Professional Documents
Culture Documents
Qaal
Qaal
CONTENTS
Tables
4.1.1 – Purge Times.......................................................................................23
4.1.2 – Level 2 Shutdown from Fire and Gas Initiation...................................31
4.1.3 – 222-LSHHH-1 Trip Reset ...................................................................40
4.1.4 – 222-LSLLL-5 Trip Reset .....................................................................40
4.1.5 – 222-PSL-105/PSH-106 Trip Reset .....................................................41
4.1.6 – 222-PSL-153 Trip Reset.....................................................................42
1.1 INTRODUCTION
With the potential for fire and explosion, the shutdown logic ensures that plant
and equipment shuts down in a safe manner and all safety conditions must
be met before it can be reset and restarted. For an overall view and
understanding of the Shutdown Philosophy refer to the following illustrations:
Note: For further details of specific fire and gas input signals and output
actions associated with the shutdown system refer to Chapter 5.
The ESD logic on the South Satellite Platform (SSP) is divided into four levels
to reflect the level of risk to the entire platform. They range from a total
platform shutdown and power failure to relatively minor, equipment specific
process stops. The different levels of shutdown are detailed below:
On SSP (and NSP) there is only one depressurised Level 1 Shutdown and is
initiated by the following:
In the event of a Level 1 Shutdown the only equipment, which remains live,
is the diesel firewater pump.
Emergency actions to incident and accident will vary from case to case. For all
anticipated types of incidents or Emergencies, ZADCO has Emergency
Response Procedures, which are designed to effectively manage a given
scenario so as to provide maximum protection and safety to personnel,
equipment and the environment.
The Upper Zakum Field Complex, including SSP is controlled and monitored
from Field Control Centre (FCC).
For details of the ZADCO Emergency Response Plan refer to the ZADCO
HSE Procedures Web Site:
http://www.zadco.com/hsee/HSE%20Procedures/New%20Procedures/
ERC-HSE%2003%2001%20FINAL%20May%2018.doc
• Inform FCC
• Maintain contact with the Emergency Control Centre (ECC) at all times
• Co-ordinate any fire fighting action with the Fire and Safety Technician
The Fire and Safety Technician and Muster Checker shall respond as per
their Emergency Team designated duties.
2 BLACK START
2.1 INTRODUCTION
A coincident 60% gas detection inside any of the Modules as detailed in the
following list will cause all electrical supplies to be isolated and a Level 1
De-pressurised shutdown through fire and gas output signal XX-583 into the
ESD system. This situation can be considered as a Black Start condition.
The power supply to the fire and gas panel is also isolated under these
conditions. The power supply is isolated after a time delay of approximately
65 seconds. Only the diesel fire water pump remains running.
• Control Room
Refer to the following illustration for specific details of the gas detection input
devices and output actions, which cause a Black Start condition.
For further details of the various inputs and outputs associated with the fire
and gas system refer to Chapter 5.
Before restarting any plant or equipment that has tripped by shutdown action,
the relevant resets are essential.
Black Start reset can only be conducted onsite and cannot be done remotely.
• Telesystem Engineer
The team shall be equipped with the relevant safety equipment and shall carry
out a preliminary check of SSP to confirm that the situation, which culminated
in the shutdown, is now clear.
The Black Start operating sequence chart shows the main steps that are to be
taken to re-start the platform. For further details refer to:
Consequently, the 22kV electricity supply cable from the Central Complex
cannot be energised until after the electrical sub-station has been purged. In
order to provide power to enable this to be done, it is necessary to use the
Emergency Diesel Generator (EDG).
The EDG room must be checked for hydrocarbons and H2S and if necessary
purged prior to attempting to start the EDG.
Refer to illustration:
The following details provide the necessary information for the start-up of the
Emergency Diesel Generator after Level 1 Shutdown and electrical isolation.
