Naveed. MOM-140 - Minutes of Weekly Quality Control Meeting 13-Mar-24
Naveed. MOM-140 - Minutes of Weekly Quality Control Meeting 13-Mar-24
PQI SCORE
97.50%
92.50%
87.50%
82.50%
Jan/23 Feb/23 Mar/23 Apr/23 May/23 Jun/23 Jul/23 Aug/23 Sep/23 Oct/23 Nov/23 Dec/23 Jan/24
Monthly PQI 97.00% 95.90% 96.50% 96.60% 98.10% 96.40% 97.80% 96.10% 96.30% 97.60% 98.10% 93.10% 98.90%
Cumulative PQI 96.70% 96.70% 96.70% 96.60% 96.70% 96.70% 96.70% 96.70% 96.70% 96.70% 96.70% 96.70% 96.70%
Month Design PQI Procurement PQI Const. PQI QA PQI QC PQI Monthly PQI Cumul. PQI
Dec-23 N/A 100.00 92.10 99.60 89.00 93.10 96.70
Jan-24 N/A 100.00 98.70 98.50 98.90 98.90 96.70
Feb-24 N/A N/A 98.60 100.00 97.80 98.60 96.70
3. RFI STATUS
TOTAL
Elect. & Instru., CP, Tele.
RFI Rejection Rate 0.21%
0.25%
Civil 0.03%
Welding/NDE
0.00%
Coating 0.82%
Mechanical 0.18%
0.00% 0.10% 0.20% 0.30% 0.40% 0.50% 0.60% 0.70% 0.80% 0.90%
Note : All Company supplied Materials (8635 Pipes) are received and Accepted by SAPID.
8A. MATERIAL RECEIVING STATUS (Contractor Supplied Material) :
SL # PO. NUMBER Discipline Manufacturer / Supplier Delivery Date Material Description Status
1
2
3
9. CIVIL TESTING
This Week Cumulative
1 1
1
09 5 8 5 6
FDT 0 4 4 9
0 200 400 600 800 1 1000 1200 1400 1600 1800
6
DIA API # 36” API 5L Gr. X65 2574 9 1017.684 2574 0 100.0%
DIA API # 28” API 5L Gr. X65 1151 0 0 1148 3 99.7%
DIA API # 26” API 5L Gr. X65 706 0 0 705 1 99.9%
DIA API # 24” API 5L Gr. X65 1215 0 0 1215 0 100.0%
DIA API # 20” API 5L Gr. X65 1287 0 0 1285 2 99.8%
DIA # 18" API 5L GR B 11 0 0 11 0 100.0%
DIA # 16" API 5L GR B 1 0 0 1 0 100.0%
DIA API # 12” API 5L Gr. X60 1021 0 0 1021 0 100.0%
DIA # 10" API 5L GR B 67 0 0 63 4 94.0%
DIA # 8" API 5L GR B 34 0 0 34 0 100.0%
DIA API # 6” API 5L Gr. X65 1160 2 37.692 1160 0 100.0%
DIA # 4" API 5L GR B 825 0 0 825 0 100.0%
DIA # 3" API 5L GR B 25 0 0 25 0 100.0%
DIA # 2" API 5L GR B 1512 0 0 1512 0 100.0%
DIA # 1.5" API 5L GR B 105 3 14.1372 105 0 100.0%
DIA # 1" API 5L GR B 14 0 0 14 0 100.0%
DIA # 0.75" API 5L GR B 35 0 0 35 0 100.0%
DIA # 1" API 5L GR B 14 0 0 14 0 100.0%
Total 11757 14 1069.51 11747 10 99.9%
10A. TIE-IN WELDING STATUS : -
36"-ECT-1 5 4 1 1 3 0 1 0 0
Total 336 330 6 100 20 85 3 1 2 13 Joint Welded 06 Joints scheduled
11. NDT-RT/AUT/PAUT (Not include first production joints)
4
Description
DIA API # 24” API 5L G r. X65
0
1
4
50
RT/PAUT Last Week
100 150
Rejected Last Week
200
6
7 RT/PAUT Total
250
Rejected Total
300 350
RT/PAUT Backlog 400
Repair Bal. 450
JT Repair Rate Remarks
500
963.6177
LAST FOUR WEEKS WELD REJECTION RATE DETAILS : REPORTS SUMMARY (NDE)
517 Weekly Repair Rate (%) Cumulative Repair Rate (%) ITEM 3rd PARTY PRIME OID
WEEK PERIOD
Joint Basis Linear Basis Joint Basis Linear Basis RTFI REPORTS 844 844 842
0.002
0.1 0.001 Jan 26, 2024 to Feb 01, 2024 2.941 0.053 5.104 0.148
0.05 AUT REPORTS 380 380 380
Feb 02, 2024 to Feb 08, 2024 0.000 0.000 5.098 0.148 PAUT REPORTS 667 667 641
0.003
0.15
Feb 09, 2024 to Feb 15, 2024 0.000 0.000 5.089 0.148 TOTAL 1891 1891 1863
TOTAL JOINT BASIS TOTAL LINEAR BASIS
Jan 16, 2024 to Jan 22, 2024 0.000 0.000 5.100 0.148
Feb,23 2024 to Feb 29, 2024 6.667% 0.03% 5.082 0.147
Feb,23 2024 to Feb 29, 2024 Joint Basis Linear Basis
Total No. of Int. Total New Coat Internal Coating Failed/Repair Joint Status
Total Released for Internal Balance for Internal Coating Period
Coating Joints
Welded Int. Coating Coated Joints
Accepted
Coating [Liquid (APCS-120)] Coated Joints Inspection Repaired Repair Insp. Remarks
(Apx.) Joints Accepted Coating Failed Cut-out Done Repair Balance Remarks
Balance. Accepted Bal.
