Name : Ridzat Ali Murphy

Position : Construction Manager


Department : Construction Department
Project : Cirata Project
Periode : 26 Okt - 25 Nov 2022

IMPLEMENTATION KP
No.
October Period Area

I First Week Retaining Wall


- Section D

- Section C

- Section B

Stone Masonry
- Section G

Slope Area
- Sortcrete

II Second Week Retaining Wall


- Section D

- Section C

- Section B

- Section I

Slope Area
- Sortcrete

III Third Week Retaining Wall


- Section B

- Section I

IV Fourth Week Retaining Wall


- Section B
IMPLEMENTATION KPI CONSTRUCTION MANAGER - CIRATA PROJECT

Item of Work Descriptiom Status

Gravel 5-7 cm Installation gravel behind retaining wall 100%


Palm fiber Installation palm fiber behind retaining wall 100%

Concrete Works pouring concrete part 2 `


curing concrete 100%
Formwork Dismantle formwork part 1 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%

Stone Masonry order materials such as sones, sand, cement 100%


Installation stone masonry 100%

Sortcrete Pouring sortcrete 100%


Gravel 5-7 cm Installation gravel behind retaining wall 100%

Formwork Dismantle formwork part 1 100%


dismantle scaffolding 100%
Dismantle formwork part 2 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%
Sand layer Installation sand layer 0,15 cm 100%
Concrete Works Pouring lean concrete 0,15 cm 100%
Rebar and Formwork Installation rebar and formwork 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 2 100%


Concrete Works Pouring concrete in retaining wall part 2 - section 2 100%
Concrete Works Pouring concrete in retaining wall part 1 - section 1 100%

Sortcrete Pouring sortcrete 100%

Concrete Works Pouring concrete in pile cap 100%


Rebar and Formwork Installation rebar and formwork in retaining wall 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 3 100%

Concrete Works Pouring concrete in retaining Wall 0%


notes
hold (material, equipment, and manpower issues)
Name : Ridzat Ali Murphy
Position : Construction Manager
Department : Construction Department
Project : Cirata Project
Periode : 26 Okt - 25 Nov 2022

IMPLEMENTATION KPI CONSTRUCTION MANAG


No.
October Period Area

I First Week Retaining Wall


- Section D

- Section C

- Section B

Stone Masonry
- Section G

Slope Area
- Sortcrete

II Second Week Retaining Wall


- Section D

- Section C

- Section B

- Section I

Slope Area
- Sortcrete

III Third Week Retaining Wall


- Section B

- Section I

IV Fourth Week Retaining Wall


- Section B
EMENTATION KPI CONSTRUCTION MANAGER - CIRATA PROJECT

Item of Work Descriptiom Status

Gravel 5-7 cm Installation gravel behind retaining wall 100%


Palm fiber Installation palm fiber behind retaining wall 100%

Concrete Works pouring concrete part 2 100%


curing concrete 100%
Formwork Dismantle formwork part 1 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%

Stone Masonry order materials such as sones, sand, cement 100%


Installation stone masonry 100%

Sortcrete Pouring sortcrete 100%


Gravel 5-7 cm Installation gravel behind retaining wall

Formwork Dismantle formwork part 1


dismantle scaffolding
Dismantle formwork part 2
dismantle scaffolding

Broken Top of pile Cutting pile head of bored pile


Excavation remove soil for broke top of pile
Sand layer Installation sand layer 0,15 cm
Concrete Works Pouring lean concrete 0,15 cm
Rebar and Formwork Installation rebar and formwork

Concrete Works Pouring concrete in retaining wall part 1 - section 2


Concrete Works Pouring concrete in retaining wall part 2 - section 2
Concrete Works Pouring concrete in retaining wall part 1 - section 1

Sortcrete Pouring sortcrete

Concrete Works Pouring concrete in pile cap


Rebar and Formwork Installation rebar and formwork in retaining wall

Concrete Works Pouring concrete in retaining wall part 1 - section 3

Concrete Works Pouring concrete in retaining Wall


Name : Ridzat Ali Murphy
Position : Construction Manager
Department : Construction Department
Project : Cirata Project
Periode : 26 Okt - 25 Nov 2022

IMPLEMENTATION KPI CONSTRUCTION MANAG


No.
October Period Area

I First Week Retaining Wall


- Section D

- Section C

- Section B

Stone Masonry
- Section G

Slope Area
- Sortcrete

II Second Week Retaining Wall


- Section D

- Section C

- Section B

- Section I

Slope Area
- Sortcrete

III Third Week Retaining Wall


- Section B

- Section I

IV Fourth Week Retaining Wall


- Section B
EMENTATION KPI CONSTRUCTION MANAGER - CIRATA PROJECT

Item of Work Descriptiom Status

Gravel 5-7 cm Installation gravel behind retaining wall 100%


Palm fiber Installation palm fiber behind retaining wall 100%

Concrete Works pouring concrete part 2 100%


curing concrete 100%
Formwork Dismantle formwork part 1 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%

