PT Truba Juring Engineering is preparing to lift a 75.6 ton daerator at the Cilacap 2 x 300 MW CFSPP project in Cilacap, Central Java for client Chengda Corporation of China. A Demag CC2000 crane with a 300 ton capacity will be used. Safety checks show the crane's lifting capacity of 97 tons with a safety factor of 1.2 provides adequate capacity for the 80.6 ton total lift weight including the daerator, shackles and hooks. Rigging will use 6 slings each rated at 250 tons attached in a four leg basket hitch configuration. Radio communication will be used to coordinate the lift.
PT Truba Juring Engineering is preparing to lift a 75.6 ton daerator at the Cilacap 2 x 300 MW CFSPP project in Cilacap, Central Java for client Chengda Corporation of China. A Demag CC2000 crane with a 300 ton capacity will be used. Safety checks show the crane's lifting capacity of 97 tons with a safety factor of 1.2 provides adequate capacity for the 80.6 ton total lift weight including the daerator, shackles and hooks. Rigging will use 6 slings each rated at 250 tons attached in a four leg basket hitch configuration. Radio communication will be used to coordinate the lift.
PT Truba Juring Engineering is preparing to lift a 75.6 ton daerator at the Cilacap 2 x 300 MW CFSPP project in Cilacap, Central Java for client Chengda Corporation of China. A Demag CC2000 crane with a 300 ton capacity will be used. Safety checks show the crane's lifting capacity of 97 tons with a safety factor of 1.2 provides adequate capacity for the 80.6 ton total lift weight including the daerator, shackles and hooks. Rigging will use 6 slings each rated at 250 tons attached in a four leg basket hitch configuration. Radio communication will be used to coordinate the lift.
PROJECT : CILACAP 2 x 300 MW CFSPP MAT'L. NAME : DAERATOR LOCATION : CILACAP CENTRAL JAVA DATE OF ERECTION :
PLAN AND CHECKLIST FOR LIFTING WORK
NO DESCRIPTION MAIN CRANE TAILING CRANE
I. CRANE TYPE AND MODEL DEMAG CC2000
CAP.300 TON II. ERECTION LOAD 1. Erection Weig 75.60 Ton 2. Weight of Shac 2,00 Ton 3. Weight of Hoo 3.00 Ton 4. Weight of Spr - Ton TOTAL LOAD 80.60 Ton
III. CRANE DATAS
1. Crane Capacit 300.00 Ton 2. Crane Conditi 100.00 % 3. Main Boom + 30M +30M 4. Load line reeving 9.00 Meter 5 . Super lift co 150.00 Ton 6. Working Radi 34.00 Meter 7. Lifting Capacit 97.00 Ton
IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.20
Total Load V. LIFTING DEVICE 1. Sling Wire Size 2.25" x 15 M 2. Sling Quantity 6.00 PCs 3. Max. Breaking 4 x 250 Ton 4. Sling Wire Ar Four leg basket hitch 5. Sling Wire ( 4 x 50 Ton 6. Shackle ( Saf 4 x 35 Ton 7. Spreader / Li - Ton 8. Chain Block ( - Ton
VI. METHODE OF COMMUNICATION TO BE USED Radio Communication
VII. GROUND CONDITION Level
VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION NIL
IX. SETTING ELEVATION OF EQUIPMENT GL. + 25.000
PREPARED BY, VERIVY BY, APPROVED BY,
Rigging Section Safety Section
COMPANY : PT TRUBA JAYA ENGINEERING CLIENT : CNEEC OF CHINA PROJECT : INDRAMAYU 3 x 330 MW CFSPP MAT'L. NAME : MAIN GIRDER K4 (54 TON) LOCATION : INDRAMAYU, WEST JAVA DATE OF ERECTION : 10-Sep-08
PLAN AND CHECKLIST FOR LIFTING WORK
NO DESCRIPTION MAIN CRANE
I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300
CAP.50 TON CAP.300 TON II. ERECTION LOAD 1. Erection Weight 28.70 Ton 25.35 Ton 2. Weight of Shackle 1.00 Ton 1.00 Ton 3. Weight of Hook - Ton 2.20 Ton 4. Weight of Sprea - Ton - Ton
TOTAL LOAD 29.70 Ton 28.55 Ton
III. CRANE DATAS
1. Crane Capacity 50 Ton 300 Ton 2. Crane Condition 100 % 100 % 3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M 4. Load line reeving 6.00 Line 4.00 Line 5 . Super lift coun - Ton - Ton 6. Working Radius 20.34 Meter 26.00 Meter 7. Lifting Capacity 50.00 Ton 36.20 Ton
IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.684 1.268
