Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 12

猎豹数据中心项目

MY03 - PROJECT CHEETAH

Method Statement:
IT Cabling
(For the internal building)

Prepared Verified by Approved


by by

Mingsy
Phua

MQ Communications Sdn Bhd

Date: 18/3/2024

Version: 000
Table Content

N Content Pag
o e
1 Objective 3
2 Responsibilities 3
3 Pre-Operational Check 3-4
4 Operating Procedures for Material 4
Transportation
Additional Safety Measures for Material
5 4
Transportation
6 Emergency Procedures 5
7 Training and Certification 5
8 HIRARC 6-
14
Attachment 15 -
9
1) Forklift Checklist 26
1. Objective:
The objective of this method statement is to outline the laying IT cabling, GI
conduit and install Access point for on the construction site, ensuring the safety
of workers, equipment, and materials, especially during the transportation of
construction materials.

2. Scope
-Termination cabling to the patch panel at rack
-Testing cabling
-

3. Equipment
-stripper
-

4. Machinery

5. Transportation
-material notice in sub con group
-any delivery clash with other sub con at same time

6. Responsibilities:

● ALL - (5 point PPE)

● Site Supervisor: Responsible for overseeing and approving the scissor

lift operations on the site, including the safe transportation of


construction materials.

● Scissor Operator: Qualified and certified operator responsible for

operating the Scissor safely and efficiently, particularly during the


installation cabling, GI piping and Access point. (Harness)

● Banksman: The banksman plays a crucial role in ensuring safe scissor

lift operations. Responsible for guiding the scissor operator, providing


clear and accurate signals during installation of material. The banksman
ensures safe movements, especially in areas with limited visibility, and
helps maintain a safe working environment. (PPE, Flag (G/R), Ong vest)

7. Pre-Operational Checks:
Before Ladder ,inspection and buddy system

Before using the scissor lift, the operator must conduct the following checks:

● Ensure that scissor is being inspected by PMI and its Check for any visible
signs of damage or leaks.

● Ensure the operator to done prior inspection of the scissor lift.

● Ensure all controls and instruments are functioning properly.

● Ensure the work area deploy with exclusion zone (Cone and plastic stick)

● Ensure the scissor lift is equipped with a working fire extinguisher.

● Ensure that Banksman is available before work start.

8. Operating Procedures for Material Installation:

● Installation of Material: Operate the scissor lift at a site, When install

materials, the scissor operator should follow the same care as during the
install process. ensuring they are stable and not at risk of falling or
rolling.

● Termination and testing

9. Additional Safety Measures for Installation Material:


● Safety official at site to check all the machinery equipment.

● Operator wear Safety harness with double lanyard

● To comply with banksman/signalman instruction during transportation

esp at the public road and spaca constraint area.


10. Emergency Procedures:

● Follow Huashi emergency procedures and plan.

● In case of an accident or breakdown during installation, the scissor

operator should immediately report the incident to the site supervisor


and Huashi ESH

● If there is a emergency, exp fire the operator should use the fire

extinguisher to contain the fire and evacuate the area. Emergency


contact numbers and the location of fire extinguishers should be known
to all site personnel.

11. Training and Certification:


All scissor operators must be trained, certified to operate a scissor lift for
installation material. Regular refresher training sessions should be conducted to
ensure operators are up to date with safety procedures and regulation
Trade Contractor: MQ Communications Sdn Bhd
Name: Eric Lee
No. 7 Lot 7634 Light Industrial Area, Jalan SG Rasau 21, 41300 Klang
Address:
Selangor
Telephone No: +65 94784881
Email Address: eric.lee@mqcoms.com

Project Title: MY03


Description of the Task / Activity: Fiber termination, Cat 6 cable termination and WIFI mounting
in MY03
Site Address and Location:
Start Date and Time:
Finish Date and Time:

Name Role / Trade


-Name List Attach with PDF
Document

Personnel
Involved:

Site Supervisor: Mingsy Phua Tel: +60 19216 6522


Key Plant and Tools:
Nil
(Attach Certification)
Splicing machine, fiber striping tools, Cat 6 connector, wireless
Key Materials: AP, mounting bracket

Other Essential Equipment:


(E.g. Access Platforms, Winches, Ladder
Ladders etc.)

