LIST OF ATTEMPTED QUESTIONS AND ANSWERS (Cases in Op Management - 260606)

You might also like

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

LIST OF ATTEMPTED QUESTIONS AND ANSWERS (cases in op management - 260606)

Multiple Choice Multiple Answer


Question This Question refers to the case of 'Hansa Tractomotive Ltd.' : After completion of
manufacturing, Jay Jee took following actions :-
Correct Answer Dispatched the consignment by Express Roadlines by truck ,
Raised the Hundi for the invoiced amount ,
Did not send the consignment by Hansa's designated carrier

Multiple Choice Single Answer


Question This Question refers to the case of 'Universal Fasteners Ltd.' : During the meeting with
G.M (Mr. Kaul) Store Keeper Mr. Bapat informed that purchases were made from :-
Correct Answer Several sources

Multiple Choice Single Answer


Question This question refers to case on 'Uma Tools Pvt Ltd (UTPL)' : One of the following is not a
variable overhead:-
Correct Answer Space

True/False
Question This Question refers to 'Uday Electroplating Shop' : As per cost figures collected,
Expected volume of work on special equipment next year is 10,000 Nos.
Correct Answer True

Multiple Choice Single Answer


Question This Question refers to the case of Narmada Electricals Ltd.: In the existing method, the
scarp generated in processes like machining was stored in :-
Correct Answer Scrap yard

Match The Following


Question Correct Answer Your Answer
Anonymous letter received by M.D. Need to justify Need to justify
This question refers to the case of Seen in top hotels with suppliers No material facts to support the
'Northern Machinery Ltd.' : Senior arguments
buyers
Reason for failure to convince the No material facts to support the No confidence in Material manager
Board of Directors arguments and Senior buyers
Lot of items on the agenda Need to be concise and to the point Need to be concise and to the point
Multiple Choice Multiple Answer
Question This Question refers to the case of 'Divgi Metalwares Private Limited' : The new items
contracted by the company are handled by the development department for :-
Correct Answer Submission of samples ,
Manufacture of one or two production lots ,
Transfer to manufacturing department for regular production,after successful development

Multiple Choice Multiple Answer


Question This Question refers to the case of 'Classic Engineering Components Ltd.' : The company
has well established machine shop having more than 150 machines and :-
Correct Answer A heat treatment shop , Metrology section , Packing section
Multiple Choice Single Answer
Question This Question refers to the case of 'The Gujrat Engineering company Limited' : The
company also executes :-
Correct Answer Rush orders

Select The Blank


Question This Question refers to 'Uday Electroplating Shop' :The owner finds it ________ to get part
time employees when there is heavy work load.
Correct Answer Difficult
LIST OF ATTEMPTED QUESTIONS AND ANSWERS
(CASES OF OPERATIONS MANAGEMENT-1)
Multiple Choice Multiple Answer
Question This question refer to the case on "Allied Industries Pvt Ltd" : Following are cost elements
of make indicator :-
Correct Answer Transport cost , Tooling cost , Indirect Employee cost

Your Answer Transport cost , Tooling cost , Indirect Employee cost , Power cost

True/False
Question This Question refers to the case of 'Classic Engineering Components Ltd.' : Mr. Sen was
informed by Mr. Ravikant, Materials Manager that counting is not necessary at every stage
as they count at the initial stage and since their workers and supervisors are experienced,
they can easily identify the components at each stage of production.
Correct Answer True

True/False
Question This question refers to case on 'Weldtech India Pvt Ltd (WIPL)' : Project duration can
always be reduced by deploying additional recourses.
Correct Answer False

LIST OF ATTEMPTED QUESTIONS AND ANSWERS (cases of operation mgt -2)


True/False
Question This Question refers to the case of 'Divgi Metalwares Private Limited' : The order has been
finalized from a leading engineering firm.
Correct Answer False
True/False
Question This Question refers to the case of 'Autogears Private Limited' : It takes 0.2 minutes to
measure dimensions and set aside gear into the trolley.
Correct Answer True

Multiple Choice Single Answer


Question This Question refers to the case of 'Eagle Machine Company' : The President demands that in
the remaining quarter the firm should :-
Correct Answer Break even

Multiple Choice Multiple Answer


Question This Question refers to the case of 'Narmada Electricals Ltd.' : Production or Quality
department decide when these become surplus/obsolete :-
Correct Answer Part , Component , Item

Your Answer Part , Component , Item , Material

Multiple Choice Multiple Answer


Question This question refers to case on 'Uma Tools Pvt Ltd (UTPL)' : While making Make or Buy
decisions, Buy indicator includes following costs :-
Correct Answer Raw material cost , Purchase cost , Fixed overhead cost

Your Answer Variable overhead cost , Purchase cost , Fixed overhead cost

Multiple Choice Multiple Answer


Question This question refer to the case on "Allied Industries Pvt Ltd" : Following are cost elements of
make indicator :-
Correct Answer Transport cost , Tooling cost , Indirect Employee cost
Your Answer Transport cost , Tooling cost , Indirect Employee cost , Power cost

Multiple Choice Multiple Answer


Question This Question refers to the case of 'The Gujrat Engineering company Limited' : The forged
cylinder ordered on new vendor :-
Correct Answer Was received on schedule ,
Was priced 15 % lower than the price of the previous supplier ,
Had missed out carrying out some machining operations
Your Answer Had missed out carrying out some machining operations , Was of sub standard quality

Multiple Choice Multiple Answer


Question This Question refers to the case of 'Divgi Metalwares Private Limited' : The new items
contracted by the company are handled by the development department for :-
Correct Answer Submission of samples ,
Manufacture of one or two production lots ,
Transfer to manufacturing department for regular production, after successful development
Your Answer Transfer to sales department for sales, after successful development

Multiple Choice Multiple Answer


Question This Question refers to the case 'Indus Foundries Ltd.' :Following items are readily available at
all the three locations :-
Correct Answer Raw materials , Scrap , Foundry chemicals