Method Statement:
IT Cabling
(For the internal building)
Mingsy
Phua
Date: 18/3/2024
Version: 000
Table Content
N Content Pag
o e
1 Objective 3
2 Responsibilities 3
3 Pre-Operational Check 3-4
4 Operating Procedures for Material 4
Transportation
Additional Safety Measures for Material
5 4
Transportation
6 Emergency Procedures 5
7 Training and Certification 5
8 HIRARC 6-
14
Attachment 15 -
9
1) Forklift Checklist 26
1. Objective:
The objective of this method statement is to outline the laying IT cabling, GI
conduit and install Access point for on the construction site, ensuring the safety
of workers, equipment, and materials, especially during the transportation of
construction materials.
2. Scope
-Termination cabling to the patch panel at rack
-Testing cabling
-
3. Equipment
-stripper
-
4. Machinery
5. Transportation
-material notice in sub con group
-any delivery clash with other sub con at same time
6. Responsibilities:
7. Pre-Operational Checks:
Before Ladder ,inspection and buddy system
Before using the scissor lift, the operator must conduct the following checks:
● Ensure that scissor is being inspected by PMI and its Check for any visible
signs of damage or leaks.
● Ensure the work area deploy with exclusion zone (Cone and plastic stick)
materials, the scissor operator should follow the same care as during the
install process. ensuring they are stable and not at risk of falling or
rolling.
● If there is a emergency, exp fire the operator should use the fire
Personnel
Involved:
Hazardous
Substances:
(Attach MSDS if Very Harmful / Corrosiv Dangerou Oxidising Highly Explosiv
required) Toxic Irritant e s for the Flammab es
Environm le
ent
Applicable:
Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No Yes / No
(Please Circle)
Required
Personal Protective
Equipment (PPE): Safety Hard Hats Safety Hearing Respirator
Eye
Boots Gloves Protection Protection y
Protection
Others: 1. Hi-Viz Vest 2. Coveralls 3.Please Specify
Emergency
Contact: Eric Lee @ +65 94784881
Procedures:
Name of On-Site
Provided by Main Con
First Aider:
Location of
Nearest Hospital:
All work will be undertaken by qualified competent persons with experience of the type of work described above
and in all cases, in full accordance with the safety procedures specified in the company’s Health and Safety
Manual.
Items Attached:
Yes No
(Please tick)
Sketches:
Certification of Plant etc:
Programme of Work:
Risk Assessments:
DATE : TIME :
TYPE / MODEL : LOCATION :
DRIVER’S NAME : REGISTRATION NUM :
DRIVER’S ID : DRIV. LICENSE VALIDITY :
N PARTICULARS YE NO REMARKS
O S
1 Is engine start in good condition
2 Door lock condition
3 Battery condition
4 Function up and down smooth
5 Indicator Speedometer
6 Light functioning
7 Machinery License copy
Remarks:
………………………………………………………………………………………………
…………………………………………………………………………………………
……………………………………. …………………………….