Listed below are the 12/50 divisions of construction information, as defined by the Construction

Specifications Institute (CSI)'s MasterFormat for the order.

DIVISION 01 – GENERAL REQUIREMENTS


01 10 00 SUMMARY
THIS SECTION OF THE CONTRACT DOCUMENT CONTAINS THE FOLLOWING:
1. WORK COVERED BY CONTRACT DOCUMENTS
2. WORK BY OWNER
3. WORK RESTRICTIONS
4. ACCESS TO SITE

01 11 00 SUMMARY OF WORK

01 11 13 WORK COVERED BY CONTRACT DOCUMENTS


CONSTRUCTION MUST DEMONSTRATE EXCEPTIONAL CRAFTSMANSHIP, IN
LINE WITH PROFESSIONAL EXPERTISE AND UNDERSTANDING OF PLANS AND
SPECIFICATIONS, ENSURING COMPLETE SATISFACTION OF THE
ARCHITECT/ENGINEER AND OWNER.

COMPLIANCE WITH GROUP B OCCUPANCY, TYPE V CONSTRUCTION OF THE


NATIONAL BUILDING CODE OF THE PHILIPPINES IS MANDATORY.

SERVICES UNDER THIS CONTRACT INCLUDE:


1. ARCHITECTURAL DESIGN
2. INTERIOR DESIGN
3. ELECTRICAL WORKS
4. HVAC SYSTEM

01 11 16 WORK BY OWNER
THE RESPONSIBILITY AND DUTIES OF THE OWNER DURING THE
CONSTRUCTION PROCESS SHALL INCLUDE:

1. PROVIDING FINANCING FOR THE PROJECT.


2. PROVIDING SITE SURVEYS.
3. JUSTIFYING THE PLANS AND SPECIFICATIONS.
4. JUSTIFYING OWNER FURNISHED MATERIALS.
5. ACTING ON CLARIFICATIONS AND CHANGES.
6. INTERPRETING THE DOCUMENTS.
7. COOPERATING WITH THE CONTRACTOR.
8. SELECTING ALL PROFESSIONALS ON THE PROJECT.
01 14 00 WORK RESTRICTIONS
CONSTRUCTION HOURS ON SITE: WEEKDAYS 7:30 AM - 6:00 PM, WEEKENDS 9:00
AM - 5:00 PM. SATURDAY, SUNDAY, AND HOLIDAY WORK REQUIRE PRIOR CONSULTATION
WITH THE OWNER AND CONSTRUCTION MANAGER. NO DISRUPTIVE WORK IN THE
NEIGHBORHOOD WITHOUT WRITTEN APPROVAL FROM NEIGHBORING PROPERTY
OWNER.

1. ALL NOISY ACTIVITIES.


2. INSURANCE AND LIABILITY
3. USE OF COMMON AREAS

01 26 00 CONTRACT MODIFICATION PROCEDURES


THIS SECTION CONTAINS THE REQUIREMENTS AND PROCEDURE FOR CONTRACT
MODIFICATION DURING THE CONSTRUCTION PROCESS. THIS INCLUDES:

1. MINOR CHANGES IN THE WORK


2. CHANGE ORDER REQUESTS

01 26 33 MINOR CHANGES IN THE WORK


ARCHITECTS ARE RESPONSIBLE FOR ISSUING INSTRUCTIONS FOR MINOR
CHANGES IN THE WORK THROUGH CONSTRUCTION MANAGER WITHOUT AFFECTING THE
CONTRACT SUM OR THE CONTRACT PERIOD OF TIME.
01 26 57 CHANGE ORDER REQUESTS
CONSTRUCTION MANAGERS ARE RESPONSIBLE FOR ISSUING CHANGE ORDER
THAT CONTAINS SIGNATURES OF OWNER, CONTRACTOR, ARCHITECT, AND
CONSTRUCTION MANAGER.

