal bore of the pipe. Bypass

Page 138 Tender ID - 31688


arrangements for the sluice valves above 350 mm nominal sizes shall be provided according to
clause 6.14 of IS : 2906-1984.

Hydrostatic Tests : Each valve shall be tested as described in the respective IS codes. The valve
shall not show any sign of leakage and/or sweating under test. The valve shall be tested for closed
end and open end. The stems shall also be tested for “flaw detection”
Marking : The sluice valve shall be marked with the following information in raised letters: 1. The
manufacturer’s name or trade mark, 2. The designated Nominal Pressure, 3. The nominal size of
the valve, 4. Serial Number, 5. The arrow to show the direction of turn for closing of the valve,

Transportation & Storage : The valve shall be properly packed to protect all parts from damages
and also from rusting. Valves shall be stored near to the work site, in closed stores and protected
against dust before it is actually placed in the position and jointed.
1.8 Item to include: 1. Supply of Sluice valve of designated class and nominal size, at the site of
work, including transporting and loading – unloading etc., manually or by engaging crane wherever
required without any additional cost.

Mode of Measurement and Payment : The contract rate shall be for one number of valve of the
designated class and size and for supply and jointing etc. complete as specified, under.
a) On supply of Sluice Valve with all accessories - 70% b) On satisfactory testing on line - 30%

12 Lowering, laying and jointing in position following C.I.D/F Reflex valves,


Butterfly valves and Sluice valves including cost of all labour jointing material, including
nut bolts and giving satisfactory hydraulic testing etc. complete. (Rate for all class of
valves.)
12.1 Lowering,laying and jointing in position following C.I.D/F Reflex valves, Butterfly
valves and Sluice valves
12.1.1 80 mm.
Specification:
Specifications-
General :
Valve should be lowered into the trench with tackle suitable for the weight of valve. For smaller
sizes, up to 200 mm nominal bore, the valve may be lowered by the use of ropes but for heavier
pipes suitable mechanical equipment have to be used. All construction debris should be cleared
either before or just after a joint is made. This is done by passing a pull-through in the pipe, or by
hand, depending on the size of the pipe.

Jointing : Exact location of the Sluice valve shall be got approved from the Engineer-in-charge. The
sluice work to be jointed to cast iron pipes may be joined by means of flanges cast on. The jointing
material used between flanges of pipe shall be compressed fibre board or rubber of thickness
between 3.5 mm to 6 mm. The fibre board shall be impregnated with chemically neutral mineral oil
and shall have a smooth and hard surface. Its weight per m2 shall be not less than 112 gm/mm

Page 139 Tender ID - 31688


thicknesses. Each bolt should be tightened a little at a time taking care to tighten diametrically
opposite bolts alternately. The practice of full tightening the bolts one after another shall not be
allowed.

Item to include:
1. Fixing in position and Jointing the valve in the pipe line at the exact location as per drawing or as
directed by the Engineer – in - charge including all nuts & bolts, packings, labour, tools and
equipments, including taxes
2. Testing the joints.

MODE OF PAYMENT AND UNIT OF MEASUREMENT – The contract rate shall be for one
number of valve of the designated class and size and for supply and jointing etc.

13 Providing and supplying Air Valves as per IS- 14845 and MJP’s standard
specifications double orifice type combined with screw down isolating valve, small orifice
elastic ball resting on a gun metal orifice nipple, large orifice vulcanite ball seating on
moulded seat ring, inlet face and drilled, including insurance, third party inspection
charges, loading, unloading, transportation upto departmental stores, excluding
GST levied by GOI & GOM in all respect etc. complete.
13.1 Air Valve Double Ball Flanged Type - PN -1.6
13.1.1 80 mm.
Specification:
Specification:
The item provides for supply at site or department store and fixing in position and jointing the C.I.
Double Orifice (Ball) Air Valves, without isolating Sluice Valve.

Material : The materials for manufacture of air valve shall be new and as per qualities described
below:

Sr. No Material Specifications

Page 140 Tender ID - 31688


1 Float Chamber, Cowl and cover Grey Cast Iron conforming to IS:
210, less than grade 20 or grade
220 of BS: 1452.

2 Small Orifice float Seasoned Timber ball covered


with soft rubber.

