Professional Documents
Culture Documents
Summary Report Feb 2010 (Rev 0)
Summary Report Feb 2010 (Rev 0)
Summary Report Feb 2010 (Rev 0)
1. Introduction 1
1.1 Project Objectives 1
1.2 Project Scope 1
1.3 Purpose of Report 1
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
6. Energy Management 13
6.1 Overview 13
6.2 Constraints 13
6.3 Pump Motors 13
6.4 Control Systems 13
6.5 Electrical Supply Infrastructure 14
6.6 Station Cooling and lighting 15
6.7 Pumping Duty Cycle 16
6.8 Energy Management Recommendations 16
Table Index
Table 1 Number of Pump Stations with Non-Compliant
Safety Assessments 6
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
Table 2 Asset Condition Assessment Rating 8
Figure Index
Figure 1 Typical Pump-Motor Configuration 3
Figure 2 Broken External Light Fittings 10
Figure 3 Metering Box with Exposed Cables 12
Figure 4 Exposed Manholes (Electrical & Sewer) 12
Figure 5 Flat versus Steep Performance Curves 20
Figure 6 Typical Pump Performance Curve 20
Figure 7 Pump Efficiency versus Flow 21
Figure 8 Pumping Power, Pressure and Flow versus Pump
Speed 21
Figure 9 Pump Best Efficiency Curves 21
Figure 10 Pump Curve - Sila Border Post PS, Western
Region (Pump 1) 22
Figure 11 Pump Curve - Bainounah Palace, Ghayathi,
Western Region (Pump 1) 23
Figure 12 Pump Curve - IPS2 Ghayathi, Western Region 23
Figure 13 HH Sheikh Zayed Palace, Delma 24
Figure 14 Samha East PS - Spring Loaded Check Valve and
Gear Operated Butterfly Valve 25
Figure 15 Samha East PS - Additional Pump Steel Fixings 25
Figure 16 Magnetic Motor-Pump Shaft Coupling 26
Figure 17 Energy Savings with Magnetic Pump-Motor Shaft
Couplings 27
Figure 18 Pump Control Valve in In-Line and Angle
Configuration 28
Appendices
A Pumping Station Codes, Identifiers and GPS Coordinates
B Site Safety Assessment
C Civil Assets Assessment
D Pumps and Motors Assessment
E Other Equipment and Systems
F Maintenance and Management Strategy
G ADDC GIS Object Numbers
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
1. Introduction
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 1
Summary Report
2. Pumping Station Assessments
GHD’s site safety assessments are detailed in the individual Pumping Station Assessment Reports and
summarised for all pumping stations in Appendix B.
1
Job Safety Plan for Consultancy Services for Condition Assessment and Energy Management Survey of 39 Nos. of Abu Dhabi
Distribution Company (ADDC) Pumping Stations (GHD, 22 June 2009).
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 2
Summary Report
2.4.3 Other Mechanical and Electrical Assets
Condition assessments of mechanical, electrical and instrumentation assets (other than the pumps and
motors) are detailed in the individual Pumping Station Assessment Reports and summarised for all
pumping stations in Appendix E.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 3
Summary Report
2.8 Asset Maintenance and Management Strategies
Appendix F presents a range of recommended actions and strategies for asset replacement, overhaul,
upgrade, further investigation or no action for each of the assessed pumping stations.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 4
Summary Report
3. Safety and Compliance
Site safety includes the provision of appropriate accommodation and amenities for operating personnel.
ADDC is a "nominated entity" under the Abu Dhabi Environment, Health and Safety Management
System (EHSMS) Decree. All the requirements listed in the Abu Dhabi EHSMS Code of Practice No. 10
are enforceable, including;
working at heights;
electrical safety;
occupational noise;
living and accommodation conditions (including specific requirements for working in remote
locations);
communications; and
site access, egress and security.
All of the following laws, decrees and regulations have specific requirements in relation to the safety
issues and recommendations presented in the individual Pumping Station Assessment Reports and
summarised in this report:
Federal Law No. 8 (1980) - Regulations of Labour Relations;
Ministerial Order No 32 (1982) - Regarding Determination of the ways and means to Protect
Employees against Occupational Hazards;
Cabinet Decision No. 13 of 2009 - General Standards Labour Accommodation;
Decree No. 42 of 2009 - Regarding the Abu Dhabi EHSMS; and
AD EHSMS CoP 10 - Occupational Health and Safety.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 5
Summary Report
Table 1 Number of Pump Stations with Non-Compliant Safety Assessments
No. Pump Stations where:
HAZARD Immediate Action Some Action
is Required is Required
Electric Hazards 16 1
Lighting 15 5
Noise 12 2
Site Security 8
Lock Out / Tag Out 7 2
Housekeeping (General Tidiness) 6
Mechanical Hazards (e.g. Unguarded Plant) 5 2
Ladders / Scaffolding/ Access Ways 5 1
Fire Hazard and Equipment 4
OTHER - Water Quality / Health Hazard 4
Site Access and Egress 3 2
OTHER - Telephone Communication 2
Knowledge of Site Safety Rules 1
Site Emergency Procedures 1
OTHER - Structural Safety Hazard 1
Dust / Fumes
Hazardous Substances
Working at Heights
Pressurized Equipment
Heat Illness / Stress
Personal Protective Equipment (PPE) 5
Confined Space Entry
Recommendations
Issue Personal Protective Equipment (PPE) to all ADDC pump station operators and insist that
visitors and guests provide their own PPE, rather than rely on the local pump station staff having
spare PPE available.
Provide planned, periodic first aid and safety training to all ADDC pumping station operators.
Establish and train operators in emergency procedures (call for help, emergency alerts) for all
pumping stations - especially for remote stations.
Develop English literacy of pumping stations operators so they can read and comprehend safety
manuals, equipment instructions, equipment safety bocks, etc. and report findings and operational
data accurately.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 6
Summary Report
Attend to all electrical, mechanical and general hazards as listed in individual reports.
Install, repair or replace and reinstate to full operation:
– all external lights within pumping station compounds; and
– all internal lights in pump rooms, control rooms, elevated towers, technical rooms and access
corridors within all station buildings and structures where personnel access is required.
Provide lockable and locked access hatches to all storage tanks and elevated tanks for protection of
water quality supplied to the public.
Ensure no unauthorised site access is possible.
Provide accommodation of pumping stations operating personnel (as described in current UAE Safety
Laws).
Clean up and perform routine housekeeping on all pumping stations to ensure personnel safety.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 7
Summary Report
4. Civil Asset Maintenance and Management
Good 75% 2
Fair 50% 3
Poor 25% 4
Failure Imminent 0% 5
Recommendations - General
Regular, independent, condition assessment against set assessment criteria, such as those in the
Assessment Overview Report (GHD, Nov 2009), should be undertaken every 5 years (max) throughout a
civil asset’s life.
As the asset enters the last 25% of its service life, visual inspections should be undertaken more
regularly (say, every 3 years) and supplemented with materials testing until the asset is disposed of,
rehabilitated or replaced.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 8
Summary Report
Recommendation - Storage Tanks
The individual Pumping Station Assessment Reports and this Summary Report specifies whether
material testing of the water storage and elevated tanks should be undertaken, based on the visual
inspection undertaken in this Project to more accurately assess the remaining service lives of these
critical assets (refer Appendix C).
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 9
Summary Report
5. Electrical Asset Maintenance and Management
5.1 Overview
Provision of a critical service (e.g. water supply to a community) includes both scheduled, routine and
repair maintenance as an integral part of the provision of service and is accepted and planned for in
operational staffing and budgeting.
However, this scheduled, routine and repair maintenance was not apparent with the majority of the
systems inspected in the pumping stations visited.
An exception appears to be a regular inspection of fire alarm systems. However this inspection does not
fully extend to repairs or to the provision of a maintenance log book, held locally at each station.
Maintenance logs were not evident or available during inspections.