01 41 00 REGULATORY REQUIREMENTS
1. ALL WORK MUST COMPLY WITH THE NATIONAL BUILDING CODE OF THE
PHILIPPINES.
2. ELECTRICAL, PLUMBING, AND FIRE PROTECTION CODES MUST BE ADHERED TO
DURING CONSTRUCTION.
3. STRICTLY MONITOR PRODUCT QUALITY, INSTALLATION PROCESSES (BASED ON
MANUFACTURER GUIDELINES), AND WORKMANSHIP OF SPECIFIED WORKERS TO
ACHIEVE DESIRED OUTPUT.

REFERENCES:
1. NATIONAL BUILDING CODE OF THE PHILIPPINES
2. PHILIPPINES ELECTRICAL CODE
3. NATIONAL PLUMBING CODE, AND;
4. FIRE CODE OF THE PHILIPPINES 2008

01 52 00 CONSTRUCTION FACILITIES

01 52 16 FIRST AID FACILITIES


PROVIDING FIRST AID FACILITIES ON SITE DUE TO DISTANCE FROM
MEDICAL FACILITIES. TO ASSIST WORKERS NEEDING FIRST AID DURING
CONSTRUCTION.

01 53 00 TEMPORARY CONSTRUCTION
CONTRACTOR SHALL PROVIDE TEMPORARY LADDERS, HOISTS, RAMPS, AND
PASSAGEWAYS FOR WORKER CONVENIENCE DURING CONSTRUCTION, SUITABLE FOR
ALL TRADES.

01 56 00 TEMPORARY BARRIERS AND ENCLOSURES


A BARRIER MUST BE PROVIDED DURING CONSTRUCTION TO PREVENT
UNAUTHORIZED ENTRY AND PROTECT ADJACENT PROPERTY AND PEDESTRIANS.

01 58 00 PROJECT IDENTIFICATION
INSTALL A PROJECT IDENTIFICATION SIGN AT THE CONSTRUCTION SITE
ENTRANCE FOR THE ENTIRETY OF THE PROJECT, FEATURING PROJECT DURATION AND
PERSONNEL INVOLVED THROUGHOUT CONSTRUCTION.

01 60 00 PRODUCT REQUIREMENTS
ALL MATERIALS SHALL BE STORED AND INSTALLED IN ACCORDANCE WITH THE
MANUFACTURER’S GUIDELINES.

01 64 00 OWNER-FURNISHED PRODUCTS
ANY DAMAGE TO OWNER-PROVIDED MATERIALS PRIOR TO RECEIPT SHALL NOT BE
THE RESPONSIBILITY OF THE CONTRACTOR. THE OWNER WILL BE RESPONSIBLE FOR
ANY ADDITIONAL WORK REQUIRED FOR THE INSTALLATION OF OWNER-PROVIDED
MATERIALS.

01 65 00 PRODUCT DELIVERY REQUIREMENTS


ALL MATERIALS, SUPPLIES, AND EQUIPMENT THAT WILL BE DELIVERED SHALL BE
ON TIME AND CHECK STRICTLY BEFORE KEEPING IT TO STORAGE.

01 66 00 PRODUCT STORAGE AND HANDLING REQUIREMENTS


ALL MATERIALS, SUPPLIES AND EQUIPMENT SHALL BE STORED IN A SPACE THAT
IS PROTECTED FROM DAMAGE BY MOISTURE, WATER, OR ANY OTHER THAT CAN CAUSE
HARMFUL EFFECTS TO THE QUALITY OF MATERIALS.
DIVISION 03: CONCRETE
ALL REQUIRED LABOR AND MATERIALS PERTAINING TO CONCRETE USAGE IN THE
PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE COMPLYING
WITH ALL APPLICABLE BUILDING CODES.

03 20 00 CONCRETE REINFORCING
1. USE 4-12MM DIAMETER VERTICAL REINFORCEMENT BARS WITH 10 MM DIAMETER
LATERAL TIES FOR ALL COLUMNS
2. USE 2-12MM DIAMETER TOP BARS AND 2-12MM DIAMETER BOTTOM BARS WITH
10MM STIRRUPS FOR ALL BEAMS AND GIRDER.
3. USE 6-12MM DIAMETER REINFORCEMENT BARS ON CENTER BOTH WAYS FOR
COLUMN FOOTINGS.
4. COLUMN FOOTINGS SHALL BE REINFORCED BY 6-12MM REINFORCEMENT BARS ON
CENTER BOTH WAYS

