a. Purpose
This test is carried out to demonstrate satisfactory performance of gas combustion unit.
b. Preparation
1. GCU, air fans, gas valve train (GVT), and associated accessories should be installed properly.
Integrality and tightness test for fuel gas and control air piping system should be
completed.
3. Electric cables, loop running fields site and serial / hardwired I/O Exchange with IAS should
be completed.
5. Igniters check
Sparks can be checked:
- by visual inspection through the view port
- or by checking the flame signal in control cabinet
- or by checking the flame level indicator inside flame relays (in control cabinet)
c. Procedure
1. GCU starting test
- Local operation: the GCU is driven exclusively locally by the operator with push buttons in
front of the cabinet.
- Remote operation: the GCU is driven exclusively by inputs from IAS. However, the operator
must switch the GCU in "Remote" position on the front of the control cabinet.
Prior to any ignition, the air purging will be obtained 30s after at least 2 fans are running. This
will ensure that the combustion chamber and the exhaust stack do not contain any unburned
gas when the burner will be started. This delay is internally checked by the GCU control system.
2. Capacity test
Increase capacity from min. to max. gas flow, keep stable running at full load for one (1)
hour, print data record from IAS.