Professional Documents
Culture Documents
Stress Analysis of A Gas Pipeline Installed Using HDD and Auger Bore Techniques
Stress Analysis of A Gas Pipeline Installed Using HDD and Auger Bore Techniques
Stress Analysis of A Gas Pipeline Installed Using HDD and Auger Bore Techniques
IPC2008-64436
IPC2008-64436
ABSTRACT INTRODUCTION
As part of an important project to reinforce the natural gas An assessment of the crossings was performed by splitting each
transmission network, a new pipeline has been constructed to of the sections into straight pipe and bends and those sections
transport natural gas from a major UK LNG storage facility that have different loadings. Within IGE/TD/1, there is a
into the national transmission system. requirement to assess stresses against code limits for membrane
stress and membrane plus bending stress.
The project involved the installation of several sections by
trenchless methods, namely auger boring for a number of road The stress analysis of these proposed routes required multi-
crossings and significant lengths of horizontal directional disciplinary knowledge of both geotechnical and mechanical
drilling (HDD) beneath railroads, canals and marshland. engineering. Furthermore, since IGE/TD/1 does not provide
formulae for the calculation of soil loads, traffic loads,
The installation of pipelines using trenchless techniques such as settlement loads or construction stress a variety of other
HDD continues to increase in popularity. The various methods methods were used to determine these values. Soil loads were
available offer advantages over traditional open cut techniques, calculated using guidance from the literature (Marston) and
in particular much reduced disruption during the construction from a Dutch national code, NEN 3650 [2]. Traffic loads were
of road and rail crossings. Furthermore, increased awareness calculated using the well known Boussinesq method, whilst
and responsibility towards the environment leads us to seek settlement stresses were estimated with the aid of Caesar II [4]
installation methods that cause the least disruption at the pipework stress analysis software. For auger sections the
surface and have the least impact to the environment. construction loads associated with installation were calculated
based on the axial force required to overcome friction, the
It was required to assess the proposed crossing designs against crossing length and the most onerous radius of curvature of the
acceptable stress limits set out in company specifications and crossing. At HDD sections a similar method was used but
against the requirements of UK design code IGE/TD/1 Edition based on pulling loads supplied by the HDD contractor.
4 [1], which requires that ‘additional loads’ such as soil
loadings, thermal loads, settlement and traffic loading are This paper gives a full description of the modelling technique
accounted for within the stress calculations. However, it does that was applied and gives a detailed description of the results.
not stipulate the sources of such equations and the pipeline
engineer must rely on other methods and published sources of NOMENCLATURE
information. A Cross sectional area
B1 Half width of soil column in shear
This paper presents the method used to analyse those sections Bd Auger bore diameter
of the new pipeline installed by auger boring and HDD D Pipe outside diameter
focusing on the methods and formulae used to calculate the E Young’s modulus (steel)
stresses in the pipeline from all loading sources. Es Soil elasticity modulus
FAX Auger axial load
General
The equivalent membrane and bending stresses arise from Briefly the auger bore method is a trenchless construction
different loadings which are discussed in the following method in which the bore is formed with a rotating auger head
sections. and spoil is removed by the helical screw conveyors (auger
flights). The casing or product pipe is normally simultaneously
Allowable Cyclic Stress Criteria installed by jacking with hydraulic rams. Jacking commences
Company specific standards used for the project state that the from within an excavation termed the ‘launch pit’ and it is
cyclic stress range resulting from traffic loading should be pushed towards the ‘receive pit’. This technique generally
below the following criteria, causes minimal surface disturbance
For this project, the technique was used for the shorter
Δσprincipal ≤ 35 MPa (3) crossings (up to 50m in length) of major roads, minor roads,
ditches and tracks.
Where the maximum principal stress range exceeds the
allowable limit, an analysis was carried out to determine a
number of passes per day of the given vehicle load; this was
then passed to the Client to determine acceptability.
The fatigue analysis only takes into consideration the transient Other vertical loads acting are the self weight load and, if the
loadings from traffic, since the Client confirmed that the pipe is below the water table, the load due to buoyancy.
damage accrued from pressure fluctuations is insignificant.
Ko = 1-sinφ (6)
Using the above method, the worst case loading due to the
relevant vehicle above the pipeline can be determined by
evaluating the load for a range of positions across the pipeline.
Dosin1/2θb
The determination of the traffic load is independent of the
FIGURE 2 – LOADING PATTERN PER NEN 3650 installation technique employed.
Settlement Load
Traffic Load In general when a pipeline is installed the soil in the bedding
Using the Boussinesq theory the stress, σz, at a point z due to a zone of the pipeline is disturbed, which leads to differential
point load Q at a location in space (z,r) is given by: settlement beneath the pipeline. Furthermore, differences in
soil loading occur between the send/receive pits and the
augered sections, which gives rise to further differential
5 settlement.
