Professional Documents
Culture Documents
Lecture 1
Lecture 1
Lecture 1
CONSTRUCTION (II)
1
GRADE DISTRIBUTION
7 , , 30%
12 , , 20%
Class Performance / Attendance 10 %
Final Exam 40 %
Total 100%
2
CONTENTS
(1) INTRODUCTION TO ERTH MOVING
EARTHMOVING PROCESS
EQUIPMENT SLECTION
PRODUCTION OF EARTHMOVING EQUIPENT
PRODUCTION = VOLUMN PER CYCLE* CYCLES PER
Hour
COSTT PER UNIT OF PRODUCTION = (EQUIPMENT
COST
PER HOUR/ EQUIPEMNT PRODUCTION PER
HOUR)
(2) SOIL VOLUMN CHANGE.
SWELL – SHRINKAGE –LOAD AND SHRINKAGE
FACTORS.
(3) SPOIL PILES AND SPOIL BANKS
3
SHOVELS (EXCAVATE LOOSE SOIL ABOVE TRACK LEVEL)
4
HOES (EXCAVATE LOOSE SOIL BELOW TRACK LEVEL)
5
DRAGLINE (EXCAVATE LOOSE SOIL)
6
CLAMSHELLS (EXCAVATE LOOSE SOIL )
7
LOADER (EXCAVAT LOOSE SOIL – MOVE WITH SOIL
LOADING TRUCKS)
8
DOZER (DOZING LOOSE SOIL-RIPPING HARD SOILS)
9
WHEEL TYP DOZER TRACK TYPE DOZER
10
11
SCREPER (EXCAVAT LOOSE SOIL +FILL FOR LONG
DISTANCE)
12
TRUCKS (TRANSPORTING SOIL )
13
14
(2) VOLUMETRIC MEASURE
1 cubic meter (CM) in 1.25 cubic meter 0.90 cubic meter (CM)
natural condition (CM) after digging after compaction
(in-place meter) , (Loose meter) , (compacted meter) ,
BCM LCM CCM
15
1 cubic meter
1.25 cubic meter 0.90 cubic meter
(CM) in natural
(CM) after digging (CM) after
condition
(Loose meter) , compaction
(in-place meter) ,
LCM (compacted meter)
BCM
, CCM
16
1 cubic meter (CM) of
Bank cubic meter
material as it lies in
natural state , BCM
1 (CM) of material in
the compacted state ,
Compacted cubic meter
also referred to as a net
in-place cubic meter,
CCM
17
18
19
Problem 1:
A soil weighs is 2,000 lb/cu yd (1187 kg/m3) loose and
2,500 1lb/cu yd (1483 kg/ m3) in- place. Find the swell
and load factor for the soil.
answer :
21
Problem 3:
answer :
.
B=( ) = 8.86 m
( )
. ( )
H=( ) = 2.09 m
22
Thank You for your attention