03 30 00 CAST-IN-PLACE CONCRETE
1. USE EAGLE CEMENT OR EQUAL FOR ALL CONCRETE MIXTURE.
2. BEFORE POURING OF CONCRETE MIXTURES TO ALL CONCRETE WORKS THAT CAN
BE EXPOSED TO SLIPPAGE OF WATER, ADD DISPERSAL AGENTS.
3. USE CLASS A CONCRETE MIXTURE, 1:2:4 WALLS AND THIN REINFORCED SECTION
OF THE PROJECT.
4. FOR ADDING ADDITIVES, READ AND FOLLOW THE INSTRUCTION OF THE
MANUFACTURERS.
5. TO ACHIEVE DESIRABLE RESULT, USE CONCRETE ADDITIVES AND BONDING
AGENTS TO CONCRETE MIXTURES BEFORE POURING OF CONCRETE MIXTURE.
USE HIGH BOND STRENGTH EPOXY ADHESIVE FOR CONCRETE BONDING AGENT
OR ANY EQUIVALENT PRODUCT IF NOT AVAILABLE.

03 31 00 STRUCTURAL CONCRETE
1. USE 4,000 PSI CONCRETE WITH A MAXIMUM SLUMP OF 4". CONTRACTOR IS
RESPONSIBLE FOR PROVIDING THE MIX DESIGN. USE GRADE 60 REINFORCING
STEEL (EPOXY COATED WHEN REQUIRED). CONTRACTOR IS RESPONSIBLE FOR
ALL CONCRETE TESTING (STRENGTH, SLUMP, AND AIR CONTENT).
2. 4,000 PSI STRENGTH SHALL ATTAIN BY THE WALLS AND THIN REINFORCED
SECTION AFTER 28 DAYS OF CURING PERIOD.

DIVISION 04: MASONRY


ALL REQUIRED LABOR AND MATERIALS PERTAINING TO MASONRY WORK IN THE
PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE COMPLYING
WITH ALL APPLICABLE BUILDING CODES.

04 01 00 MAINTENANCE OF MASONRY
REGULARLY EVALUATE AND POSSIBLY REAPPLY PAINT, WATER REPELLENTS,
WATERPROOFING, AND OTHER WALL COATINGS. KEEPING TRACK OF APPLIED COATINGS
IS CRUCIAL DUE TO THE VARIETY OF MATERIALS USED ON CONCRETE MASONRY WALLS,
SIMPLIFYING THE SELECTION OF REAPPLICATION MATERIALS. PROPERLY SELECTED AND
APPLIED COATINGS ENHANCE SURFACE PERFORMANCE AND LONGEVITY.

BUILDINGS MAY REQUIRE PERIODIC CLEANING TO REMOVE DIRT, STAINS, AND


MOLD. STRICTLY ADHERE TO MANUFACTURER RECOMMENDATIONS FOR CLEANING
PRODUCTS TO AVOID INJURY TO INDIVIDUALS AND STRUCTURAL DAMAGE CAUSED BY
CERTAIN COMPOUNDS.
04 01 20.51 UNIT MASONRY CLEANING

HAND CLEANING
DURING CONSTRUCTION, USE BASIC HAND TOOLS LIKE A TROWEL, CHISEL,
STIFF BRISTLE OR FIBER BRUSH, ABRASIVE BLOCK, OR FRACTURED STONE FOR
CLEANING. AVOID STEEL-WIRE BRUSHES AS THEY CAN LEAVE METAL PARTICLES
ON MASONRY, CAUSING CORROSION AND DISCOLORATION.

WATER CLEANING
CLEANING METHODS INCLUDE SCRUBBING WITH WATER AND SOAP,
SOAKING, STEAM CLEANING, AND PRESSURE WASHING. USE MINIMAL WATER
WITH WATER-BASED METHODS TO PREVENT EFFLORESCENCE FROM WATER
ENTERING THE WALL. UNPAINTED WALLS CAN USUALLY BE CLEANED BY
SCRUBBING WITH WATER AND A SMALL AMOUNT OF DETERGENT.

