Professional Documents
Culture Documents
Temporary Support and Freezing of Bridge
Temporary Support and Freezing of Bridge
net/publication/355778930
CITATIONS READS
0 288
3 authors, including:
All content following this page was uploaded by V N Heggade on 30 October 2021.
ABSTRACT
In earlier days, the majority of superstructure of cantilever bridges used to be designed by
FRQVLGHULQJ ¿[LW\ DW VXSSRUW DFKLHYHG WKURXJK PRQROLWKLF FRQVWUXFWLRQ RI SLHU DQG GHFN DQG E\
SURYLGLQJ FHQWUDO KLQJH RU VXVSHQGHG VSDQ DW WKH WLS RI FDQWLOHYHU DUPV WR PDNH WKH VWUXFWXUH
GHWHUPLQDWH+RZHYHUGXHWRGLVWUHVVRIFHQWUDOKLQJHEHDULQJVRYHUDSHULRGRIWLPHDQGH[FHVVLYH
GHÀHFWLRQGXHWRFUHHSDWWKHFDQWLOHYHUWLSVREVHUYHGLQDOPRVWDOOEULGJHVEXLOWRQWKHWKHQVWDWH
of the art design philosophy, now-a-days most cantilever bridges are designed as continuous over
VXSSRUWV E\ SURYLGLQJ FHQWUDO EHDULQJV EHORZ WKH GHFN DW SLHU ORFDWLRQ WR PDNH WKH VWUXFWXUH
GHWHUPLQDWH7KLVHOLPLQDWHVWKHSUREOHPRIH[FHVVLYHGHÀHFWLRQDWFDQWLOHYHUWLSDQGDWWKHVDPH
time increases the service life of bridge. For the construction of such cantilever superstructure,
SUHFLVHGHVLJQRIFRQVWUXFWLRQV\VWHPVLVRIXWPRVWLPSRUWDQFH,QWKLVFRQWH[WWKHSDSHUGLVFXVVHV
WKHGHWDLOVRIWZRVXFKLPSRUWDQWFRQVWUXFWLRQV\VWHPVLHWHPSRUDU\VXSSRUWIRUFDQWLOHYHUGHFN
and temporary freezing arrangement for free bearing adopted during the construction of New
Brahmaputra Bridge at Guwahati, Assam.
7KH DGYDQFHPHQWV LQ WKH ¿HOG RI EULGJH HQJLQHHULQJ KDYH OHG WR LQFUHDVH LQ WKH VSDQ OHQJWK RI
cantilever arms. Due to increase in the span of cantilever arms, the dead load of the superstructure
also increases for which high capacity temporary support and freezing arrangements need to be
provided in comparison to the conventional system for smaller span cantilever arms. This paper
also presents the progressive advancements on the development of construction systems to cater to
the challenges thrown by construction of longer cantilever arms.
}
1
General Manager (Technical), E-mail: rakesh.mehta@gammonengineers.com Gammon Engineers &
2
Deputy Manager (Technical) Contractors (P) Ltd,
3
President (Engineering) Mumbai
Bridge will provide succor to people for North Brief Description of Project
Guwahati and connect north east India with The total length of the new Brahmaputra bridge
the rest of the country. The new Brahmaputra is 1493.584 m, consisting of 2 spans of 105 m, 2
Bridge is 1493.58 meters long and has 3.5 km spans of 150 m and 8 spans of 122.6948 m. The
of approach road. foundation for bridge is of well foundation type
having double D shape of size 16 m X 10 m.
Deck of the proposed bridge consists of single
cell PSC box girder of varying depth and deck
is cast by segmental cantilever construction
method. Top width of deck is 13.875 m and
bottom width is 8.075 m. The piers are of tapered
RCC wall with semi-circular end of size 14 m X
7.0 m at well cap level and size 12 m X 5 m at
bottom of pier cap.
