R.A. BILL NO.

HOME ASSOCIATES
Name of Project : THE LANDMARK, UNDRI, PUNE.
Name of Contractor: Sandeep Gaikwad
RA Bill No: 4
Date : 9/3/2016
SUMMARY

Amount
Sr.No. Item No Description
This Bill Uptodate
Upto Last Bill
1 Running Account Bill Total (LABOUR SUPPLY) 181400 15600 197000

2 Extra Work 0 0 0

3 TOTAL = (1+2) 181400 15600 197000

4 Add S. Tax 0 0 0

5 TOTAL = (3+4). 181400 15600 197000

6 Deductions
Retention Money @ 5% 0 0 0
Debit Amount 0 0 0
T.D.S. @ 1%* (3) 1814 156 1970

7 TOTAL OF DEDUCTIONS 0.00 156 1970.00

8 NET AMOUNT (5-7) 179586.00 15444 195030.00

(RUPEES : FIFTEEN THOUSAND FOUR HUNDRED FOURTY FOUR RUPEES ONLY)


HOME ASSOCIATES

Project : THE LANDMARK

CONTRACTOR : Sandeep Gaikwad

TYPE OF WORK : Departmental Civil Work

R.A.BILL NO- 4
ABSTRACT SHEET

Stage Description Rate QTY. AMOUNT


Upto Last This Bill Upto Date Upto Last This Bill Upto Date
Bill Bill Bill Bill
I DEPARTMENTAL CIVIL WORK
i) Male Coolie 300 332 25.5 357.5 99600 7650 107250
ii) Female Coolie 200 326 35.5 361.5 65200 7100 72300
iii) Carpenter 450 10 1 11 4500 450 4950
iv) Fitter 400 4 1 5 1600 400 2000
v) Carpenter (Helper) 350 8 0 8 2800 0 2800
vi) Fitter (Helper) 350 2 0 2 700 0 700
vii) B.B.M Mason 500 14 0 14 7000 0 7000
ix) Plastering Mason 600 0 0 0 0 0 0

Total Amount 181400 15600 197000


HOME ASSOCIATES
PROJECT-THE LANDMARK.

CONTRACTOR : SANDEEP GAIKWAD

TYPE OF WORK : DEPARTMENT R.C. C WORK


R.A. Bill No : 4

Date : 9/3/2016
LABOUR SUPPLY MEASUREMENT SHEET
Sr. No. Date M/C F/C CARPEN FITTER CARP FITT B.B.M B.B.M Work done

TER (HELP) (HELP) MASON PLASTER


A & B' WING BULIDING PARKING DUCT RABBIOT SHIFTING OUTSIDE
1 6/20/2016 2.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 BLDG STACKING TO CLUB HOUSE SIDE OPEN AREA, FLAT NO-205
CLEANING WORK, DOOR SHUTTERS SHIFTING WORK.

RABBIT SHIFTIONG OF ALL WINGS FROM DUCT TO CLUB HOUSE SIDE


2 6/23/2016 4.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 AREA, 4" FLY ASH BRICK SHIFTYING TO PHASE-II AREA. 4"FLYASH BRICKS
SHIFTING WORK.

SHOP PUMP ROOM FIRE FIGHTING LINE FOUNDATION CONCRETING


3 6/27/2016 4.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 WORK, RETAINING WALL ARCH PORTION MURUM EXCAVATION WORK
LABOUR CAMP SIDE FOR PIPE LAYING.

SHOP AHEAD RAW MATERIAL SHIFTING & STACKING FOR B.B.M WORK
4 6/28/2016 0.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00
OF RAMP AREA PORTIONFROM UKT SIDE AREA.

SHOP AREA SIDE RAW MATERIAL SHIFTING FOR PARKING B.B.M & STEPS
5 6/29/2016 4.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 B.B.M WORK, 'E' BLDG FIRE FIGHTING DOOR FRAME FIXING HURDLE
PORTION AREA CHIPPING WORK.

GAP BELOW LOFT SHUTTERING & STEL BINDING WORK WITH CASTING,
6 6/30/2016 3.00 5.00 1.00 1.00 0.00 0.00 0.00 0.00
SHOP RAMP AREA STEPS B.B.M HELPER WORK.

SHOP PUMP ROOM BOX FOUNDATION CASTING WORK ALSO SHIFTING


7 7/1/2016 3.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00
OF RAW MATERIAL FOR CASTING WORK

8 7/20/2016 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 RAIN WATER HARVESTING CHAMBER SLAB CASTING WORK.

SHOP AREA SIDE RAW MATERIAL SHIFTING FOR PARKING B.B.M & STEPS
9 7/22/2016 2.50 2.50 0.00 0.00 0.00 0.00 0.00 0.00 B.B.M WORK, 'E' BLDG FIRE FIGHTING DOOR FRAME FIXING HURDLE
PORTION AREA CHIPPING WORK.

RABBIT SHIFTIONG OF ALL WINGS FROM DUCT TO CLUB HOUSE SIDE


10 7/24/2016 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 AREA, 4" FLY ASH BRICK SHIFTYING TO PHASE-II AREA. 4"FLYASH BRICKS
SHIFTING WORK.

Total 25.50 35.50 1.00 1.00 0.00 0.00 0.00 0.00