DLPS Crew-1 : 27-Feb-24 - 06-Mar-24 3 0 1 2 1 0 0 1
2386 2298 DLPS Crew-2 : 27-Feb-24 - 06-Mar-24 10 0 10 0 0 0 0 0
Weekly : 27-Feb-24 - 06-Mar-24 6 0 5 1 0 0 1 0
2379 2349 2323 30
Bal. for Weld :
Cumulative
(Incl.Tie-in, cutout 207 (upto 06-Mar-24) 2329 1395 14 1182 1052 174 7 5
Jts )
18A. APCO - INTERNAL COATING (02-INCH TO 26-INCH AT SHOP, AND 36-INCH AT FIELD) SUMMARY STATUS: - (As of 05-Mar-2024)
REMARKS:
First Batch Spools are Delivered to APCO for Internal Coating for Field Welded Joints Coating Purposes. Total 164 Spools (198 Joints) Sent to APCO. Coating Schedule from 07- Feb-2024 to 25 Feb-2024). After Coating, Received (50+67= 117 Spools)
6"-MEG-1(15CS1P04) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
12"-SBTNCL-1(6CS0P06) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
20"-LGT-2(25CS1P08) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
24''-TNTNGG-1(9CS0P06) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
26"-SJTNGT-1(6CS0P08) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
28"-LGT-1(15CS1P08) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
36"-RGP-1(9LE1P06) 1 1 1 1 1 1 1 1 1 1 1 1 - 1 1 1
36"-RGP-2(9LE1P06) 2 2 2 1 1 1 1 1 1 1 1 1 - 1 1 1
36"-ECT-1(9LE1P06) 0 0 0 - - - 1 1 1 -
Total 9 9 9 8 8 8 8 8 8 8 8 8 2 2 2 8 8 8
19C. HDD Status : [Total Scope : 36, Completed : 35] 19B. STRING LOWERING STATUS:
95 # Highway & 611 #
Highway (Old khafji Road) : Tanajib GOSP Road (Near EIV) Tanajib Marine Terminal Road SK Corridor
Estimated
Pipeline Description (QTY is Each / Loc.) Pipeline Description PKG QTY
PKG Approved Completed CP Done Backfilled
Completed/ 6mtr Completed/ 6mtr Completed/ 6mtr Completed/ 6mtr
Scope Excavation Insp.
CP Done Scope Excavation Insp.
CP Done Scope Excavation Insp.
CP Done Scope Excavation Insp.
CP Done
19D. Camel Crossing Status 20A. PRECAST FOUNDATION STATUS : 20B.HCIS TYPE IV FENCE (SEC-02)
COATED (APCS-113A & APCS-113C) Total Fnds Concrete Poured Total Line/Corner/Gate Posts 1350
S.No. PIPE Line Estimated (Approx) (Precast+Casin Situ)
Foundations Installed Weekly Progress Last Week
Pipeline Description Scope TGP RD#2 - West TOTAL COATED Backfilled Weekly Line/Gate /Corner Posts 0
PMT Rd-East PMT Rd-West
24"-KM23 24"-KM24 24"-KM25 1 24"TNTNNG-1 P/L 136 134 134 Brace Posts 0
Cumulative 1070
6"-MEG-1 7 0 0 2 12"SBTNCL-1 P/L 102 99 99 Progress
Line/Gate /Corner Posts
12"-SBTNCL-1 5 1 1 1 1 1 5 5 3 26" SJTNGT-1 P/L 140 138 138 of Full Thrust Anchor Block 280
Brace Posts
20C. Concrete Pouring Status:
20"-LGT-2 7 1 1 1 1 1 5 5 4 36"RGP-1 P/L 110 109 106 (Mass Concrete) :-
24''-TNTNGG-1 7 1 1 1 1 1 5 6 5 36"RGP-2 P/L 110 108 106 Total : 28 Completed : 28
26"-SJTNGT-1 5 1 1 1 1 1 5 5 6 28" LGT-1 P/L 106 105 103 TGP:
1) SJTNGT-1 (26”) : A-202
GOSP :
1) ECT-1 (36”) : A-901
28"-LGT-1 7 1 1 1 1 1 5 4 7 20" LGT-2 P/L 100 97 94 2) TNTNGG-1 (24”) : A-104
3) SBTNCL-1 (12”) : A-302 2) TNTNGG-1 (24”) : A-101
4) RGP-1 (36") : A-501
36"-RGP-1 7 0 0 8 6" MEG-1 P/L 68 55 52 5) RGP-2 (36"); A:401 KM 22 SCRAPPER: -
36"-RGP-2 7 0 0 9 36" ECT-1 P/L 73 68 67 6) MEG-1 (6") : A-801 1) SJTNGT-1 (26”) : A-201
7) LGT-1 (28") : A-701 2) SBTNCL-1 (12”) :A-301
Common Foundations_ 8) LGT-2 ( 20") - A-601
36"-ECT-1 0 0 0 10 575 569 565
(Electrical & Instrumentation)
Total 52 5 5 5 5 5 25 25 Total : 1520 1482 1464 n/a n/a
Overhead power line(OHPL) Pole Foundation completed Status :- Total (27), Completed (27). Beach Valve Station (Gas)
1) RGP-1 (36") : A-405, A-404
- Pole Installation Completed = 27 Nos EIV: 2) RGP-2 (36") : A-505, A-504
- ASCR cable installation for OHPL is Completed for 26 poles. Inspected and accepted. 1) TNTNGG-1 (24”) : A-102, A-103 3) LGT-1 (28") : A-705, A-704 Beach
2) RGP-1 (36") : A-403, A-402 Valve Station (Crude)
- MV cable installation and backfilling on going FINISHED (EIV to SBTNCL& RISER POLE near burn pit). Sheath test of MV cable FINISHED 3) RGP-2 (36") : A-503, A-502 1) & 2). TAB- A-902 & A-903
4) LGT-1 (28") : A-703, A-702
EIV-Station (34.5KV) 656-G80(XFR)T-401(PAD)@KM-22 635-G80(XFR)T-402(PAD)@EIV PRIMARY KM22- SBTNCL-1 (34.5KV) Existing armless line pole
2 (CABLE TYPE ; 1-3C 70mm2) PRIMARY SIDE SIDE 1600 600 SHEATH TEST PASSED 2 (CABLE TYPE ; 1-3C 70mm2) NO. 450A Cable Riser Pole 30 1 1 TIE IN BALANCE
Preparation ongoing.