It appears that they are not repaired and that ordinary interior fittings are then fitted to provide essential
lighting, often of mechanical tank level gauges. The fittings and the wiring are not safe, or are
inappropriate. It is not clear if the fittings are installed by the maintenance engineers or the operators (in
desperation) but it does indicate a failure of maintenance practice.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 10
Summary Report
5.3 Availability of Maintenance
At many pumping stations, operators state that reported faults are not actioned and that they are not able
to obtain simple spares that they are capable of fitting themselves when required (e.g. lamps for pilot
indicators and spare lamps for interior lights).
We suspect that a majority of faults are caused by fluctuating power supply regulation and by power
supply surges. All stations are at particular risk, due to their location, from electrical surges caused by
lightning. Flow and pressure instrumentation is particularly sensitive to surge damage from this cause.
Further, it was noted that many station operate with individual phase voltages above 230 V AC which is
the general upper limit for mains powered equipment. Motor power supplies voltages need to be
maintained below this level.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 11
Summary Report
Figure 4 indicates significant safety issues as two manholes are left exposed. As the broken covers can
be seen lying nearby, it would appear that the situation has not occurred recently. While this situation
exists in a depot, outlying stations will not be maintained to a higher standard.
Figure 3 Metering Box with Exposed Figure 4 Exposed Manholes (Electrical &
Cables Sewer)
5.7 Recommendations
Maintenance quality and completeness is to be specified and directed as a Management Objective.
Conduct an annual thermo scan on all major switchboards, control panels and motor cable
terminations. This will find most common faults.
During the course of these pumping station assessments, electrical testing did not indicate that motor
resistance testing was going to show anything useful. Load tests showed that some motors were
operating in overload conditions, but this should have been clear apparent at station commissioning
and doesn’t need to be checked annually.
Maintain a log of maintenance actions to be kept on each site and regularly reviewed by Senior
Management staff.
Specific, routine maintenance tasks, able to be performed by operators, should be defined and
appropriate training given to the operators.
A procedure to obtain maintenance spares is to be formulated and implemented.
Instrumentation repairs are to be logged and the cause of fault is to be determined, wherever
possible.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 12
Summary Report
6. Energy Management
6.1 Overview
The Abu Dhabi Distribution Company (ADDC) has a mandate to manage its operations as efficiently as
possible. The sole power source used to distribute water, apart from tanker deliveries, is electricity and
therefore the management of electric power is a principal concern to the ADDC. Power is consumed
within a pumping station by:
Pump motors;
Control systems;
Electrical supply infrastructure;
Station cooling and lighting; and
Various station systems (e.g. fire alarms, exterior lighting)
6.2 Constraints
As water supply is a critical service, energy management must be examined in the context of water
supplied on an ‘as required’ basis rather than on the basis of greatest efficiency. Accordingly, elevated
storage tanks may need to be kept filled to within a narrow range of head rather than filled on, say, the
basis of average daily usage with the consequent pressure variations. Thus, a clear statement of these
operational constrains needs to be formulated for each station before detailed management strategies
can be considered.
During the conduct of the pump station assessment, there was no evidence that the operators have a
clear understanding of the operational constraints and requirements of their stations. Some stations
appear to be run only to change water in the tanks where distribution pressure is sufficient to supply the
needs of the distribution network. Other stations are required to boost pressure for tanker filling to reduce
waiting times. These operations are not energy efficient but are time and cost effective.
Recommendation
When new motors are purchased for new installations, or for replacement, higher efficiency units should
be considered.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 13
Summary Report
6.5 Electrical Supply Infrastructure
Efficiency in power supply is mainly dependent on appropriate selection of components (i.e. cable sizes
and maintenance of a high power factor). Specific comment on the sizing of HT and LT supply cables is
beyond the scope of this report. However, only one instance of significant supply sag with increasing
load was noted during station testing (viz. Liwa Rest House Pumping Station, Western Region).
Generally, where stations are provided with dedicated supply transformers it was noted that these units
were significantly oversized. In many cases units were only loaded to approximately 20% of their
capacity. As few stations are running at near capacity, or requiring more than about 33% of pumping
capacity to be used at any on time, this over capacity represents a significant inefficiency due to standing
‘iron’ losses in the transformer.
If losses are 1- 2 % of full load capacity, a 500 KVA transformer will consume up to 24 x 10 Kw-hr (240
Kw-hr) per day. This may be balanced against a possible pumping requirement of 4 hrs x 30 Kw (120
Kw-hr) per day of productive load. The imbalance is clear.
A proportion of stations visited were fitted with Power Factor (PF) correction. Installations consisted of:
Automatic correction panels integral to the Main Switchboard (MSB);
Automatic correction panels external to the MSB, typically wall mounted adjacent to the MSB; and
Correction applied to individual motors, fitted internally in the motor control panel.
Where performance could be verified, either by observation of control action or direct measurement only
about 50% of units were working. In some instances controllers appeared to have been connected to the
wrong measuring point, in others the controllers were simply faulty. Where measurement was possible,
only about 50% of capacitors were working and displayed a name plate ‘VAr’. Reasons for the high
failure rate are speculative, but most likely failure is due to over temperature and over voltage/surge
affecting the controller.
Recommendations
To provide surge/spike protection to existing stations, the fitting of an automatic panel represents the
most straight forward option. To circumvent the poor field performance, units should be fitted with surge
protection and thermostatic fans for the capacitor compartments.
For new stations, it is recommended that Power Factor (PF) correction be installed in the motor control
panels and directly switched when motors are operated. As with automatic panels, thermostatically
controlled fan cooling should be provided for the PF panels. As a maintenance aid, a means of testing
operation (e.g. space for clamp meter connection) should be provided.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 14
Summary Report
6.6 Station Cooling and lighting
Consideration of station cooling and lighting needs to be segregated into consideration of the pumping
room and control and amenity rooms. Control and amenity rooms require comfortable air conditioning
and energy management will be achieved in these spaces by the appropriate selection of plant and
placement. Selection of air conditioning plant will be affected by maintenance considerations, however it
was noted that older pumping stations are cooled by packaged, thru-wall systems, which are not energy
efficient.
Recommendation
An air conditioning replacement programme, swapping thru-wall units for more efficient split systems,
would provide significant savings as air conditioners appear to be run continuously. A simple time
control strategy matched to station operating hours could provide additional savings.
Recommendation
Thermostatically controlled, directed air ventilation-only systems should be designed and provided for
pump rooms to deliver the coolest possible air to the pump motors.
Recommendation
Care should be taken with future stations to ensure that lighting can be controlled such that only the
required level of lighting is used. This could be achieved by reduced general lighting and increased,
locally switched, task lighting.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 15
Summary Report
6.6.3 Lighting of pumping rooms
Pump rooms are all provided with high efficiency lighting fittings, either HID or fluorescent, and these
have been observed to be appropriately controlled, (i.e. used only when necessary).
Recommendation
Simple control by operators, aware of energy saving intentions, will provide an adequate control strategy
in this area.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 16
Summary Report
7. Motor Control Systems
7.1 Overview
In newer stations, control systems are being configured for possible remote control and monitoring. In
this context, it is important that the control system have a reliable power system that will continue to
function during a power failure, or at least long enough to signal the power fail condition to a central
location. From observation it is also noted that stations with a PLC based control system, most often
featuring a mimic panel display, include redundant power supply systems within their wiring.
At two pumping stations (i.e. Jabbana, Western Region and Jubail Island, Eastern Region), batteries
have been provided to power the control system during a power outage. However in one case (i.e.
Jabbana) the charging system had been removed. Where the control system is based on a computer
screen operator interface, an Uninterrupted Power Supply (UPS) system has been provided to ensure
continuity of power supply.
Although this report does not consider a requirement for control systems to be active to safely shut-down
a station upon loss of power (i.e. to close non-return valves to prevent backflows), it would seem prudent
that every station automatically returns to a safe condition upon complete loss of power.
The actual need for control systems, beyond electrical safety interlocks and motor protection, must be
considered in the context of station staffing, as local staff (if trained) will always out-perform a control and
monitoring system.
It is also noted that when an operator was present, the majority of stations can be operated even though
the control system has failed. This assertion warrants further investigation as it was noted that, for the
four Grain Al Ayesh Pumping Stations (Nos. 1 to 4), the control system is capable of preventing manual
operation of the system.
