BILL OF QUANTITY

PROYEK : RSIA SURABAYA

LOKASI : SURABAYA

START FINISH TAHUN 2022


HARGA SATUAN TOTAL HARGA
NO URAIAN PEKERJAAN BOBOT (%) JULI AGUSTUS SEPTEMBER OKTOBER
01/07/2022 06/10/2022 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 (Rp.) (Rp.)

PEKERJAAN AIR CONDITIONING 1-Jul-22 6-Oct-22

1 Pengadaan Dan Pemasangan Air Conditioning

a AHU 1 ~ 4 1-Jul-22 30-Aug-22 40,36 4,48 4,48 4,48 4,48 4,48 4,48 4,48 4,48 4,49 156.600.000 626.400.000
Area : Ruang OK 1
Merk : Fujiaire/Daikin/York
Kapasitas : 97.000 Btuh
Air Flow : 1.600 CFM

2 Instalasi Pipa Refrigerant Pipe & Drain Pipe


a Pipa Tembaga ASTM B280
AHU 1 Pipa ( 12.7 mm ) Ø 1/2" + Pipa ( 28.6 mm ) Ø 1-1/8" + Insulasi 20 mm 4-Aug-22 14-Aug-22 1,88 0,63 0,63 0,63 511.396 29.149.591
AHU 2 Pipa ( 12.7 mm ) Ø 1/2" + Pipa ( 28.6 mm ) Ø 1-1/8" + Insulasi 20 mm 14-Aug-22 24-Aug-22 2,01 1,01 1,01 511.396 31.195.177
AHU 3 Pipa ( 12.7 mm ) Ø 1/2" + Pipa ( 28.6 mm ) Ø 1-1/8" + Insulasi 20 mm 24-Aug-22 3-Sep-22 1,45 0,48 0,48 0,48 511.396 22.501.439
AHU 4 Pipa ( 12.7 mm ) Ø 1/2" + Pipa ( 28.6 mm ) Ø 1-1/8" + Insulasi 20 mm 3-Sep-22 13-Sep-22 1,55 0,77 0,77 511.396 24.035.628
Refigerant Chemours R410A 13-Sep-22 16-Sep-22 0,82 0,82 2.550.000 12.750.000
Hanger, Dudukan, Fitting 4-Aug-22 13-Sep-22 0,77 0,11 0,11 0,11 0,11 0,11 0,11 0,11 11.963.183 11.963.183

b Pipa Drain
PVC class AW c/w isolasi, support, hanger & fitting
pipa : dia. 1" 9-Aug-22 13-Sep-22 0,31 0,05 0,05 0,05 0,05 0,05 0,05 74.375 4.760.000

3 Instalasi AC, Ducting, Jasa, & Material


BJLS 0,5 mm + Insulation 20 mm 9-Aug-22 13-Sep-22 2,63 0,44 0,44 0,44 0,44 0,44 0,44 260.007 40.800.335
BJLS 0,6 mm + Insulation 20 mm 9-Aug-22 13-Sep-22 11,72 1,95 1,95 1,95 1,95 1,95 1,95 294.091 181.924.436
Trocellen Air Pro 20 mm (1,2 m x 20 m) 9-Aug-22 13-Sep-22 10,59 1,76 1,76 1,76 1,76 1,76 1,76 211.842 164.287.708

Hepa with Box Include Media Filer H14 9-Aug-22 13-Sep-22 6,78 1,13 1,13 1,13 1,13 1,13 1,13 6.575.000 105.200.000
Perforated RAG 500x300 9-Aug-22 13-Sep-22 1,11 0,18 0,18 0,18 0,18 0,18 0,18 1.075.000 17.200.000
FAG 300x300 20-Sep-22 25-Sep-22 0,09 0,04 0,04 345.000 1.380.000

C. MATERIAL BANTU, DLL 9-Aug-22 25-Sep-22 3,29 0,41 0,41 0,41 0,41 0,41 0,41 0,41 0,41 51.079.248 51.079.248

4 Pekerjaan Panel Kontrol dan Kabel Power


a Panel Controller AHU DX Sytem 20-Sep-22 27-Sep-22 5,67 2,84 2,84 88.000.000 88.000.000
- Controller with PLC Siemens
- Setting & Monitoring Temperature, Relative Humidity
- Display HMI 7 Inchi Brand Wientek
- Safety Interlock Electrik heater
b Sensor Temperature & Relative Humidity (RH) 20-Sep-22 27-Sep-22 0,52 0,26 0,26 2.710.000 8.130.000
c Sensor Differential Pressure room Analog with Casing SS 20-Sep-22 27-Sep-22 0,72 0,36 0,36 3.710.000 11.130.000
d Kabel Power Dari Panel AHU & Outdoor
Kabel Power AHU 1 ~4 NYY 4 x 4 mm2 20-Sep-22 25-Sep-22 0,94 0,47 0,47 60.647 14.555.345
Kabel Power Heater NYY 4 x 2,5 mm2 dlm Conduit PVC 3/4" 20-Sep-22 25-Sep-22 0,69 0,34 0,34 44.598 10.703.564
Kabel Power Outdoor AHU 1 ~ 4 NYY 4 x 10 mm2 dlm Conduit PVC 3/4" 20-Sep-22 25-Sep-22 0,77 0,39 0,39 120.029 12.002.891

Kabel Kontroller From IU to OU AWG 18 1-Oct-22 6-Oct-22 0,35 0,35 20.200 5.488.340
Kable Thermostat & Communication AWG 18 1-Oct-22 6-Oct-22 0,21 0,21 20.200 3.232.000
e Kabel Feeder Dari Panel AHU Ke SDP Panel by Other
f Cable tray & Support 6-Oct-22 9-Oct-22 0,42 0,21 0,21 6.524.214 6.524.214
g Accessories & Support Cable 6-Oct-22 9-Oct-22 1,03 0,51 0,51 15.976.635 15.976.635

5 Biaya Persiapan dan Lain Lain


- Biaya Pengirman Unit & Material 1-Jul-22 9-Oct-22 0,81 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 0,05 12.500.000 12.500.000
- Biaya Akomadasi & Transportation 1-Jul-22 9-Oct-22 1,03 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 0,07 16.000.000 16.000.000
- Biaya Lifting & Handling 1-Jul-22 30-Aug-22 0,52 0,06 0,06 0,06 0,06 0,06 0,06 0,06 0,06 0,06 8.000.000 8.000.000
- Biaya test Commisioning 6-Oct-22 9-Oct-22 0,97 0,48 0,48 15.000.000 15.000.000
100,00
4,66 4,66 4,66 4,66 5,40 11,33 12,34 12,20 11,19 7,42 7,76 5,23 5,23 1,89 1,33
- 4,66 9,33 13,99 18,66 24,06 35,39 47,73 59,93 71,12 78,54 86,31 91,54 96,78 98,67 100,00