PROCEDURE FOR TESTING
SCP - JO CONTINUOUS EMISSION 1 of 6
MONITORING SYSTEM (CEMS)
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI038
PROCEDURE FOR TESTING Rev. No : 00
CONTINUOUS EMISSION MONITORING 2 of 6
SYSTEM (CEMS)
DOCUMENT NO : P-T3109-EI038
- SDCC : Original
- CNEEC : Copy
- All Dept. : Copy
TABLE OF CONTENT
NO DESCRIPTION PAGES
1 PURPOSE 3
2 REFERENCE DOCUMENT 3
3 INSTRUMENT TO BE USED 3
4 SAFETY PRECAUTION 3
5 PREPARATION TO COMISSIONING 4
6 PROCESS OF COMMISSIONING 4
7. ATTACHMENT 5
Attachment HSE Aspects Identification, Risk Assessment
6
and Risk Control
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI038
PROCEDURE FOR TESTING Rev. No : 00
CONTINUOUS EMISSION MONITORING 4 of 6
SYSTEM (CEMS)
1. PURPOSE
2. REFERENCE DOCUMENT
3. INSTRUMENT TO BE USED
1.1 Measuring components gases (H2O, O2, CO, CO2, SO2, NO, NOX)
1.2 Sample gas cooler
1.3 NOX converter
1.4 “THERMOR 3K” for gas filling monitoring
1.5 Screwdriver set
1.6 Multi meter
4. SAFETY PRECAUTION
o To protect the internal gas path, the gas connections are closed with
stoppers. Please DO NOT remove these stoppers until connecting the
gas lines.
o Electric contacts that could touch during work should not contain current
or should be protected against physical contact. When opening
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI038
PROCEDURE FOR TESTING Rev. No : 00
CONTINUOUS EMISSION MONITORING 5 of 6
SYSTEM (CEMS)
5. PREPARATION TO COMMISSIONING
o Prior to applying the energy supply all cable connections for the external
and internal connections must be checked for tight fit
o Connect the device to the mains; compare the main voltages with the
specifications given on the rating plate before commissioning.
6. PROCESS OF COMMISSIONING
6.1 Make sure that the S700 analyzer is set up for mains voltage
6.2 Make sure that the sample gas conditioning system is operationally
ready.
6.3 Switch on the power switch. When the S700 has been switched on
the microprocessor performs an automatic self-test procedure.
6.4 If no fault is detected, the OK will appear at the end of line, thereafter
the display will change to the measuring display.
6.5 Wait for the warm-up time to pass. Wait until the function LED is
green.
SCP - JO INDRAMAYU SPP PROJECT DOC. No:
P-T3109-EI038
PROCEDURE FOR TESTING Rev. No : 00
CONTINUOUS EMISSION MONITORING 6 of 6
SYSTEM (CEMS)
6.6 Then wait another 10 minutes for the internal temperature to stabilize.
1. Calibration
a. Automatic Calibration
b. Manual Calibration
7. ATTACHMENT