Total Load SF > 1.2 OK SF > 1.2 OK V. LIFTING DEVICE 1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M 2. Sling Quantity t 2.00 PCs 2.00 PCs 3. Max. Breaking Fo 2 x 190 Ton 2 x 190 Ton 4. Sling Wire Arran One leg bridle hitch One leg bridle hitch 5. Sling Wire ( Saf 2 x 32 Ton 2 x 32 Ton 6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton 7. Spreader / Lifti - Ton - Ton 8. Chain Block ( S - Ton - Ton
VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication
VII. GROUND CONDITION Level Level
VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -
IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M
PREPARED BY, CHECKED BY, APPROVED BY,
Rigging Engineer Area Manager Site Manager
COMPANY : PT TRUBA JAYA ENGINEERING CLIENT : CNEEC OF CHINA PROJECT : INDRAMAYU 3 x 330 MW CFSPP MAT'L. NAME : MAIN GIRDER K3 (47.4 TON) LOCATION : INDRAMAYU, WEST JAVA DATE OF ERECTION : 10-Sep-08
PLAN AND CHECKLIST FOR LIFTING WORK
NO DESCRIPTION MAIN CRANE
I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300
CAP.50 TON CAP.300 TON II. ERECTION LOAD 1. Erection Weight 24.40 Ton 23.00 Ton 2. Weight of Shackle 1.00 Ton 1.00 Ton 3. Weight of Hook - Ton 2.20 Ton 4. Weight of Sprea - Ton - Ton
TOTAL LOAD 25.40 Ton 26.20 Ton
III. CRANE DATAS
1. Crane Capacity 50 Ton 300 Ton 2. Crane Condition 100 % 100 % 3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M 4. Load line reeving 6.00 Line 4.00 Line 5 . Super lift coun - Ton - Ton 6. Working Radius 23.35 Meter 26.00 Meter 7. Lifting Capacity 38.30 Ton 36.20 Ton
IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.508 1.382
Total Load SF > 1.2 OK SF > 1.2 OK V. LIFTING DEVICE 1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M 2. Sling Quantity t 1.00 PCs 2.00 PCs 3. Max. Breaking Fo 1 x 190 Ton 2 x 190 Ton 4. Sling Wire Arran One leg bridle hitch One leg bridle hitch 5. Sling Wire ( Saf 1 x 32 Ton 2 x 32 Ton 6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton 7. Spreader / Lifti - Ton - Ton 8. Chain Block ( S - Ton - Ton
VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication
VII. GROUND CONDITION Level Level
VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -
IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M
PREPARED BY, CHECKED BY, APPROVED BY,
Rigging Engineer Area Manager Site Manager
COMPANY : PT TRUBA JAYA ENGINEERING CLIENT : CNEEC OF CHINA PROJECT : INDRAMAYU 3 x 330 MW CFSPP MAT'L. NAME : MAIN GIRDER K2 ( 32 TON) LOCATION : INDRAMAYU, WEST JAVA DATE OF ERECTION : 10-Sep-08
PLAN AND CHECKLIST FOR LIFTING WORK
NO DESCRIPTION MAIN CRANE
I. CRANE TYPE AND MODEL SCM M900 KOBELCO 7300
CAP.50 TON CAP.300 TON II. ERECTION LOAD 1. Erection Weight 17.40 Ton 14.60 Ton 2. Weight of Shackle 1.00 Ton 1.00 Ton 3. Weight of Hook - Ton 2.20 Ton 4. Weight of Sprea - Ton - Ton
TOTAL LOAD 18.40 Ton 17.80 Ton
III. CRANE DATAS
1. Crane Capacity 50 Ton 300 Ton 2. Crane Condition 100 % 100 % 3. Existing Boom + L 90.8M+ 60M 60.9M+ 39.6M 4. Load line reeving 6.00 Line 4.00 Line 5 . Super lift coun - Ton - Ton 6. Working Radius 25.44 Meter 26.00 Meter 7. Lifting Capacity 29.73 Ton 36.20 Ton
IV. SAFETY FACTOR ( Lift. Cap. X Crane Condition ) 1.616 2.034
Total Load SF > 1.2 OK SF > 1.2 OK V. LIFTING DEVICE 1. Sling Wire Size ( 2.0" x 4 M 2.0" x 4 M 2. Sling Quantity t 1.00 PCs 2.00 PCs 3. Max. Breaking Fo 1 x 190 Ton 2 x 190 Ton 4. Sling Wire Arran One leg bridle hitch One leg bridle hitch 5. Sling Wire ( Saf 1 x 32 Ton 2 x 32 Ton 6. Shackle ( Safe 1 X 35 Ton 1 X 35 Ton 7. Spreader / Lifti - Ton - Ton 8. Chain Block ( S - Ton - Ton
VI. METHODE OF COMMUNICATION TO BE USED Radio Comunication Radio Comunication
VII. GROUND CONDITION Level Level
VIII. OVER HEAD OR UNDER GROUND OBSTRUCTION - -
IX. SETTING ELEVATION OF EQUIPMENT GL. +74.6 M GL. +74.6 M