3 Large Orifice float Seasoned Timber ball covered


with hard vulcanite

4 Orifice, Guide and mechanism 12 % chromium steel conforming


to IS : 1570 or stainless steel
conforming to BS : 970 3045-15

5 Sealing Ring Moulded rubber of suitable


quality.

6 Fixing nuts & bolts Conforming to IS: 1363

7 Jointing material Mill board on flanged rubber or


orifice bracket.

8 Spindles 12 % chromium steel conforming


to IS : 1570 or stainless steel
conforming to BS : 970 3045-15.

Manufacturing : The double orifice air valve shall be manufactured with small and large orifices.
The small orifice shall be meant to ensure that accumulated air shall be released by displacement
of valve in working condition of the main. The large size orifice shall ensure high rate of air
discharge when main is being filled in. The buoyant ball shall seal the orifice and the ball shall be
held in the position by the line pressure. The ball shall only leave the seating during fillings and

Page 141 Tender ID - 31688


emptying of the line when the pressure is reduced to about atmospheric pressure. The orifice
sizes, shapes, diameter of the balls, weights, the distribution of the mass of the ball, free board
requirements shall be properly provided. For trouble free operation under specified maximum
working pressure, the balls shall be properly provided in the guides to avoid wobbling of balls.

Flanges and Tapers : The pipe connection flanges of air valves shall conform to IS : 1537. The
tapers for connecting the valve to the main shall be cast in gray cast iron, conforming to IS : 210
grade 25. Both ends of the tapers shall have integrally cast flanges and drilled to suitable size.

Hydrostatic Test : All air valves shall be hydraulically tested at works of manufactures and should
be capable of withstanding a test pressure of 30 kg/cm2 and working pressure of 20 kg/cm2.

Marking : The air valve shall be marked with the following information in raised letters :
1. The manufacturer’s name or trade mark,
2. The designated Nominal Pressure,
3. The nominal size of the valve,
4. Certification / Serial Number,
5.Letters "MIDC"

Transportation & Storage : The valve shall be properly packed to protect all parts from damages
and also from rusting. Valves shall be stored near to the work site or department store, in closed
stores and protected against dust before it is actually placed in position and jointed.
Submittals : The contractor shall furnish,
1. Details of weight and diameter of float required,
2. Discharge capacity curves (pressure against discharge of air)
3. Inflow capacity curves (inflow of air against vacuum pressure)
4. Sealing pressure required for each size of valves.

Item to Include :
1. Supply of Double orifice (ball) valve of nominal size, at the site of work, including transporting,
loading-unloading etc. The item also includes all taxes .
Mode of Measurement and Payment : The contract rate shall be for supply of one number of air
valve of the size and for jointing etc. complete as specified. Payment will be as under :- a) On
supply of air valve and accessories -70% b) On satisfactory testing on line - 30%

14 Lowering, laying and f ixing in proper alignment and position all types of
C.I. air valves as directed by Engineer-in-charge including cost of conveyance from
stores to site of work, cost of all material and giving satisfactory hydraulic testing,
etc. complete.(for all class of valves).
14.1 Air Valve Double Ball (PN-1 and PN - 1.6)
14.1.1 80 mm.
Specification:

Page 142 Tender ID - 31688


Specification:
The item provides for Lowering, laying and fixing in proper alignment and position all types of C.I.
air valves.

Flanges and Tapers : The pipe connection flanges of air valves shall conform to IS : 1537. The
tapers for connecting the valve to the main shall be cast in gray cast iron, conforming to IS : 210
grade 25. Both ends of the tapers shall have integrally cast flanges and drilled to suitable size.

Jointing : Exact location of the valve shall be got approved from the Engineer-in charge. The air
valve to be jointed to cast iron pipes shall be jointed by means of flanges cast on. The jointing
material used between flanges of pipe and valve shall be compressed fiberboard or rubber of
thickness between 3 mm to 6 mm. The fiber board shall be impregnated with chemically neutral
mineral oil and shall have a smooth and hard surface. Its weight per m2 shall be not less than 112
gm/mm thicknesses.
Each bolt should be tightened a little at a time taking care to tighten diametrically opposite bolts
alternately. The practice of full tightening the bolts one after another shall not be allowed.
Several proprietary flexible joints are available for jointing air valve with pipes and these may be
used with the specific approval of the authority, however they shall be used strictly in accordance
with the manufacturer’s instructions.
For joints of valves in small diameter cast iron piping, copper alloy screwed unions or ferrules shall
be used, and for large diameter the joints shall be made by flanged connecting pieces.

