Title:-Incoming Material Inspection Checklist

Department:-Quality Cantrol
Indus Emergency Vehicle Pvt Ltd Date -01/03/2024
Item Name - SHUTTER MCD

Ref. Documents
Sr.No Test Critera Specification Method Observation/Remarks
PO/SPEC./DRG

OUTER DIA

PCD
PTO Top Flange ID
1
Dimension
STEP

HOLE DIA

NO. OF HOLE

7 In-Put Source(AC/DC)

8 Pressure

9 Warning whistle Second

10 demand valve working

11 Regulator Oparting

12 Facepiece & Breathing tube condtion

13 Entire Apparatus Condition

14 Deflection test

15 Roller condtion Acceptable

16 Gear ratio

OUTER DIA
PCD
ID
Bottom Flange
17
Dimension STEP

HOLE DIA

NO. OF HOLE

23 Suction out-late --

24 Delivery outlate --
25 Capacity(LPM/LBS) --

26 Visual Condion Visual No Damage Found

27 Rotation --

28 Nozzle working(Jet & Flow)

29 Hieght 1180 MM PO DIMENSTIONAL 1445 MM

30 Width 1128 MM PO DIMENSTIONAL 1117 MM

31 Paint condition Visual Accepatable

32 Junction Box --

Remarks :- Total Quantity Of Shutter 02 Nos(Same Dimenstion). Accepatable

Checked By -Riyaz Rtahod /pinal