This start-up is part of the overall Black Start Reset procedure as referenced
at Paragraph 2.2 Step 11. For further details of the Emergency Generator
Switchgear Sequence, Emergency Lighting and Black Start Panel refer to the
following illustrations:
• Ensure that fuel oil is available from the Fuel Oil Tank S-002
• Ensure that valves in the Diesel Fuel supply and return lines to the
Essential Services Generator Day Tank S-003 are open
• Ensure that the Cooling Water Header Tank V-021 and Cooling Water
Receiver V-016 for the diesel engine are full
• Oil Pre-heater
• Water Pre-heater
At the EDG Control Panel select the diesel engine controller Normal/Bypass
to Bypass mode. This switch is mounted inside the control panel.
Select the auto-manual selector switch to Manual using HS-242 and start the
EDG using the manual Pushbutton PB-107.
Check the EDG and confirm that the Generator is operating normally and no
alarms are active.
Manually close the main EDG Circuit Breaker and energise the Essential
Services Switchboard and Charger Circuits for Essential Services
Switchboard and Bypass Panel.
Select the auto-manual switch to AUTO mode and Close the following Circuit
Breakers:
• EDG Package
• Lifeboat Package
The Emergency Diesel Generator is now on line and the SSP Black Start
continues from Paragraph 2.2 Step 12.
As soon as the utilities have been purged, the instrument air system may
be operated.
The following details provide the necessary information for the start-up of the
Instrument Air Compressor A after Level 1 Shutdown and electrical isolation.
This start-up is part of the overall Black Start Reset procedure as referenced
at Paragraph 2.2 Step 50.
Air Compressor K-001A and B are supplied from the essential switchboard.
Air Compressor K-001C can only be started once the 22kV supply has been
reinstated and non-essential 380V AC switchboard is normalised.
• Open all compressor drain valves to check for moisture and drain as
required
• Carry out a visual check of the system and confirm that the position of
manual valves on the instrument air system has not been changed
from the operating position at the time of shutdown
• Check that MCC selector switches for all instrument air compressors,
air coolers, cooling water pumps and dryers are in the On position
Bypass shutdown relays inside the local control panel to enable local start
prior to the reset of the shutdown system at PD-1.
Start Cooling Water Pump 222-P-008A and Cooling Water Fin Fan Cooler
222-EM-003A using pushbuttons 222-PB-70 and 222-PB-72 respectively.
Check the operating conditions of the Air Compressor Cooling Water Pump
and Cooling Water Fin Fan Cooler and confirm they are operating normally.
222-K-001B may be started at a later stage in the same way except that the
compressor selector switch 222-HS-246 should be turned to Standby.
Start Instrument Air Dryer 222-V-009A/B autotimer controller. Check that the
dryer sequence is operating correctly and the Dew Point is below -20°F. If the
dew point is not acceptable, open the drain valve at the header ends so that
the instrument headers may be purged.
When the receiver is fully charged, check that the compressor loads and
unloads automatically by the influence of the pressure switches.
The instrument air system is now in operation, operating on power from the
Essential Services Board. Ensure all Shafer actuated valves are reset and
ensure they are operational.
Normalise the deluge system by closing deluge valves that opened if the
instrument air pressure dropped to <50psig.
At this point in the Black Start Reset procedure it can be considered that the
platform and all modules are purged and gas free.
Essential utilities such as HVAC, instrument air and firewater are available.
Electrical Supervisor to give clearance to receive 22kV power from the Central
Complex by closure of the relevant circuit breakers at Central Complex.
The Electrical Supervisor and Technician are responsible for energising the
6.6kV and 380V switchboards from the 22kV supply and the normalisation of
the essential services switchboard.
When 22kV power supply is available and all switchboards are energised with
normal power, the Essential Switchboard bus tie opens. At this stage the EDG
can be stopped.
All electrical switchboards (AC and DC supplies) incoming and outgoing circuit
breakers can be closed.
The telemetry department should check that the Master Terminal Units
(MTUs) are operational and links with the FCC are functioning.
The black start reset is now complete and the utility systems are in normal
operation. The Platform Safety systems and Fire and Gas panel are in normal
operation.
3.1 SHUTDOWN
This selector switch is provided for manned and unmanned status of the
platform.
Specific details of all inputs that will cause a Level 1 Shutdown and all
associated output actions can be found on the following illustrations:
For further details of input and output devices and actions associated with fire
and gas detection refer to Chapter 5.