Item to Include :
1. Fixing in position and Jointing the valve in the pipe line (excluding isolating valve) at the exact
location as per drawing or as directed by the Engineer-incharge including all nuts & bolts,
packings, labour, tools and equipments.
3. Testing the joints

Mode of Measurement and Payment : The contract rate shall be for supply of one number of air
valve of the size and for jointing etc. complete as specified.

15 Wet Mix Macadam -- Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with water at
OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform
layers with paver in sub- base / base course on well prepared surface and compacting with
vibratory roller to achieve the desired density. Laying By Grader/Paver.
Specification:
Specification-
This work shall consist of laying and compacting clean, crushed, graded aggregate and granular
material, premixed with water, to a dense mass on a prepared subgrade/sub- base/base or

Page 143 Tender ID - 31688


existing pavement as the case may be in accordance with the requirements of these
Specifications. The material shall be laid in one or more layers as necessary to lines, grades and
cross-sections shown on the approved drawings or as directed by the Engineer.

The thickness of a single compacted Wet Mix Macadam layer shall not be less than 75 mm. When
vibrating or other approved types of compacting equipment are used, the compacted depth of a
single layer of the sub-base course may be increased to 200 mm upon approval of the Engineer.

Materials

Aggregates

Physical requirements: Coarse aggregates shall be crushed stone. If crushed gravel/shingle is


used, not less than 90 per cent by weight of the gravel/shingle pieces retained on 4.75 mm sieve
shall have at least two fractured faces. The aggregates shall conform to the physical requirements
set forth in Table 400-10 below.

Aggregate may satisfy requirements of either of the two tests.To determine this combined
proportion, the flaky stone from a representative sample should first be separated out. Flakiness
index is weight of flaky stone metal divided by weight of stone sample. Only the elongated particles
be separated out from the remaining (non-flaky) stone metal. Elongation index is weight of
elongated particles divided by total. non-flaky particles. The value of flakiness index and elongation
index so found are added up.
If the water absorption value of the coarse aggregate is greater than 2 per cent, the soundness test
shall be carried out on the material delivered to site as per IS: 2386 (Part-5).
Materials finer than 425 micron shall have Plasticity Index (PI) not exceeding 6.The final gradation
approved within these limits shall be well graded from coarse to fine and shall not vary from the
low limit on one sieve to the high- limit on the adjacent sieve or vice versa

Construction Operations

Provision of lateral confinement of aggregates: While constructing wet mix macadam,


arrangement shall be made for the lateral confinement of wet mix. This shall be done by laying
materials in adjoining shoulders along with that of wet mix macadam layer

Preparation of mix: Wet Mix Macadam shall be prepared in an approved mixing


plant of suitable capacity having provision for controlled addition of water and forced/ positive
mixing arrangement like pugmill or pan type mixer of concrete batching plant. For small quantity of
wet mix work, the Engineer may permit the mixing to be done in concrete mixers. Optimum
moisture for mixing shall he determined in accordance with IS:2720 (Part-8) afterreplacing the
aggregate fraction retained on 22.4 mm sieve with material of 4.75 mm to22.4 mm size. While

Page 144 Tender ID - 31688


adding water, due allowance should be made for evaporation losses.However, at the time of
compaction, water in the wet mix should not vary from the optimuvalue by more than agreed limits.
The mixed material should be uniformly wet and nosegregation should be permitted.