Specific Identified Residual


Hazards:
(Or refer to the task specific Risk Fallen from height
Assessments - Health and Safety
Form 7)

Specific Staff Training: SOC & SIC

Submission of all relevant documents ie: RA, SWP, workers


1. name list to owners and all materials spec etc to owners for
approval before commencement of works

Sequence of Operations: 2. Stripping of fiber cables


(Include sketches if
required) 3. Trimming of individual fiber strands

4. Termination of fiber using splice machine

5. Termination of Cat 6 cables


6. Installation of wireless APs with mounting bracket using ladder
7. Housekeeping
8.
9.
10.

Temporary Supports and


Props Required to Nil
Facilitate the Works:
(If none, state ‘Nil’)

Method of Access and


Egress to the Work Area:
Ladder
(E.g. Step Ladders, Ladders,
Scaffold, Trestles, EWP etc.)

- Do not go up to the top 3 steps of the ladder


Fall Protection Measures: - To implement buddy system to hold ladder prevent from
(E.g. Guard Rails, Toe toppling
Boards, Brick Guard, Safety - Make sure that the gates on the platform guard rails are
Harnesses, Exclusion Zones closed and are locked in place
etc.) - Never reach out beyond the confines of the platform

Hazardous
Substances:
(Attach MSDS if Very Harmful / Corrosiv Dangerou Oxidising Highly Explosiv
required) Toxic Irritant e s for the Flammab es
Environm le
ent

Applicable:
Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No
(Please Circle)

Storage Arrangements: Nil

Details of Permits to Work: Work at height using ladder

Safe Work Loads:


(Detail any limits on the loadings applicable to
Nil
temporary plant / equipment or fixed elements of
the structure)

Required
Personal Protective
Equipment (PPE): Safety Hard Hats Safety Hearing Respirator
Eye
Boots Gloves Protection Protection y
Protection
Others: 1. Hi-Viz Vest 2. Coveralls 3.Please Specify

Emergency
Contact: Eric Lee @ +65 94784881
Procedures:

Name of On-Site
Provided by Main Con
First Aider:

First Aid First Aid Box


Provided by Main Con
Facilities: Location:

Location of
Nearest Hospital:

All work will be undertaken by qualified competent persons with experience of the type of work described above
and in all cases, in full accordance with the safety procedures specified in the company’s Health and Safety
Manual.

Prepared by: Andrew De


Date:
8 Mar 2024
Job Position: Operation Manager

Reviewed by: Eric Lee


Date:
8 Mar 2024
Job Position: Managing Director

Items Attached:
Yes No
(Please tick)

 
Sketches:

 
Certification of Plant etc:

 
Programme of Work:

 
Risk Assessments:

PREPARED BY : REVIEWED BY :…………… APPROVED BY :…… ………

Name : Mingsy Phua Name : Name :

Designation : Project Manager Designation : Designation :


ATTACHMENT

MY03- PROJECT CHEETAH 6


CHECKLIST

DATE : TIME :
TYPE / MODEL : LOCATION :
DRIVER’S NAME : REGISTRATION NUM :
DRIVER’S ID : DRIV. LICENSE VALIDITY :

N PARTICULARS YE NO REMARKS
O S
1 Is engine start in good condition
2 Door lock condition
3 Battery condition
4 Function up and down smooth
5 Indicator Speedometer
6 Light functioning
7 Machinery License copy

Remarks:
………………………………………………………………………………………………
…………………………………………………………………………………………

…… Inspected by Operator Verify by SHE Personnel

……………………………………. …………………………….
Name: Name:

You might also like