Penawaran Yard Lippo

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Item Description Unit Q ty Unit Price Amount Remarks

A Preparation 准备 Set 1 8.640.000 8.640.000

B Reinforcement Concrete Slab Work 钢筋混凝土板工程 Set 1 751.839.929 751.839.929

Sub Total : 760.479.929


Roundown : 760.000.000
PPN 11% : 83.600.000
Grand Total : 843.600.000

Remark
Pay ment's Method:
1. Down payment 20% at contract signed
2. 35% when 50% progress work
2. 40% when 100% progress work
4. 5% retaintion for 3 months

数字 名稱 單位 數量 單價 複價 備註
Number Description Unit Quantity Unit price Amount Remarks
A Preparation 准备
1 Surveying and safety 测量与安全 lot 1 1.440.000 1.440.000
2 Worker mess 工人乱七八糟 lot 1 7.200.000 7.200.000

SubTotal 小计 8.640.000

B Reinforcement Concrete Slab Work 钢筋混凝土板工程


1 Form Work 表格工作 m1 1.170 43.200 50.544.000
2 Reinforcement Bar 钢筋 wiremesh M-8 single m2 3.900 91.619 357.315.929
3 Concrete Slab 混凝土楼板 K 300, t : 7cm m3 273 1.260.000 343.980.000

SubTotal 小计 751.839.929

Total 全部的 760.479.929

You might also like