Smaller pumping stations feature mechanical, fast acting non-return valves in series with each pump.
Such systems are stable under power failure conditions and need no control or operator action to ensure
stability.
The majority of control systems employed in pumping stations are run on 24V DC. Some utilise 230V AC
instrumentation, and one system is apparently 110V AC.
If stations retain local control there in no need for control systems to remain powered during power
failures.
The need for a mimic and control panel is questionable as staff have sufficient time to gather the
monitoring information presented on the panels and can easily be aware of station operation without the
assistance of coloured lights.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 17
Summary Report
7.3 Recommendations
In the absence of a clear policy on automation, it is assumed that station control will remain local.
It would seem prudent, therefore, that station controls allow for full manual override and operation of
pumps under all circumstances.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 18
Summary Report
8. Mechanical Asset Maintenance and Management
8.1 Overview
This section presents a sound, technical approach to selection of pumps, motors, pipework and
associated mechanical equipment.
The ADDC pumping stations discussed in this report contain a total of 126 off “centrifugal water pump
sets” with associated pumps, electric motors, pipework, and flow control valves.
Overhung-Impeller, End Suction, Vertical Split Case - both close and long coupled type. These
pumps most often have been used on low water delivery rate duties starting from 10 l/s.
Double suction, single or two stage with axial (horizontal) or vertical split type case. These pumps
have been used on high water delivery rates up to 300 l/s.
Multistage vertical, centrifugal motor pumps. Typically this type of pump would be installed on system
with low water delivery rate and very high system pressure. This type of pumps has been observed in
the pumping station serving the Sea Palace.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 19
Summary Report
Figure 5 Flat versus Steep Performance Curves
2. Selection of pump design performance point within the highest efficiency area of pump curves.
Figure 6 below illustrates how many different pump types and sizes can be selected for given flow
duty. It is important to select the pump with highest pumping efficiency.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 20
Summary Report
3. Accurate estimation of piping (network) system dynamic pressure losses and static heads.
Figure 7 below illustrates how inaccurate estimates will result is selection of under or oversized
pumps, hence lower pumping efficiency.
4. Accurate estimation and selection of pump flow rate (water delivery rate) is essential. Inaccurate
estimates will result is selection of under or oversized pump, hence lower pumping efficiency.
5. Accurate selection of pump flow duty point – pump duty point should be the same as estimated duty.
A fixed speed pump can perform with high efficiency for one duty point only. In order to achieve high
pumping efficiency for changing delivery rates, variable speed pumps should be used. Figures below
represent pump power and efficiency curves at variable speed condition.
Figure 8 Pumping Power, Pressure and Flow Figure 9 Pump Best Efficiency Curves
versus Pump Speed
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 21
Summary Report
6. Accurate selection of electric motor for pump duty.
Electric motors should be sized to pump pumping duty and pump performance within entire
performance range of the impeller. Unnecessarily oversized motors are less efficient and will
contribute to reducing the efficiency of the pump.
Figure 10 Pump Curve - Sila Border Post PS, Western Region (Pump 1)
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 22
Summary Report
Figure 11 Pump Curve - Bainounah Palace, Ghayathi, Western Region (Pump 1)
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 23
Summary Report
8.2.6 Pump – Pipe Connections
All pump stations were observed to have installations divided into two categories:
1. Pumps directly connected to adjoining pipework; and
2. Pumps connected via single bellow rubber couplings.
There was no obvious reason why some pumps have been pipework hard connected and some not.
On number of pumping stations where flexible couplings have been installed on pumps, flexible
couplings have been braced (hard locked in position) with steel brackets (refer Figure 13). This situation
often occurs where pumps are not fixed (bolted) into the plinths. It is suspected these methods have
been applied in order to prevent pump movement during start-up moments.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 24
Summary Report
Figure 14 Samha East PS - Spring Loaded Check Valve and Gear Operated Butterfly Valve
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 25
Summary Report
8.2.9 Pumps and Mechanical Maintenance and Service
No evidence of service or preventative maintenance has been found at any of the visited pumping
stations. Most (if not all) abnormalities, malfunctions or technical problems found appear to be related to
a complete lack of service and regular maintenance.
8.3.1 Pump – Motor Mechanical Coupling, Shaft Alignment and Replacement of Damaged
Shaft Couplings
It is recommended the following urgent action to be taken by ADDC:
1. Replace ALL pump-motor shaft couplings, condition rated at 4, 5 or 6, with new couplings; and
2. Conduct shaft alignment on all listed pumps (94 off) assessed as being out of manufacturer’s
allowable limits.
NOTE: Both the above actions should be conducted at the same time. Do not replace damaged coupling
unless it follows with immediate shaft alignment.
Estimated budget cost for pump alignment per pumping station = AED 5,000
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 26
Summary Report
The principal of the magnetic coupling operation is based on two magnetic discs mounted on both ends
of motor and pump shaft with a tiny air gap between them. Mechanical power and torque is transferred
from motor to pump through the magnetic force existing between two discs.
The advantages of magnetic coupling application include:
Maintenance free coupling with a life expectancy exceeding the pump set;
Pumps with magnetic couplings do not require shaft alignment; and
Energy savings.
Magnetic coupling provide a disconnected “cushioned” start because the motor does not need to
overcome load inertia, the peak demand and duration of current are reduced significantly leading to
energy savings (refer to Figure 17).
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 27
Summary Report
As an example of fitting magnetic couplings, a budget sample (per each pump) for the Liwa Hotel Pump
Station is:
Pumps 3 off, each 12 l/s water flow, motor 30 kW, speed 2870 rpm
AED 12,000 - Coupling cost (each)
AED 13,000 - Cost (each): Installation, commissioning
AED 25,000 - Total budget per pump
Surge tanks are recommended to complement and minimise water hammer in pumped pressure mains
due to transient pressures in the distribution network.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 28
Summary Report
– Ensure that related pumps and pipework surrounding each coupling is secured correctly.
Reminder – many couplings have been braced in order to secure moving and unfixed pump sets
or secure incorrectly supported pipework with valves.
3. In all other pumping stations with pumps hard connected (no couplings) into the pipework – install
appropriate flexible couplings.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 29
Summary Report
– Based on current pumping stations and future plans and designs, select a few pump types and
sizes for use on all ADDC stations.
Bigger pumping stations can be designed using a greater number of smaller pumps also used in
smaller stations.
Pumping stations with a growing water demand can have additional smaller (standard) size pumps
added on rather than oversized, inefficient pumps installed at commissioning.
– The advantages of standardizing pump sets can also be applied to electric motors, valves, meters,
pipe fittings, instruments, control panels, electrical boards, etc.
Pump availability and stand-by capacity
– Equipment (pumps) availability and stand-by capacity is integral with standardization and use of
multiple smaller pump sets rather than lesser number of larger pumps or a variety of different
pump equipment.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 30
Summary Report
9. Technician and Operator Training
9.1 Overview
Any consideration of operator training must be undertaken in the context of future station operation. It
has been suggested that fully automatic operation with remote monitoring is being considered. If this
strategy is to be adopted, this must be clearly defined before decisions are made concerning technician
and operator training.
Full Automation
If fully monitored and controlled is being considered then it is assumed to include the following features:
All pump scheduling centrally managed;
All pump and station alarms centrally monitored;
All status information (e.g. flow and cumulative flow) centrally monitored.
Monitoring of this nature requires a significant investment in station and central plant and requires a
(relatively) high capacity data link. With a system of this type, the current number of operators is
unnecessary, and indeed is unwanted. At most, a site security/ guard function is all that is required.
Accordingly, operator training is irrelevant. Regular checks would be undertaken by a maintenance team
who would also provide a rapid response in case of major faults. To date, all stations visited have
significant spare pumping capacity, so the loss of a single pump would not constitute an urgent situation.
Loss of power and fire alarms are more of a concern.
