Professional Documents
Culture Documents
HVPD - CIRED 2013 - Combined Power Quality and Condition Monitoring of Offshore Networks
HVPD - CIRED 2013 - Combined Power Quality and Condition Monitoring of Offshore Networks
HVPD - CIRED 2013 - Combined Power Quality and Condition Monitoring of Offshore Networks
Paper 1334
Paul MCKEEVER
Narec – UK
paul.mckeever@narec.co.uk
unplanned outages.
ABSTRACT
The subsea cables in both the offshore renewables and oil
The authors present a paper detailing their experiences and gas industries have the following common
(over the past 5 years) in the insulation condition characteristics:
monitoring of land-sea export cables and subsea array and
They require a long repair and/or replacement lead
platform interconnection cables in the UK offshore
time.
renewables and oil & gas industries. The paper focusses on
The repairs are expensive to do as a cable
the use of partial discharge (PD) testing to detect and
lift/repair vessel is often required.
locate pre-fault PD activity and also the use of time domain
Unplanned outages are much more expensive than
reflectometery (TDR) techniques to provide a ‘fingerprint’
scheduled, preventative maintenance during
of the cables and to help pinpoint cable faults after they
planned outages.
have occurred.
Operators need to ensure the networks have high reliability,
The paper will also discuss a ‘holistic’ monitoring
good maintainability and maximum availability. The
approach, combining a number of condition monitoring
advantages of carrying out on-line condition testing of in-
technologies, to achieve necessary information to support
service subsea cables are:
improved CBM. For the HV networks, power quality
monitoring should be integrated with the monitoring of
partial discharge (PD), cable sheath current and weather The diagnostic can be made without the need for
data (i.e. wind, wave or tidal energy resources, power flows an outage.
and occurrence of overvoltage/overcurrent conditions), The cable is assessed under normal (and abnormal)
with the further cross-correlation of all of these condition operating conditions.
and state parameters, in order to allow for the early The data can be used to support Condition Based
detection, faster identification and efficient resolving of Maintenance (CBM) to predict and prevent
faults, failures and other problems during the operation. failures by the detection of ‘incipient’ cable faults.
The purpose of such an integrated monitoring platform is The techniques ensure the continuous, reliable
therefore, to provide an advanced ‘early warning’ against operation of the cable networks.
insulation faults to enable planning of preventive or
corrective maintenance to be carried out and to avert ECONOMIC DRIVERS
unplanned outage It is anticipated that 18 GW of offshore wind could be
deployed in the UK by 2020, and that a similar large-scale
INTRODUCTION deployment of marine energy systems (wave and tidal) will
The causes of the various cable insulation faults in subsea follow afterwards [1]. Further development and
cable networks are numerous, some being due to poor implementation of these low-carbon generating
installation (producing PD in cable joints and cable technologies, however, is strongly influenced by their
terminations), inadequate mechanical protection of the currently high capital, operational and maintenance costs. In
cables (leading to external abrasion and subsequent failure) fact, most of the technical and technology barriers to their
and also the mechanical wear caused by movement of the full-scale deployment are, in one way or another, directly
subsea cables with tidal changes. Prior to failure, these associated with the corresponding costs. Recently the UK,
‘incipient’ cable faults can produce PD activity which can the Department of Energy & Climate Change (DECC)
be detected and located (‘mapped’) to enable the operator to suggested that overall costs of offshore wind generated
plan and carry out preventative maintenance and avoid electricity (from development, construction and operations)
Paper 1334
should fall to about £100/MWh by 2020 to make this propagate to the cable ends. This sensor is well suited to
technology truly competitive [1], [2]. It can be concluded, on-line PD measurements as is non-intrusive and in many
therefore, that there is an urgent need to reduce operating cases can be installed without the need for an outage.
and maintenance costs of both existing and future offshore
wind farms. The sensor is installed either onto the cable earth connection
or around the cable core with earth looped back through.
PARTIAL DISCHARGE TESTING OF Pictures of both installations on subsea cable circuits are
OFFSHORE NETWORKS shown in Figure 2 and Figure 3. .
Paper 1334
pulse width up to 10us. The test set-up is shown in Figure security-related protection as well as control aspects of
4. system operation.
With such techniques TDR testing has been performed TDR Red Phase – Injection
Available at Satellite Platform
Waveform Display
cables up to 108 km in length to identify the return time of Figure 6 6.6kV Subsea circuit overview
1.5
the cable and positions of land cable joints and land-subsea 1
cable transition joints [4]. Off-line, pinpointing TDR measurements were used to
Chan 1
0.5
0
locate the fault and direct the cable repairs.
