LUMBERS and Another V W COOK BUILDERS PTY LTD (IN LIQ)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 31

412

LUMBERS and Another v W COOK BUILDERS PTY LTD (IN LIQ)


HIGH COURT OF AUSTRALIA
5
GLEESON CJ, GUMMOW, HAYNE, CRENNAN and KIEFEL JJ

26, 27 February, 18 June 2008 — Canberra


[2008] HCA 27 10

Equity — Quantum meruit — Services performed and subcontractors paid —


Entitlement to compensation — Appellants entered into oral agreement with
building company for construction of domestic dwelling — Respondent performed
some of construction work — Appellants did not request respondent perform any 15
services or pay any subcontractors — Whether claim for quantum meruit or money
paid available.

Restitution — Unjust enrichment — Appellants accepted benefit of construction


work performed by and at expense of respondent — Claim that it would be
unconscionable for appellants to retain benefit — Appellants made no direct request 20
of respondent — Whether restitutionary claim available.

Contract — Third parties — “Cost plus” oral agreement between building company
and owners — Informal reorganisation within building company’s corporate group
— Benefit and burden of oral agreement informally assigned by building company 25
to related company — No notice given to owners of reorganisation or assignment —
Some subcontractors paid directly by owners — Acknowledgment by building
company that owners had met all progress claims made and paid all monies due
under oral agreement — Whether related company can demand compensation from
owners for difference between amounts paid by owners and amounts outlaid by
related company together with margin for supervision and profit. 30

The appellants (the Lumbers) entered into a contract with W Cook & Sons Pty Ltd
(Sons) under which Sons was to build a house for the Lumbers. W Cook Builders Pty Ltd
(in liq) (Builders) claimed that it entered into a contract with Sons, pursuant to which
Builders was to build the house and the benefit of Sons’ contract with the Lumbers was 35
transferred to Builders. The Lumbers were not aware of the contract between Sons and
Builders. About 4 years after the construction of the house was completed, the liquidators
of Builders made a claim to the Lumbers, alleging that the Lumbers had not paid all that
should have been paid for building the house. The Lumbers did not pay to Builders the
money claimed.
Builders commenced proceedings in the District Court of South Australia against the 40
Lumbers and Sons. Builders’ claims were in contract and also in “restitution/unjust
enrichment”. An order was made that Builders provide security for Sons’ costs. Builders
did not do so, and the proceeding as against Sons was stayed. Builders proceeded against
the Lumbers, and was not successful. Builders appealed, and the Full Court of the
Supreme Court of South Australia allowed the appeal on the basis that Builders’ restitution 45
claim should succeed.
On the appeal, the issue for the court to determine was whether the Full Court erred in
finding that Builders was entitled to restitution from the Lumbers.

50
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 413

Held, allowing the appeal (per Gummow, Hayne, Crennan and Kiefel JJ, Gleeson CJ
agreeing with the proposed orders):
(i) The Full Court’s approach, in not considering the contract between Sons and the
Lumbers in determining whether Builders was entitled to restitution from the Lumbers,
was flawed because:
(a) it was not correct to say that Builders did the work and Sons did not. If there was
no concluded agreement as between Builders and Sons before Builders did work
or paid money at Sons’ request, then it would have had a claim against Sons for
work done and money paid at Sons’ request. However, if an enforceable contract
was made then no action would lie for a quantum meruit while the contract
remained on foot. If Builders did work or paid money, Sons could point to that
work or payment by Builders as done or paid in performance of Sons’
obligations to the Lumbers.
(b) the letter from Sons to the Lumbers of 1 February 1999, in which Sons
disavowed any claim for further payment from the Lumbers, was not relevant to
the nature or content of the contractual relationship between Sons and the
Lumbers: at [111]–[114], [117], [123].
(ii) The contract between the Lumbers and Sons was such that the Lumbers accepted no
benefit at the expense of Builders which it would be unconscionable to retain. Builders had
no claim against the Lumbers for the price of any work or labour it performed or for any
money paid, because it could not point to any request by the Lumbers that it do any work
or pay any money. Reference to whether the Lumbers “accepted” any work or benefit of
any money paid by Builders is irrelevant, because of the legal relationships between the
various parties: at [125], [126].

Appeal
This was an appeal from orders made by the Full Court of the Supreme Court
of South Australia.

D F Jackson QC and M R Burnett instructed by Lynch Meyer Lawyers for the


appellants.
G O’L Reynolds SC, R D Ross-Smith and B R Kremer instructed by
Rick Schroeder for the respondent.
[1] Gleeson CJ. In September or October 1993, W Cook & Sons Pty Ltd
(Sons) entered into an oral agreement with the appellants, Mr Matthew Lumbers
and Mr Warwick Lumbers, to construct a house at North Haven, near Adelaide.
Mr Matthew Lumbers owned the land and Mr Warwick Lumbers had an
unregistered lease for life over the property. For present purposes, it is
unnecessary to distinguish between Mr Matthew Lumbers and Mr Warwick
Lumbers (the Lumbers) as parties to the contract. The house was described by the
primary judge as “quite distinctive”. It ultimately cost more than $1m to build.
It was completed in May 1995.
[2] In circumstances that will be described below, most of the work required by
the contract, which included the engagement of building subcontractors and
supervision of their work, was performed, not by Sons, but by W Cook Builders
Pty Ltd (in liquidation) (Builders). This change in the identity of the builder
occurred without the knowledge or approval of the Lumbers. Builders and Sons
were members of the same corporate group, but their shareholders and directors
were not identical, and at some stage, for reasons that were not made clear in the
evidence, their interests diverged. The proceedings giving rise to this appeal
arose out of claims by Builders to be remunerated for its services. The claims
414 AUSTRALIAN LAW REPORTS HCA