Local Automation
Station operators could use their existing automation (i.e. scheduling and standby selection and
response to flow or level signals) to operate the station. Control would still be centralised but would be
restricted to the monitoring of fault information and key process information (e.g. actual or cumulative
flow). Such a system would require a relatively low capacity data link, possible based on a GSM link
with individual data calls on schedule and in fault situations. As with full automation, this option doesn’t
require operators and therefore training is irrelevant. As before however, there is a need for a competent
maintenance team who are able to monitor the reports and to respond as required.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 31
Summary Report
Operators typically appear to ignore the automatic controls and manually control the pumps and their
scheduling. The hours run metering suggests that the principle concern of the operators is to maintain
equal hours run for each pump.
Lack of control maintenance has also allowed/required operators to develop their own methods of
operating the station. At Samha East Pumping Station, it was noted that, to shut down a pump, operators
would close the flow isolation valve and then shut down the pump using the local emergency stop
control. This (now) routine procedure was necessitated by the failure of the non-return valves, which
remain ineffective. At the same station all main isolator switches on all the motor control panels were
damaged. This can only have been the result of frequent operation of the isolators which should not
have been routine. The reason for why this procedure in still in place is unknown, but the results are
broken isolators, which are an urgent safety concern.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 32
Summary Report
10. GIS Object Identifiers
Recommendation
It is recommended that the uncorrelated GIS Objects (‘blank’ cells) be established (or re-established) in
ADDC’s GIS.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 33
Summary Report
11. Conclusions and Recommendations
11.2 Conclusions
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 34
Summary Report
Pump Station operator accommodation and amenities in nearly all older sites is non-existent or sub-
standard.
ADDC, as a representative organisation of the Abu Dhabi government, will be expected to meet these
government labour laws and regulations sooner than the general industry.
Nearly all pump stations lack dedicated site office facilities with amenities for operations staff and for safe
storage of pump station records.
Power transformers are up to 2 times larger the total power demand of the pump station they serve.
Based on preliminary calculations, the energy losses in some transformers is higher than the energy
requirements of the pump station running at full capacity.
Unqualified Technicians
While evidence of maintenance has been done, it has been of a temporary nature or been carried out by
unqualified persons, resulting in unsafe electrical equipment, unstable pipe to pump connections or poor
quality repairs which will require repair in the near future.
When maintenance is eventually carried out, it is undertaken either by the untrained operators (out of
desperation), or by others who remove components for repair, but in many cases do not reinstalled them.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 35
Summary Report
GHD’s assessment revealed a considerable number of pumps, motors and instruments had been
removed from service for many months, and often, for years.
11.3 Recommendations
It is strongly recommended that ADDC to develop a standardized, but simple, design brief for its future
built pump stations that minimises the issues related to efficiencies, ‘over design’, remote locations,
maintenance/service, reliability and untrained operations staff.
This “standard design brief” should be developed around a performance-based process of “go back to
basics” design and construction focussing on modular, standardised components. The performance
criteria should ensure pumping station components can be combined to produce both small and large
capacity pumping stations, while allowing individual pumping stations to grow to meet local growing
demand. All design consultants and construction contractors should be bound to follow this Standard to
ensure uniform, simple, robust designs are delivered to construct uniform and simple, very efficient, low
maintenance but very well engineered pumping stations. Value engineering should not detract from
adherence to uniform designs and equipment configurations.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 36
Summary Report
Fully Automated
Monitoring of this nature requires a significant investment in station and central plant and requires a
(relatively) high capacity data link. With a system of this type, the current number of operators is
unnecessary, and indeed is unwanted.
Local Automation
Station operators could use their existing automation (i.e. scheduling and standby selection and
response to flow or level signals) to operate the station. Control would still be centralised but would be
restricted to the monitoring of fault information and key process information (e.g. actual or cumulative
flow.
Personnel Qualifications
It is recommended that implementation of routine servicing and preventative mechanical and electrical
maintenance to be carried out at all of ADDC pumping stations. All maintenance work should be
conducted by qualified, licensed personnel (i.e. licensed electrician, licensed plumber, pump mechanic,
qualified electro-mechanical commissioning technician) by either a specialised company or on sub-
contract to ADDC regional bases.
The routine “maintenance” team would travel to all stations over 12 months to provide standard service
and maintenance, while the other team would be attend all emergency calls and undertake planned
repair works. Both teams would be equipped with large size 4-WD truck equipped with all necessary
tools, small spare parts and equipment elements.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations 37
Summary Report
Appendix A
Pumping Station Codes, Identifiers and
GPS Coordinates
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
Pumping Station Codes, Identifiers and GPS Coordinates
GPS Field
PS Coordinates
Region Area Pump Station Description ADDC MAXIMO ID
