Construction Of Isolation Bay,Vehicular lane ,Storm Water Open Monsoon Drain,Cargo Apron With Link Taxi and Basic

Strip at Maharaja Agarsen Airport

Contractor : Client:- PWD B&R (BR) Hisar,


Authority's Engineer: Executive Engineer, Provincial Division No-III, PWD B&R, Hisar
S.S BUILDERS Haryana

SITE WORK INFORMATION REPORTS- HISAR AIRPORT


Date of Submission:- 01-02-2024 Date of Inspection:- 02-02-2024
Location (RD) Length Depth
S. N SIDE Width (m) Qty. (cum) Description of work Status Remark
From To (Towards) (m) (m)
1 1+320 1+470 RHS 150.00 70.00 0.20 2100.00 Soil Stabilization At Basic Strip Area (8.30)
2 0+660 0+700 LHS 30.00 1.30 0.89 34.71 Excavation of Soil For Monsoon Drain Offset 125 from Runway Center
3 2+370 2+410 RHS 40.00 70.00 0.700 1960.00 Excavation of Soil at basic Strip
4 11.5 WMM Top Level Recording ,FDD & surface regularity test at Isolation bay

Summary of Projected Qty. (Cum)


S. N Item Projected Qty. Executed Qty. RFI Qty. Bal Qty. Remarks
1 C&G 110655 110655 SQM 0.00
2 Excavation For Stabilization 292263 207187 CUM 1,960 85076.00
3 Excavation For Drain 50868 483 CUM 35 50385.29
4 Soil Stabilization 292263 70383 CUM 1400 221880.00
5 GSB 22206 14082 CUM 2088,5 8124.00
6 WMM 18,504 14496 CUM 1392 4008.00
7 DLC 33416.00 765.00 CUM 0.00 32651.00

As per the notification issued from time to time by the National Green Tribunal regarding Air Quality Index, mining of aggregates has been closed thrice
Note:;
this winter season and is still closed.