CHEMICAL CLEANING
USE CHEMICAL CLEANING SOLUTIONS TO CLEAN CONCRETE MASONRY
SAFELY, AVOIDING RAW OR UNDILUTED ACIDS. DILUTED ACIDS SHOULD BE USED
CAUTIOUSLY AFTER THOROUGHLY WETTING THE WALL TO PREVENT DAMAGE TO
THE CEMENT MATRIX AND NATURAL WATER REPELLENT. AVOID APPLYING ACIDS
UNDER PRESSURE.

04 06 00 SCHEDULES OF MASONRY

04 06 20 SCHEDULES FOR UNIT MASONRY


UNLESS SPECIFIED, INTERNAL WALLS: 150MM THICK CHB. PLUMBING
WALLS: MIN. 150MM THICK. CELLS WITH 1 PART EAGLE CEMENT, 3 PARTS SAND.
REINFORCE WITH 10MM DIA. ROUND DEFORMED BARS SPACED ≤0.80M. FINISH PER
ELEVATION DRAWINGS WITH 1 PART CEMENT, 1 PART LIME, 3 PARTS SAND MIX.

04 22 00 CONCRETE UNIT MASONRY


1. USE 5"X8"X16" CHB NLB 400 PSI IN ALL INTERIOR WALLS. REINFORCED CHB WITH
VERTICAL BARS EVERY 60CM AND HORIZONTAL BARS EVERY 3 LAYERS. USE LAC
CHB OR EQUIV. APPROVED BY ARCHITECT.
2. USE STANDARD MORTAR MIX THROUGHOUT CONSTRUCTION.

DIVISION 05: METALS


ALL REQUIRED LABOR AND MATERIALS PERTAINING TO METAL WORK IN THE
PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE COMPLYING
WITH ALL APPLICABLE BUILDING CODES.

05 12 00 STRUCTURAL STEEL - GENERAL


STRUCTURAL STEEL FRAME (BEAMS AND COLUMNS) AND MISCELLANEOUS
MEMBERS TO CONFORM TO ASTM A992, 50 KSI. BOLTS TO CONFORM TO ASTM A307 OR
A325. PAINTING: 1-COAT RUST-INHIBITIVE PRIMER.
DIVISION 06: WOOD, PLASTICS, &
COMPOSITES
06 20 00 FINISH CARPENTRY
WOOD VENEER FINISH CASEWORK, SOLID WOOD AND/OR PLASTIC LAMINATE
COUNTERS

06 20 23 INTERIOR FINISH CARPENTRY


1. 2 METERS X 0.70 METERS WOOD VENEER FINISH CASEWORK BUILT-IN CLOSET
IN BEDROOM
2. WOODEN PANEL FLOOR-TO-CEILING ROOM DIVIDER

DIVISION 07: THERMAL AND MOISTURE


PROTECTION
ALL REQUIRED LABOR AND MATERIALS PERTAINING TO THERMAL AND MOISTURE
PROTECTION IN THE PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE
DOCUMENTS, WHILE COMPLYING WITH ALL APPLICABLE BUILDING CODES.

07 10 00 DAMPPROOFING AND WATERPROOFING

ALL WATERTIGHT JOINTS AND PENETRATIONS IN WALLS, FLOORS, AND ROOFS


MUST BE BUILT USING AUTHORIZED METHODS AND MATERIALS.

07 11 00 DAMPPROOFING

07 11 16 CEMENTITIOUS DAMPPROOFING

CONSULT CLIENT, OWNER, AND ARCHITECT FOR ALTERNATIVES IF NEEDED.

1. COAT EXPOSED CONCRETE IN TOILETS AND BATHROOMS WITH CEM-KOTE


CW PLUS OR EQUIVALENT.
2. USE CEM-KOTE CW PLUS OR EQUIVALENT FOR BALCONY AND KITCHEN
TOPS.

07 13 00 SHEET WATERPROOFING

07 13 53 ELASTOMERIC SHEET WATERPROOFING

1. USE MONDO LIQUID SEAL OR EQUIVALENT FOR ALL EXTERNAL WALLS.


CONSULT CLIENT, OWNER, AND ARCHITECT FOR ALTERNATIVES IF
NEEDED.

