Cirata项目施工计划 Cirata project construction plan(2022/11/25-2022/12/25)KPI

Schedule
Amount MONTHLY TARGET
Work Description 工期
Engineering area 工 (Fill in the main process or individual items) Start Finish
程区域 QTY Unit TARGET 1st WEEK TARGET 2nd WEEK TARGET 3rd WEEK TARGET 4thrd WEEK
工作描述 (以主要的工序或单项为项填写) 总工期 总工期 NOTES
总数量 单位 (27-4/12.2022) (4-11/12/2022) (11-18/12/2022) (18-25/12/2022)
开始 结束
part III Foot rebar 86 t 2022/11/25 2022/12/3 66.89
part III Foot concrete 284 m3 2022/12/4 2022/12/6 284.00
part I-II RW rebar (4.8m) 34 t 2022/11/25 2022/11/28 34.00
part I-II RW formwork(4.8m) 202 m2 2022/11/27 2022/12/2 202.00
part I-II RW concrete(4.8m) 184 m3 2022/12/3 2022/12/4 184.00
part III RW rebar(4.8m) 35 t 2022/12/8 2022/12/13 20.00 15.00
part III RW formwork(4.8m) 187 m2 2022/12/15 2022/12/20 160.29
part III RW concrete(4.8m) 170 m3 2022/12/21 2022/12/22 170.00
TYPE.C B区 part I-II RW rebar(9.6m) 18 t 2022/11/30 2022/12/7 11.25 6.75
part I-II RW formwork(9.6m) 202 m2 2022/12/8 2022/12/13 115.43 86.57
part I-II RW concrete(9.6m) 184 m3 2022/12/14 2022/12/15 184.00
part III RW rebar(9.6m) 25 t 2022/12/15 2022/12/19 20.00 5.00
part III RW formwork(9.6m) 188 m2 2022/12/20 2022/12/25 188.00
part III RW concrete(9.6m) 171 m3 2022/12/26 2022/12/27
part I-III RW rebar(11m) 10 t 2022/12/20 2022/12/28
part I-III RW formwork(11m) 110 m2 2022/12/24 2022/12/29
part I-III RW concrete(11m) 103 m3 2022/12/30 2022/12/31
(8-2) make hole 420 unit 2022/11/28 2022/12/18 140.00 140.00 140.00
(8-2) grouting 420 unit 2022/11/29 2022/12/19 140.00 140.00 120.00 20.00
(8-2) pvc hole 280 unit 2022/12/13 2022/12/19 240.00 40.00
Slope area
(8-2) install U300 100 m 2022/12/13 2022/12/19 85.71 14.29
(8-2) install steel mesh 1080 m2 2022/12/15 2022/12/25 1,080.00
(8-2) shotcrete 90 m3 2022/12/26 2023/1/5