Code
North East
C01 Central Region Abu Dhabi City Sea Palace (new) DW-AUH-E17-WPS1 24° 27.963' 54° 24.379'
C02 Central Region Abu Dhabi City H. H. Shk. Khalifa PS DW-AUH-W30-WPS1 24° 26.726' 54° 20.845'
C03 Central Region Abu Dhabi City H. H. Shk.Hamdan PS DW-AUH-W1902-WPS1 24° 26.875' 54° 21.781'
C04 Central Region Abu Dhabi City Jubail Island PS DW-SAL-WPS1 24° 31.933' 54° 27.628'
E01 Eastern Region Baniyas Military Accommodation DW-WTB-WPS2 23° 55.189' 52° 57.818'
E02 Eastern Region Al Khatim Al Khatim DW-KHT-WPS1 23° 50.698' 52° 41.094'
E03 Eastern Region Samha Samha West DW-SMW-WPS1 24° 39.016' 54° 54.734'
E04 Eastern Region Samha Samha East DW-SME-WPS1 24° 40.767' 54° 46.194'
E05 Eastern Region Samha Ghanada DW-GND-WPS2 24° 46.874' 55° 05.511'
E06 Eastern Region Shahama Zubara DW-AHL-WPS1 24° 39.016' 54° 54.734'
E07 Eastern Region Shahama Shahama DW-SHM-WPS1 24° 23.708' 54° 31.179'
W01 Western Region Sila Sila border post DW-SIL-GWF-WPS1 24° 08.713' 51° 38.782'
W02 Western Region Sila Sila Mena P.S DW-SIL-WPS4 24° 08.269' 51° 38.917'
W03 Western Region Ghayathi IPS 2 DW-RWS-WPS2 24° 09.077' 51° 38.326'
W04 Western Region Ghayathi Ghayathi DW-GHT-WPS1 23° 54.068' 52° 44.364'
W05 Western Region Ghayathi Bida Al Mutawa DW-BMW-WPS1 23° 51.596' 52° 45.030'
W06 (Not Used) (Not Used) (Not Used) (Not Used) (Not Used)
W07 Western Region Ghayathi Bainounah Palace DW-GHT-WPS2 23° 59.681' 52° 37.186'
W08 Western Region Ghayathi Sir Baniyas - PS 1 (Old) DW-SBN-WPS1 24° 18.959' 52° 37.043'
W09 Western Region Ghayathi Sir Baniyas - PS 2 (New) DW-SBN-WPS2 24° 16.800' 52° 47.182'
W10 Western Region Liwa Jabbana Main PS / TFS DW-LWE-JBN-WPS1 25° 03.260' 54° 04.944'
W11 Western Region Liwa HH Shk. Zayed Palace DW-LWA-MUZ-WPS1 23° 07.084' 53° 46.559'
W12 Western Region Liwa Liwa Hotel DW-LWA-SMZ-WPS1 23° 34.558' 53° 16.114'
W13 Western Region Liwa Rest house area DW-LWW-DFR-WPS1 23° 07.023' 53° 45.256'
W14 Western Region Liwa Mougab DW-LWW-MQB-WPS1 23° 11.462' 53° 38.976'
W15 Western Region Liwa Hamrour DW-LWW-HMR-WPS1 23° 07.001' 53° 36.598'
W16 Western Region Liwa Shaya DW-LWW-CHA-WPS1 23° 08.612' 53° 41.361'
W17 Western Region Liwa BuSaddain DW-LWW-SDN-WPS1 23° 09.903' 53° 38.989'
W18 Western Region Mirfa Mirfa TFS DW-MRF-WPS1 24° 05.240' 53° 28.466'
W19 Western Region Mirfa Tarif DW-TRF-WPS1 24° 02.295' 53° 45.871'
W20 Western Region Mirfa Abu Al Abyad Old PS DW-ABL-WPS1 24° 06.909' 53° 52.938'
W21 Western Region Mirfa Abu Al Abyad New PS DW-ABL-WPS2 24° 10.385' 53° 46.368'
W22 Western Region Mirfa Grain Al Ayesh - 1 DW-GSH-WPS1 22° 09.940' 53° 36.057'
W23 Western Region Mirfa Grain Al Ayesh - 2 DW-GSH-WPS2 23° 07.084' 53° 38.989'
W24 Western Region Mirfa Grain Al Ayesh - 3 DW-GSH-WPS3 23° 05.999' 53° 36.623'
W25 Western Region Mirfa Grain Al Ayesh - 4 DW-GSH-WPS4 23° 02.531' 53° 27.571'
W26 Western Region Delma HH Shk. Zayed Palace DW-DLM-WPS1 24° 29.877' 52° 20.003'
W27 Western Region Delma Al Jabal Shabia, PS No. 2 DW-DLM-WPS2 24° 55.032' 52° 21.383'
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations A1
Summary Report
Appendix B
Site Safety Assessment
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
SITE SAFETY ASSESSMENT
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Site Acces s and Egres s Y es No Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es No Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es No Y es Y es Y es Y es Y es Y es Y es Y es Ye s . Y es
Site Security Y es Y es Y es Y es Y es Y es No No Y es Y es Y es Y es Y es Y es Y es Y es Y es No Y es Y es Y es No Y es Y es Y es Y es No No Y es Y es Y es Y es No Y es Y es No Y es
Lighting Y es Y es Y es Y es No Ye s . No Y es No No Y es Ye s . Ye s . Ye s . No No No No No Y es Y es Y es Y es No No No No No Y es Y es No Y es Y es Y es Y es No No
Electrical Hazards Y es No No Y es Y es No No No Y es Y es No No No Ye s . No Y es Y es Y es No Y es Y es Y es Y es No No No No No Y es No Y es Y es Y es Y es Y es Y es Y es
Nois e Y es Y es Y es Y es Y es Y es Y es No Y es Y es Y es Y es Y es No Ye s . Y es Y es No No No No No Y es Y es Y es Y es No Y es No Y es No Y es Y es No Y es No No
Dus t / Fum es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es
Working at Heights Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es
Ladders / Scaffolding Y es Y es Y es Y es Y es No No No Y es Y es Y es Ye s . Y es No No Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es Y es
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations B1
Summary Report
Appendix C
Civil Assets Assessment
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
CONDITION ASSESSMENT - Buildings & General Infrastructure
Pumping Station
Asset
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Access Road 2 2 2 1 2 2 4 4 4 4 3 1 4 4 4 3 2 5 4 4 3 2 1 2 2 3 5 3 4 3 1 4 4 4 4 4 2
Boundary Fence / Walls 2 2 2 NA 2 2 3 4 1 NA 3 1 3 3 4 2 2 NA 2 3 3 2 1 2 2 2 NA 6 2 NA 1 2 2 2 2 6 2
Entry Gate NA 2 2 NA 2 2 3 3 NA NA 3 3 2 5 4 2 2 NA 2 3 3 2 1 2 2 2 NA 3 2 NA 1 2 6 2 2 3 2
Security House NA NA NA NA 2 NA 3 3 1 NA NA 1 NA 5 NA 3 2 NA 2 3 NA NA 1 2 2 2 NA NA 2 NA 1 2 2 2 2 NA NA
External Walls NA NA NA NA 2 NA 3 3 1 NA NA 1 NA 4 NA 3 2 NA 2 3 NA NA 1 2 2 2 NA NA 2 NA 1 2 2 2 2 NA NA
Roof NA NA NA NA 2 NA 3 2 1 NA NA 1 NA 3 NA 3 2 NA 2 3 NA NA 1 2 2 2 NA NA 2 NA 1 2 2 2 2 NA NA
Internal Walls NA NA NA NA 2 NA 3 3 1 NA NA 1 NA 4 NA 3 2 NA 2 4 NA NA 1 2 2 2 NA NA 2 NA 1 2 2 2 2 NA NA
Internal Amenities NA NA NA NA 2 NA 3 NA NA NA NA 1 NA NA NA 3 2 NA 2 5 NA NA 1 3 3 2 NA NA 2 NA 1 2 2 2 2 NA NA
Pump House 2 2 2 1 2 3 3 4 1 3 3 1 2 3 3 3 2 3 2 3 3 2 1 2 2 2 2 4 2 4 1 2 2 2 2 NA 3
External Walls 2 2 2 1 2 3 3 4 1 3 3 1 2 3 3 3 2 3 2 3 3 2 1 4 2 3 2 4 2 4 1 2 2 2 2 3 3
Roof 2 2 2 1 2 4 3 4 1 3 3 1 2 3 3 3 2 3 2 3 3 2 1 3 2 2 3 NA 2 4 1 2 2 2 2 3 3
Internal Walls 2 2 2 1 2 3 3 4 1 3 3 1 2 3 3 3 2 3 2 3 3 2 1 3 2 2 2 4 2 4 1 2 1 2 2 3 3
Office & Internal Amenities NA NA NA 1 NA 6 3 NA 1 3 6 1 2 3 3 NA NA NA NA 3 NA 2 1 3 2 3 2 4 2 NA 1 2 2 2 2 NA NA
Accommodation NA NA NA NA NA NA NA 5 6 NA NA NA NA 3 NA NA 2 NA 6 5 6 NA NA NA NA NA 5 NA 2 NA 1 NA NA NA NA NA NA
External Walls NA NA NA NA NA NA NA 5 6 NA NA NA NA 3 NA NA 2 NA 6 NA 6 NA NA NA NA NA 5 NA 2 NA 1 NA NA NA NA NA NA
Roof NA NA NA NA NA NA NA 5 6 NA NA NA NA 3 NA NA 2 NA 6 NA 6 NA NA NA NA NA 5 NA 2 NA 1 NA NA NA NA NA NA
Internal Walls NA NA NA NA NA NA NA 5 6 NA NA NA NA 3 NA NA 2 NA 6 NA 6 NA NA NA NA NA 5 NA 2 NA 1 NA NA NA NA NA NA
