COMPANY : PT TRUBA JURONG ENGINEERING

CLIENT : CHENGDA CORPORATION OF CHINA


PROJECT : CILACAP 2 x 300 MW CFSPP
MAT'L. NAME : DAERATOR
LOCATION : CILACAP CENTRAL JAVA
DATE OF ERECTION :

PLAN AND CHECKLIST FOR LIFTING WORK

NO DESCRIPTION MAIN CRANE TAILING CRANE

I. CRANE TYPE AND MODEL DEMAG CC2000


CAP.300 TON
II. ERECTION LOAD
1. Erection Weig 75.60 Ton
2. Weight of Shac 2,00 Ton
3. Weight of Hoo 3.00 Ton
4. Weight of Spr - Ton
TOTAL LOAD 80.60 Ton

III. CRANE DATAS


1. Crane Capacit 300.00 Ton
2. Crane Conditi 100.00 %
3. Main Boom + 30M +30M
4. Load line reeving 9.00 Meter
5 . Super lift co 150.00 Ton
6. Working Radi 34.00 Meter
7. Lifting Capacit 97.00 Ton

IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.20


Total Load
V. LIFTING DEVICE
1. Sling Wire Size 2.25" x 15 M
2. Sling Quantity 6.00 PCs
3. Max. Breaking 4 x 250 Ton
4. Sling Wire Ar Four leg basket hitch
5. Sling Wire ( 4 x 50 Ton
6. Shackle ( Saf 4 x 35 Ton
7. Spreader / Li - Ton
8. Chain Block ( - Ton

VI. METHODE OF COMMUNICATION TO BE USED Radio Communication

VII. GROUND CONDITION Level

VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION NIL

IX. SETTING ELEVATION OF EQUIPMENT GL. + 25.000

PREPARED BY, VERIVY BY, APPROVED BY,

Rigging Section Safety Section


COMPANY : PT TRUBA JAYA ENGINEERING
CLIENT : CNEEC OF CHINA
PROJECT : INDRAMAYU 3 x 330 MW CFSPP
MAT'L. NAME : MAIN GIRDER K4 (54 TON)
LOCATION : INDRAMAYU, WEST JAVA
DATE OF ERECTION : 10-Sep-08

PLAN AND CHECKLIST FOR LIFTING WORK

NO DESCRIPTION MAIN CRANE

I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300


CAP.50 TON CAP.300 TON
II. ERECTION LOAD
1. Erection Weight 28.70 Ton 25.35 Ton
2. Weight of Shackle 1.00 Ton 1.00 Ton
3. Weight of Hook - Ton 2.20 Ton
4. Weight of Sprea - Ton - Ton

TOTAL LOAD 29.70 Ton 28.55 Ton

III. CRANE DATAS


1. Crane Capacity 50 Ton 300 Ton
2. Crane Condition 100 % 100 %
3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M
4. Load line reeving 6.00 Line 4.00 Line
5 . Super lift coun - Ton - Ton
6. Working Radius 20.34 Meter 26.00 Meter
7. Lifting Capacity 50.00 Ton 36.20 Ton

IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.684 1.268


Total Load SF > 1.2 OK SF > 1.2 OK
V. LIFTING DEVICE
1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M
2. Sling Quantity t 2.00 PCs 2.00 PCs
3. Max. Breaking Fo 2 x 190 Ton 2 x 190 Ton
4. Sling Wire Arran One leg bridle hitch One leg bridle hitch
5. Sling Wire ( Saf 2 x 32 Ton 2 x 32 Ton
6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton
7. Spreader / Lifti - Ton - Ton
8. Chain Block ( S - Ton - Ton

VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication

VII. GROUND CONDITION Level Level

VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -

IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M

PREPARED BY, CHECKED BY, APPROVED BY,

Rigging Engineer Area Manager Site Manager


COMPANY : PT TRUBA JAYA ENGINEERING
CLIENT : CNEEC OF CHINA
PROJECT : INDRAMAYU 3 x 330 MW CFSPP
MAT'L. NAME : MAIN GIRDER K3 (47.4 TON)
LOCATION : INDRAMAYU, WEST JAVA
DATE OF ERECTION : 10-Sep-08

PLAN AND CHECKLIST FOR LIFTING WORK

NO DESCRIPTION MAIN CRANE

I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300


CAP.50 TON CAP.300 TON
II. ERECTION LOAD
1. Erection Weight 24.40 Ton 23.00 Ton
2. Weight of Shackle 1.00 Ton 1.00 Ton
3. Weight of Hook - Ton 2.20 Ton
4. Weight of Sprea - Ton - Ton

TOTAL LOAD 25.40 Ton 26.20 Ton

III. CRANE DATAS


1. Crane Capacity 50 Ton 300 Ton
2. Crane Condition 100 % 100 %
3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M
4. Load line reeving 6.00 Line 4.00 Line
5 . Super lift coun - Ton - Ton
6. Working Radius 23.35 Meter 26.00 Meter
7. Lifting Capacity 38.30 Ton 36.20 Ton

IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.508 1.382


Total Load SF > 1.2 OK SF > 1.2 OK
V. LIFTING DEVICE
1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M
2. Sling Quantity t 1.00 PCs 2.00 PCs
3. Max. Breaking Fo 1 x 190 Ton 2 x 190 Ton
4. Sling Wire Arran One leg bridle hitch One leg bridle hitch
5. Sling Wire ( Saf 1 x 32 Ton 2 x 32 Ton
6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton
7. Spreader / Lifti - Ton - Ton
8. Chain Block ( S - Ton - Ton

VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication

VII. GROUND CONDITION Level Level

VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -

IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M

PREPARED BY, CHECKED BY, APPROVED BY,

Rigging Engineer Area Manager Site Manager


COMPANY : PT TRUBA JAYA ENGINEERING
CLIENT : CNEEC OF CHINA
PROJECT : INDRAMAYU 3 x 330 MW CFSPP
MAT'L. NAME : MAIN GIRDER K2 ( 32 TON)
LOCATION : INDRAMAYU, WEST JAVA
DATE OF ERECTION : 10-Sep-08

PLAN AND CHECKLIST FOR LIFTING WORK

NO DESCRIPTION MAIN CRANE

I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300


CAP.50 TON CAP.300 TON
II. ERECTION LOAD
1. Erection Weight 17.40 Ton 14.60 Ton
2. Weight of Shackle 1.00 Ton 1.00 Ton
3. Weight of Hook - Ton 2.20 Ton
4. Weight of Sprea - Ton - Ton

TOTAL LOAD 18.40 Ton 17.80 Ton

III. CRANE DATAS


1. Crane Capacity 50 Ton 300 Ton
2. Crane Condition 100 % 100 %
3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M
4. Load line reeving 6.00 Line 4.00 Line
5 . Super lift coun - Ton - Ton
6. Working Radius 25.44 Meter 26.00 Meter
7. Lifting Capacity 29.73 Ton 36.20 Ton

IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.616 2.034


Total Load SF > 1.2 OK SF > 1.2 OK
V. LIFTING DEVICE
1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M
2. Sling Quantity t 1.00 PCs 2.00 PCs
3. Max. Breaking Fo 1 x 190 Ton 2 x 190 Ton
4. Sling Wire Arran One leg bridle hitch One leg bridle hitch
5. Sling Wire ( Saf 1 x 32 Ton 2 x 32 Ton
6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton
7. Spreader / Lifti - Ton - Ton
8. Chain Block ( S - Ton - Ton

VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication

VII. GROUND CONDITION Level Level

VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -

IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M

PREPARED BY, CHECKED BY, APPROVED BY,


Rigging Engineer Area Manager Site Manager