• Signal from the PLC-1 Cabinet XXO-837 initiated from FCC Matra
PA/PZ Display
• Signal from the PLC-2 Cabinet XXO-838 initiated from FCC Matra
PA/PZ Display
Activation of any of the previously detailed Level 1 inputs will cause the
following simultaneous actions:
WHPT
Production Separators
222-V-001A
222-V-001B
222-V-001C
They are depressurised by opening vent valves XCV-12, XCV-15 and XCV-82
for Separators A/B/C respectively.
The associated Oil Booster Pumps P-001A/J and Crude Transfer Pumps
P-012A/D are stopped. The pump sequence is inhibited from starting the
standby pumps.
Closing Shutdown Valve 222-XCV-18 in the gas trunkline shuts off gas to the
Central Complex.
Fuel gas to the flare system is stopped by closing valve 222-HV-74 separator
gas outlet header and 222-HV-80 fuel gas from gas trunkline.
All electrical supplies are isolated other than those required by the fire and
gas panel.
Diesel fire pump 222-P-016 is started if no gas is present in the pump room.
There will be a 60 second time delay prior to isolating 220V AC Inverter IV-11
supplying 220V AC UPS which feeds the MATRA Console, PLC Cabinets,
Operator Console and Data Concentrator.
There will be a 1 second time delay prior to isolating the 48V DC Supplies to
Controls and Instruments, BC-010.
For further details of input and output devices and actions associated with fire
and gas detection refer to Chapter 5.
The fire and gas panel will remain operational for 24 hours along with
navigational aids and some emergency lighting at escape points, which are
supplied by their own batteries.
Note: 48V DC power supplies to the fire and gas panel will be lost in
65 seconds in case of gas coincidence in the control room. BC-10-1
battery circuit breakers will trip after 65 seconds.
4.1 SHUTDOWN
• By a signal derived from within the shutdown system signifying that all
the separators are shutdown
• Fire and Gas signal XXO-584 from Fire and Gas Panel 222-CP-003
For detailed information and specific input and output actions for the
Emergency Shutdown and Fire Gas System refer to the following illustrations:
Note: Further details and information for ESD Level 2 input and output
actions can be found in Chapter 5.
Upon initiation of this trip, the following responses/ actions automatically take
place and the separator valves close.
A Level 2 Shutdown does not affect utility systems such as HVAC and
Instrument Air.
4.2 START-UP
This procedure assumes the SSP is manned. Upon initiation of a fire or gas
alarm all personnel should respond as per the platform muster procedures.
The steps required to confirm and rectify the cause of the shutdown and to
normalise the system are detailed in the following table:
No Action By
No Action By
1 Check the alarm status of the air compressors and the FCC/
instrument air pressure at the instrument air receiver. SSP
If the alarm status indicates that one of the compressors
may be restarted and it is safe to do so, immediately
attempt to restart.
2 If an Air Compressor start is successful, allow the air SSP
pressure to stabilise at normal operating pressure of
±210psig.
Stop all non-essential consumers using air.
3 Carry out systems check and confirm all operating FCC/
utilities are normal. SSP
4 When it is confirmed all is normal, the SSP operator FCC/
shall reset the ESD-2 Trip at the Shutdown Panel PD-1. SSP
5 Re start the process in accordance with established SSP
procedure.
No Action By
5 LEVEL 3 SHUTDOWN
5.1 SHUTDOWN
Refer to illustrations:
• Water Injection
• The Crude Oil Transfer Pump is stopped and the pump sequence
system is inhibited from starting the standby pump. After a time delay
the gas outlet is then closed. After further time delay the oil booster
pumps are stopped
Activation of PB-526 or telemetry signal XXO-669 from the FCC initiates the
following actions:
• Pipeline Valve HV-182 closes, stopping the injection water supply from
the Central Complex
5.2 START-UP
Once the shutdown fault has been identified and rectified, the shutdown reset
can be given from the FCC (except for oil flow lines) or from the Local Control
Room and restart as per established procedures.