Spreading of mix: Immediately after mixing, the aggregates shall be spread uniformly and evenly
upon the prepared subgrade/sub-base/base in required quantities, In no case should these be
dumped in heaps directly on the area where these are to be laid nor shall their hauling over a
partly completed stretch be permitted.
The mix may be spread either by a paver finisher or motor grader. For portions where mechanical
means cannot be used, manual means as approved by the Engineer shall be used. The motor
grader shall be capable of spreading the material uniformly all over the surface. Its blade shall
have hydraulic control suitable for initial adjustments and maintaining the same so as to achieve
the specified slope and grade. The paver finisher shall be self-propelled, having the following
features.
(1) Loading hoppers and suitable distribution mechanism (ii) The screed shall have tamping and
vibrating arrangement for initial compaction to the layer as it is spread without rutting or otherwise
marring the surface profile. (i) The paver shall be equipped with necessary control mechanism so
as to ensure that the finished surface is free from surface blemishes.The surface of the aggregate
shall be carefully checked with templates and all high or low spots remedied by removing or adding
aggregate as may be required. The layer may be tested by depth blocks during construction. No
segregation of larger and fine particles should be allowed. The aggregates as spread should be of
uniform gradation with no pockets of fine materials.
Compaction: After the mix has been laid to the required thickness, grade and crossfall/camber the
same shall be uniformly compacted, to the full depth with suitable roller. If the thickness of single
compacted layer does not exceed 100 mm, a smooth wheel roller of 80 to 100 KN weight may be
used. For a compacted single layer upto 200 mm, the compaction shall be done with the help of
vibratory roller of minimum static weight of 80 to 100 KN or equivalent capacity roller. The speed of
the roller shall not exceed 5 km/h.In portions having unidirectional cross fall/superelevation, rolling
shall commence from the lower edge and progress gradually towards the upper edge. Thereafter,
roller should progress parallel to the centre line of the road, uniformly over-lapping each preceding
track by at least one third width until the entire surface has been rolled. Altemate trips of the roller
shall be terminated in stops at least 1 m away from any preceding stop. In portions in camber,
rolling should begin at the edge with the roller running forward and backward until the edges have
been firmly compacted. The roller shall then progress gradually towards the centre parallel to the
centre line of -the road uniformly overlapping each of the preceding track by at least one-third
width until the entire surface has been rolled.
Any displacement occurring as a result of reversing of the direction of a roller or from any other
cause shall be corrected- at once as specified and for removed and made good. Along forms,
kerbs, walls or other places not accessible to the roller, the mixture shall be thoroughly compacted
with mechanical tampers or a plate compactor. Skin patching of an area without scarifying the
surface to permit proper bonding of the added material shall not be permitted. Rolling should not

Page 145 Tender ID - 31688


be done when the subgrade is soft or yielding or when it causes a wave-like motion in the sub-
base/base course or subgrade. If irregularities develop during rolling which exceed 12 mm when
tested with a 3 metre straight edge, the surface should be loosened and premixed material added
or removed as required before rolling again so as to achieve a uniform surface conforming to the
desired grade and crossfall. In no case should the use of unmixed material be permitted to make
up the depressions.Rolling shall be continued till the density achieved is at least 98 per cent of the
maximum dry density for the material as determined by the method outlined in IS: 2720 (Part-8)
After completion, the surface of any finished layer shall be well-closed, free from movement under
compaction equipment or any compaction planes, ridges, cracks and loose material. All loose,
segregated or otherwise defective areas shall be made good to the full thickness of the layer and
recompacted.

Setting and drying: After final compaction of wet mix macadam course, the road shall be allowed to
dry for 24 hours.
Opening to Traffic Preferably no vehicular traffic of any kind should be allowed on the finished wet
mix macadam surface till it has dried and the wearing course laid.
Quality control: Control on the quality of materials and works shall be exercised by the Engineer in
accordance with Section 900.
Rectification of Surface Irregularity
Where the surface irregularity of the wet mix macadam course exceeds the permissible tolerances
or where the course is otherwise defective due to subgrade soil getting mixed with the aggregates,
the full thickness of the layer shall be scarified over the affected area, re-shaped with added
premixed material or removed and replaced with fresh premixed material as applicable and
recompacted in accordance with Clause 406.3. The area treated in the aforesaid manner shall not
be less than 5 in long and 2 m wide. In no case shall depressions be filled up with unmixed and
ungraded material or fines.
Arrangement for Traffic During the period of construction, arrangement of traffic shall be done as
per Clause
Measurements for Payment
Wet mix macadam shall be measured as finished work in position in cubic metres.

16 Providing and applying tack coat on the prepared surface heating by fames in Boiler
and spraying bitumen set footed in bitumen boller on B.T. surface 2.5 kg/10 sqm.(VG-30
bulk bitumen rates are considered to arrive at rates)
Specification:
General : The item pertains to providing and spraying bituminous tack coat over WMM surface
or Bituminous surface.