Internal Amenities NA NA NA NA NA NA NA 5 6 NA NA NA NA 3 NA NA 2 NA 6 NA 6 NA NA NA NA NA 5 NA 2 NA 1 NA NA NA NA NA NA
Internal Roads 3 2 2 1 2 2 4 6 1 4 3 1 3 3 3 3 2 5 2 2 3 2 1 3 3 2 NA 4 NA NA 1 2 1 2 2 3 2
Internal Paths NA NA NA NA 3 2 4 2 1 NA 3 1 3 4 NA 3 2 NA 2 2 3 2 1 3 3 2 NA NA NA NA 1 2 1 2 2 3 2
Landscaping NA NA NA NA 2 2 NA 2 1 NA 3 NA NA NA NA NA 2 NA NA NA 3 NA 1 NA NA NA NA NA NA NA NA 2 2 2 2 NA NA
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations C1
Summary Report
COND ITION ASSESSMENT - Storage/ Transfer Water Tanks
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
STORAGE / TRANSFER TANK 01
External - Walls 2 2 2 1 3 2 3 4 1 3 3 1 4 3 3 3 2 3 3 4 3 2 1 4 4 3 4 4 4 4 2 2 2 2 2 4 4
External - Roof 2 2 2 1 2 2 3 3 1 3 3 1 3 3 3 3 2 3 3 3 3 2 1 4 4 2 3 3 3 4 1 2 2 2 2 3 3
Extern al - Roof Acces s 2 2 2 1 2 2 2 4 1 3 3 1 3 3 3 3 2 3 3 3 3 2 1 3 2 2 3 3 4 5 1 2 2 2 2 3 3
External - Roof Hatches 2 2 1 1 3 2 2 3 1 3 3 1 3 3 3 3 2 3 3 4 3 2 1 3 4 2 4 3 4 5 1 2 2 2 2 3 5
Internal - Walls NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA
Internal - Floor NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA
Internal - Roof NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA NA
Water Level Indicator 2 2 1 1 2 3 NA
6 1 6 5 6 3 2 3 3 NA
2 1 NA3 NA
3 6 6 NA6 3 2 2NA2 2 NA NA NA NA
Material Testing (Yes / No) No YES YES No YES YES YES YES No No YES No YES YES YES YES YES YES YES YES YES No No YES YES YES YES YES YES YES No No No No No YES YES
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations C2
Summary Report
CONDITION ASSESSMENT - Storage/ Transfer Water Tanks
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
ELEVATED TANK 01
Tank Tower/ Stand 2 2 3 1 3 2 3 2 2 2 3
Tank Tower Acces s 2 NA 3 1 4 2 5 2 2 2 3
Pipe Ris ers 1 NA 3 1 3 2 5 2 2 2 3
Pipe R is er Supports 2 2 3 1 3 NA 5 2 2 2 3
External - Walls 2 2 3 1 3 2 3 2 2 4 3
External - Roof 4 2 NA NA NA NA NA 3 4 4 NA
Internal - Walls NA 2 NA NA NA NA NA 2 NA NA NA
Material Testing (Yes / No) No YES YES No YES No YES YES YES YES YES
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations C3
Summary Report
CONDITION ASSESSMENT - Pipework & Valves (Suction Side)
Pumping Station
Pipework & Valves
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
E01
E02
E03
E04
E05
E06
E07
C01
C02
C03
C04
Suction Header Pipework 2 2 2 1 2 2 2 3 1 2 3 NA 3 3 3 3 2 3 3 3 3 2 1 NA NA NA 2 2 1 4 1 2 2 2 2 NA NA
Suction Header Valves 2 2 2 1 2 2 3 3 1 3 3 NA NA 3 NA NA 3 NA NA 3 NA 2 1 2 2 2 2 2 1 5 1 2 2 2 2 NA NA
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations C4
Summary Report
CONDITION ASSESSMENT - Pipework & Valves (Delivery Side)
Pumping Station
Pipework & Valves
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Delivery Header Pipew ork 2 2 2 1 2 2 2 3 1 2 3 1 3 3 3 3 2 3 3 3 3 2 1 2 2 2 2 3 1 4 1 2 2 2 2 3 3
Delivery Header Valves 2 2 2 1 2 2 3 3 1 3 3 NA 3 NA 2 NA 3 NA 2 3 NA 2 1 2 2 2 2 NA 1 4 1 2 2 2 2 NA NA
Flexible Couplings
Pum p 1 NA 3 2 1 NA NA NA 4 1 3 NA 2 3 3 NA 3 3 3 2 3 4 2 5 2 2 2 2 NA 1 3 4 2 2 2 2 6 6
Pum p 2 NA 3 2 1 NA NA NA 4 1 3 NA 2 3 3 NA 3 3 3 2 3 4 2 5 2 2 2 2 NA 1 3 4 2 2 2 2 6 6
Pum p 3 NA 3 2 1 NA NA 4 1 3 NA 2 3 NA 3 3 3 2 3 4 2 5 2 2 2 2 NA 1 3 4 2 2 2 2 6 6
Pum p 4 NA 4 3 3 3 2 3 2 1 3 4 2 2 2 2
Pum p 5 NA 4 3 3
Pum p 6 NA 3 3
Non-Return Valve
Pum p 1 2 3 2 1 3 2 3 6 4 6 3 1 3 3 5 3 3 3 3 3 3 2 4 2 2 2 2 3 1 5 1 2 2 2 2 3 3
Pum p 2 2 3 2 1 3 2 3 4 4 3 3 1 3 3 5 3 3 3 3 3 4 2 4 2 2 2 2 NA 1 5 1 2 6 2 2 3 3
Pum p 3 2 3 2 1 6 3 6 4 3 3 1 3 5 3 3 3 3 3 3 2 4 2 2 2 2 3 1 5 1 2 2 2 2 3 3
Pum p 4 2 4 3 3 3 3 3 2 1 NA 1 2 6 2 2
Pum p 5 2 4 3 3
Pum p 6 2 3 3
Isolation Valves
Pum p 1 2 3 2 1 6 2 3 2 4 3 3 1 3 3 3 3 3 3 3 3 3 2 4 2 2 2 2 3 1 5 1 2 2 2 2 3 6
Pum p 2 2 3 2 1 3 2 3 2 4 3 3 1 3 3 3 3 3 3 6 3 3 2 4 2 2 2 2 NA 1 5 1 2 2 2 2 3 3
Pum p 3 2 3 2 1 5 3 2 4 3 3 1 3 5 3 3 3 6 3 6 2 4 2 2 2 2 3 1 5 1 2 2 2 2 3 3
Pum p 4 2 2 3 3 3 3 3 2 1 6 1 2 2 2 2
Pum p 5 2 2 3 3
Pum p 6 2 3 3
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations C5
Summary Report
Appendix D
Pumps and Motors Assessment
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
CONDITION and PERFORMANCE ASSESSMENT - Pumps and Motors
Pumping Station
Pumps
and Motors
W18
W01
W03
W05
W08
W10
W12
W14
W16
W19
W21
W23
W25
W27
C02
C03
W02
W04
W07
W09
W11
W13
W15
W17
W20
W22
W24
W26
C01
C04
E01
E03
E05
E07
E02
E04
E06
Pump Condition
Pump 1 2 3 2 1 3 2 2 3 1 2 3 1 3 3 3 3 3 4 3 4 4 2 1 3 3 2 2 NA 1 4 1 2 2 2 2 4 3
Pump 2 2 3 2 1 3 2 2 3 1 2 3 1 NA 3 3 3 4 4 3 3 4 2 1 3 3 2 2 NA 1 4 1 2 2 2 2 4 3
Pump 3 2 3 2 1 3 2 3 1 3 3 1 NA 3 3 3 4 6 3 5 2 1 3 3 2 2 NA 1 4 1 2 2 2 2 4 3
Pump 4 2 3 3 4 6 3 3 2 1 6 1 2 2 2 2
Pump 5 2 4 3 3
Pump 6 2 3 3
Motor Condition
Motor 1 2 2 2 1 4 1 5 3 2 3 3 2 5 3 3 3 4 3 3 4 3 3 2 2 2 2 3 NA 1 3 1 2 2 2 2 3 3
Motor 2 2 2 2 1 3 5 4 3 2 3 3 2 NA 4 5 3 3 3 5 4 3 3 2 2 2 2 3 NA 1 3 1 2 2 2 2 4 5
Motor 3 2 2 2 1 5 3 3 2 3 3 2 NA 3 3 3 4 6 4 3 3 2 2 2 2 3 NA 1 3 1 2 2 2 2 3 3
Motor 4 2 6 5 3 5 6 4 3 1 6 6 2 2 2 2
Motor 5 2 5 4 NA
Motor 6 2 5 NA
Coupling Condition
Coupling 1 1 4 2 1 2 2 4 1 2 2 1 3 3 3 3 2 2 3 3 4 2 2 5 5 2 2 3 1 4 1 2 2 2 2 4 3
Coupling 2 1 3 2 1 1 2 4 1 2 2 1 NA 3 3 3 2 2 3 3 4 2 2 5 5 2 2 NA 1 4 1 2 2 2 2 4 3
Coupling 3 1 3 2 1 1 4 1 2 2 1 NA 3 3 2 2 3 3 4 2 2 5 5 2 2 3 1 4 1 2 2 2 2 4 3
Coupling 4 1 3 2 NA NA 3 2 1 NA 1 2 2 2 2
Coupling 5 1 3 3
Coupling 6 1 3 3
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations D1
Summary Report
VIBRATION AND ALIGNMENT - Pumps and Motors
Pumping Station
Pumps and Motors
W05
C03
W01
W02
W03
W04
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C04
E01
E02
E03
E04
E05
E06
E07
Max. Vibration (m m/s)
Pump Set 1 NA 1.58 3.12 1.40 NA NA NA NA NA NA NA 0.66 0.93 1.14 0.30 1.12 0.75 1.91 0.77 0.32 3.82 7.21 0.62 0.46 0.80 1.00 0.34 NA 0.75 2.03 1.07 0.88 1.51 0.82 0.92 0.52 1.62
Pump Set 2 NA 0.70 1.56 1.31 NA NA NA NA NA NA NA 0.63 NA 0.76 0.61 2.41 0.53 1.30 0.92 0.92 7.96 12.18 2.19 0.34 0.34 0.24 0.64 NA 1.85 1.99 0.53 0.32 0.58 0.38 0.77 0.49 1.43
Pump Set 3 NA NA 4.54 2.62 NA NA NA NA NA NA 0.39 NA 0.36 2.91 0.61 1.60 NA 0.76 5.84 12.35 0.91 0.45 0.20 0.36 0.71 NA 0.46 1.88 0.45 0.64 0.63 0.34 0.96 0.23 0.44
Pump Set 4 NA NA 1.21 0.55 NA 0.82 0.39 0.50 0.67 NA NA 0.68 0.87 0.36 1.09
Pump Set 5 NA NA 1.41 0.20
Pump Set 6 NA 0.85 0.12
Comm ents
Note: 'NA' or 'Blank' = Not Applicable or Data Not Available. LEGEND - Vibration and Alignment