Re-opening of the Oil Inlet Lines will require a reset at SSP Shutdown
Panel PD-1.
Specific start-up details for the systems affected by a Level 3 Shutdown can
be found in Paragraph 8.5 and the subsequent paragraphs.
6.1 SHUTDOWN
Refer to illustrations:
• Water Injection
6.2 START-UP
Step Action By
1 Call up SSP Module 11 Control Mimic and confirm FCC/
High Flow Alarm and subsequent isolation valve SSP
responded closed.
2 Investigate and if possible rectify the flow problem. FCC/
SSP
Operator intervention may be required at SSP
WHPT
and/or WHPT.
3 Reset the Level 4 by activation of XXO-688 and FCC/SSP
equalise the pressure upstream and downstream
of the HV.
4 Open IPSV at the affected WHPT. WHPT
5 Re-open the relevant Isolation HV Valve when the SSP
flow line has been pressurised.
Step Action By
1 Call up SSP Module 1 Control Mimic and confirm FCC
High or Low Pressure Alarm and subsequent ESD
valve responded closed.
2 Investigate and if possible rectify the cause of FCC/SSP
the alarm.
3 To prevent automatic reopening of the isolation FCC
valve, give a close signal from the FCC.
4 Reset the alarm condition at the SSP Shutdown SSP
Panel PD-1.
5 If the WHPT is tripped, reopen WHPT valves to FCC/SSP
bring the WHPT back on line and reopen the flow
line isolation valve at the SSP.
Step Action By
1 Call up SSP Train 1 Control Mimic and confirm that FCC
222-PSL-147 is active and that 222-XCV-18 Gas
Trunkline Isolation Valve has closed.
HV-66, HV-72 and HV-131 will close if XCV-18
fails to close.
2 Investigate and if possible rectify the cause of the FCC
alarm.
If the pressure switch is active, repressurisation
may be necessary. This is achieved by opening
XCV-018, pressurising the system and normalising
PSL-147.
3 When the Low Pressure problem has been FCC/SSP
identified and rectified, reset the Level 4 Trip
Condition at the SSP Shutdown Panel-PD-1
4 Confirm that 222-XCV-18 re-opens. FCC/SSP
5 Confirm that separator operations are stable. FCC/SSP
Most Level 4 Shutdown conditions can be reset remotely from the FCC and
the Separator restarted without intervention at the SSP.
The specific input devices associated with this level of shutdown for Train A is
detailed below, however the actions for Trains B and C are identical.
Upon initiation of this trip, the following actions automatically take place.
The associated Crude Oil Booster Pumps 222-P-01A/C and Crude Oil
Transfer Pumps 222-P-0012A/D stop.
The following steps are required in order to normalise the system after the
different inputs as previously described.
Step Action By
1 Call up SSP Train 1 Control Mimic and confirm that FCC
222-LSHHH-1A/B is active and the shutdown of
the pumps and valves is in accordance with a
Level 4 Shutdown.
2 Investigate and rectify the cause of the high level FCC
alarm.
3 Clear the High Level. FCC
Reset Level 4.
Start a Transfer pump and operate until the High
Level clears.
Restart the Separator in accordance with
established procedures.
When 222-LSHHH-1A/B is active the Separator
Inlet Valve, HCV-170 is inhibited from opening.
Note: Following a reset, the separator system will trip again if the alarm
condition is not cleared within 10 minutes.
Step Action By
1 Call up SSP Train 1 Control Mimic and confirm that FCC
222-LSLLL-5 is active and the shutdown of the
pumps and valves is in accordance with a Level 4
Shutdown.
2 Investigate and rectify the cause of the low level FCC
alarm.
Step Action By
3 Reset Level 4. FCC
Clear the Low Level.
Establish a level in the Separator to clear the Low
Level Alarm.
Restart the Separator in accordance with
established procedures.
When 222-LSLLL-5 is active, the Transfer Pumps
are inhibited from starting.
Note: Following a reset, the separator system will trip again if the alarm
condition is not cleared within 10 minutes.
