Date : 06 Oct 2016

To : Operator Dept.

Cc : Safety Dept.

Cc : Technical Dept.

From : OCEAN LYNX

Sub : Apply for WBT ENCLOSED SPACE PERMIT

Dear Sir,

Please kindly requested for Enclosed Space Permit to purpose Tank’s Inspection on 06 Oct
2016.

a. Vessel Tank’s (WBT 2W, 4W, 6W, 7W) has dry and checked LEL and follow as per
Company SMS Procedures and ISGOT guidance ( Atmosphere 21 % and LEL < 1 % of
Tank’s.

b. All Tank has been Gas Free

c. Safety Meeting conducted by Master, C/O, Duty Officer, Bosun and the crew who enter.

d. Portable Gas Meter last Calibration : 03 Oct 2015

e. Portable Gas meter tested before use : 06 Oct 2016

Attached herewith Risk Assessment in the File

Please issue Enclose Space Entry Permit as Necessary.

Capt. Lin Huahui______


Master of OCEAN LYNX