Sr No.

SYSTEM COMMENT ACTION BY COPLETION DATE

1 URBAN OASIS

1. MONITORS ARE IN RMA PROCESS ONCE ITS DELIVERED WE CAN


COMPLETE COMISSIONING.
1. TESTING AND COMMISIONING BY RINTU
2. SPC VARIATION TO BE SUBMITTED DEPENDING UPON MONITOR , SPC AND
A CCTV
CAMERA VARIATION APPROVAL
2. VARIATIONS TO BE SUBMITTED BY HARIS
3. 16 DOME CAMERAS NEED TO BE DELIVERED.

4. VARIATION FOR 4CAMERAS NEED TO BE SUBMITTED.

B INTERCOM TESTING ONGOING SAM WILL HANDEL EXPECTED COMPLETION BY 27TH FEB 2024

C ACCESS CONTROL TESTING ONGOING SAM WILL HANDEL EXPECTED COMPLETION BY 27TH FEB 2024

2 NAFFCO FACTORY COMISSIONING


PROJECT NAME
BRIJITH WILL TEST AND PREPARE THE SITE
EXPECTED COMPLETION DATE 16TH MARCH
1 PROJECT STORE SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


EXPECTED COMPLETION DATE 16TH MARCH
2 FOAM FACTORY SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


EXPECTED COMPLETION DATE 16TH MARCH
3 CASTING FACTORY SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


EXPECTED COMPLETION DATE 16TH MARCH
4 OLD TECHNO PRO SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


EXPECTED COMPLETION DATE 16TH MARCH
5 FIRE TRUCK SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


EXPECTED COMPLETION DATE 16TH MARCH
HQ Factories - 1 & 4 SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.
6
BRIJITH WILL TEST AND PREPARE THE SITE
EXPECTED COMPLETION DATE 16TH MARCH
HQ Factories - 2 & 3 SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
2024
VIDEO GUARD.

BRIJITH WILL TEST AND PREPARE THE SITE


HQ BUILDING PART 2 -Setting out and HQ EXPECTED COMPLETION DATE 16TH MARCH
7 SIRA INSPECTION AND VIDEO GUARD TO BE COMPLETED FOR SIRA IN PARALLEL HE WILL OBTAIN
building 2024
VIDEO GUARD.

3 MIRAMAR
GRAPHICS FOR iPad is only pending . 5times
33VILLAS / 44 HANDED OVER. REMAINING VILLAS HANDING OVER
1 GRMS we have revised . Final revision not yet will be coordinated by Irfan & Dileep
ONGOING
finalised

1/4 BUILDING HANDED OVER. SYSTEM IS READY HANDING OVER


2 LIGHTING CONTROL will be coordinated by Irfan & Dileep
ONGOING

3 BMS SYSTEM HANDING OVER ONGOING will be coordinated by Brijith & Dileep

4 ACCESS CONTROL SYSTEM HANDING OVER ONGOING will be coordinated by Brijith & Dileep