07 21 00 THERMAL INSULATION

1. UNDERLAY ROOFING WITH POLYETHYLENE FOAM INSULATION OR EQUIVALENT.


CONSULT CLIENT, OWNER, AND ARCHITECT FOR ALTERNATIVES IF NEEDED.
DIVISION 8: OPENINGS
ALL REQUIRED LABOR AND MATERIALS PERTAINING TO DOOR, WINDOWS AND
OTHER OPENING USAGE IN THE PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE
DOCUMENTS, WHILE COMPLYING WITH ALL APPLICABLE BUILDING CODES. ALL SLEEPING
AREAS ARE PROVIDED WITH AN OPERABLE DOOR AND WINDOW.

08 01 00 OPERATION AND MAINTENANCE OF OPENING

08 01 36 OPERATION AND MAINTENANCE OF PANEL DOORS


EXTERNAL DOORS AND FRAMES NEED SUITABLE FINISHES FOR SEALING
AND PROTECTION, POSSIBLY WITH ADDITIONAL FLASHING FOR EXPOSED AREAS.
METAL CHANNEL CAPPING AT THE HEAD IS REQUIRED FOR ALL EXTERNAL DOORS,
WHILE FIRE-RATED DOOR SETS IN EXPOSED AREAS MUST HAVE STEEL FACES
AND EDGE COVERS ON ALL CORNERS FOR LONGEVITY.

08 14 00 WOOD DOORS

08 14 16 WOOD DOORS
1. VERIFY DOOR AND WINDOW SCHEDULE ON ARCHITECTURAL DRAWINGS FOR
ACCURATE SIZES AND QUANTITIES.
2. INSTALL SOUNDPROOF PLYWOOD COMPOSITE ENTRY INTERIOR ROOM
DOORS FOR SPECIFIED INTERIOR OPENINGS FROM HEBEI JINLUXI IMPORT
AND EXPORT CO. OR EQUIVALENT. CONSULT WITH CLIENT, OWNER, AND
ARCHITECT IF NEEDED.

08 15 00 PLASTIC DOORS
1. TOILET AND BATH DOOR MEASURES 0.60 METERS IN WIDTH AND 2.10 METERS IN
HEIGHT.
2. USE POLYVINYL CHLORIDE LOUVERED DOOR FOR ALL TOILET AND BATHROOM
DOOR FROM ATLANTA INDUSTRIES INCORPORATED OR ANY EQUIVALENT
PRODUCT CONSULTED TO CLIENT, OWNER AND ARCHITECT INCASE OF
UNAVAILABILITY

08 51 13 METAL WINDOWS
1. 1.20 METERS X 0.40 METERS ALUMINUM AWNING WINDOWS LOCATED IN BEDROOM
AND LIVING AREA.
2. 1.20 METERS X 1.20 METERS ALUMINUM AWNING WINDOWS LOCATED IN LIVING
AREA

08 70 00 HARDWARE
1. USE BOSTIK SILICON SEALANT TO ALL WINDOW OPENINGS OR ANY EQUIVALENT
PRODUCT CONSULTED TO CLIENT, OWNER AND ARCHITECT INCASE OF
UNAVAILABILITY
2. USE BHMA 613 OR US10B FINISH FOR ALL HARDWARE. INSTALL LEVERS FOR
LATCH AND LOCK SETS, EXCEPT FOR SERVICE AREAS WHERE SPHERICAL KNOBS
ARE PREFERRED. MASTER KEY ALL LOCKS TO MATCH THE PARK'S SYSTEM.

08 71 00 DOOR HARDWARE
1. PROVIDE 3 CONCEALED HINGES (SOSS 5/8 IN. X 2-3/4 IN. SATIN CHROME
INVISIBLE HINGE) FOR 2100 MM HEIGHT DOOR.
2. USE LEVER TYPE LOCK SETS FOR ALL DOORS IF NOT SPECIFIED ON WORKING
DRAWINGS. USE SAME BRAND WITH HINGES.