⎛ ⎞ 2
⎜ ⎟ For the analysis, finite element analysis using the CAESAR II
3Q ⎜ 1 ⎟ software [4] was used to determine the bending stresses due to
σz = 2 ⎜ 2 ⎟ the weight of the soil, pipe and fluid for the auger bored
2πH ⎜ ⎛ r ⎞ ⎟
⎜1 + ⎜ H ⎟ ⎟ sections. The models comprised of beam elements with springs
⎝ ⎝ ⎠ ⎠ (7) modelling the soil restraint in the vertical (upward and
downwards), axial and lateral directions. The soil load
corresponding to the open cut and auger sections being applied
The effects of multiple loads Q are calculated from the as distributed loads.
summation of each load. The total load due to traffic is then
calculated as The spring values were calculated using the guidance presented
by the ASCE [5]. The soil restraint is represented by a bi-linear
spring relationship consisting of an ultimate load and a
Using the above method, the settlement stress is provided A detailed analysis of the loads on the pipeline during
directly. It should be noted that this settlement stress is distinct installation of the HDD sections was carried out by others and
from a settlement stress that may be caused due to this paper deals only with the loads in the pipeline after
consolidation at sections where open-cut techniques are used. installation.
Construction Load
Construction loads arise where physical force has been exerted
to ‘fit-up or ‘fit-in’ the pipeline. For conventional open-cut
trench installations, construction loads are minimal. However,
for trenchless installations such as auger bore, the pull and
alignment stresses can be significant
For the auger bored sections, the push through force will be
greater than the force required to overcome friction. FAX is the
axial soil friction load/unit length,
D
FAX = μ ⋅ D ⋅ ( 2 ⋅ ρ s ⋅ H + π ⋅ ρ p ⋅ t + π ⋅ ρ f ⋅ )⋅ g
4 (9)
From the crossing drawings, the maximum radius of curvature FIGURE 4 – THE HDD PROCESS
on any of the sections will be 40D m (cold field bend
curvature). Thus the membrane and bending construction Soil Load
stresses for the auger bored sections during pull through are For HDD installations the soil loads presented in section C4.8
given by, of NEN 3650 are appropriate. For sand this is given by,
− Kh tan ϕ
F .L ⎛ F ⎞⎛ ⎞
σ m −aug = Ax (10) Qn ,r1 = ⎜⎜ γh − r ⎟⎟⎜1 − e B1 ⎟ D (12)
A ⎝ 2 B1 ⎠⎜⎝ ⎟
⎠
HDD SECTIONS ⎛ F ⎞
Qn ,r 2 = ⎜⎜ γh − r ⎟⎟ D (13)
⎝ 2 B1 ⎠
General
Briefly this method involves drilling a pilot hole with a
continuous drill string along a pre-determined path. A back- Where, B1, is the half width of the soil column in shear and Fr
reamer is then attached to the string when it emerges at the is the adhesion due to arching, as defined in NEN 3650. For
opposite side of the crossing. The reamer then bores out the the purpose of these analyses Fr was conservatively assumed to
pilot hole and the pipe is then pulled through. Drilling fluid is be zero meaning that the load in sand reduces to the Marston
injected into the hole during drilling and reaming to stabilise trench load, whilst the load in clay or peat soils reduces to the
the hole and remove spoil. The drilling fluid is water with neutral load, both of which are considered conservative for this
Er
σ b−hdd = (15)
The re-rounding factor, frr accounts for the reduction of
R circumferential bending stress due to the ring stiffening effect
of internal pressure and is given by,
P( D − t )
σhp = (16) And ky is a deflection factor dependent on the loading and
2t support angles θt, θs and θb as per Figure 2.
And the ring membrane stress, σm-ring due to the total external Axial Membrane Stress
load, Qtot, The axial membrane stresses due to the construction type are
presented in equations 10 and 14. For auger bored sections the
membrane stress due to settlement as determined using Caesar
Qtot II was also included.
σ m−ring = (17)
2t
At bend locations all of the above stresses were multiplied by a σ eq m = σ cm−tot 2 + σ am−tot 2 − σ c m−totσ a m−tot (24)
stress concentration factor due to the geometry, given by,
CONCLUSIONS
A method has been presented that shows the process for
determining the acceptability of stresses at pipeline crossings
installed by trenchless methods, namely auger boring and
HDD.
REFERENCES
1. IGE/TD/1 Edition 4, Recommendations on
Transmission and Distribution Practice - Steel
Pipelines for High Pressure Gas Transmission,
The Institution of Gas Engineers
2. NEN 3650, ‘Requirements for Steel Pipeline
Transportation Systems’, Nederlands
Normalisatie Institut, March 2006.
3. BS 7608:1993, fatigue design and assessment of
steel strucrtures, BSi
4. COADE CAESAR II Pipe Stress Analysis
Software, Version 5.0.
5. Guidelines for the Seismic Design of Oil and Gas
Pipeline Systems, Prepared by the Committee on
Gas and Liquid Fuel Lifelines of the ASCE
Technical Council on Lifeline Earthquake
Engineering
6. Design Manual for Roads and Bridges, Volume 1
Section 3 part 14, Loads for Highway Bridges,
The Highways Agency, 2001
7. Strength of steel culvert sheets bearing against
compacted sand backfill, Highway Research
Record 30, Highway Research Board
(Washington DC), Meyerhof G.G. and Baikie
L.D, 1963