Material : Asphalt or bitumen shall be straight run conforming to IS:73 or industrial bitumen as
per IS: 702 of suitable consistency satisfying the requirement of physical properties as given in

Page 146 Tender ID - 31688


table below
PHYSICAL PROPERTIES OF BITUMEN
( physical properties as per IS 73: 2006)

Sr. No. Characteristics Requirements Method of

Test

1 Penetration at 250 C in 20 to 40 IS: 1203

1/10 mm

2 Softening point (R&B) 50 to 90 IS: 1205

3 Ductility at 270 C (Min. 3 IS: 1208


is

cms)

4 Loss on heating percent 1 IS: 1212

(Maximum)

5 Solubility in CS2 percent 99 IS: 1216

(Minimum)

Page 147 Tender ID - 31688


Spraying Tack Coat :
Preparation of Base :
The surface on which the tack coat is to be applied shall be cleaned of dust and any extraneous
material before the application of the bitumen binder, by using a mechanical broom or any other
approved equipment/method as specified by the Engineer-in-charge.

Application of Binder :
In bitumen shall be heated to the temperature ranging 150° to 160° C. appropriate to the grade of
bitumen used and approved by the Engineer-in-Charge and sprayed on the base at the rate
specified in Table below. The rate of spreading is in item of straight run bitumen.
RATE OF APPLICATION OF TACK COAT

Type of surface Bitumen quantity in kg per 10 m2 area

WBMSurface treated with primer 11kg as specified

Bitumen Surfaces. 3/2.5 kg as specified

The bitumen shall be applied uniformly with the aid of either self propelled or towed bitumen
pressure sprayer with self heating arrangement and spraying bar with nozzles having constant
volume or pressure system capable of spraying binder at specified rates and temperature so as to
provide a uniformly unbroken spread of bitumen. The tack coat shall be applied just ahead of the
on coming bituminous construction.
Item to Include : The item includes supplying and laying of bituminous tack coat etc. according to
the details mentioned in this specification and as per directions of Engineer-in-Charge, including
heating all material, labour, transportation, tools, including all taxes, duties, octroi etc., equipment
and machinery.
Mode of Measurement and Payment : Tack coat shall be measured in terms of surface area of
application in square meter. The rate shall be per sqm of area of spraying tack coat.

17 DENSE BITUMINOUS MACADAM: Proving and laying dense bituminous macadam


using crushed aggregates of Grading 1, premixed with bituminous binder of specified grade
of Bitumen @ 4.50 per cent by weight of total mix and filler, transported to site with VTS ,
laid over a previously prepared surface, finished to the required grade, level, alignment, and
rolling to achieve the desired density for 76-100 mm compacted thickness .USING Batch

Page 148 Tender ID - 31688


mix type hot mix plant with SCADA, Sensor Paver, Vibratory roller with Stone Dust
filler.(VG-30 bulk bitumen rates are considered to arrive at rates)
Specification:
Specification:
General : The work shall consists of construction, in a single course, of compacted crushed
aggregates premixed DENSSE bituminous macadam, to serve as base / binder course, laid
immediately after mixing, on a base prepared previously in accordance with the requirement of
these specifications and in conformity with the line, grades and cross sections shown on the
drawing or as directed by the Engineer-in- Charge.
Material : Bitumen : The Bitumen shall be paving bitumen of suitable penetration grade 30/40 or
60/70 as per Indian Standard Specification for “Paving Bitumen” IS: 73-1961. 17.2.2 Aggregates :
The aggregate shall consists of crushed stone, crushed gravel, shingle or other strong, durable
fairly cubical shape and free form disintegrated pieces organic or other deleterious matters and
adherent coating. The aggregate for bitumen macadam shall conform to the grading given in Table
below :
(As per IRC:94-1986)
Table AGGREGATE GRADING OF DENSE BITUMINOUS MACADAM
Sieve Designation Grading number
37.5 mm – 100
26.50 mm 100
85-100
19.00 mm 85-100 71-95
13.20 mm 63-82 58-82
9.50 mm 52-74 52-72
4.75 mm 39-54 35-50
2.36 mm 28-43 28-43
0.60 mm 15-27 15-27
0.3 mm 7-21 7-21
0.15 mm 5-15
5-15 0.075 micron 2-8 2-8
Bitumen Content 4.5% 4.5%
Note: - For compacted thickness upto 50 mm, grading 1 will only be used, while as for thickness
greater than 50 mm, grading 2 could be used. The maximum thickness of any single shall not be
more than 75mm.
Binder Content : The binder bitumen content shall be so decided as to achieve the design
requirements of the mix set forth in Table. The Marshall method for arriving at the binder content
shall be adopted.
Job Mix Formula : The contractor shall intimate to the Engineer-in-Charge in writing, at least 20
days before the start of the work, the job mix formula proposed to be used for the work and shall
give the following details