3 3 Trasformer 656-G80(XFR)T-401, 402(PAD)@KM-22 635-G80(XFR)T-Pole Mounted TXFR 3 Trasformers TP Testing completed and Accepted. 3 Energization Package (OHPL) KM22 & EIV (Tie in Balance)
KM22-SBTNCL-1 (34.5KV)
4 MV CABLE HIPOT (CABLE TYPE ; 1-3C- 120mm2 & 70 EIV and Dead End Riser Pole 2 HI-POT Tests are Completed and Accepted by POD/SAPID. 4 Switch Rack GOSP, BVS, KM22, TGP BVS , KM 22 DONE
mm2
21C. FOC Installation, splicing and testing Status : (16-Jan-2024) 21D. CCTV CAMERA STATUS:
2 splice Completed External Fixed Camera 2MP with pole mounting Foundation
2 OPTIPED SP # 2 @ KM. 05+650 OPTIPED SP # 3 @ KM. 11+700 24F SM (IT) 5880 100% 16 12 EA 28 Installation
(1 Loc. Cable Cut) accessories Ongoing.
Foundation
3 OPTIPED SP # 3 @ KM. 11+700 PED MTGP09-25 (IT) (UNDER PACKAGE-09), (EXISTING) 24F SM (IT) 3025 100% Splice Completed. External PTZ Camera with Wiper with bracket 2 2 EA 4 Installation
Ongoing.
Splice Completed.
KM22/EIV TO TGP
4 Optiped SP # 5 (EXISTING) KM. 12.511 / RGP-I EIV STN / 635-RTU-0001 (SP # 9) 72F SM (NON-IT) 418.06M 100% Existing Pending. Camera pole
Foundation
5 Km. 12.511 / RGP-I EIV STN / 635-RTU-0001 (SP # 9) 652-RTU-0001 KM. 13.3 @ TNTNGG-1 EIV-1 (SP # 8) 24F SM (NON-IT) 184.0M 100% Splice Completed. 7M CCTV Camera pole 2 2 EA 4 Installation
Ongoing.
Foundation
6 652-RTU-0001 KM. 13.3 @ TNTNGG-1 EIV-1 (SP # 8) 663-RTU-0001 @ SK KM 22 (SP # 1) 24F SM (NON-IT) 1615.0M 100% Splice Completed. 5M CCTV Camera pole 10 8 EA 18 Installation
Ongoing.
8A Splice
7 Optiped SP # 8 (EXISTING) @ 008+935.7M OPTIPED SP # 8A @ 13+044.1M 24F SM (NON-IT) 3967.2M 100% Completed. Field Equipment Network (FEC)
Foundation
8 OPTIPED SP # 8A @ 13+044.1M NEW CP STATION @ KM. 25+113 RGP-1 24F SM (NON-IT) 61.30M 100% Splice Completed. Outdoor Field Equipment Cabinet 436X647 3 3 EA 6 Installation
Ongoing.
9 OPTIPED SP # 8A @ 13+044.1M TGP NEW SCRAPER RECEIVER 24F SM (NON-IT) 2196.80M 50% Communications cables
10 TGP NEW SCRAPER RECEIVER TGP NEW SCRAPER LAUNCHER 24F SM (NON-IT) 11930M 0% CAT 6 FTP cable outdoor/ direct buried 955 675 M 1630 40%
Splice Completed.
BVS 11 635-RTU-0002 EIV (BEACH VALVE STATION EIV) EXISTING OPTIPED SP # 2 24F SM (NON-IT) 2341.20M 100% Existing Pending. CAT 6 UTP cable 6 4 M 10
GOSP 12 NEW SCRAPER RECEIVER AT TANAJIB GOSP PLANT EXISTING MH # 17P (SP # 1A) 24F SM (NON-IT) 157.2M 100% Ready to splice 12 FOC cable, SM, direct burial 940 815 M 1755 40%
CLOSED REJECTED
OPEN : 34 Remark
Total Submitted
CSD OID PROPONENT / PTSD SAPMT/SAVID SAPMT SAPMT/SAPID
SAPID advised Sinopec to work for Pipeline Hydrotest, Cleaning, and Layup Procedure and submit to Aramco. All Procedures need to be approved by Proponent
and the relevant Pipeline Department. SAPID advised submitting the Sample Hydrotest package for Review and approval. 31-Dec-2023
Pipeline Internal Cleaning, Hydrotest and Layup - As per the SAPMT/CSD/SAPID Comments on 24" Pipeline Hydro test Calculation, Contractor is revising the Procedure of Hydro test, swabbing, Nitrogen Layup. 30-Jan-2024
1 OPEN SINOPEC
Procedure & status - 24" Pipeline (Seg.1&2 ) Hydro test Completed. Dewatering completed. Swabbing Activity Ongoing 29-Feb-2024
- 6" Pipeline Hydro test Completed. Dewatering completed. Swabbing Activity Ongoing 31-Mar-2024
- 20" Caliper Run completed on 13-Feb-2024. Water filling Started on 05-Mar-2024
Internal Coating, Micro Crack Repir and Inspection Day shift Crews: 30-Jan-2024
2 Recovery Plan for Internal Coating of Girth Weld New Joint, Repair Internal Coating crew : 2 Crews (DLPS) OPEN
29-Feb-2024 SINOPEC/DLPS
Joints. CLOSED 31-Mar-2024
Scope : Perform 10 pipe pcs of 36” weld overlay in CladTek(Dammam) and 10 Butt welds for RGP-1, 2 and ECT-1 (36" X0.875" - 4 Jts, 36" x 1.125" - 06 Jts) :
- For Field Clad Welding CladTek Field Cald Welding Procedure (CT-00-WPS-772) (Rev. 0)(GTAW) has been submitted to SAPMT/SAPID. Cladteck Internal Coating
Demonstration to be done with SAPID Team.
30-Nov-2023
- Shop Overlay Welding at CladTek Shall be monitored by SAVID. Contractor will submit IAP for SAVID Approval.
30-Dec-2023
Trunk line Clad Welding - SAPID advise that at the time of the kick-off meeting for field Clad work, the Proponent should also be invited.
4
(36"- RGP1,RGP2,ECT1) - Claded Pipe Spools MR has been submitted in EPM on 05-Dec-2023. OPR Approved in EPM. OPEN 30-Jan-2024 SINOPEC
29-Feb-2024
- IAP Approved. Transfered Pipes Pipes Material Receiving Inspection Completed in Cladtek. Clad Welding Activity will be done Next week.
31-Mar-2024
- Clad Welding Activity has been started at Clad tek facility on 13-Jan-2024
- Overlay Welded Spool Received at Site. (36" X0.875" - 4 Jts, 36" x 1.125" - 03 Jts) on 31-Jan-2024.
