MEASUREMENT SHEET (Tentative)

Measurement
Item
Item Description Breadth/ Height/ Unit Rate Amount (Rs.)
No. No Length Quantity
Width Depth
1 Excavation for Foundation
Dismentling 50 7.50 7.50 1.000 2,812.50 Cft
79.59 Cu.m 3,000.00 238,781.25
2 Excavation for Foundation
Footings 50 7.50 7.50 6.000 16,875.00 Cft
477.56 Cu.m 800.00 382,050.00
3 P/A Anti Termite proofing -
Shed-1 1 110.00 155.00 17,050.00 -
Shed-2 1 100.00 120.00 12,000.00 -
29,050.00 Sft -
2,698.75 Sq.m 150.00 404,811.75
4 Earth Filling -
Shed-1 1 110.00 155.00 1.000 17,050.00 -
Shed-2 1 100.00 120.00 1.000 12,000.00 -
29,050.00 Cft -
822.12 Cu.m 1,200.00 986,538.00
5 PCC (1:4:8) in Foundation -
Under Footings 50 7.50 7.50 0.330 928.12 Cft -

1 of 3
Measurement
Item
Item Description Breadth/ Height/ Unit Rate Amount (Rs.)
No. No Length Quantity
Width Depth
Excavation for Foundation 26.27 Cu.m 8,000.00 210,126.37
6 Steel G-60 -
Nos Bars C.Length U. Weight Weight (lbs)

Footings #6 bars @ 6" c/c 50 30 8.08 1.502 18,204.24 -


Pedestal Columns #8 bars 50 8 12.00 2.670 12,816.00 -
#3 dia rings @ 8" c/c 50 11 7.50 0.376 1,551.00 -
#3 dia rings @ 8" c/c 50 22 2.25 0.376 930.60 -
Plinth Beams #6 bars 1 6 1,130.00 1.502 10,183.56 -
#3 dia rings @ 8" c/c 1 1455 5.16 0.376 2,822.93 -
Flooring #4 @ 9" c/c 1 29,050.00 SFT @ 1.87 lbs per Sft 54,323.50 -
100,831.83 Lbs -
45,737.32 Kgs 392.00 17,929,028.69
7 RCC (1:2:4:) in Footings -
50 7.00 7.00 1.750 4,287.50 Cft -
121.34 Cu.m 16,000.00 1,941,380.00
8 RCC (1:2:4:) in Pedestal Columns -
50 2.00 2.00 9.000 1,800.00 Cft -
50.94 Cu.m 16,000.00 815,040.00
9 RCC (1:2:4:) in Plinth Beam -

2 of 3
Measurement
Item
Item Description Breadth/ Height/ Unit Rate Amount (Rs.)
No. No Length Quantity
Width Depth
Excavation for Foundation
Shed-1 2 110.00 1.25 1.500 412.50 -
2 155.00 1.25 1.500 581.25 -
Shed-2 2 100.00 1.25 1.500 375.00 -
2 120.00 1.25 1.500 450.00 -
1,818.75 Cft -
51.47 Cu.m 16,000.00 823,530.00
10 PCC (1:4:8) Under Floor -
Shed-1 1 110.00 155.00 0.330 5,626.50 -
Shed-2 1 100.00 120.00 0.330 3,960.00 -
9,586.50 Cft -
159.23 Cu.m 8,000.00 1,273,839.60
11 PCC (1:4:8) Under Floor -
Shed-1 1 110.00 155.00 0.500 8,525.00 -
Shed-2 1 100.00 120.00 0.500 6,000.00 -
14,525.00 Cft -
241.26 Cu.m 16,000.00 3,860,120.00

28,626,464.41