: T22035-CD-000-ELE-REQ-005
FOR INFORMATION
2 08 Feb 23 TRFB CDW BST
ONLYINFORMATION
FOR INFORMATION TRFB
1 20 Jan 23 CDW BST
ONLYINFORMATION
FOR INFORMATION
0 11 Jan 23 TRFB CDW BST
ONLYINFORMATION
REV. DATE DESCRIPTION PREPARED CHECKED APPROVED
THIS VOLUME EMBODIES PROPRIETARY INFORMATION OF PT. PP PERSERO THIS VOLUME OF THE MATERIAL DESCRIBED THEREON MAY
DOC. NO. : T22035-CD-000-ELE-REQ-005
THIS VOLUME EMBODIES PROPRIETARY INFORMATION OF PT. PP (PERSERO) TBK. THIS VOLUME OR THE MATERIAL DESCRIBED THERE ON MAY
NOT BE COPIED OR DISCLOSED IN ANY FORM OR MEDIUM TO THIRD PARTIES OR USED FOR OTHER THAN THE PURPOSE FOR EHICH IT HAS BEEN
PROVIDED, IN WHOLE OR IN PART IN ANY MANNER EXCEPT AS EXPRESSLY PERMITTED BY PT. PP (PERSERO) TBK.
REVISION LOG
Page |2
DOC. NO. : T22035-CD-000-ELE-REQ-005
TABLE OF CONTENT
1. GENERAL 4
2. ITEMS TO BE PURCHASED 4
3. DOCUMENT ATTACHED TO THIS REQUISITION 5
4. ORDER OF PRECENDENCE 5
5. SCOPE OF WORK AND SUPPLY 6
6. DEVIATION 6
7. DOCUMENT REQUIREMENT 6
8. VENDOR RESPONSIBILITY 7
9. TECHNICAL SPECIFICATION 7
a. APPENDIX-1: List Scope of Work andScope of Supply – Main Equipment and AccessoriesScope of Inspection
b. APPENDIX-3: Technical Standard/Code and Local RegulationDeviation Form
c. APPENDIX-4: Scope of Supply – Electrical and InstrumentPerformance test
e. APPENDIX-5 Deviation and Clarification List
Page |3
DOC. NO. : T22035-CD-000-ELE-REQ-005
[1.] GENERAL
This requisition covers the requirement for MV & LV Switchgear and Distribution Panels to be purchased
by PT PP (Persero), Tbk. for Sumbawa-2 Gas Engine Power Plant 30 MW in Labuhan Badas, Sumbawa
Regency, West Nusa Tenggara Province.
1.1 This requisition covers the requirements for bid including design engineering (issue and approval of
document), fabrication/manufacturing, inspection, testing and transportation of New Centrifugal Pump for
NPK Chemical Project of PT. Pupuk Iskandar Muda (PIM), located at Krueng Geukueh, North Aceh.
Metric System shall be used except pipe sizes for which the nominal pipe sizes shall be used.
1.3 Language:
English shall be used in the documents, calculations, and drawings to be prepared for this project.
Definitions
Name of the Project – xxx
Location – xxx
Purchaser – means PT PP (Persero), Tbk. and its designee who acts on its behalf for Purchase Order.
ClientOwner – means the clientOwner for whom the Purchaser performs work in which Goods are to
be incorporated.
Vendor – means the firm or company with whom Purchase Order is to be placed.
Page |4
DOC. NO. : T22035-CD-000-ELE-REQ-005
The material and quantities to be furnished shall be in accordance with the requirements specified in this
requisition and reference documents specified in Section 3. Requisition (Bill of Quantity / BQ) of xxx,
not limited to various material specification of xxx., and the requirements specified in this purchasing
specification, and reference documents.
Page |5
DOC. NO. : T22035-CD-000-ELE-REQ-005
Page |6
DOC. NO. : T22035-CD-000-ELE-REQ-005
4.[6.] DEVIATION
Unless vendor purposes any exceptions and alternatives, Vendor’s design shall be strictly in compliance
with this purchasing specification. If Vendor purposes any deviation and exception which are deemed
necessary, a list of deviations and exceptions with explanations shall be submitted with their proposal to
Purchaser. Please fill in the FORM-32 Deviation. (See APPENDIX-3)
Only deviations submitted in writing using the Deviation Form per FORM-32, and approved by
Purchaser/ClientOwner before order, will be accepted. In the event that Vendor complied without any
exceptions to the requirement, Vendor shall also return FORM-2 with statement “NO DEVIATION”
printed, together with Vendor’s quotation.
Page |7
DOC. NO. : T22035-CD-000-ELE-REQ-005
The function of the low voltage (LV) system is to provide low voltage (400 V, 3 phase, 3 wire and 400/230 V,
3 phase, 4 wire) AC auxiliary power to loads consisting of small motors, lighting, general low voltage
distribution panels, etc.
The LV system will supply normal power to 3-phase as well as single phase AC loads; the vital electrical loads
in the plant & substation will be supplied from the 400 V essential service buses and/or from 230 V
uninterruptible power supplies.
Each MCC shall be equipped with one (1) set of 3-phase and neutral main buses, a set of 3-phase and neutral
auxiliary buses for each vertical multi-tier arrangement of units, and a ground bus.
