AUICO KUWAIT
ea "ALICO KUWAIT
‘Quantitative Risk Assessment
Project Ne
iProject Name: Hessah Al -Mubarak plot Number-161
Ref: No AL/RA/CR/0026
Assessment Location: Hessah 161 site
‘Assessor Nam
Maju Thomas /Rasheed/Afsal
Description of work: Cradle Erection &Usage for Peripheral Clading Work
Ttem | Activty/ | Hazard/eondiion hat | Consequence safety Precautions Needed to control the Rsk tO ALARP] Residual Wesporsiole
Equipment | could develop Hazards Person
Manual Handling s up top 15 KG only
Proper access and egress for the bracket
fixing Area
+ Use rated & approved brackets and anchor|
bots capable for for load withstanding as per
lapproved design.
+ bracket must be fix on concrete wall or
floor aya competent person.
+ Use retroactive lifeline and Full body
harness for personal protection for rated
cradte | Falling of material, rope fixing on Bracket. and edge work, i Site
1 | cretion | Falingof personal, | 4 c + Cradle shall be fix as per manufacturer Supervisor
Property Damage instruction, /setary tier
+ Ensure competent supervision
|+Rope shall be protected from the edges to
lavoid deterioration.
Use crippling eye wire rope or minimum 3
bul dog clamp for suspended load.
suse buddy system,
/sBarricade the underneath area while
Jerecting and use signage's
Alico Kuwait QRA 8/5/2021,‘ALICO KUWAIT
Defective Cradle
All the cradles shall be third party inspected
and certified.
Obtain permit from Main contractor.
/*Conduct Pre use inspection by using
icheckIst.
|*Conduct Pre Use TBT.
+ Opeartor shall be Trained and Authorized.
+ D0 not use in adverse weather condition
+ Make sure of Cradle service sticker
site
Supervisor/S
afety Officer
Alico Kuwait QRA
}
i
> Erected by @ Competent Authorized perosn.
+Visual Inspection Before use.
+ Dedicated separate electrical power.
+ concuct Trail lift by checking primary break
Jand secondary emergency break.
+ Barricade the usage zone with signage's.
Do not stand under the force of gravity.
|+Suspended ropes shall be protected from
[sharp edges.
isplay of SWL.
Load shall evenly distributed inside the
platform.
» All electrical swltiches emergency switches
manual system must be inspected before
use, Must not be Over loaded.
site
Supervisor
SOP | /satety officer
8/5/2021,~ ALICO KUWAIT
|Full body harness connected to a Separate
Life line from a Seperate Bracket and fall
Jarrestor grab for each worker for Harness.
Snchoage.
5 | Satandared Safety net shall be fixed above:
: or rd
s Maer shall be socured inside the cade, as
3 febardanioahtrstosaaw undeenont eee] _ ste
4 a ° Proper acer and agrees Aesop} Enaneer/
2 |*Platform always clean and free of debries. 58 Supervisor
£ Scour at must ot be removed and act.
. 3 se proper glows, las suléng machine
g = |for handling Glasses and materials.
2
g
a z /-weather forecast must be
io 5 communicated to the work force.
5 + work shall not be conducted during a
. 2 Z extreme weather condition i co
g strom strong wind, thick fog Safety officer
¢
2
a Folew proper menus handing procedure
el saved pinch points =
6 ui c superse
ig Ale S0P safety Officer
3
pA ico Kuwait
Tasca wanemae j alo Fae Maja Thomas
Alico Kuwait QRA
HSE - Deparlment
8/5/2021Project No:
Project Name : Hessah Al Mubrak Distric Plot
Quantitative Risk assessment Ref: No:
AL/RA/HM/026
Location: Hessah Al- Mubrak Plot no-161
Safety Risk Evaluation matrix
Risk category
Very Unlikely (A)
Unlikely
Frequent
Control regime
a
[The activity shall not be carried out as the Risk is intolerable/unacceptable. Adequate
Icontrol measures shall be be established to bring the risk levels to at least 'Medium’
lbefore the activity can be performed. Such additional control measures must be in place|
before the activity can commence.
|The Risk is tolerable. The activity shall be further analyzed to determine if any
ladditional control measures are required. If required, such ad
[shall be established before the activity can be performed.
jonal control measures
IThe Risk is acceptable. No additional control measures will be required.
> Maju Thomas
HSE - Department