Page 149 Tender ID - 31688


: a. Source and location of all materials.
b. Proportions of all materials expressed as follows where each is applicable Binder bitumen 4.5%
- as percentage by weight of total mix. Coarse aggregate - as percentage by weight of total
aggregate Fine aggregate - including mineral filler
c. A single definite percentage passing each sieve for the mixed aggregate.
d. The results of test enumerated in Table as obtained by the Contractor
e. Test results of physical characteristics of aggregates to be used
f. Mixing and compacting temperature
While working out the job mix formula, the Contractor shall ensure that it is based on a correct and
truly representative sample of the materials that will be used actually in the work and that the mix
and its ingredients satisfy the physical and strength requirements of these specifications. Approval
of the job mix formula shall be based on independent testing by the Engineer-in-Charge for which
samples of all ingredients of the mix shall be furnished by the Contractor as required. The
approved job mix formula shall remain effective unless and until modified by the Engineer-
inCharge. Should a change in the source of materials be proposed, a new job mix formula shall be
established and got approved from the Engineer-in- Charge before actually using the mix and
materials.
Permissible Variations from the Job Mix Formula .The Contractor shall have the responsibility of
ensuring proper proportioning of materials in accordance with the approved job mix formula and
producing a uniform mix. The permissible variations of the individual percentages of the various
ingredients in the actual mix from the job mix formula may be within the limits as specified in Table
below. These variations are intended to apply to individual specimens taken for quality control
tests.
Table
PERMISSIBLE VARIATIONS FROM THE JOB MIX FORMULA
Sr. No.
Sieve Size Permissible Variations Base/binder Course
13.2 mm and larger
9.5 mm and 4.75 mm
2.36 mm and 1.18 mm,
0.6 mm and 0.30 mm
0.15 mm 0.075 mm
Binder content
+ 8%
+ 7%
+ 6%
+ 5%
+ 4%
+ 3%
+ 0.5%

Page 150 Tender ID - 31688


Proportioning of Material : The bitumen content for premixing shall be 4.5% by weight of the total
mix except when otherwise directed by Engineer-in-Charge. The quantities of the aggregates to be
used shall be sufficient to yield the specified thickness after compaction.
Variation in Proportion of Material : The contractor shall have the responsibility for ensuring proper
proportioning of materials and producing a uniform mix. A variation in binder content ± 0.3% by
weight of total mix shall however, be permissible for individual.
Construction Operations :
General : The work of laying shall not be taken up during rainy or foggy weather or when the base
course is damp or wet, or during dust storm or when the atmospheric temperature in shade is 150
or less.
Preparation of the Base : The base on which bituminous macadam is to be laid shall be prepared
shaped and conditioned to the specified lines, grades and cross sections and a priming coat shall
be applied.
Preparation and Transport of Mix : Bituminous macadam mix shall be prepared in hot mix plant of
adequate capacity and capable to yield a mix of proper and uniform quality with thoroughly coated
aggregate. The plant shall have co-ordinated set of essential units capable of producing uniform
mix within the job mix formula.

MANUFACTURING AND ROLLING TEMPERATURES Bitumen Peutratia

Bitumen Mixing (°C) Aggregate

Mixing (°C) Mixed

Material (°C) Rolling

(°C) Laying

(°C) 35 160-170 160-175 170 Max. 100 Min. 130 Min.

65 150-165 150-170 165 Max. 90 Min. 125 Min

. 90 140-160 140-165 155 Max. 80 Min. 115 Min.

The mix shall be transported from the mixing plant to the point of use in suitable tipper vehicles.
The vehicles employed for transport shall be clean and be covered over in transit if so directed by
the Engineer-in-Charge.