0.09 Satisfactory.
1.01 Not Acceptable, Shaft realignment required.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations D2
Summary Report
Appendix E
Other Equipment and Systems
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
CONDITION ASSESSMENT - Other Mechanical Equipment and Systems
Pumping Station
Mechanical Equipment
W02
W12
W22
W03
W04
W05
W07
W08
W09
W10
W13
W14
W15
W16
W17
W18
W19
W23
W24
W25
W26
W27
W01
W11
W20
W21
C04
C01
C02
E01
E02
E03
E04
E05
E06
C03
E07
Overhead Crane NA NA NA 1 2 5 2 3 1 6 3 1 3 3 3 1 2 4 3 2 3 2 1 2 2 2 2 NA 1 3 1 2 1 2 2 6 6
Security House Air Conditioning NA NA NA NA 2 NA 3 4 1 NA NA 1 NA NA NA 3 3 NA NA 5 NA NA 1 3 2 2 NA NA 2 NA 1 NA NA NA NA NA NA
Pump Room Air Conditioning NA 2 2 NA NA 4 4 4 NA 5 6 NA NA NA 5 NA NA NA NA 5 4 3 NA NA NA NA 3 6 4 5 NA NA NA NA NA 5 6
Control Room Air Conditioning 2 2 2 1 2 3 3 4 1 5 5 1 3 5 5 2 3 5 6 5 NA 3 1 3 3 6 2 NA 2 NA 1 2 2 2 2 3 3
Pump Room Ventilation 2 NA NA 1 2 NA NA NA 1 NA NA 1 3 6 NA 3 5 6 6 NA NA NA 1 3 2 2 NA NA NA NA 1 2 2 2 2 NA NA
Surge Tank 1 6 6 1 6 4 3
Surge Tank 2 1 3
Air Compressor 4
Diesel Generator 2 5 4 NA
Fire Protection Equipment 2
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations E1
Summary Report
CONDITION ASSESSMENT - Electrical Equipment and Systems
Pumping Station
Electrical Equipment
W12
W18
W23
W01
W02
W03
W04
W05
W08
W09
W10
W11
W15
W16
W17
W21
W22
W24
W25
W26
W27
W07
W13
W14
W19
W20
E04
C01
C02
C03
C04
E01
E02
E03
E06
E07
E05
Switchboards
3 4 4 1 3 4 4 5 2 3 4 1 3 3 4 3 3 3 3 3 3 3 2 2 2 2 5 4 2 4 4 2 3 3 3 4 3
& Motor Controls
Electrical Equipment
Pump Station Earthing 5 3 3 3 4 2 5 NA 1 4 3 NA 4 3 3 3 2 3 3 NA 3 NA 6 NA 2 2 5 4 4 6 1 2 2 2 2 4 3
Lightning Protection NA NA NA 2 NA 3 NA NA 3 NA 3 1 NA 3 4 3 2 NA NA NA 3 NA 2 2 3 2 NA NA NA NA 3 2 2 2 2 3 NA
Pump Room Crane NA NA NA 1 2 4 NA 3 1 NA NA 2 3 3 3 3 2 3 3 2 NA NA 2 2 2 2 2 NA 1 NA 2 2 2 2 2 3 4
Pump Control Panel 2 3 3 1 4 3 4 3 1 4 4 3 3 4 5 3 2 3 4 5 3 3 2 3 4 4 4 6 4 NA 2 2 3 2 2 3 3
Power Cabling 2 2 3 4 2 3 4 4 1 3 4 4 4 4 3 4 2 3 3 4 4 2 2 2 2 2 3 5 2 4 2 2 2 2 2 3 3
Room Lighting 3 4 NA 2 5 3 2 3 2 6 3 6 4 5 4 4 3 3 4 3 2 2 3 2 2 4 3 6 2 NA 1 2 2 2 2 3 3
Exterior Site Lighting 6 NA NA 1 4 2 4 5 4 6 4 5 5 5 6 5 5 6 5 3 4 2 2 3 6 3 4 6 4 5 3 2 2 2 2 3 4
Fire Alarm System NA 1 NA 1 NA NA NA NA 6 NA NA 6 NA NA NA NA 6 NA NA 4 NA NA NA 2 4 2 NA NA 3 NA 6 3 3 4 2 NA NA
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations E2
Summary Report
Appendix F
Maintenance and Management Strategy
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations F3
Summary Report
SITE SAFET Y - Recommended Actions
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Personal Protective Equipment and First Aid Kits - Supply
and maintain at all pump stations. Saf ety Signage - Install
Know ledge of Site Saf ety Rules X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
signs at site entrance and Pump Room (Saf ety Boots,
Eye & Ear Protection).
Hearing Protection - Provide to all operators (and visitors
Excessive Noise
to be suitably equiped).
Site A ccess Road - Upgrade ac cess road f or improved
Site Acc ess and Egress X X
site access.