-0.5
-1
-1.5
HOLISTIC MONITORING SYSTEM The off-line TDR testing was conducted at both ends of the
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
An advanced, flexible and real-time sensing and diagnostic cable. The TDRreturn time was measured on an un-faulted
Yellow Phase – Injection at Satellite Platform
Time (uSec)
Available Waveform Display
Chan 1 Curs 1 Curs 2
intelligence, capable of correctly identifying state, condition phase. TDR measurements from the main platform showed
1.5
and performance of monitored HV networks, is required for the location of the fault at 99.54% of the cable length out
1
0.5
from platform. The step response waveform is shown in
Chan 1
condition-based management (CBM) schemes. Essentially, Figure 7. This was at location of around 56 m out from the
-0.5
-1
this requires combining a range of power quality and satellite platform and coincided with the entry point of the
-1.5
conditioning monitoring, protection and control cable to the subsea cable pipe.
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Time (uSec)
– Injection
technologies into a ‘holistic’ multi-parameter system. TDR Blue
Chan 1Phase
Available at Satellite
Waveform Display
Curs 1 Platform
Curs 2
0
state/condition/performance identification and subsequent -0.5
-0.1
-0.2
-0.3
-0.4
-0.5
-0.6
-0.7
2 3 4
Time (uSec)
It was found that the cause of the fault had been due to the
Figure 5 Holistic monitoring system overview
(mechanical) stress-relieving ‘bung’ at the end of the pipe
becoming dislodged. The cable had failed due to abrasion
One important advantage of integrating system state
due to mechanical movement of the cable, with respect to
identification functionalities and whole-system or
the fixed subsea pipe that led to the cable failure through a
individual-component performance and condition
sheath fault to earth.
monitoring into one multi-parameterised platform is that this
will allow assessment of power quality and reliability levels
The cable fault was repaired with new cable joints and
to be combined with the analysis of insulation condition and
OLPD tests were carried out at both ends of the cable circuit
Paper 1334
after the repair to ensure that the new cable joints had been technology in the offshore wind and oil and gas industries.
installed correctly. These tests showed the re-instated cable Such systems are of particular interest to the offshore
was discharge-free and thus suitable for service windfarm operators who are more likely to suffer from
higher levels of faults due to early-life, ‘infant mortality’
CASE STUDY – ON-LINE PD DETECTION failures with their new subsea cable installations.
Following faults at joints on the land cable section of an The offshore windfarm operators have expressed a need for
offshore wind farm 33kV export cable feeder, it was a multifunctional, integrated state/condition/performance
decided to perform partial discharge monitoring. An monitoring platform to allow for the implementation of
overview of the circuit is in Figure 8 optimal and cost-effective preventive maintenance action.
Such an integrated system is required for the
The tests involved installing equipment at the on-shore implementation of improved and more effective CBM
substation to log the PD over time. schemes. Essentially, this requires combining a range of
power quality and conditioning monitoring, protection and
Offshore Wind
control technologies into a ‘holistic’ multi-parameter
33kV Grid Substation
farm
system.
33kV Switching
Circuit 1 Circuit 2
Offshore 33kV
GIS Switchgear
complementary cable condition monitoring technologies,
including monitoring of partial discharge (PD), distributed
temperature sensing (DTS), cable sheath current, power
Land Cables 3 x single
core
Land-Subsea
Cable Joints
3 core Subsea
Cables quality monitoring (PQM), weather/tidal data, power flow,
and overvoltage/overcurrent events. With cross correlation
of all of these condition and state parameters, it will then be
Figure 8 33kV Export cables overview possible to provide the necessary level of detailed
diagnostic data required for implementing and CBM.
PD signals were observed during the monitoring session on
L3. A PD location was subsequently carried out and one As cost reduction in operation and maintenance costs can
joint in the circuit with PD was identified. The client only be achieved if there is a radical rethink on present asset
subsequently replaced the joint. PD monitoring after management practice, with a move towards CBM viewed as
replacement, showed the high PD activity had been ceased, essential. Furthermore, for effective CBM to be
as shown in Figure 9. implemented, detailed, real-time (continuous) diagnostic
intelligence and data on both the state and condition of the
This prompt maintenance gave confirmation the cable MV and HV subsea cable networks is necessary.
insulation was now in a healthy state for continuous
operation and reduced the risk of an unplanned outage. REFERENCES