DAILY Progress Report Dated:- 22-03-2024

Name of Work:- DEVELOPMENT OF INTERNATIONAL AIRPORT HISAR – EXTENSION OF EXISTING


RUNWAY AND TAXIWAYS
Workers engaged by Contractor :- KCC Buildcon Pvt. Ltd.
Skilled (In Daily Basis) Unskilled (In Daily Basis)
Category No. Category No.
Concretes 0 Mate 0
Steel work labour 0 Bhisty 0
Mason 0 Mazdur ( Man ) 0
Plant Maintenance 3 Mazdur ( Woman ) 0
Diesel Distributer 2 Mazdur ( Boy ) 0
Detail of Material received at Site last day (in Stock):-
Materials Qty. (Tonne) Materials Quantity (Tonne)
40 MM 0.00 Stone Dust 0
25 MM 0.00 GSB 0
20 MM 0.00 Bitumen 0
10 MM 0.00 WMM 0
Details of Plant equipment and transport machineries working on site.
Machinery Name Breakdown & Machinery
Qty. Maintenance etc. Name Qty. Breakdown & Maintenance etc.

Compactor 3 1 WMM Plant 1


Tipper 10 2 RMC Plant 2
JCB 1 Utility 6
Loader 1 2 PTR 2 1
Excavator 0 1 Grader 0 1
Water Tanker 1 B Sprayer 2
Tractor 1 HMP 1
Sensor Paver 1 TANDAM 2 1
Brief particulars of work in progress
Location Side L(m) W(m) D(m) Qty.(Cum) Remark
A. Excavation of Soil

B. Laying of Soil

C. Soil Stablisation

D. Laying of GSB

E. Laying of WMM

F. Laying of DBM

G. Working of Concrete

H. Laying of DAC

I. Laying of SDAC
0+400 to 0+620 220.00 5.75 0.05 63.25 Laying Of SDAC Layer at PTT to old apron Road
J. Laying of PQC

K. Level Recording

Other Actvities :-
A. Pqc pannel dummy cutting on apron & curing.
B.:- Lab testing reports and working activities pics (GPS Map Camera) send in real time.