Step Action By
Step Action By
1 Confirm that 222-PSL-190 is active and the FCC
Separator and Transfer Pump Systems have
shutdown in accordance with a Level 4 Shutdown
2 Investigate and rectify the cause of the low- FCC
pressure condition. SSP
3 Reset the Separator Level 4 trip alarm for the first FCC
separator to be started.
Restart the Separator in accordance with
established procedures.
Reset and restart further separators as necessary.
7 PLANNED SHUTDOWN
7.1 INTRODUCTION
• Hydrocarbon Tank
• Flare Tower
• Field Production has taken the necessary steps for the manual
shutdown of the Wellhead Platforms (WHPT) feeding the SSP
Step Action By
1 Stop oil production from WHPTs by closing the FCC/WHPT
Wing and Header Safety Valves (HSV).
2 If required, stop Water Injection by call up of SSP FCC
Module 11 Mimic and initiate 222-XXO-669.
3 Prepare to shutdown the online Separator trains FCC
by allowing the level in the Separator to fall to
45% and stop the individual Transfer Pump
222-P-001A/D.
Close individual separator step valves
222-HCV-170/207/249.
Place Separator gas to Flare Pressure Control
Valves 222-PCV-117/130/205 to manual mode and
close fully.
Put Gas to Trunkline Pressure Control Valves
222-PCV-116/129/204 in manual mode and close
fully to isolate gas to the Central Complex.
An individual separator train can be shutdown via
222-XXO-198/200/604 via a control signal from
the FCC.
4 Stop the Corrosion Inhibitor and Biocide Injection
Package. Refer to Chapter 3.
The SSP is now in a pressurised shutdown mode; the subsequent actions are
dependant on the purpose for the initial shutdown. The following section
details the steps required to shutdown the SSP and maintain production
requirements.
A 12in bypass line is provided from the platform intake manifold to the oil
trunkline, which allows crude oil from the wellhead platforms to be routed to
the Central Separation Platform (CSP) Separators.
• Production has identified the platforms and well strings, which are
to remain on line to optimise production rates
• All pigging operations from SSP Oil Flow Lines and Oil Trunkline are
suspended during bypass operations
Confirm that the following valves are in the closed position. Refer to the
schematic for the location of the valves.
SSP Bypass
6
4
1 222-XCV-79
222-V-005
Sub Sea Pipeline
to
Central Complex
Corrosion
Inhibitor
2 222-HCV-123 7
Step Action By
1 Connect a nitrogen hose to the pig Launcher purge SSP
point and pressurise the launcher to 150psig.
Perform leak test as per Steps 1 and 2.
2 Allow the Pig Launcher to stand for 30 minutes. If SSP
the pressure drops significantly then the leak must
be found and rectified before continuing with the
procedure.
Leak check can be done using soapy water
3 Close the ½in Purge Connection valve and SSP
disconnect the nitrogen hose.
4 Put oil trunkline Low Pressure Switch, FCC
222-PSL-190 into bypass mode.
5 Commence reducing SSP production rate to FCC/
approximately 100 000BPD. WHPT
Close in wells as per Production guidelines
6 Confirm that CSP operations are stable. FCC CSP
7 Open Pig Launcher outlet valve: 222-HV-124. SSP
8 Open the 12in valve in the inlet bypass line to SSP SSP
pig launcher kicker line.
9 Open the 12in valve at the SSP bypass line outlet SSP
from Oil Feed Manifold C.
10 Divert SSP oil risers from Oil Feed Manifolds A and SSP
B to Manifold C.
Each riser is capable of being routed to A, B or C
Manifolds.
11 Close Production Separator A, B and C 24in inlet SSP
valves.
12 ALLOW the Booster Pumps for SSP Production FCC
Separators A, B and C to trip on low level via
LSLL-32, LSLL-49 and LSLL-50 respectively.
The pumps trip on LL2 unless it is necessary to
defeat LL2.
13 STOP the Corrosion Inhibitor and Biocide Injection SSP
Package.
Step Action By
14 CLOSE the Oil Trunkline Pig Launcher Bypass SSP
Valve 223-HCV-123.
The SSP Gas Oil Separation system is now
bypassed.