08 80 00 GLAZING
PROVIDE 1-INCH SEALED INSULATED GLASS, MADE UP OF 1/4-INCH-THICK CLEAR
FLOAT GLASS WITH E2 COATING ON INTERIOR PANES. PROVIDE HEAT MIRROR GLASS
UNITS ON NORTH WALLS. USE TEMPERED GLASS WHERE REQUIRED.

08 81 23 EXTERIOR GLASS GLAZING


6MM THICK REFLECTIVE GLASS ON BALCONY
DIVISION 9: FINISHES
ALL REQUIRED LABOR AND MATERIALS PERTAINING TO FINISHES REQUIRED IN
THE PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE
COMPLYING WITH ALL APPLICABLE BUILDING CODES.

09 22 16 NON-STRUCTURAL METAL FRAMING


1. METAL STUD WALL AND CEILING FRAMING.

09 24 00 CEMENT PLASTERING
1. PLASTER ALL EXPOSED CONCRETE SURFACES OF 20 CM THICK EAGLE
WALLRIGHT BEFORE APPLYING PAINT AND FINISHES.

09 30 00 TILING

09 30 13 CERAMIC TILING
1. CLEAN SURFACES THOROUGHLY AND INSTALL PROPER UNDERLAYMENT AS
PER MANUFACTURER GUIDELINES.
2. OWNER SUPPLIES SPECIFIED CERAMIC TILES FOR PREFERRED KITCHEN
WORKTOP FINISHES.
3. USE NON-SKID CERAMIC TILES (600MM X 1200MM) FROM MARIWASA
CERAMICS INC. FOR TOILETS AND BATHROOMS.
4. USE BOSTIK TILE ADHESIVE OR EQUIVALENT. CONSULT CLIENT, OWNER,
AND ARCHITECT IF NEEDED.

09 50 00 CEILINGS
1. USE 12MM MOISTURE-RESISTANT GYPSUM BOARDS, SUCH AS BOYSEN®
PERMATEX™ #3101, FOR CONSTRUCTION.
2. APPLY 1⁄2” FIBER CEMENT BOARDS (600MM X 1200MM) WITH FLAT LATEX PAINTED
FINISH ON BALCONY.
09 60 00 FLOORING
1. USE 900MM X 400MM BENIN CREAM CERAMIC TILES FROM FLOOR CENTER FOR
BALCONY FLOORING, WITH COLOR-COORDINATED ABC TILE ADHESIVE AND
GROUT.
2. USE 600MM X 600MM GLAZED AND STAIN-RESISTANT CERAMIC TILE FLOORING
FROM FLOOR CENTER.
3. INSTALL NON-SKID CERAMIC TILES (600MM X 1200MM) FROM FLOOR CENTER FOR
TOILETS AND BATHROOMS.

09 80 00 ACOUSTIC TREATMENT
1. GYPROC GYPSUM CEILING TILE PREFAB TYPE III CLASS A FIRE RATING
2. WHITE COAT OF SILENCE SOUND ABSORBING PAINT FOR WALLS FROM
ACOUSTICAL SURFACES, INC.

09 91 00 PAINTING
THIS SECTION OUTLINES PAINTING MATERIALS AND CONTRACTOR
RESPONSIBILITIES.

THE PAINTING CONTRACTOR MUST SUPPLY ALL PERSONNEL, TOOLS, AND


EQUIPMENT NEEDED FOR PAINTING AND FINISHING WORK ACCORDING TO THE PROJECT
SCHEDULE. THEY MUST KEEP THEIR MATERIALS ORGANIZED AND CLEAN, STORING
COMBUSTIBLE GOODS CAREFULLY. OILY RAGS MUST BE PLACED IN METAL CONTAINERS
AND REMOVED DAILY.

UPON COMPLETION, THE CONTRACTOR MUST REMOVE PAINT SPOTS AND


DELIVER FLAWLESS WORK. THEY ARE ACCOUNTABLE FOR PROTECTING THEIR WORK
AND OTHERS', LIABLE FOR ANY DAMAGE CAUSED BY THEMSELVES OR THEIR
EMPLOYEES.