Telephone Communication - Install a land line for site Site Emergency Procedures;
X X X X X X
emergencies and reliable communications. Telephone Communication
Security Fence - Install/ repair f encing and gates. Site Security X X X X X X
Pow er Cabling, Ducting and Trays - Modif y to make saf e. Electrical Hazards X X
Unused Storage Tank - Decommission tank to make saf e. Structural Safety Haz ard X
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations F1
Summary Report
CIVIL ASSETS - Recommended Actions
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Site Access - Upgrade access road. X X X X X
Security Fencing - Install security fencing to prevent unauthorised entry. X X X
Security Fencing - Modif y height to prevent unauthorised entry. X X X X
Security Fencing - Repair broken fencing/ gates. X X X X
Security Fencing - Repair transf ormer f ence. X
Internal Roads - Repair missing pavers and holes. X
Security House - Repair broken fixtures. X X
Accommodation - Install accommodation facilities. X X X X X X X X X X
Accommodation - Repair broken f ixtures. X X
Accommodation - Upgrade/ Replace accommodation facilities. X X X X X X
Operations Of fice - Provide space or construct operations of fice. X X X X X X X X X X X X X X X X X X X X X X X
Guard House - Repair w ater supply services. X X X X
Control Room - Investigate/ repair structural cracking. X
Control Room - Repair doors. X X
Pump House - Install floor sump and dew atering pump. X
Pump House - Investigate and repair structural cracks. X
Pump House - Repair air conditioning. X
Pump House - Repair doors/ w indow s. X X X X X X
Pump House - Safety modif ications required. X X
Elevated Tow er - Repair doors/ roof hatches. X X X X
Elevated Tow er - Saf ety modif ications required. X X X
Storage Tanks - Decommission old storage tank. X
Storage Tanks - Investigate cracking and leakage. X X X X X X X X X
Storage Tanks - Modify/ repair storage tanks/ fixtures. X X X X X X X X X X X X X X X X X X X X X X
Surge Tanks - Demolish unsaf e shelter. X
Instrumentation - Install f low / pressure metering. X X X
Instrumentation - Install storage level indicators. X X X X X X
Instrumentation - Repair/ replace flow / pressure metering. X X X X X X X X X X X X
Instrumentation - Repair/ replace storage level indicators. X X X X X X X X X X X X
Pipew ork & Valves - Install/ repair f lexible couplings. X X X
Pipew ork & Valves - Modify/ align pipew ork. X X X X X X X X X X
Pipew ork & Valves - Repair/ replace pipew ork. X X X X X
Pipew ork & Valves - Repair/ replace valves. X X X X X X X X X X X X X
Pipew ork & Valves - Upgrade pipe/ valve sizes. X X X X
General Operations - Confirm this pump station is to be retained. X
General Operations - Improve operators communication skills. X
General Operations - Modify duty pump selection. X
General Operations - Record hours run f or all pumps. X
Housekeeping - Clear site of loose debris, clean bird debris from around
X X X X X X X X X X X X X X X
storage hatches and fixtures, remove trip hazards.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations F2
Summary Report
MECHANICAL ASSETS - Recommended Actions
Pumping Station
Action
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Accom modation - Repair broken fixtures . X
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations F3
Summary Report
ELECTRICAL ASSETS - Recommended Actions
Pumping Station
Action
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Control Room - Repair lighting. X X X X X
Fire Fighting Sys tem - Ins tall/ com m iss ion s ys tem . X X
Fire Fighting Sys tem - Repair/ m odify fire fighting equipm ent. X X X X X
Pum p-Motor Set - Res pecify m otors to higher tem perature rating. X X X
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations F4
Summary Report
Appendix G
ADDC GIS Object Numbers
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations
Summary Report
ADDC GIS OBJECT NUMBERS - Correlated to GHD Pumping Station Field Data
W01
W02
W03
W04
W05
W07
W08
W09
W10
W11
W12
W13
W14
W15
C01
C02
C03
C04
E01
E02
E03
E04
E05
E06
E07
Pump Station Facility 7 8 6141 8081 9 123932 6454 12412 11393 9089 39 8769 45 53 41 12049 81 3521 36 38
Pump House
Storage Tank No 1 129 136137 15498, 15499 18369 139, 140 15810 21665 962961 641 702701 19345 13186 218 207 21330 221 19697 198 200
Storage Tank No 2 15496, 15497 139, 140 15810 642 13185 219 208
Storage Tank No 3 138, 141 226
Storage Tank No 4 138, 141
Elevated Tank No 1 142 143 144 15809 644 235 230
Elevated Tank No 2
Suction Header Valve 1
Suction Header Valve 2
Suction Pump Isolation Valve 1 7182 7195 228270 312809 7211 251145 311349 20181 18905 9760 302991 202101 9842 9832 9898 9862 304028 9734 9777
Suction Pump Isolation Valve 2 7194 7197 228265 312812 7210 251140 311348 20180 18908 9748 302994 202098 9840 9830 9900 9862 304030 9732 9775
Suction Pump Isolation Valve 3 7199 228261 312815 7203 251146 311347 18904 9746 302992 202097 9838 9828 9902 9864 304033 9730 9773
Suction Pump Isolation Valve 4 228267 311346 302993 202102 10078 9826
Suction Pump Isolation Valve 5 228269 9834
Suction Pump Isolation Valve 6 9923
Pump/ Motor 1 10 12 2905 7213 21 28 3537 7156 978 657 44 4849 2578 67 54 83 72 5219 35 41
Pump/ Motor 2 11 13 2904 7214 20 29 3539 7153 979 658 43 4850 2577 66 53 84 73 5221 34 40
Pump/ Motor 3 14 2903 7215 19 27 3538 7154 659 42 4851 2579 61 52 85 74 5222 33 39
Pump/ Motor 4 2902 7155 4852 2580 106 51
Pump/ Motor 5 2900 50
Pump/ Motor 6 55
Non-Return V alve 1 7273 7268 228276 312811 7279 7284 251144 311355 20193 18912 9919 202093 10004 9906 9970 10010 304019 9918 9995
Non-Return V alve 2 7274 7275 228275 312814 7278 7286 251138 311356 20192 18910 9990 202096 10003 9905 9971 10011 304032 9917 9994
Non-Return V alve 3 7276 228274 312817 7277 7283 251142 311354 18911 9991 202095 10002 9904 9972 10018 304035 9916 9993
Non-Return V alve 4 228273 311357 202099 10079 9903
Non-Return V alve 5 228272 9908
Non-Return V alve 6 9909
Delivery Isolation Valve 1 7181 7196 228280 312810 7212 7253 251141 311350 20183 18909 9761 302995 202104 9841 9831 9897 9869 304020 9735 9778
Delivery Isolation Valve 2 7193 7198 228281 312813 7210 7254 251143 311351 20185 18906 9749 302996 202084 9839 9829 9899 9864 304031 9733 9776
Delivery Isolation Valve 3 7200 228279 312816 7204 7248 251139 311352 18907 9747 302997 202100 9837 9822 9901 9866 304034 9731 9774
Delivery Isolation Valve 4 228278 311353 302998 202103 10077 9825
Delivery Isolation Valve 5 228277 9833
Delivery Isolation Valve 6 9924
Delivery Header Valve 1
Delivery Header Valve 2
Surge Tank 1 387163 337
Surge Tank 2
Surge Tank 3
Com m e nts
Note : 'NA' or 'Blank' = Not A ppliable or Data Not Available.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations G1
Summary Report
ADDC GIS OBJECT NUMBERS - Correlated to GHD Pumping Station Field Data
W16
W17
W18
W19
W20
W21
W22
W23
W24
W25
W26
W27
Pump Station Facility 37 48 50 3841 4177 8449 8417 8453 8451 12401 106
Pump House
Storage Tank No 1 199 222 229 12529 18705 18690 18707 18706 21346 21345
Storage Tank No 2
Storage Tank No 3
Storage Tank No 4
Elevated Tank No 1 23 175
Elevated Tank No 2
Suction Header V alve 1
Suction Header V alve 2
Suction Pump Isolation V alve 1 9759 9871 9895 303359 302671 302212 302721 302696 310961 311009
Suction Pump Isolation V alve 2 9755 9873 9893 303362 302674 302211 302724 302699 310963 311010
Suction Pump Isolation V alve 3 9753 10076 303360 302672 302209 302722 302697 310965 311011
Suction Pump Isolation V alve 4 9875 303361 302673 302210 302723 302698
Suction Pump Isolation V alve 5
Suction Pump Isolation V alve 6
Pump/ Motor 1 38 75 82 2257 5185 4833 4497 4841 4837 6833 6850
Pump/ Motor 2 37 76 81 2258 5186 4834 4498 4842 4838 6834 6849
Pump/ Motor 3 36 105 2259 5187 4835 4499 4843 4839 6835 6848
Pump/ Motor 4 77 2260 5188 4836 4500 4844 4840
Pump/ Motor 5
Pump/ Motor 6
Non-Return V alve 1 9989 10019 9965 303377 310967 311020
Non-Return V alve 2 9922 9959 9964 303376 310968 311017
Non-Return V alve 3 9921 10074 303375 310969 311019
Non-Return V alve 4 9960 303374
Non-Return V alve 5
Non-Return V alve 6
Delivery Isolation V alve 1 9758 9870 9896 303363 302675 302213 302725 302700 310962 311016
Delivery Isolation V alve 2 9756 9872 9894 303364 302676 302214 302726 302701 310964 311015
Delivery Isolation V alve 3 9754 10075 303365 302677 302215 302727 302702 310966 311014
Delivery Isolation V alve 4 9874 303366 302678 302216 302728 302703
Delivery Isolation V alve 5
Delivery Isolation V alve 6
Delivery Header V alve 1
Delivery Header V alve 2
Surge Tank 1
Surge Tank 2
Surge Tank 3
Com m e nts
Note : 'NA' or 'Blank' = Not A ppliable or Data Not A vailable.
76/10239/11871 Condition Assessment and Energy Management Survey of ADDC Water Pumping Stations G2
Summary Report