- Clad Welding Kick-Off Meeting has been Completed on 13-Feb-2024
SAPID raised concern about the SAES-W-012 Para 10.7.6 of Duration of Each Clad Welding Joint's Welding Duration requirement.
- As per SAES-W-012 Para 10.7.6, "welded joints shall be completed within 24 hours after starting". As per the Approved WPS, the Full GTAW process of Each
36" with Max. thick of 28mm+3mm CRA welding will take a minimum of 5 days by two welders to complete.
OPEN 29-Feb-2024
4A Field Clad Joint Welding Duration - The Contractor will process the PT of the incomplete joint on the first day to avoid any risk of crack, and process the preheat to the required temperature as SINOPEC/CSD
CLOSED 31-Mar-2024
approved WPS mentioned, then continue welding on the next day.
- To conclude the Field clad Welding Duration Requirement, Contractor Raised TQ to CSD through SAPMT. ( Ref. TQ # MIP16-ENG-TQ-0231; 26-Feb-2024).
- TQ Accepted by CSD through CRM. (CRM # 4045220685) (SAPMT-T-3859; 05-Mar-2024)
SAPID raised concern about the Back Purging According to Cladding Standard SAES-W-019 (1).
- As per SAES-W-019 Pra 7.4, "Back purging shall be carried out using inert gas conforming to AWS A5.32 and the back purging shall be maintained until the
completion of at least 10 mm of the weld deposit thickness.
Field Clad Joint Welding Back Purging - Due to no access, the end of the tie-in joint will be sealed by water-soluble paper, and back purging between the sealed space until the root completed. An 29-Feb-2024
4B OPEN SINOPEC/CSD
Requirement oxygen analyzer will monitor the oxygen content during back purging. When the root completed, the back of weld is filled with pure protective gas. The back 31-Mar-2024
purging hose and the Oxygen Analyzer will be removed after root pass welding .
- To conclude the Field clad Weld Joint's Back Purging Requirement, Contractor Raised TQ to CSD through SAPMT. ( Ref. TQ # MIP16-ENG-TQ-0230; 26-Feb-
2024).
SAPID raised concern about the Visual Inspection Requirement according to Cladding Standard SAES-W-019 (1)
- As per SAES-W-019 Para 9.5, "Root pass of all welds shall be visually inspected with the aid of a boroscope, camera or vision sensor. Visual Examination shall
Field Clad Joint Welding For visual inspection ensure uniform and adequate penetration. 29-Feb-2024
4C
Requirement - Due to lack of access, the cladding tie-in joint will undergo RT/PT/manual UT. If any defects are found at the root, the joint will be cut out and re-welded. OPEN 31-Mar-2024 SINOPEC/CSD
- To conclude the Field clad Weld Joint's Visual Inspection Requirement, Contractor Raised TQ to CSD through SAPMT. ( Ref. TQ # MIP16-ENG-TQ-0229; 26-Feb-
2024).
SAPID raised concern about the Hydro test Water Quality & Layup Requirement
36" Internal Coated with Cladded Joints Hydro test OPEN 29-Feb-2024
4D - Since the Welding Material is under II(C)-Alloy 625, the Water Quality Requirement & Layup as per SAES-A-007, [Chloride Requirement is No Restriction. SINOPEC/CSD
Water Quality & Layup Requirement CLOSED 31-Mar-2024
- Contractor will follow SAES-A-007 Water Quality Requirement.
SAPID raised concern about the Visual Inspection Requirement according to Cladding Standard SAES-W-019 (1)
36" Internal Coated with Cladded Joints Hydro test OPEN 29-Feb-2024
4E - Since the Welding Material is under II(C)-Alloy 625, the Water Quality Requirement as per SAES-A-007, [Chloride Requirement is No Restriction.] SINOPEC/CSD
Water Quality Requirement CLOSED 31-Mar-2024
- Contractor will follow SAES-A-007 Water Quality & Layup Requirement.
- Slope Stability Analysis Test Report and Revised MS has been submitted to SAPMT for further Action. (Ref. : Revised MS-1099; Rev.02; 11-Jan-2024)
HDD string Struck 28" LGT-1 at Tanajib Area, SK- - CSD has commented on the Submitted Revised MS-1099; Rev.03, Contractor is Coordinating with the Subcontractor and updating the Contractor Response. 15-Dec-2023
25-Jan-2024
8 Corridor KM13 - CSD comments are incorporated and resubmitted to SAPMT/CSD on 11-Feb-2024. [MIP16-MS-1099 – Construction MS for Excavation and Connection of Stuck OPEN 29-Feb-2024 SINOPEC
HDD Pipe 28 LGT-1 At Tanajib Area, SK-Corridor KM13 (Rev. 04)"] 31-Mar-2024
- MS Approved by SAPMT/CSD. Manual Excavation Started from 05-Mar-2024
SAPID Expressed its concern for the Valves Placed at site without Proper Preservation. MOV installed with Space Heaters need to be Energized as per
Manufacturer Recommendations. Sinopec to take Action for Valves Preservation or the issue will be escalated.
- Sinopec Procurement is in Discussion with Valve Actuator Manufacturer to Get Recommendation about Preservation of valves and Energization Requirements 31-12-2023
9 Valves Placed at Site at site. OPEN 30-Jan-2024
SINOPEC
- 45 Actuators are removed from the Valve and Placed and Preserved inside the Warehouse. 29-Feb-2024
- Permanent Valve Installation will be start from Next Week. 31-Mar-2024
10 Preservation Checklist
INFO
SAPID Advised to follow Preservation checklist developed as per Manufacturer Recommondations and it should be part of RFI SINOPEC
CLOSED
SAPID Advised to share Pathforwarded for the Joints that need field internal coating and have not been Blasted before welding
11 Internal Field Coating (APCO)
- Contractor has Delivered Field Welded Spools to APCO For Internal Coating Purposes. Total 164 Spools (198 Joints) were Sent to APCO. Coating Schedule from INFO
07- Feb-2024 to 25 Feb-2024) CLOSED SINOPEC
- 50 Internal Coated Spools are Received from APCO on 27-Feb-2024. (Stored in Laydown Area)
SAPID Informed to Contractor, from Jan. 2024 onwards 1) The Monthly PQI score Requirement will be >95% 2) All the Standard violations ACD will be 30 Days
from the Date of Issue 3) All Preservation Related violation's ACD will be 14 Days.