ALL PAINT AND SUPPLIES MUST BEAR THE APPLICABLE BRAND'S TRADEMARKS
AND MUST NOT BE MIXED WITH OTHER BRANDS.
09 91 23 INTERIOR PAINTING
1. EPOXY COATINGS IN TOILET ROOMS
2. ALKYD ENAMEL SEMI-GLOSS PAINTS ON SCHEDULED WALLS AND CEILINGS.
3. CEILINGS PAINTED WHITE.
4. WALLS PAINTED SOUNDPROOFING PAINTS DOUBLE-COATED

DIVISION 10: SPECIALITIES


ALL REQUIRED LABOR AND MATERIALS PERTAINING TO SPECIALTIES REQUIRED IN
THE PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE
COMPLYING WITH ALL APPLICABLE BUILDING CODES.

10 28 00 TOILET, BATH, AND LAUNDRY ACCESSORIES

10 28 13 RESIDENTIAL BATH ACCESSORIES


1. WALL-HUNG WATER CLOSET
2. HCG WALL-HUNG LAVATORY
3. HCG CONCEALED SHOWER SET ABOVE ALCOVE BATHTUB
4. HCG KITCHEN SINK WITH FAUCET
10 35 00 STOVES
10 35 23 COOKING STOVES
1. 60CM ULTIMATETASTE 700 COOKING RANGE WITH INDUCTION COOKTOP
AND 54L CONVECTION OVEN
10 44 00 FIRE PROTECTION SPECIALTIES
MANUAL EXTINGUISHING EQUIPMENT LOCATED IN ACCORDANCE WITH NFPA 10.

DIVISION 12: FURNISHINGS


ALL REQUIRED LABOR AND MATERIALS PERTAINING TO FURNISHINGS REQUIRED
IN THE PROJECT CONSTRUCTION ARE ALL SPECIFIED IN THESE DOCUMENTS, WHILE
COMPLYING WITH ALL APPLICABLE BUILDING CODES.

12 12 00 WALL DECORATIONS
1. 90X80” AND 40X65” COMMISSIONED PAINTING IN LIVING AREA
2. 80X60” COMMISSIONED PAINTING IN BEDROOM

12 21 00 WINDOW CURTAINS
1. 95” DOUBLE PANEL SHEER CURTAIN

12 50 00 FURNITURE
1. 1200X500MM COFFEE TABLE IN LIVING AREA
2. 1600X600MM DINING TABLE IN DINING AREA
3. 450X450MM BEDSIDE TABLE IN BEDROOM
4. USE LG NEW SMART INVERTER WITH WATER DISPENSER, AUTOMATIC ICE MAKER
AND THINQ, 700X1760X680MM IN KITCHEN
12 52 00 SEATING
1. USE ABENSON HOME JOSHUA SOFA SET 3-SEATER URATEX FOAM BEIGE WITH 4
BACK PILLOWS, 2000X600MM IN LIVING AREA.
2. USE 2 IKEA LILLANAS CHAIR, CHROME PLATED/GUNNARED BEIGE, 520X480X870MM
IN DINING AREA

12 59 16 SYSTEMS FURNITURE
FREESTANDING COMPONENT SYSTEMS FURNITURE IN THE UNIT.

DIVISION 23: HEATING, VENTILATING, AND


AIR CONDITIONING
ALL REQUIRED LABOR AND MATERIALS PERTAINING TO HEATING, VENTILATING,
AND AIR CONDITIONING REQUIRED IN THE PROJECT CONSTRUCTION ARE ALL SPECIFIED
IN THESE DOCUMENTS, WHILE COMPLYING WITH ALL APPLICABLE BUILDING CODES.

23 05 93 TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS:


SUPPLY TESTING APPARATUS AND INSTRUMENTS, AND CONDUCT ALL
PROCEDURES TO OPTIMIZE THE PERFORMANCE OF HEATING, VENTILATING, AND
AIR CONDITIONING SYSTEMS.

23 07 13 DUCT INSULATION:
USE EXTERNAL FIBERGLASS BLANKET TYPE THERMAL INSULATION WITH
FIBER-SCRIM-KRAFT FACING FOR ALL SUPPLY AND OUTSIDE AIR DUCTS PASSING
THROUGH AMBIENT AIR OR UNCONDITIONED SPACES.