Total length of Viaduct portion at Amingaon
side is 144 m and at Guwahati side is 108 m,
consisting of 6 spans of 24 m (3 span continuous)
at Amingaon side and 4 spans of 27 m (4 spans
continuous) at Guwahati side. The general
Fig.1 Site Layout arrangement of bridge is given in Fig. 2.
v) Type of Superstructure : Main Bridge Cast-in –situ segmental continuous Pre-stressed box girder
Constructed by Balanced cantilever method (Length = 1433.584 m) and
cast-in-situ pre-stressed box girder constructed by supporting arrangement
(Length = 60 m)
Viaduct Portion : Cast-in-situ Pre-stressed T- Girder (Length = 252 m)
vi) Bearing : Pot/PTFE Free bearing at P6 to P11 & P13 to P18, Pot/PTFE Fixed bearing at P12
vii) Seismic Transmission : 3 Nos. of 4 MN Capacity at each Pier Location except Fixed Pier P12
Unit (STU)
Expansion Joint : Modular strip seal type for movement of 800 mm at P6 & P18
Table 1. Design Data
The length of segment is of two types: 2.915 m Adopted Procedure for Casting of in-Situ
and 3.75 m. The summary of Cantilever span Segments for cantilever arm is as follows:-
arrangement for the main bridge is given in i) After the casting of pier cap, bearings and
Table 2. sand jacks (temporary supports) are placed
Table 2. Span Arrangement Summary over pier cap. The bearings are provided
with conventional freezing arrangement
Sr. Cantilever No. of No. of 5HPDUNV
and are locked in position Fig. 7a.
No. arm (m) segments on T-arms
each side ii) The pier head i.e. units 1a and 1b of total
9 m length are cast by providing brackets
1 75 22 4
from pier cap. After the pier head achieves
2 61.474 16 5 VXI¿FLHQW VWUHQJWK WKH FRUUHVSRQGLQJ
3 61.474- 16-14 2 Unbalanced cables are stressed. Temporary supports in
47.948 cantilever the form of cables are provided in the pier
head and pier cap which act as anchorage during casting of cantilever units Fig. 7b.
Fig. 7a Fig. 7b
Fig. 7a and 7b Casting of Pier Head and First Segment for Cantilever Arms
iii) The advanced freezing arrangement is now YLLL $IWHU WKH FDVWLQJ RI ¿IWK VHJPHQWV WKH
provided and the conventional freezing Shock Transmission Unit (STU) is placed
arrangement is released. in position.
iv) The next units 2a and 2b are also cast on the ix) On completion of casting of all segments,
same bracket arrangement from pier cap the CLC gantries are brought symmetrically
and the corresponding cables are stressed. towards the Center of pier and dismantled
v) The Cantilever construction gantries (CLC before casting of continuity unit.
gantry) are erected on segment nos. 2a and x) After casting of adjacent T-arms, the continuity
2b on either side of the pier. unit is cast by providing a suspended platform
vi) Using the CLC gantry, segments 3a and from the tip of the cantilever.
3b are cast. After the concrete achieves xi) The advanced freezing arrangement is
VXI¿FLHQW VWUHQJWK WKH FRUUHVSRQGLQJ released, the temporary support 19K15 strands
cables are stressed. are cut and the continuity cables are stressed.
vii) In this manner the entire cantilever span [LL *HQHUDODQG¿QLVKLQJLWHPVDUHFRPSOHWHG
is completed on either side of the pier 4. REQUIREMENT OF ENABLING
Photo-1. WORKS FOR CONSTRUCTION OF
CANTILEVER SPAN
For the New Brahmaputra Bridge, numerous
enabling systems were required, right from caissons
for substructure to form traveler for superstructure.
However, two of the most important construction
systems were the temporary support during
cantilever construction and freezing arrangement for
bearing. The temporary support is required to make
the structure stable or determinate during cantilever
construction and the freezing of bearing is required
to restrict the longitudinal and transverse movement
of free bearings i.e. to restrict all horizontal forces
developed either due to wind or seismic loads, or
due to stressing of the longitudinal cable during
Photo 1 Balanced Cantilever Construction cantilever construction.
Suitable development and precise design of these on temporary support in active direction was 250
construction systems is as important if not more ton as per the proposed construction sequence.
than permanent design of any cantilever bridge, For Jaigarh bridge 125 ton capacity sand jack was
large or small span. If any of the above two systems provided on each temporary support just below the
fail or do not work properly during construction, it web of box units. Temporary supports are square
is more disastrous than the failure of bridge due to RCC column of size 900 x 900 mm and it rests on
wrong design. projected part of well cap photo 2.
4.1. Temporary Support For Superstructure
Generally, now-a-days for continuous cantilever
EULGJHV EHDULQJV HLWKHU ¿[HG RU IUHH DUH SURYLGHG
at center of piers and this is the main support which
transfers all the vertical or horizontal forces to
substructure/foundation from superstructure. But
during construction, the bearing support acts as a
single support till the stich segments of individual
spans are cast. So, temporary supports on either side
of the bearings are required which provide stability
to the cantilever span during construction.