INFO
15 PQI Score & Standard Violation ACD Duration - Contractor QC Department, shared these New Requirements with Construction Department & Management Team on the Internal Meetings. SINOPEC
CLOSED
- Contractor updated and Revised the New Monthly PQI score requirement (> 95 %) on Quality Objective (Rev. 02) and Transmitted to SAPMT/SAPID/SAVID for
Information. ( Ref. : T-5322; 21-Feb-2024)
SAPID Advised to Contractor to Clarify the 06" P/L Pressurization Location changes.
- The proposed pressurization point was within the width of the BI-DI scraper and there was a risk of movement during pressurizing, that's the reason contractor
6" P/L Water Filling Location decided to change the pressure injection point from BV to TGP. INFO
16 SINOPEC
(SV : EPM # 4500638224; ACD : 20-02-2024) - The Actual changes in pressurization point has been communicated to Proponent through SAPMT. CLOSED
- Contractor has been revised the Pressurization Point changes information on the Hydro test Procedure’s relevant pages (Schematic Drawing of Flooding &
Hydro test Diagram, Hydro test Calculation sheet) and shared it with Relevant Procedure Approval Parties.
12" (SBTNCL-1) PIPELINE PMCC PUNCH ITEMS STATUS 25-FEB-2024
Pipeline PMCC PMCC QC STATUS CIVIL MECH WELD COATING ELECT INST CP TELE Safety ENG Grand Total
Pipeline PMCC PMCC QC STATUS CIVIL MECH WELD COATING ELECT INST CP TELE Safety ENG Grand Total
ENG. To be Check 4 4
Inspected 11 40 51
12" NO
Work Not Done 21 20 52 1 94
Request for closure 1 1
Grand Total 33 60 52 1 4 150
ENG. To be Check 1 1
Inspected 4 10 14
26" YES Work Not Done 23 13 18 190 23 267
Request for closure 14 292 56 171 32 65 1 631
Under QCI Verification. 2 5 5 12
Grand Total 39 305 56 175 50 256 23 6 15 925
Pipeline PMCC PMCC QC STATUS CIVIL MECH WELD COATING ELECT INST CP TELE Safety ENG Grand Total
Inspected 21 24 45
26" NO
Work Not Done 23 1 23 47
Grand Total 44 25 23 92
PIPELINE PMCC PUNCH ITEMS STATUS 25-FEB-2024
NO ITEM YES ITEM
GRAND
PIPELINE DECIPLINE TOTAL TOTAL CLOSED IN WORK CONFIRMED TOTAL CLOSED IN WORK CONFIRMED
(YES&NO) (NO) SYSTEM ONGOING COMPLETION DISAGREED (YES) SYSTEM ONGOING COMPLETION DISAGREED
CIVIL 97 33 12 21 64 11 53
COATING 377 52 52 325 4 321
CP 77 1 1 76 40 19 11 6
ELECT 104 104 25 71 7 1
ENG 16 4 4 12 7 5
12" INST 284 284 169 108 7
MECH 364 60 39 21 304 20 284
Safety 7 7 1 6
TELE 17 17 17
WELD 70 70 2 68
TOTAL 1413 150 51 99 0 0 1263 271 949 36 7
NO ITEM YES ITEM
GRAND
PIPELINE DECIPLINE TOTAL TOTAL CLOSED IN WORK CONFIRMED TOTAL CLOSED IN WORK CONFIRMED
(YES&NO) (NO) SYSTEM ONGOING COMPLETION DISAGREED (YES) SYSTEM ONGOING COMPLETION DISAGREED
CIVIL 83 44 20 23 1 37 24 13
COATING 198 23 23 175 175
CP 23 23 23
ELECT 62 62 16 39 7
ENG 15 15 10 5
26"
INST 267 267 86 90 68 23
MECH 330 25 22 3 307 12 294 1
Safety 6 6 1 5
WELD 56 56 56
TOTAL 1040 92 42 49 1 604 161 371 85 24
MIP PKG16 PRE-COMMISSIONING WORK STATUS 6-Mar-24
Pipeline No. Segment Area Gauging Status Caliper Survey Status Water filling/ Hydrotest/Dewatering Swabbing and Air Drying Lay-up Status ILI Status Remarks
No.
- On 30-Aug-2023 Calliper survey run completed - Swabbing Activity Started on 10-Nov-23 (Barred tee Cleaning and Valve Installed& 26"
Completed. before Hydro Test due to slight deformation of - Water filling Started on 03-Nov-2023 ( BIDI-2 Run, HD Form Pig - 1 Run, LD Form Pig-3 Layup Activity ongoing)
SBTNCL-1 (12") Found Slight Deformation. the Gauging Plate. - Pressurization started on 04-Nov-2023 Run, MD Foam Pig - 2 Run. [8th Run Completed on on Layup Activity Started on 09-Dec-2023 Not yet Done.
(15KM LG) Segment No. 1 SBCL-2@KM22 of SK-1 to Tanajib
Const.Plant
decided to proceed with - Caliper Completed on 30-Aug-2023 - Strength Test Accepted on 08-Nov-2023 16-Nov-23] Nitrogen Layup completed on 10-Dec-23 (MFL Tool with Nitrogen)
[Downstream] - Tightness Test Accepted on 09-Nov-2023 - No traces of water found. Pipeline Pressure: 50 PSI
Caliper Survey. - Final Caliper Report Approved by PTSD(ISU) - Dewatering Completed on 10-Nov-2023 - Dew point Archived with Dry Air on 09-Dec-2023 *Dew Point: -1.8°C
Approval. (-8.9 Dew Point Temp.) Purity of Nitrogen: 97.4%
Segment
Pipeline No. No. Area Gauging Status Caliper Survey Status Water filling/ Hydrotest/Dewatering Swabbing and Air Drying Chemical Cleaning Lay-up Status ILI Status Remarks
- Swabbing Started on 26-Feb-2024
-Filling Activity Started from 15-Feb-2024. - 3rd Run Swabbing Completed on 29-Feb-2024
'-Filling Activity Completed on 16-Feb-2024. - No traces of water were found.
MEG-1 (6") Caliper Run Completed on 25-Jan-24 - Spool Hydro is ongoing.
-Pressurization started on 20-Feb-2024 Not yet Done.
(29KM LG) Segment No. 1 Tanajib Gas Plant to Shore Preliminary Report Submitted to SAPMT on 01-
- Strength test Completed on 21-Feb-2024; 6.58PM - Drying will be started Once All Spool Install. NOT APPLICABLE Not yet Done.