15 CLOSE 222-PIC-116/129/204 on manual to isolate FCC
gas to the Central Complex.
Flaring shall be sanctioned only when absolutely
necessary.
16 CLOSE 222-HCV-76, the Gas Trunkline Pig SSP
Launcher Bypass valve.
Valve Description
Note: 222-HV-208 and the transfer pump suction and recycle valves should
not be closed before draining of separator is accomplished. This is to
enable the draining of the oil outlet line via 222-HV-208 and the pump
casing to the hydrocarbon drain tank.
Valve Description
6in Valve Downstream of 222-XCV-154, from HC Drain Tank,
222-V-019.
2in Valve Booster Pumps 222-P-001A/B/C vent to separator.
2 x ½in Valve Corrosion Inhibitor (Gas) on gas outlet line.
½in Valve Biocide Injection to Separator inlet line (upstream valve).
6in Valve Upstream of Bursting Disc 222-PSE-109.
6in Valve Upstream of Bursting Disc 222 PSE-110.
2in Valve Upstream of 222-XCV-12, depressurising valve to flare.
24in Valve Downstream of 222-HCV-170, Separator Inlet Valve.
8in Valves Minimum flow recycle from Booster Pumps,
222-P-001A/B/C
Note: Minimum flow recycle from Booster Pumps P-001A/B/C to be left open
to enable draining of the recycle line through the Transfer pump
casing to the HC Drain Tank 222-V-019. On completion of recycle line
draining, the 8in valves are to be locked closed.
Step Action By
1 Slowly drain the Separator to the Hydrocarbon SSP
Drain tank.
Foaming and carry over from the HC tank may
result if draining is carried out too fast.
2 When draining is complete, open 222-PCV-116 SSP
bypass and complete the depressurisation of the
separator.
3 Connect a water hose to the sample connection
SSP
point on the separator inlet line.
4 Connect N2 hose to the 2in bridle of Level SSP
Transmitter 222-LT-4.
While draining, the separator to be kept under a
positive N2 pressure.
5 Drain the separator to the hydrocarbon drain tank SSP
using 2 x 3in ball valves at the base of the
separator.
6 Open the ½in sample valve and displace the SSP
remaining oil to the separator.
7 Lock closed the ½in sample valve after the flush. SSP
8 OPEN HV-208 and Booster Pump P-001A Suction SSP
Valve, HV-81 and drain pump suction line via
pump casing to the HC drain.
Repeat for P-001B/C suction lines. HV-208 to be
closed/disabled on completion of draining.
9 OPEN Booster Pump P-001A recycle valve SSP
PCV-582 and drain pump recycle line via pump
casing to the HC Drain.
10 Repeat for P-001B/C recycle lines. Recycle block SSP
valves downstream of PCVs to be locked closed
on completion of draining.
11 Remove the ½in needle valve from the sample SSP
connection point upstream of HV-208 in the oil
outlet line.
Step Action By
Step Action By
The separator is now ready for inerting and draining as follows:
22 Using the Nitrogen (N2) connection, pressurise the SSP
Separator to 30psig.
23 Depressurise to flare via 222-PCV-116. SSP
24 Repeat steps 22 and 23 at least three times. SSP
25 Using a gas test meter or Draeger, test for SSP
separator hydrocarbon content aiming for <1%
LEL.
26 Repeat N2 purge until Lower Explosive Limit (LEL) SSP
is <1%.
27 With a separator N2 pressure of 5psig, drain the SSP
separator to the HC Tank.
Ensure all sight glasses are drained.
28 Close and Lock the 2 x 6in Ball valves from the SSP
Separator to the hydrocarbon drain tank.
29 CLOSE and Lock the 2 x 4in Ball valves upstream SSP
of 222-PSV-107/108.
30 CLOSE and Lock the 6in Ball valve from the SSP
separator to the open drain.
The separator can now be spade isolated as detailed on the following list:
An air blower may be installed at the top of a vessel/tank either to force air to
the bottom through ducting with other top openings used for gas release or by
forcing air in and providing other top openings with suspended ducts.