The temporary supports are in the form of either
sand jacks or stability cables, depending upon Photo 2 Temporary Support For Jaigarh Creek Bridge
instability reaction developed based on total self-
weight of cantilever arms and their construction
methodology/sequence of casting of segments
Fig. 8.
The sand jacks of required capacity are provided
HLWKHU GLUHFWO\ RQ SLHU FDS LI VXI¿FLHQW VSDFH LV
available) or above RCC/steel column which
is resting over well cap/pile cap or temporary
foundation.
In Brahmaputra Bridge, initial distance between that reaction on temporary support reduces. After
temporary supports on either side of bearing was increasing the pier cap width, it was possible to
proposed as 4.46 m considering maximum space provide the temporary supports above pier cap and
availability on pier cap. For that proposed 4.46 the distance between them increased from 4.46 m to
m distance between temporary support, reaction 7.310 m. The vertical forces in temporary support
coming on each side of temporary support was 6200 were recalculated in lieu of increased distance
ton considering all in-situ segment cast in single between supports and found out that load on each
pour, however this reaction further reduced to side support was 4250 ton considering in-situ box
4100 ton by considering segments cast in 3 stages. segment cast in single pour and 2600 ton considering
Such high reactions were coming as each segment segments to be cast in 3 stages. Typical casting
weight varies from 160 ton to 140 ton and form sequence for box segments is shown in Fig. 10.
traveler self-weight is 90 ton. Total self-weight of
one pair of cantilever arm is 7000 ton. To reduce
the vertical reaction in temporary support, it was
required to increase the distance between temporary
supports or construct another temporary support
in between cantilever arms. The construction of
another temporary support in between the cantilever
arms was ruled out as construction of any extra
foundation in Brahmaputra River for temporary
support is not cost effective as well as it increases
the construction period. Therefore only option was
to increase the center to center distance between
temporary support and these temporary supports Fig. 9 Change in Pier Cap Width
would be constructed either from well cap or outside
the well cap on temporary foundation as designed
pier cap width was only 6.2 m. Support from well
cap or outside well cap was not advisable as the
VLWHZDVIUHTXHQWHGHYHU\\HDUE\ÀDVKÀRRGVZLWK
YHU\KLJKFXUUHQWYHORFLW\DQGZLWKORWVRIÀRDWLQJ
GHEULV 7KH FXUUHQW YHORFLW\ GXULQJ ÀRRGV LV PRUH
than 5 m/sec. So with debris coming along with
high water current velocity, there is always a chance
to hit or damage the temporary support. Also if we
were going for temporary foundation for temporary
support from outside the well cap then construction Fig. 10 Segments Casting Sequence
of temporary foundation for vertical load of around
2000 ton in each support location required number The entire construction sequence is planned such
of piles and very large dia. pile either RCC/steel due WKDWWKHUHLVVXI¿FLHQWIDFWRURIVDIHW\IRUUHVWRULQJ
to very high water current velocity and scouring moment over the overturning moment. The
nature of bed. It was found that construction of following loads were considered in the calculation
temporary foundation from outside of well cap was of the forces on the temporary support:-
not viable due to time and cost consideration and i. Self-weight of the box girder (2.5% extra
at the same time dismantling those foundations was for dimensional imbalance for shore side
not possible. segments)
To overcome these problems, it was necessary to ii. Self-weight of the cantilever construction
increase the Center to Center distance between gantry = 90 ton.
