LOAD DISTRIBUTION SCHEDULE

Project / Building Name : SENIOR STAFF ACCOMODATION Main Contractor: ALBARQ NATIONAL GENERAL CONTRACTING
Add/Location : LV ROOM Electrical Contractor : OHM ELECTROMECHANICAL CONTRACTING
Distribution Board No. / Ref. MDB-01 Incoming Cable size / type: 7x1C 630mm2 XLPE/AWA/PVC
Fed from : TRANSFORMER-1 Main breaker type & rating : 1600A TP ACB (300-500mA ELP

Incomer MCCB/ Circuit Load per point (KW)


TOTAL TOTAL
CCT ref. ACB Fault
Cable Size mm2 Earth size mm2 DB/Load name CONNECTED DIVERSIFIED REMARKS
No. rating(A)T Duty kA R Y B (KW) (KW)
P

RYB1 300 50 4C 150mm2 XLPE/WA/PVC 1x1C 95mm2 ECC SMDB-G1 35.30 46.80 44.00 126.10 0.00
1600 A TP ACB (300-500mA)ELP

RYB2 300 50 4C 150mm2 XLPE/WA/PVC 1x1C 95mm2 ECC SMDB-G2 46.87 45.67 44.97 137.50 78.68
RYB3 400 50 4C 240mm2 XLPE/WA/PVC 1C 120mm2 ECC SMDB-KIT 70.10 60.20 64.40 194.70 146.82
RYB4 160 50 4C 70mm2 XLPE/WA/PVC 1C 35mm2 ECC SMDB--SER 27.41 22.01 25.41 74.83 50.88
RYB5 500 50 4C 300mm2 XLPE/WA/PVC 1C 150mm2 ECC SMDB-AC1 68.40 68.40 71.25 208.05 187.25
RYB6 500 50 4C 300mm2 XLPE/WA/PVC 1C 150mm2 ECC SMDB-AC2 72.38 70.39 70.39 213.16 191.84
RYB7 400 50 4C 240mm2 XLPE/WA/PVC 1C 120mm2 ECC 200 KVAR CAP. BANK
RYB8 300 50 FUTURE LOAD 63.57 63.57 63.57 137.00 123.30
RYB9 160 50 FUTURE LOAD 25.00 25.00 25.00 75.00 58.45
RYB10 100 50 SPARE
TOTAL CONNECTED LOAD PER PHASE(KW) 409.03 402.04 408.99 837.21
TOTAL CONNECTED LOAD PER (KW) 1220.05
TOTAL DIVERSIFIED LOAD (KW) 837.21
LOAD DISTRIBUTION SCHEDULE
Project / Building Name : SENIOR STAFF ACCOMODATION Main Contractor: ALBARQ NATIONAL GENERAL CONTRACTING
Add/Location : LV ROOM Electrical Contractor : OHM ELECTROMECHANICAL CONTRACTING
Distribution Board No. / Ref. MDB-02 Incoming Cable size / type: 7x1C 630mm2 XLPE/AWA/PVC
Fed from : TRANSFORMER-2 Main breaker type & rating : 1600A TP ACB (300-500mA ELP
MCCB/ Circuit Load per point (KW)
Incomer

TOTAL TOTAL
CCT ref. ACB Fault
Cable Size mm2 Earth size mm2 DB/Load name CONNECTED DIVERSIFIED REMARKS
No. rating(A)T Duty kA R Y B (KW) (KW)
P

RYB1 400 50 4C 240mm2 XLPE/WA/PVC 1C 120mm2 ECC SMDB-G3 67.95 64.95 63.20 196.10 117.15
1600A TP ACB (300-500mA)ELP

RYB2 300 50 4C 150mm2 XLPE/WA/PVC 1C 95mm2 ECC SMDB-G4 48.10 52.90 46.00 147.00 83.92
RYB3 500 50 4C 300mm2 XLPE/WA/PVC 1C 150mm2 ECC SMDB-AC3 78.08 76.09 76.09 230.26 207.23
RYB4 500 50 4C 300mm2 XLPE/WA/PVC 1C 150mm2 ECC SMDB-AC4 76.95 79.80 76.95 233.70 210.33
RYB5 225 50 4C 95mm2 XLPE/WA/PVC 1C 50mm2 ECC FIRE PUMP 25.00 25.00 25.00 75.00 60.00
RYB6 500 50 4C 300mm2 XLPE/WA/PVC 1C 150mm2 ECC 250KVAR CAP. BANK
RYB7 300 FUTURE LOAD 48.18 48.18 48.18 144.53 115.62
RYB8 200 FUTURE LOAD 30.00 30.00 30.00 90.00 54.98
RYB9 100 SPARE
RYB10 SPACE
TOTAL CONNECTED LOAD PER PHASE(KW) 374.26 376.92 365.42 849.24
TOTAL CONNECTED LOAD PER (KW) 1116.59
TOTAL DIVERSIFIED LOAD (KW) 849.24