(MFL Tool with Nitrogen)
[Upstream] Feb-2024 - 10th Mar.will start Drying.
- Tightness test Completed on 22-Feb-2024; 6.58PM
- Dewatering Completed on 26-Feb-2024
Segment No. 1 Tanajib Gas Plant to Shore -Filling Activity Started from 05-Mar-2024. Not yet Done.
(TGP to EIV)
LGT-2 (20") Caliper Run Completed on 13-Feb-24 Not yet Done.
Segment No. 2 MFL Tool during Nitrogen
(29KM LG)
(EIV to BVS)
Tanajib Gas Plant to Shore Preliminary Report Submitted to SAPMT on 24- -Filling Activity Started from 05-Mar-2024. Not yet Done. (Scope, Precom sequence To be Not yet Done.
purging to align with Pkg.1 & 4.
[Upstream] Feb-2024 Confirmed)
Segment No. 3
(BVS to Offshore) Tanajib Gas Plant to Shore Not yet Done. Not yet Done.
RGP-1 (36")
(29KM LG) Segment No. 1 Shore to Tanajib Gas Plant Not yet Done. Not yet Done. Not yet Done. NOT APPLICABLE Not yet Done.
(MFL Tool during dewatering.)
[Upstream]
PTSD/SAPMT SAPID PTSD(PSU/ISU) /SAPMT SAPID PTSD (PSU/ISU) PTSD(PSU) /SAPMT SAPID PTSD/SAPMT SAPID PTSD/SAPMT SAPID NAPD Oper. Eng. / PTSD SAPID (PSP-645;Rev.02) (MS-1103; Rev.1)
SBTNCL-1 (12") Approved. Approved. Approved by PSU/ISU. Approved. Approved. Approved. Approved. Approved. Approved. To be Submit.
SJTNGT-1 (26") Approved. Approved. Approved by PSU/ISU. Approved. Approved. Approved. Approved. Approved. Approved. To be Submit.
Approved. Approved.
SAPID Verbally Approved, Under SAPID Review. Under Review
Under Review by PSU/ISU. Under Review
TNTNGG-1 (24") Approved. Approved. (T-5065; 02-Jan-24) PMT and Prop. Approved. Water Test Report under Approved. (T-5138;13-Jan-24)
PMT and Prop. To be Submit.
review by PTSD (T-5119;07-Jan-24)
Verbally Approved. Approved by Proponent Revised Procedure sent to Advance Procedure Copy Approved by Proponent Advance Procedure Revised Procedure sent to Approved by Proponent
MEG-1 (6") Approved. Official Approval
through Email on 16-Jan-24 Approved. SAPMT and Proponent on 17- shared to SAPID on 18-
through Email on 16-Jan-24 Copyonshared to SAPID SAPMT and Proponent on 17- through Email on 16-Jan-24
Pending. Jan-24 Jan-24. 18-Jan-24. Jan-24
LGT-1 (28") Approved. Approved by Proponent. Approved by Proponent. Revise and Resubmit Approved by Proponent. Approved by Proponent. To be Submit.
PROCEDURE FOR FILLING, HYDROTESTING AND BULK Revised/updated as per the comments attached for
Not approved - see comment below
DEWATERING OF 06’’-MEG-1 PIPELINE review and approval
Approved with comments
PROCEDURE FOR SWABBING, AND AIR DRYING OF 6’’-MEG-1
Revised/updated procedure attached for final Approved
PIPELINE
approval
Justification for the Proponent Comment
PROCEDURE FOR NITROGEN PURGING & FINAL LAYUP OF 06’’- provided.
Approved
MEG-1 PIPELINE
attached for review and approval
Procedure for Base Line Survey of 06” MEG‐1 Pipeline Approved Approved
MIP PKG16 PRE-CO
SL No. Pipeline Name Segments Area
SBTNCL-1 (12")
1 Segment No. 1 SBCL-2@KM22 of SK-1 to Tanajib Plant
(15KM LG)
SJTNGT-1 (26")
2 Segment No. 1 SBCL-2@KM22 of SK-1 to Tanajib Plant
(15KM LG)
MEG-1 (6")
4 Segment No. 1 Tanajib Gas Plant to Shore
(29KM LG)
Segment No. 1
LGT-2 (20")
5 Segment No. 2 Tanajib Gas Plant to Shore
(29KM LG)
Segment No. 3
LGT-1 (28")
6 Segment No. 1 Tanajib Gas Plant to Shore
(29KM LG)
ECT-1 (36")
7 Segment No. 1 Shore to Tanajib GOSP
(03KM LG)
RGP-1 (36")
8 Segment No. 1 Shore to Tanajib Gas Plant
(29KM LG)
RGP-2 (36")
9 Segment No. 1 Shore to Tanajib Gas Plant
(29KM LG)
16 PRE-COMMISSIONING STATUS
Cleaning
Gauging Status
Caliper Survey Status
Hydrotest Status
Status
Completed Completed Completed / Accepted Completed
Completed
Completed Completed Completed / Accepted
Completed
Completed, Preliminary
Completed Completed Water filling completed
Report under PTSD review
Completed, Preliminary
Completed Completed Not yet Done.
report
Not yet Done. Not yet Done. Not yet Done. Not yet Done.
Not yet Done. Not yet Done. Not yet Done. Not yet Done.
Not yet Done. Not yet Done. Not yet Done. Not yet Done.
Not yet Done. Not yet Done. Not yet Done. Not yet Done.
US
MFL Status Lay-up Status
Not yet Done. Completed (Dry Layup)
BR.OF SINOPEC
TANAJIB AREA INT.
PKG-16 PIPELINES PETROLEUM 37 31 0 0 0 0 0 0
SERVICE CORP.
