Professional Documents
Culture Documents
Gas Pipileline Info
Gas Pipileline Info
Gas Pipileline Info
Malaysia’s Peninsular Gas Utilization (PGU) pipeline network is the backbone of the transmission of
natural gas in Peninsular Malaysia. In operation since the early 1980’s sourcing gas from offshore
Terengganu, the network has been aggressively expanded in the 1990’s to supply 2 Bscfd of gas to
major customers in Peninsular Malaysia.
PETRONAS Gas Berhad (PGB) has conducted an integrity study for the oldest PGB pipelines i.e. 36” sales
gas, 8” propane and 8” butane pipelines located at Kerteh, Terengganu. The pipelines are inspected via
in-line inspection to ascertain the conditions, and the periods of inspection are as follows:
• 36” sales gas – in year 1994 and 2002
• 8” propane and butane – in year 1996, 2001 and 2006
Abstract of Papers (cont’d):-
PGB also carried out root cause analysis (RCA) to analyze in detail the problems and issues faced by the
pipelines. From the investigations, it is evident that the external corrosion control from KP 8 to KP 22 is
not effective due to the environment that the pipelines are located. The pipelines are located in
graphitic, rocky and hard soil areas where there is virtually no electrolyte to transmit ICCP current to
protect the pipelines. The rocky and hard soil also induced damages to the coating i.e. disbondment,
cracking, peeling, wrinkling etc.
Abstract of Papers (cont’d):-
Few options have been studied to solve the root causes of the problem and the one that deem feasible
is replacement of the pipelines from KP 8 to KP 22 and relocate that portions to Loop 1’s Right Of Way
(R.O.W) which is less hilly without rocky and hard soil thus good soil for ICCP system.
Based on corrosion rates derived from integrity studies performed in 2001 and 2006, the 8-inch
propane and 8-inch butane have remaining life of less than 3 years. Similarly, the 36-inch sales gas
pipeline has 15 years remaining life. The remaining life is calculated based on a “do-nothing” approach.
There are many challenges while executing the project which will be shared during the presentation.
The presentation will share the experience of PGB in tackling the problems through its in house
technical capabilities. Among the key items are:
• Tools in executing detail designs
• Experienced of the team
• Changes in the route during detail design
• Authorities requirements
• Correct assessment of the site
8” PGU I Butane Pipeline
Relocation Project
- The Challenges
11-12th October 2011
7th Asian Pipeline Conference and Exhibition
All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by
any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.
Objective
Telok Kalong
To protect from corrosion, they were coated
Export
Regulating
Terminal with coal tar enamel coating and equipped with
Station
impressed current cathodic protection (ICCP)
system.
Rocky, Hilly and Dry terrain of PGU I with sample of Graphitic rocks found at the
locations along Right of Way (ROW)
A World Class Gas and Utilities Company
Rocky and hard soil conditions on all hilly areas of
PGU I ROW
Hard Soil below the pipe that repair crew needed to hack and loosen out using
hydraulic hacking machine.
A World Class Gas and Utilities Company
The rocky and hilly conditions induced various types
of damages to the coating
Coating Damage i.e. coating break due to pipeline resting on rock
Pipeline
Graphitic rocks
CIPS 2007
3.00
2.50
Potential (mV)
2.00
1.50
1.00
0.50
0.00
0 12 24 36
Chainage (km )
CIPS results show that Cathodic Protection (CP) under protection mostly at hilly
areas. Issue of CP under protection has been prolonged for 10 years at least
despite mitigations that we have performed i.e. ICCP upgrading and sacrificial
anode installation.
Check
Weld Number
Compare to Welding Book
for Confirmation
Continuous Supply to
customers. Short
duration of windows
given by Producers
(GPPs)
Liquid arrangement
Customers’ different
requirements
Abandon C4 Pipeline
between KP 8 to KP 24
KP 24
Location of
Seasonal Swamp
What we do ???
Swampy area:
Pipe transferred using Mechanical Plug insertion and enough for pipe buoyancy.
Pipe transferred using pulling by excavator.