JEP Request For Reconsideration Masablang Waterworks Project Letter-BAC Chairman NIA CAR
JEP Request For Reconsideration Masablang Waterworks Project Letter-BAC Chairman NIA CAR
Subject: Request for Consideration for the behind schedule of Construction of Masablang
Waterworks, Masablang, Tabuk City, Kalinga
SIR:
Please be informed that unnecessary delays occurred on the Construction of Tuga Waterworks
due to the following reasons to wit:
1. That the rotary driller that was intended for the drilling of the said project was busy
drilling for other projects;
2. That as a result, we have to wait for the mobilization of the rotary driller at the project
site;
3. That last month, the said driller was mobilized to the site and started drilling;
4. That after the completion of drilling the test well was completed;
5. That the test well was subjected to 24 hours of pumping test to develop the aquifer (water
bearing formation);
6. That the test well encountered several interruptions due to tripping of thermal protector of
the submersible pump;
7. That the electrical source do not have the adequate power supply to operate the said
submersible pump;
8. That there is a need to install transformer to step up the load and operate the pump
efficiently;
9. That the installation of transformer will take time to materialize subjected to submission
of several requirements and its approval by the KAELCO;
Considering that delays due to late mobilization of the rotary driller on the construction of the
project, and the requirement of transformer to be installed at the site, were not in our control and
in the end not at our fault, may we request for a consideration of offsetting those delays in our
favor. This is to put our schedule on date with no delays.
Hoping for your preferential action to the above mentioned request.