• H2S is Nil
Upon completion of the separator final inspection, carry out the following
de-spading and leak test activities:
Step Actions
1 Remove all equipment from inside the separator.
2 Carry out final inspection of the separator to ensure all is in order,
then close man ways.
It is the responsibility of Senior Production person on site to
ensure a final internal inspection is conducted.
3 Re-instate any instruments, bridles or sight glasses that have
been removed for calibration/cleaning.
4 Ensure that all level switches, bridles gauge glasses and all
instruments are lined correctly.
This is to eliminate pockets of oxygen remaining in the system.
Step Actions
5 Connect a Nitrogen (N2) hose to the 2in bridle of 223-LT-4 and
pressurise the Separator to 200psig.
Note: The PSVs are set at 225psig.
6 Using a soap solution, check the manholes and all disturbed
flanges for leaks.
7 Depressurise the separator on successful completion of the
manhole leak test.
8 Pressure purge the separator with nitrogen to 30psig.
Repeat the pressure purge until oxygen content is Nil.
9 Remove blinds and spades from the separator under a slight
nitrogen flow.
10 Using nitrogen pressurise the separator to 200psig and carry out
a leak test.
Rectify any leaks found.
11 Carry out a final oxygen content to confirm that oxygen content is
Nil.
• Injection water
• Flare system
8.1 INTRODUCTION
This procedure provides the necessary information for the re-start of the
process after the 22kV main power supply has been re-established.
Reinstatement of 22kV power supply is part of the Black Start procedure.
This procedure assumes that the gas trunkline is pressurised and fuel gas is
to be imported from the trunkline.
Fuel gas may be taken from the separator gas manifold upstream of the
Separator Pressure Control Valves, 222-PCV-116/119/204 or from the gas
trunkline, downstream of the last block valve. For a normal black start, fuel
gas is available from the gas trunkline; this procedure makes this assumption.
If there is no gas in the trunkline this operation is delayed until gas becomes
available from the production separators, 222-V-001A/B/C.
Fuel gas is now being supplied through the fuel gas header to the flare system
as normal.
• Ensure all valves to and from the standby ignition system are open
• Select automatic operation. The panel will not operate until the 'remote
ignition impulse' is sent to the panel from the FCC. This impulse
triggers off the automatic ignition sequence on the panel and the
solenoid valves will open
• With the solenoid valves open, gas and air are admitted into the
ignition line
• After a delay as set on timer T1 (Note: this will be a long time due to
distance to flare) to allow the igniters line to fill with the gas/air mixture,
a spark is generated in the ignition chamber. This spark will travel
along the ignition lines to light the pilots
• If after the final attempt, the pilot failure condition remains, the pilot
failed lamps and remote ‘pilot failed’ alarms will remain
Note: If the three-way switch is turned to reset during the auto ignition
sequence, the sequence will be stopped. Restarting the ignition
sequence can only occur by resetting the three-way switch to auto,
then giving an impulse to the panel from the ‘remote ignition switch’
Note: If pilot ignition is not achieved, the previous step is repeated three
times.
Due to the unavailability of the remote ignition facility, the flare is normally lit
using flare ignition cartridges.
• Ensure there is a liquid level in the sump tank such that the
non-hazardous area drain inlet is submerged
• Ensure that the system is lined up and respective valves are opened or
closed as required
• Check that the hydrocarbon drain tank vent to flare and the fuel gas
supply to the hydrocarbon drain tank are open
Instructions for the preparation and operation of the production wells are
detailed in UZ-POM010 – Upper Zakum – Wellhead Platforms – Plant
Operating Manual, Chapter 2.
The following steps provide the necessary details for the reinstatement
Production Separator 223-V-001A.
Set gas to flare Pressure Control Valve, PCV-117 at 100psig in auto mode.
Set Separator Level Control Valve, 222-LCV-4 in manual mode at 25% open.
Energise the platform shutdown systems for the well streams and the
separators.
The process systems are now ready to receive hydrocarbons from the
Wellhead Platforms. Reinstatement of operations can commence as detailed
in the following steps.