Spreading : The mix transferred from the tipper at site to the paver shall be spread immediately by
means of self propelled mechanical paver with suitable screeds capable of spreading, tamping,

Page 151 Tender ID - 31688


and finishing the mix true to the specified lines,grades and cross sections. The paver finisher shall
have the following essentials feature : a) Loading hoppers and suitable distributing mechanism. b)
All drives having hydrostatic drive/control. c) The machine shall have a hydraulically extendable
screed for appropriate width requirement. d) The screed shall have tamping vibrating arrangement
for initial compaction to the layers as it is spread without rutting or otherwise marring the surface. It
shall have adjustable amplitude and infinitely variable frequency. e) The paver shall be equipped
with necessary control mechanism so as to ensure that the finished surface is free surface
blemishes. f) The paver shall be fitted with an electronic sensing device for automatic leveling and
profile control within the specified tolerances. g) The screed shall have the internal heating
arrangement. h) The paver shall be capable of either 2.5 to 4.0 m width to 4.0 to 7.0 m width, as
stipulated in the contract. i) The paver shall be so designed as to eliminate skidding/slippage of the
tyres during operation. However, in restricted locations and in narrow widths where the available
plant cannot be operated in the opinion of the Engineer-in-Charge, he may permit manual laying of
the mix. The temperature of the mix at the time of laying shall be in the range of 1200 C to 1350 C.
In multi layer construction the longitudinal joint in one layer shall offset that in the layer below by
about 150 mm. However, the joint in the top most layer shall be at the centerline of the pavement.
Longitudinal joint and edges shall be constructed true to the delineating line parallel to the central
line of the road. All joints shall be cut vertical to the full thickness of the previously laid mix and the
surface painted with hot bitumen before placing fresh material.

Rolling : After the spreading of mix, shall be thoroughly compacted by rolling by set of rollers at
speed not more than 5 km per hour, immediately following close to the paver. The initial or
breakdown rolling shall be with 8 to 12 tonns vibratory roller or other approved equipment. Rolling
should start as soon as possible after the material has been spread. Rolling shall be done with
care to keep from unduly roughening the pavement surface. Rolling of the longitudinal joints shall
be done immediately behind the paving operation. After this the rolling shall commence at the
edges and progress towards the center longitudinally except that on super elevated portions it shall
progress from the lower to the upper edge parallel to the central line of the pavement. The initial or
break down rolling and final rolling shall be done, with 8 to 10 tonnes static weight smooth (3wheel
steel roller or tandem) as soon as it is possible to role the mix without cracking the roll surface or
having the mix pick up on the roller wheels. The second or intermediate rolling shall follow the
breakdown rolling with vibratory roller of 8-10 tonne static weight as closely as possible to the
paver and be done while the paving mix is still at a temperature that will result in maximum density.
The final rolling shall be done while material is still workable enough for removal of roller marks
with 8 to 10 tonnes static weight. During the initial or break down rolling and final rolling, vibratory
system shall be switched off. The joints and edges shall be rolled with 8 to 10 tonne static roller.
When the roller has passed over the whole area once, any high spots or depressions, which
become apparent shall be corrected by removing or adding mix material. The rolling shall then be
continued till the entire surface has been rolled to 98% of the average laboratory density
compaction, there is no crushing of aggregates and all roller marks have been eliminated. Each
pass of the roller shall uniformly overlap not less than one-third of the track made in the preceding

Page 152 Tender ID - 31688


pass. The roller wheel shall be kept damp if necessary to avoid bituminous material from sticking
to the wheels and being picked up. In no case shall fuel-lubricating oil be used for this purpose, nor
excessive water poured on the wheels. Rolling operations shall be completed in every respect
before the temperature of the mix falls below 800 C. Roller(s) shall not stand on newly laid material
while there is risk that it will be deformed thereby. The edges along and transverse of the lean
bituminous macadam laid and compacted earlier shall cut to their full depth so as to expose fresh
surface which shall be painted with a thin coat of appropriate binder before the new mix is placed
against it.

Item to Include : The item includes providing all material, all labour, plant for heating asphalt,
mixing plant, trolley/truck/dumper, vibratory roller, paver finisher, tools and equipment required to
carry out the work as per specifications.

Mode of Measurements and Payment : The dense bituminous macadam of specified thickness
shall be measured as finished work in Square Meters. The contract rate shall be per Sq. Mtr. and
shall be paid after satisfactory completion of work as per the specifications.

Page 153 Tender ID - 31688


Signed By : PRAKASH BIRBAL CHAVAN

Organisation Unit : MAHARASHTRA


INDUSTRIAL
Signed Date DEVELOPMENT
: 18/10/2023
CORPORATION

Page 154 Tender ID - 31688

You might also like