23 31 00 HVAC DUCTS AND CASINGS:


INSTALL DUCTWORK AND ASSOCIATED COMPONENTS FOR HVAC SYSTEMS.
1. OMNI CEILING MOUNT EXHAUST FAN XFC-300 FROM IPRICE FOR
COMMON TNB.
2. SPLIT TYPE DUAL INVERTER STANDARD AIR CONDITIONER FROM LG
PRODUCTS FOR BEDROOMS.

23 60 00 CENTRAL COOLING EQUIPMENT:


PROVIDE PACKAGED AIR CONDITIONING EQUIPMENT WITH INDOOR CONDENSING
UNITS FEATURING CENTRIFUGAL FANS FOR DUCTED CONNECTIONS TO EXTERIOR WALL
LOUVERS. USE COATINGS AND FASTENERS SUITABLE FOR LONGEVITY IN COASTAL
ENVIRONMENTS. ENSURE VENTILATION AIR PROVISION DURING OCCUPIED HOURS.
DIVISION 26: ELECTRICAL
THE ELECTRICAL INSTALLATION MUST BE CARRIED OUT IN LINE WITH PERMITTED
DESIGNS AND UNDER THE SUPERVISION AND GUIDANCE OF A REGISTERED
PROFESSIONAL ELECTRICAL ENGINEER OR MASTER ELECTRICIAN. IN ALL ELECTRICAL
WORKS AND MATERIALS, THE PROVISIONS OF THE MOST RECENT EDITION OF THE
PHILIPPINE OR NATIONAL ELECTRIC CODE MUST BE OBSERVED.

26 05 00 COMMON WORK RESULTS FOR ELECTRICAL

26 05 19.23 MANUFACTURED WIRING ASSEMBLIES

1. ALL WIRES MUST BE COPPER, SOFT-DRAWN AND ANNEALED, AND HAVE A


CONDUCTIVITY OF 98 PERCENT.
2. IT MUST BE SMOOTH AND FAITHFUL TO CYLINDRICAL FORM, AND IT MUST
BE WITHIN 1% OF THE ACTUAL SIZE REQUIRED.
3. USE PHELPS DODGE OR PHILFLEX BRAND WIRES AND CABLES, OR ANY
PRODUCTS LABELED AS EQUAL, FOR ALL WIRES AND CABLES.

26 05 33.13 CONDUITS FOR ELECTRICAL SYSTEM

1. ALL EXPOSED OR EMBEDDED WIRING AND CABLES MUST BE ENCLOSED IN


STANDARD 1 1/2-INCH CONDUIT BY MOLDEX OR ANY PRODUCTS LABELED
AS EQUAL.

26 5 33.16 BOXES FOR ELECTRICAL SYSTEM

1. USE MEDIUM SIZED BOXES THAT ARE 1/8" THICK AND 2-1/8" DEEP.
2. USE APPLETON BOXES OR ANY OTHER ACCEPTABLE ALTERNATIVE.
3. THE CONNECTION BETWEEN THE CONDUIT AND THE BOX MUST BE
THREADED.

26 06 00 SCHEDULES FOR ELECTRICAL

SEE ELECTRICAL DRAWINGS FOR MORE DETAILS.

26 24 00 PANELBOARDS

26 24 16 PANELBOARDS

1. PANEL BOARD (CIRCUIT BREAKER) 2 BRANCHES

26 51 00 INTERIOR LIGHTING

26 5119 LED INTERIOR LIGHTING

1. DIMMABLE RECESSED PIN LIGHT IN KITCHEN/LIVING AREA/BEDROOM


2. COVE LIGHTING IN KITCHEN/LIVING AREA/BEDROOM
3. ACRYLIC AND ALUMINUM LED PENDANT LIGHT
4. SURFACE MOUNTED LED CENTER LIGHT
5. FLUSH FLUORESCENT IN TOILET
6. USE ENERGY EFFICIENT PIN LIGHT WHEREVER POSSIBLE.