• Open platform inlet shutdown valve on wellhead flow line, close bypass
valve
• Gradually increase the flow from the well by opening additional strings
When normal operating pressures and levels are achieved all overrides shall
be removed after ensuring that the trip switch is healthy and has been reset
as required.
Reinstatement of the crude oil booster and transfer pumps can now take place
as described in the following paragraph.
Crude oil leaves the separator and joins a 20in header that supplies the
booster pump suction manifold. Crude from Separator A is routed via the
manifold to Oil Booster Pumps 222-P-001A/C. The booster pumps discharge
to a common 14in header, which feed the suction of the crude transfer pumps.
If the Crude Transfer Pumps 222-P-012A/D are not on line, the transfer pump
bypass valve must be opened.
When a liquid level develops in 222-V-001A, start one oil booster pump
(assumed P-001A).
Semi Auto mode is the normal operating mode for the SSP.
Semi Auto mode requires that the pumps selected in this mode need to be
started manually but the remainder of the logic is under full sequence control.
8.6.1 Preparation
• Field selector switches for the suction and discharge valves are in the
remote control position (222-HS-81 and 222-HS-82)
Call up SSP Train 1 Control Mimic display and issue a Start Command for Oil
Booster Pump 222-P-001A and observe:
Confirm with SSP that Booster Pump Recycle Valve 222-PCV-502, has
opened.
Place Separator Level Control Valve 222-LCV-4 in auto mode with set point
of 50%.
Note: The pump shutdown logic is bypassed when field operation is selected
and the following trips are not operational:
• Seal failure
Start the second oil booster pump using the same procedure when the oil flow
rate is high enough to warrant it.
For detailed illustration of the start logic for Crude Oil Transfer 222-P-012A
refer to the following illustrations:
The following description provides specific details for the start-up and
reinstatement of 222-P-012A in the Semi Auto mode, which is the normal
mode of operation. Further details for pumps start-up and operation can be
found in Chapter 2.
Call up SSP Train 1 Control Mimic, display and issue a Start Command for the
selected transfer pump and observe:
The oil starts to flow to the trunkline as soon as the crude transfer pump
discharge valve is opened.
This procedure details a first time start. Normally the plant is lined up to the
satellite oil manifold at the Central Complex with the exception of the booster
and transfer pumps.
Reinstatement and line out of the trunkline is carried out in conjunction with
the start-up of the transfer pumps. The following override may need to be
applied in order to be able to complete the reset and start-up.
• Open 222-XCV-35
• As soon as the crude oil transfer pump has reached operating speed
and its discharge valve has been opened, open the oil pig launcher
bypass valve gradually, maintaining normal discharge pressure
upstream of the valve. The oil will flow to CSP and the pressure in the
trunkline will begin to increase
• When the sub sea pressure has risen to normal operating pressures
reinstate 222-PSL-190, low pressure in oil trunkline and reset any
related overrides on the platform shutdown system for the oil trunkline
Inform Central Complex that South satellite is ready to start transferring gas.
Place 222-PCV-117 in auto mode and slowly increase the set point to
100psig, 222-PCV-116 will start to open and 222-PCV-117 will start to close.
Raise the set point of Separator-A, Level Control Valve 222-LCV-4 to the
normal operating level.
When the gas trunkline pressure has risen, normalise gas trunkline Low
Pressure Switch 222-PSL-147.
When gas from the second production separator is transferred to the trunkline,
open block valves and shutdown valves in the second header. Ensure that
222-HCV-73 is closed; increase the set point of 222-PIC-130 slowly, as for the
first stream.
Detailed instructions for the preparation and operation of the Water Injection
well are contained UZ-POM010 – Upper Zakum – Wellhead Platforms – Plant
Operating Manual, Chapter 3.
The following description assumes that injection water is available from the
Central Complex.
Open the 2in bypass of 222-HV-182, Pig Receiver Bypass, to pressurise the
water injection manifold, then open 222-HV-182.
Slowly open HCV-L, choke valve on wellhead flow line. Vent air, if any is
present, through the 1in line.
When pressure has risen in the wellhead flow line, indicated by PI, open HV
shutdown valve on flow line, and close HCV.