Consultant Logo Client Logo Contractor Logo

PROJECT NAME Data Date

WORK FLOW - FINISHES & MEP WORKS


General Date : 5-Jan-20
MEP Preparation and Rope pulling, Wire
Slab Access Pulling etc
4 days 6 Nos

Surface Preparation + Grouting 6 days 6 Nos Bedroom/Living Wall Ceiling


Civil Clearance
MEP 2nd Fix above POD (40%) 35 days 30 Nos Partial Blockworks 6 days 20 Nos
MEP Clearance MEP Clearance 6 days
6 days 10 Nos 6 days 6 Nos 6 days 10 Nos Bedroom/Living Wall &
Gypsum Works above POD Partial Drywall wherever applicable Spray Plaster - Ceiling Floor
Kitchen - Wall & Floor Kitchen- Ceiling Balcony - Floor Balcony - Ceiling

POD Placing in Permanent Location 10 days 6 Nos Balance Blockworks 8 days 30 Nos Drywall Support frame 6 days 15 Nos Drywall Support frame 3 days 5 Nos Upstand 6 days 3 Nos
Civil Clearance Civil Clearance Civil Clearance
4 days 15 Nos 8 days 8 Nos 8 days 3 Nos 4 days 2 Nos 5 days 3 Nos
Plumbing Works Completion MEP Embedded Works MEP Embedded Items MEP Embedded Items MEP 2nd Fix Completion Floor Drain Seepage Pipe MEP 2nd Fix Completion
8 days 3 Nos 8 days 3 Nos
MEP Clearance MEP Clearance MEP Clearance MEP Clearance
Leak & Flow test & approval 4 days 4 Nos Plaster/Lining 8 days 10 Nos Drywall Closure 6 days 25 Nos Drywall Closure 3 days 5 Nos Waterproofing and Leak Test 6 days 2 Nos
MEP Clearance (2 days)
4 days 4 Nos Acoustic Lay 4 days 5 Nos Surface Preparation 2 days 5 Nos Screed 4 days 2 Nos
Fire sealant application by MEP Inspected by DCD approved third Party
Screed 4 days 5 Nos Floor Drain Seepage Pipe 3 days 2 Nos Handrail 4 days 8 Nos
MEP Clearance
Completion of HVAC Valve package 10 days 10 Nos Tiles 12 days 20 Nos Waterproofing 6 days 2 Nos Cladding Works AAB 6 days AAB
MEP Clearance
Close Gypsum board above POD 6 days 20 Nos Ceiling Grid Works 10 days 40 Nos Acoustic Lay + Screed 3 days 2 Nos Tiles Completion 4 days 4 Nos
MEP Clearance (14 days) MEP Clearance MEP Clearance
Ceiling Closure 8 days 20 Nos Wall and Floor Tiling 3 days 2 Nos Ceiling Grid Works 6 days 5 Nos Ceiling Grid Works 5 days AAB
MEP Clearance MEP Clearance MEP Clearance
Paint 1st Coat 6 days 15 Nos Kitchen Carcass 12 days 10 Nos Ceiling Closure 6 days 3 Nos Ceiling Closure 4 days AAB

LED Light and LPG 4 days 8 Nos 3 days


Door Frame Installation Paint 1st Coat Paint 1st Coat
6 days 20 Nos Termination 6 days AAB

Wardrobe carcass 10 days 20 Nos


Wild Air Wild Air
Wardrobe Shutter/ Door
Kitchen Cabinet Shutter MEP Final Fix MEP Final Fix
Shutter
All Above dates are Working days.
Paint Final Coat Kitchen hood & Cooker Paint Final Coat Paint Final Coat