Total 31 0 0 0
CNS PIPELINE HYDRO PROCEDURE, MS SUBMISSION AND CURRENT PIPLINE STATUS 17/Dec/2023
FILLING, HYDROTESTING &
CLEANING GAUGING CALIPER SURVEY DEWTERING
ILI Swabbing and Air Drying Nitrogen Purging and Final Layup
PIPELINE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE Remarks
Contractor Contractor PTSD(PSU/ISU)
Status Status Status Contractor Procedure# Status Contractor Procedure# Status Contractor Procedure# Status Contractor Procedure# Status
Procedure# Procedure# /SAPMT
Under Review by
Under Review by PTSD Under Review by PTSD CNS-033,REV.00; Under Review by PTSD
MEG-1 (6") CNS-051,REV.00 PTSD CNS-046 REV.00 CNS-026 REV.00
Under Review by
Under Review by PTSD
CNS-053,REV.00 CNS-054,REV.00 PTSD CNS-056,REV.00 Under Review by PTSD
2. PQI
Month Monthly PQI Cumulative PQI
Jan/23 97.00% 96.70%
Feb/23 95.90% 96.70%
Mar/23 96.50% 96.70%
Apr/23 96.60% 96.60%
May/23 98.10% 96.70%
Jun/23 96.40% 96.70%
Jul/23 97.80% 96.70%
Aug/23 96.10% 96.70%
Sep/23 96.30% 96.70%
Oct/23 97.60% 96.70%
Nov/23 98.10% 96.70%
Dec/23 93.10% 96.70%
Jan/24 98.90% 96.70%
4. LBE STATUS
Discipline Open Closed
MECHANICAL 71 736
WELDING 145 3090
COAT 49 662
CIVIL 6 908
ELEC. & INSTRU, CP, TEL. 20 129
TOTAL 291 5525
5. INCR STATUS
Discipline Open Closed
Mechanical 1 55
Coating 17 143
Welding 0 50
Civil 2 30
Elect. & Instru., CP, Tele. 8 28
TOTAL 28 306
6. SA NCR STATUS
Discipline Open Closed
Mech./Wel /Coat. 0 2
Civil 0 0
Total 0 2
7. SA WS STATUS
Discipline Open Closed
Mechanical 0 0
Welding 2 2
Coating 0 0
Civil 0 0
Total 2 2
9. CIVIL TESTING
Discipline Pass Fail and Retested
FDT 8155 0
Grout 1240 0
Concrete 1764 5
Water ( Sampling) 16 0
Err:509 Err:509 Err:509
Total 11348 26
81 553
127 503
454 2232
31 863
10 111
Joint Basis
Label Value Labels
1 0% Pointer Err:509
2 5% Thickness 0.50%
3 10% Rest 60%
4 15%
5 30%
Linear Basis
Label Value Labels
1 0.00% Pointer Err:509
2 0.10% Thickness 0.01%
3 0.20% Rest 0.70%
4 0.30%
5 0.60%
Next Quality Training Topic: -
1) Pipeline Internal Cleaning, Gauging, and Hydro testing. (Tentative Training Plan: Aug. 17, 2023)
3) HV/MV Equipment Testing & Power System Energizations (Tentative Training Plan: 09-Nov, 2023)
PACKAGE LINEAR BASIS (OVERALL)
16 0.18%
Additional Stone Column is required by CSD. Management decide to follow the comments.
Letter need to be submitted for claim.
Soil Improvement
Design need to be updated
Service Provider need to be Mobilized.
9-Nov, 2023)
CSD. Management decide to follow the comments.
INTERNAL+
SPOOL INT. & EXT. COATING STATUS EXTERNAL TOTAL
EXTERNAL
RELEASED FOR COATING 197 630 827
AFTER COATING RECEIVED AT SITE 47 370 417
DESCRIPTION DELIVERY NOTE
DELIVERY
PIPE SIZE
DATE
DIA API # 24” API 5L Gr. X65 07/Jan/20
DIA API # 36” API 5L Gr. X65 26/Jan/20
DIA API # 26” API 5L Gr. X65 30/Apr/20
DIA API # 06” API 5L Gr. X65 21/Jul/20
DIA API # 20” API 5L Gr. X65 07/Apr/21
DIA API # 12” API 5L Gr. X60 11/Oct/21
DIA API # 28” API 5L Gr. X65 16/Oct/21
O2 Scavenger Calculaion as per SAES-A-007 Apx.A
Residual Scavenger )
cavenger
20 )
Marjan Increment Project - Package 16
Project Schedule Plan
Column1 Column3 Column4 Column6 Column7
SCOPE Completed
Milestone Description Start End Remarks Percentage
Construction Foundation Works
Concrete finishing and Coating application 11/27/2023 12/5/2023 80%
Work Activity @ Crude BVS and Gas BVS
Partial Partial
Excavation Work for Cable Trenches and Foundation Pit 54 20 Completed Completed Pipe Crossing Area is on hold in both Gas and Crude BVS 70%
Installation of Lighting and Camera Poles Foundation 12/6/2023 12/11/2023 Subject to clearance of Pipe Crossing Area in both BVS 0%
Installation of Lighting and Camera Poles 12/12/2023 12/17/2023 Subject to clearance of Pipe Crossing Area in both BVS 0%
Cable Laying for Electrical and Telecom Cables 11/28/2023 12/7/2023 0%
Backfilling and Soil Compaction for the Cable Trench 12/9/2023 12/14/2023 0%
Installation of Field Equipment Panels 12/18/2023 12/24/2023 0%
Installation of Lighting Fixtures and CCTV Cameras including Terminations 12/25/2023 12/30/2023
Subject to clearance of Pipe Crossing Area in both BVS 0%
Work Activity between Gas & Crude / Crude & Transition Yard
Excavation Work for Cable Trenches 11/28/2023 11/30/2023 Subject to finalize the cable route between Crude BVS and Transition Yard by Sinopec 0%
Cable Laying of Fiber Optic Cables 11/28/2023 12/7/2023 Subject to finalize the cable route between Crude BVS and Transition Yard by Sinopec 0%
Backfilling and Soil Compaction 12/9/2023 12/14/2023 Subject to finalize the cable route between Crude BVS and Transition Yard by Sinopec 0%
Testing and Commissioning
Testing and Commissioning 1/1/2023 1/10/23 Subject to clearance of Pipe Crossing Area and Transition Yard by Sinopec 0%
CNS PIPELINE HYDRO PROCEDURE, MS SUBMISSION AND CURRENT PIPLINE STATUS 12/Dec/23
FILLING, HYDROTESTING Nitrogen Purging and Hydrotest &
CLEANING GAUGING CALIPER SURVEY & DEWTERING
ILI Swabbing and Air Drying
Final Layup Layup
PIPELINE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE Procedure
PTSD(PSU/ISU) PTSD(PSU) NAPD Oper.