Stone Masonry order materials such as sones, sand, cement 100%


Installation stone masonry 100%

Sortcrete Pouring sortcrete 100%


Gravel 5-7 cm Installation gravel behind retaining wall 100%

Formwork Dismantle formwork part 1 100%


dismantle scaffolding 100%
Dismantle formwork part 2 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%
Sand layer Installation sand layer 0,15 cm 100%
Concrete Works Pouring lean concrete 0,15 cm 100%
Rebar and Formwork Installation rebar and formwork 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 2 100%


Concrete Works Pouring concrete in retaining wall part 2 - section 2 100%
Concrete Works Pouring concrete in retaining wall part 1 - section 1 100%

Sortcrete Pouring sortcrete 85%

Concrete Works Pouring concrete in pile cap


Rebar and Formwork Installation rebar and formwork in retaining wall

Concrete Works Pouring concrete in retaining wall part 1 - section 3

Concrete Works Pouring concrete in retaining Wall


Notes
Subcon Off
Name : Ridzat Ali Murphy
Position : Construction Manager
Department : Construction Department
Project : Cirata Project
Periode : 26 Okt - 25 Nov 2022

IMPLEMENTATION KPI CONSTRUCTION MANAG


No.
October Period Area

I First Week Retaining Wall


- Section D

- Section C

- Section B

Stone Masonry
- Section G

Slope Area
- Sortcrete

II Second Week Retaining Wall


- Section D

- Section C

- Section B

- Section I

Slope Area
- Sortcrete

III Third Week Retaining Wall


- Section B

- Section I

IV Fourth Week Retaining Wall


- Section B
EMENTATION KPI CONSTRUCTION MANAGER - CIRATA PROJECT

Item of Work Descriptiom Status

Gravel 5-7 cm Installation gravel behind retaining wall 100%


Palm fiber Installation palm fiber behind retaining wall 100%

Concrete Works pouring concrete part 2 100%


curing concrete 100%
Formwork Dismantle formwork part 1 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%

Stone Masonry order materials such as sones, sand, cement 100%


Installation stone masonry 100%

Sortcrete Pouring sortcrete 100%


Gravel 5-7 cm Installation gravel behind retaining wall 100%

Formwork Dismantle formwork part 1 100%


dismantle scaffolding 100%
Dismantle formwork part 2 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%
Sand layer Installation sand layer 0,15 cm 100%
Concrete Works Pouring lean concrete 0,15 cm 100%
Rebar and Formwork Installation rebar and formwork 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 2 100%


Concrete Works Pouring concrete in retaining wall part 2 - section 2 100%
Concrete Works Pouring concrete in retaining wall part 1 - section 1 100%

Sortcrete Pouring sortcrete 100%

Concrete Works Pouring concrete in pile cap 100%


Rebar and Formwork Installation rebar and formwork in retaining wall 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 3 100%

Concrete Works Pouring concrete in retaining Wall


Notes
Name : Ridzat Ali Murphy
Position : Construction Manager
Department : Construction Department
Project : Cirata Project
Periode : 26 Okt - 25 Nov 2022

IMPLEMENTATION KPI CONSTRUCTION MANAG


No.
October Period Area

I First Week Retaining Wall


- Section D

- Section C

- Section B

Stone Masonry
- Section G

Slope Area
- Sortcrete

II Second Week Retaining Wall


- Section D

- Section C

- Section B

- Section I

Slope Area
- Sortcrete

III Third Week Retaining Wall


- Section B

- Section I

IV Fourth Week Retaining Wall


- Section B
EMENTATION KPI CONSTRUCTION MANAGER - CIRATA PROJECT

Item of Work Descriptiom Status

Gravel 5-7 cm Installation gravel behind retaining wall 100%


Palm fiber Installation palm fiber behind retaining wall 100%

Concrete Works pouring concrete part 2 `


curing concrete 100%
Formwork Dismantle formwork part 1 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%

Stone Masonry order materials such as sones, sand, cement 100%


Installation stone masonry 100%

Sortcrete Pouring sortcrete 100%


Gravel 5-7 cm Installation gravel behind retaining wall 100%

Formwork Dismantle formwork part 1 100%


dismantle scaffolding 100%
Dismantle formwork part 2 100%
dismantle scaffolding 100%

Broken Top of pile Cutting pile head of bored pile 100%


Excavation remove soil for broke top of pile 100%
Sand layer Installation sand layer 0,15 cm 100%
Concrete Works Pouring lean concrete 0,15 cm 100%
Rebar and Formwork Installation rebar and formwork 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 2 100%


Concrete Works Pouring concrete in retaining wall part 2 - section 2 100%
Concrete Works Pouring concrete in retaining wall part 1 - section 1 100%

Sortcrete Pouring sortcrete 100%

Concrete Works Pouring concrete in pile cap 100%


Rebar and Formwork Installation rebar and formwork in retaining wall 100%

Concrete Works Pouring concrete in retaining wall part 1 - section 3 100%

Concrete Works Pouring concrete in retaining Wall 85%


Notes
hold (material, equipment, and manpower issues)