The Bidder shall provide AC distribution panels to supply AC power to all items of plant which require AC
power. Distribution panels shall be provided with top and bottom removable metal gland plates which shall be
drilled on site to suit the cable glands or conduit. All top entry points shall be sealed to prevent the ingress of
moisture. All gland plates shall be fitted with gaskets.
All switchgear, control gear and fuse gear shall be located indoors, in metal-clad sheet steel cubicles with front
access doors, and be manufactured and tested in accordance with relevant International Standards. Main
switchboards shall be extendible at both ends.
The main busbars together with the tee-off busbars connecting the main busbars to the isolating/protective
devices on all incoming and outgoing circuits shall be contained in a separate compartment within the
switchboard. The bus bars shall be air insulated except where solid insulation is a design feature. The main
busbars shall have the same current rating throughout their length.
Apparatus which has to be removed from a panel or cubicle for maintenance purposes shall either be of the
withdrawable type or shall be readily removable without disturbing other apparatus or wiring.
Medium voltage switchgear shall be referring to IEC 62271, and the circuit breakers specified as GCB shall be
refer to IEC/IEEE 62271-37- 013 standard.
The Bidder shall propose suitable transfer scheme to achieve safe and reliable operation during start-up,
normal operation, normal shutdown and emergency shutdown, of which the Bidder shall demonstrate his
proposed scheme for Owner approval.
Low-voltage switchgear and control gear shall be to IEC 60439 Form 4 with air break circuit-breakers,
contactor units, molded case circuit-breakers. All points of isolation shall incorporate a feature for fitting a
padlock when in the open position.
The equipment shall be rated to withstand the mechanical forces and thermal effects of the maximum
prospective fault current at the point of application.
Page |9
DOC. NO. : T22035-CD-000-ELE-REQ-005
MV switchboard busbar safety shutters shall be indelibly identified, in English, in accordance with the
following:
Busbars Color - signal red; marking – BUSBARS; lettering color - white; minimum lettering height -
35mm
Incoming Color - lemon; marking - DANGER LIVE CABLES; lettering color signal Feeder red;
minimum lettering height - 35mm
Circuit Color – lemon
On bus-section units both sets of shutters shall be painted signal red and labeled 'busbars'. Voltage transformer
spout shutters shall be painted lemon yellow.
Circuit earthing facilities shall be provided for all incoming and outgoing circuits of MV switchboards to
fulfill safety requirement. Operation of the earthing switches shall only be possible in the removed position of
the switching device and by means of a key switch. Short time current and making capability of the earthing
switch shall conform to the charateristics of the metal clad unit. In addition, provision shall be made to earth
each MV busbar at two separate points.
Withdrawable units shall be provided with lockable shutters to prevent inadvertent access to live connections
when the unit is withdrawn.
All operational and maintenance interlocking and any other feature necessary to comply with the Owner's
Safety Rules shall be provided including a padlocking facility on:
a. Busbar and circuit shutters.
b. Voltage transformer shutters.
c. Truck position selector mechanism (busbar earth/service/circuit earth).
d. Circuit-breaker open / close control switch.
e. Circuit-breaker local/remote control selector switch
Operational interlocking shall be provided to ensure the correct sequence of operation of the generator and
station transformer (if applicable) circuit switchgear. This shall be of the electrical type in compliance with a
Standard for safety circuits to be agreed with the Owner.
Full maintenance interlocking shall be provided to render the primary and tee-off connections safe for access
by personnel from all points of supply. The maintenance interlocking shall be of the mechanical interference
(trapped key) type employing a system of unique keys. The interlocking scheme shall include the substation
end of the power station circuits and be coordinated with the substation-interlocking scheme as necessary.
The drive circuits for the generator circuit switchgear shall be located in a dedicated control panel affording
physical separation from all other circuits. Each power supply shall have its own external lockable isolator.
system)
c. IP 55 - For outdoor and indoor expected water splash (Shelter)
7.[10.] SCHEDULE
1. Vendor shall submit the overall schedule showing detailed items of engineering work, manufacturing,
inspection and test, and estimated time arrival (ETA).
2. Partial shipment will be allowed if it is contributed to improve the schedule.
P a g e | 11
DOC. NO. : T22035-CD-000-ELE-REQ-005
Refer to Table 3.
APPENDIX- 1
LIST SCOPE OF WORK AND SUPPLY
FORM-1
(X : Required)
CONTRACTOR
NO. ITEM VENDOR VENDOR’s
/ PURCHASER
CONFIRMATION
P a g e | 12
DOC. NO. : T22035-CD-000-ELE-REQ-005
No t e s :
1. Vendor shall complete the information as final document
2. Supervise by vendor
P a g e | 13
DOC. NO. : T22035-CD-000-ELE-REQ-005
APPENDIX- 2
LIST SCOPE OF WORK AND SUPPLY
(This is example for Centrifugal Pump. It shall be established specifically for each equipment/material/services)
FORM-1
(X : Required)
CONTRACTOR
NO. ITEM VENDOR VENDOR’s
/ PURCHASER
CONFIRMATION
No t e s :
1. Vendor shall complete the information as final document
2. Supervise by vendor
APPENDIX- 2
TECHNICAL DEVIATION FORM
FORM-2
P a g e | 15
DOC. NO. : T22035-CD-000-ELE-REQ-005
APPENDIX- 3
PERFORMANCE TEST
a. Material certificate *R R R
P a g e | 16
DOC. NO. : T22035-CD-000-ELE-REQ-005
ABBREVIATION: