DOCUMENT NO : P-T3109-EI-012
- SDCC : Original
- CNEEC : Copy
- All Dept. : Copy
TABLE OF CONTENT
NO DESCRIPTION PAGES
1 TITLE 3
2 SCOPE 3
3 OBJECTIVE 3
4 REFERENCE 3
DOCUMENT NO. :
P-T3109-EI-012
CONSTRUCTION PROCEDURE FOR ISSUED DATE :
IMPULSE TUBE INSTALLATION WORKS 21-02-2009
5 RESPONSIBILITY 3
6 WORK PROCEDURE 3
6.1 GENERAL 3
6.4 MATERIAL 4
1. TITLE
2. SCOPE
3. OBJECTIVE
DOCUMENT NO. :
P-T3109-EI-012
CONSTRUCTION PROCEDURE FOR ISSUED DATE :
IMPULSE TUBE INSTALLATION WORKS 21-02-2009
This is to assure that the requirements of Impulse Tube works are meets the
codes requirements and contract specifications. To make sure, the works
are carried out in acceptable workmanship and follow the requirements in
the quality manual.
4. REFERENCE
5. RESPONSIBILITY
5.1 The Instrument Engineer at site shall be responsible for the planning
scheduling and coordination, record and monitor progress of
instrument works. To guide the supervisors in the field in terms of
engineering and technical problems.
6. WORK PROCEDURE
6.1 GENERAL
6.4 MATERIAL
Each Tube or items of equipment to be installed shall be Inspected to
check that it's data agrees with the Specification
2. Pipes or tubes installed, but not connected, will have the ends
closed in an air approved method to prevent the entry of any
foreign material.
12. Multi-core tubing will not be bent to radi less than the
manufacturers recommendation.
DOCUMENT NO. :
P-T3109-EI-012
CONSTRUCTION PROCEDURE FOR ISSUED DATE :
IMPULSE TUBE INSTALLATION WORKS 21-02-2009
13. Special care will be taken when multi core tubing is being
installed in low ambient temperature.
14. All impulse piping will in general be run with a slope of not
more than 1.2 except where otherwise specified. The slope of
the impulse pipe work shall be down from the tapping point for
liquids, steam and condensable, and up from the tapping for
gas service, unless special provisions are made for venting
and draining.
15. Ensure that the correct sitting of vents and drains are at the
highest or lowest points of the piping run.
Attachment 1
Attachment 2
Attachment 3
Attachment 4
Attachment 5
METHOD ‘D’