temporary supports and so it was decided to increase iii. Wind load acting upwards on one cantilever
the pier cap width from 6.2 m to 8.55 m Fig. 9, so arm
Project Name Total Length Total Self C/C Reaction Temporary Support Details
of Cantilever Weight of Box distance on One
Arm Units for One between Temp. Type Dimension Total
Cantilever Temp. Support Quantities
Arm support (R1/R2)
Jaigarh Creek 64 m 1250 ton 9.0 m 250 ton RCC with 900 x 900 Concrete
Bridge (1-Stage 125 ton mm - 45 cum
Casting) Capacity HYSD Steel
Sand Jack – 4 ton
Balason Bridge 128 m 2800 ton 7m 600 ton Steel With Built- Structural
(2-Stage 325 ton up-1000 x Steel
Casting) Capacity 1000 mm – 42 ton
Sand Jack
Brahmaputra 148.5 m 7000 ton 7.31 m 2600 ton HT Strand 14 nos x 19 HT-Strands
Bridge (3- Stage K15 – 4.6 ton
Casting)
4.2 Bearing Freezing Arrangement restrict the movement in both direction Figs. 12 and
The next important construction system for cantilever 13 and Photo 47KHQRV¿[HGEHDULQJVSURYLGHG
construction of bridges is the freezing of bearings. at P12 location are for 3560 ton vertical load and 630
This freezing arrangement restricts the longitudinal ton horizontal load in longitudinal direction as well as
and transverse movement of free bearings during transverse direction, whereas at other pier locations,
cantilever construction. POT/PTFE free bearings are 2 nos. free bearings are provided for varying vertical
provided at Piers P6 to P11 and P13 to P18 location loads and 630 ton horizontal load in transverse
for the continuous cantilever span, which is free to direction. Bearing load details at each pier location for
move in longitudinal direction only and POT/PTFE bridge are given in Table 4 and the layout is given in
¿[HGEHDULQJVDUHSURYLGHGDW3LHU3ORFDWLRQWR Fig. 14.
Fig. 12 Free Guided Bearing (2089 x 2412 mm) Fig. 13 Fixed Bearing (1858 x 1454 mm)
Table 4 Bearing Loads and Movements
To avoid occurrence of a large amount of horizontal P13 to P17-10 locations), three numbers of STU’s
IRUFHLQVHLVPLFFRQGLWLRQDWWKHRQO\¿[HGEHDULQJ are provided having maximum capacity of 400 ton.
i.e. P12 location for 1.493 km long continuous span, The approx. weight of STU is approx. 3 ton and it is
Shock Transmission units (STU) are provided at all connected to the pier cap with 10 nos. 39.5 dia. high
free bearing pier locations. These STU’s are designed VWUHQJWKEROWVDQGFRQQHFWHGWRWKHVRI¿WRIEULGJH
to distribute the sudden loads due to seismic and deck with 12 nos. 36 dia. high strength bolts
braking etc. uniformly on all piers at the same time The general arrangement of STU is shown in Photo
allowing the movement for slowly induced loads and )LJ while the details of connection of STU
due to temperature, creep and shrinkage. units between pier cap and segments of cantilever
At every free pier location (i.e. At Piers P7 to P11 & arm is shown in Photo 6 and Fig. 16.
7DEOH/RDG&DOFXODWLRQIRU)UHH]LQJ$UUDQJHPHQW
The conventional freezing arrangement comprises In case of New Brahmaputra bridge, the arrangement
of the followings- had to resist the total desired horizontal force of
i. Steel built up beams (2 nos.) designed for the 300 ton 7DEOH before STU is activated. As the
horizontal force. force was quite large, the conventional freezing
ii. Packing either by wooden or steel. arrangement as described above could not be
designed and therefore, alternate arrangement had to
iii. High tension bolts connecting the two steel
be thought of to freeze the free bearing till the STU
built up beams.
becomes active. So the conventional arrangement
When the bearing tries to slide, it is arrested by was provided only to lock the bearing till the time
the built up beam which takes reaction from the the main advanced freezing arrangement was to
pedestal of the bearing through the packing. The be provided. The design horizontal force for the
entire system is held in position by the tie/tension conventional freezing arrangement was 160 ton
bolts. 7DEOH.
A special type of longitudinal restrainer was pier cap to allow rotation within the permissible
developed for P7 and P17 based on High friction limits of the bearing.
grip bolt mechanism. This longitudinal restrainer
was designed to resist the 300 ton horizontal forces
as mentioned in 7DEOH. The freezing arrangement
comprised of steel built up beam connected to the
VRI¿WRIWKHER[JLUGHUQHDUWKHIDFHRIWKHSLHUFDS
7KH EXLOW XS EHDP ZDV ¿[HG WR WKH VRI¿W RI ER[
girder by high friction grip bolts (Macalloy bar). An
HODVWRPHULF SDG ZDV SURYLGHG WR WKH ÀDQJH RI WKH
built up beam that would hit the face of the pier cap
thus transferring the horizontal force to the pier cap.
The arrangement was provided on both sides of the
pier cap Photo 8.