(Piping)
PTSD/SAPMT SAPID PTSD/SAPMT SAPID SAPID SAPID SAPID PTSD/SAPMT SAPID PTSD/SAPMT SAPID (Rev. 01)
/SAPMT /SAPMT Eng. / PTSD
Re-Submitted
SBTNCL-1 (12") Approved. Approved. Approved. Approved.
(23-Nov-23)
Approved. Approved. Approved. Approved.
SJTNGT-1 (26") Approved. Approved. Approved. Approved. Approved. Approved. Approved. Approved. To be Submit. Approved. Approved. Approved. Approved.
26" Caliper Run Completed on 04-Sep-2023; Hydro test Package Approved by SAPID.
DOWNSTREAM
Approved. 1st Gauging Plate Found Deformation. Approved with Comments by PTSD/SAPMT Approved with comments. Final Electronic Geometry Tool Caliper Approved by PTSD/SAPMT. -Filling Activity Started from 19-Oct-2023.)
SJTNGT-1 (26") Approved by PTSD/SAPMT. -Waiting for Response. 4th Run of Cleaning Apx. 23 Kg of Debris Approved by PTSD/SAPMT. Approved by SAPID. Const. Proposed to proceed with Caliper CNS-006,REV.00; (Status-5) Survey Inspection Report shared to CNS-008,REV.02; Procedure Revised and resubmitted. - Pressurization started on 31-Oct-
[CNS-001,REV.02] CNS-001,REV.02; received - SAPID Accepted. [CNS-002,REV.02; TGPPD-3235; 30-Aug-23 [CNS-002,REV.02; TGPPD-3235; 30-Aug-23 Survey. CRM # 4044901103 & 4044913428 CNS-006,REV.00; SAPMT/SAPID. T-4656; 12-Oct-23 CNS-008,REV.02; 2023,2.00PM.
CRM # 4044847481 [TGPPD-3176; 16-Aug.] [T-4365;22-Aug-23] (23-Aug-23) Calliper Run completed on 04-Sep-2023 T-4001;07-Jun-23 T-4451;07-Sep-23 [T-4574;28-Sep-23] CRM # 4044930045 T-4693;22-Oct-23 - Strength test Completed on 01-Nov-2023
[TGPPD-3256; 30-Aug-23] [TGPPD-3334; 26-Sep.] [TGPPD-3428; 18-Oct.] - Tightness test Completed on 02-Nov-2023
- Dewatering Completed on 06-Nov-2023
Approved with Comments by PTSD/SAPMT. Approved with comments. 24" Caliper Run Completed on 06-Dec-2023; Approved by PTSD/SAPMT.
24" Internal Cleaning started on 24-Nov- 24" Internal Cleaning started on 24-Nov- CNS-020,REV.00; (Status-5) Initial Caliper Survey Inspection Report CNS-036,REV.00; Procedure Revised and resubmitted.
TNTNGG-1 (24") 2023. 2023. 6th Run(Bi-Di) ongoing 29-Nov-23 CRM # 4044927860 & 4044913385 CNS-020,REV.00; shared to SAPMT/SAPID. T-4555;25-Sep-23 CNS-036,REV.01;
3rd Run of cleaning is ongoing. (26-Nov-23) T-4296;09-Aug-23 T-4452;07-Sep-23 [T-4965;14-Dec-23] CRM # 4044981241 T-4895;04-Dec-23
[TGPPD-3262; 30-Aug-23] [TGPPD-3333; 26-Sep.] [TGPPD-3368; 02-Oct.]
Under Review
PMT and Prop. Under Review by PTSD
MEG-1 (6") CNS-051,REV.00; CNS-046,REV.00;
T-4870;04-Dec-23 T-4960;14-Dec-23
Approved by SAPMT.
[MS-1097, Rev.00;
ECT-1 (36") T-4378;27-Aug-23]
[TGPPD-3277; 20-Sep.]
Under Review Under Review
PMT and Proponent. PMT and Proponent.
CNS-051,REV.00; (CNS-052,REV.00;
T-4869; 29-Nov-23) T-4938;12-Dec-23)
Under Review by PTSD
RGP-1 (36") Not Applicable. CNS-048,REV.00;
T-4959;14-Dec-23
UPSTREAM
MFL Swabbing and Air Drying Nitrogen Purging and Final Layup Piping Hydrotest & Layup Procedure
PIPELINE PROCEDURE CURRENT STATUS PROCEDURE CURRENT STATUS PROCEDURE CURRENT STATUS PROCEDURE MS
NAPD Operation Engineering / PTSD SAPID PTSD/SAPMT SAPID PTSD/SAPMT SAPID Proponent/SAPMT SAPID SAPMT CURRENT STATUS
ReSubmited
ECT-1 (36") CNS-030,REV.00;
T-4954;13-Dec-23
ReSubmited
RGP-1 (36") CNS-031,REV.00; Not Applicable.
T-4955;13-Dec-23
UPSTREAM
ReSubmited
RGP-2 (36") CNS-032,REV.00;
T-4970;14-Dec-23
ReSubmited ReSubmited
LGT-2 (20") CNS-027,REV.00; CNS-034,REV.00;
T-4952;13-Dec-23 T-4964; 14-Dec-23
ReSubmited ReSubmited
LGT-1 (28") CNS-029,REV.00; CNS-036,REV.00;
T-4953;13-Dec-23 T-4966; 14-Dec-23
CNS PIPELINE HYDRO PROCEDURE, MS SUBMISSION AND CURRENT PIPLINE STATUS 10/Dec/23
FILLING, HYDROTESTING Nitrogen Purging and Hydrotest &
CLEANING GAUGING CALIPER SURVEY & DEWTERING
ILI Swabbing and Air Drying
Final Layup Layup
PIPELINE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE PROCEDURE Procedure
PTSD(PSU/ISU) PTSD(PSU) NAPD Oper.
(Piping)
PTSD/SAPMT SAPID PTSD/SAPMT SAPID SAPID SAPID SAPID PTSD/SAPMT SAPID PTSD/SAPMT SAPID (Rev. 01)
/SAPMT /SAPMT Eng. / PTSD
Re-Submitted
SBTNCL-1 (12") Approved. Approved. Approved. Approved.
(23-Nov-23)
Approved. Approved. Approved. Approved.
SJTNGT-1 (26") Approved. Approved. Approved. Approved. Approved. Approved. Approved. Approved. To be Submit. Approved. Approved. Approved. Approved.