Since Pier head unit and pier cap for pier P7 seismic restrainers had not been proposed due to
DQG 3 ZHUH ¿UVW UHDG\ DV VXFK WKLV W\SH RI provision of STU. A gap of 1000 mm between the
ORQJLWXGLQDO UHVWUDLQHU ZDV SURYLGHG ¿UVWO\ two corbels was kept and this gap was packed with
for Piers P7 and P17. However, the formwork a steel built-up girder. The Gap of 1000 mm was
DUUDQJHPHQW EHFDPH GLI¿FXOW IRU WKH UHYLVHG provided as the maximum longitudinal movement of
shape of pier head and hence took more time. span is 800 mm so that after completion of the entire
Similarly, during installation of freezing units, bridge the corbels should not restrict the longitudinal
stressing of 48 Nos. of 4.2 m length Macalloy movement of expansion joint. A 50 mm elastomeric
tension bars at each pier location also increased pad was provided on the front face of built-up steel
the time cycle. At the same time the cost increased girder to take care of the impact of longitudinal
due to the cost of 48 nos of Macalloy bars of 4.2 horizontal force during construction. A 10 mm gap
m length i.e. 42 ton considering all pier locations. was also maintained between the elastomeric pad
So, overall the entire process led to increased and corbel to allow rotation within the permissible
time cycle and increased costs as compared to limits of the bearing. The elevation and plan view of
time cycle and costs considered in construction longitudinal restrainer is shown in Figs. 22 and 23.
schedule. The construction of this longitudinal restrainer did
So, it was necessary to modify the proposed QRWLQFXUDQ\VLJQL¿FDQWDGGLWLRQDOFRVWVRUGHOD\HG
longitudinal system provided at Piers P7 and P17 to the time cycle as compared to the earlier proposed
a seismic longitudinal restrainer type system at other longitudinal restrainer. The corbel of longitudinal
pier locations to save extra time and cost. This was restrainer is cast along with pier cap and pier head
done by providing the restrainer type corbel over XQLWVDWDOOSLHUORFDWLRQVH[FHSW¿[HGSLHU37KH
pier cap and another corbel from outside of web of details of revised longitudinal restrainer are given
pier head unit. In this bridge, permanent longitudinal in Photo-9.
pad was removed. Total quantities required in new proposed longitudinal restrainer is given in
earlier proposed longitudinal restrainer and Table-6.
Table 6 Details of Quantities for Longitudinal Restrainer for One Pier Location
For the new proposal, high quantity of reinforcement arrangement and freezing of bearing are very
was required in comparison to concrete because important undertakings for balanced cantilever
almost 45 % of the reinforcement quantity was for bridges where sliding bearings are proposed. For
the purpose of anchorage provided in the existing New Brahmaputra Bridge at Guwahati, as the
pier cap and pier head diaphragm as both the dead weight of superstructure was very large,
restrainers were corbel structures. new solutions had to be developed to cater for
the huge horizontal forces. The solutions also had
&21&/86,21
WR EH HFRQRPLFDO ZLWK PLQLPXP PRGL¿FDWLRQ
Progressive developments in the design of bridges to the existing structure and enabling simplicity
will have to be supported by equal advancements LQ H[HFXWLRQ 7KH ¿QDO SURSRVDO IRU ORFNLQJ RI
in the construction systems for the successful bearings scores better on both cost and effort
completion of the project. The temporary support parameters.
Photo 10 Completed Aerial View of the Bridge Photo 11 Connecting Jalukbari Flyover
The New Brahmaputra Bridge at Guwahati was 2. Dr. V. K. Raina, Avinash Y. Mahendrakar,
opened to public on 29.01.2017. The new bridge Amrendra N. Singh, “Philosophy of CAMBER-
has decreased congestion on the existing Straight &255(&7,21WR2EWDLQ&RUUHFW'HFN3UR¿OHLQ
Bridge and has improved connectivity across the Cantilever Construction…. Brahmaputra Bridge
Brahmaputra. With the completion of the Jalukbari at Guwahati, India”, ING-IABSE seminar Mysore
À\RYHUWKHHQWLUHDUHDKDVJRWDEHDXWLIXOPDNHRYHU 2014 on Elevated Transport Corridors. pp. 160-
169.
6. REFERENCES
91+HJJDGH³%HDULQJV WKHLU&RQ¿JXUDWLRQV 3. V N Heggade, A.N.Singh, “New Saraighat Bridge-
with in Bridge” System, The Bridge and Structural Vital Link to Gateway of North East”, CEMCON
Engineer, Vol 43/Number 4/December 2013, pp. 2017, ICI Pune centre, Pune 14 to 16 September
23-35. 2017, pp 93-106.