included claims for reimbursement of amounts paid to various subcontractors,


and a fee for supervision. The Lumbers made progress payments to Sons,
as requested, at intervals over the period from April 1994 to May 1995.
Without the knowledge of the Lumbers, Sons paid those amounts to Builders.
Builders claimed that a balance (ultimately found to be $261,715) remained due 5
and unpaid.
[3] The making of the 1993 building contract by the Lumbers and Sons was
asserted by Builders in its statement of claim, and was not denied. It was never
suggested that there was a novation of the contract, or that the contract was
10
terminated, either by the Lumbers or by Sons. The trial judge found that the
payments made to Sons by the Lumbers did not cover the whole of the cost of
the building work. The possibility that the Lumbers remain indebted to Sons is
a matter upon which the Lumbers rely in resisting the claim made against them
by Builders. 15
[4] In November 1999, more than a year after Builders went into liquidation,
Builders demanded payment from the Lumbers of a certain amount. Builders also
claimed the same amount from Sons. This appeal concerns only the claim against
the Lumbers. As will appear, the adjudication of the claim in the South Australian
courts was constrained by the course of the proceedings, and by the absence of 20
the evidence of at least one key potential witness.
[5] Builders commenced an action in the District Court of South Australia,
joining as defendants the Lumbers and Sons. It was alleged that the Lumbers,
or alternatively Sons, were or was liable to Builders for “the contract price less
the amount paid”. That was a reference to the 1993 contract. It was alleged by 25
Builders that, in addition to the contract between the Lumbers and Sons, there
were “arrangements” between Sons and Builders, under which Builders would
carry out the building work required by the Lumbers. It was not alleged that the
Lumbers were parties to those “arrangements”. The statement of claim alleged
oral “proposals”, made by Sons in early 1994, and said to have been accepted by 30
Builders. The proposals are referred to in more detail below under the heading
“Reorganisation”. The statement of claim alleged that the “proposal and
acceptance constituted a contract between [Sons] and [Builders].” It alleged that,
under the contract, Builders became legally bound to Sons to take over
responsibility for the construction work and, further, that Sons assigned to 35
Builders the benefit of the 1993 building contract. As will appear, the primary
judge accepted the first part of that allegation of the legal effect of what occurred,
but not the second. The statement of claim went on to allege that the amount
claimed was due by the Lumbers to Builders, or alternatively to Sons “to be held
on trust for” Builders. The claims against the Lumbers were based on contractual 40
assignment or, alternatively, “restitution/unjust enrichment”.
[6] Before the action was fixed for hearing, Builders was ordered to provide
security for Sons’ costs. Such security was not provided. The action against Sons
was stayed, although it appears from an observation of the trial judge that it could 45
still be revived. He said it was “in a static condition”. Hence, Sons was not an
active party in the proceedings at trial or on appeal. The claim by Builders against
Sons has never been litigated. Because of the stay order, something in the nature
of an interpleader was not possible. Builders, at trial, pursued its action against
the Lumbers separately from its claim against Sons. The trial judge described the 50
effect of the stay order as follows:
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 415

The Orders were however conditioned so that Builders could not pursue any derivative
claims … Builders could therefore no longer claim that, if Sons were the correct
plaintiff, Builders was beneficially entitled to any sum owed by the Lumbers to Sons.
Nor could it argue that Sons was entitled to recover the balance outstanding on Builders
behalf in the event of “a legal black hole”.

[7] The claim against the Lumbers based on assignment was dismissed in the
South Australian courts and is not now pursued. That leaves this court to deal
with the claim based on “restitution/unjust enrichment” in the context just
described; a claim that failed at first instance but succeeded on appeal in the Full
Court of the Supreme Court of South Australia. Before turning to the relevant
principles it is necessary to say more about the facts, and the history of the
litigation.

The Cook group of companies


[8] In 1993, Sons was the main operating company of the Cook family, which
had established a significant reputation in the building industry since about 1910.
The respondent, Builders, was another in the Cook group of companies. At the
time of the reorganisation referred to below, Builders was a dormant company.
Mr Jeffrey Cook managed the practical side of the business of Sons, and later
Builders, but had little or no involvement in the administration of either company.
Mr David McAdam was a long-time employee of the Cook group. Mr McAdam’s
mother was married to Mr Jeffrey Cook’s father. Though Mr McAdam and
Mr Cook had known each other for 50 years, it appears that their relationship
was, or became, strained. Mr McAdam was secretary of Sons and, until
March 1994, a director of Builders. He had been responsible for financial
management and contract administration of all of the companies in the Cook
group since 1963. A partnership operating under the name of Portrush Traders
employed all employees of the companies in the group. The evidence does not
reveal the identity of the partners. After Builders ceased to be dormant, Builders
and Sons shared common staff and administration and operated a common bank
account. Mr McAdam entered into the respective company journals the sums to
be allocated to each company. At the relevant times, the shareholders in Builders
were members of Mr Jeffrey Cook’s immediate family. Mr Jeffrey Cook was a
director. After the reorganisation Mr McAdam resigned as a director of Builders.
He continued as a director of Sons, which was then under his control.
The building contract
[9] Negotiations for the construction of the house were conducted between
Mr Warwick Lumbers and Mr McAdam. Much of the confusion, and many of the
deficiencies in the evidence, in this case arose from the fact that neither party
called Mr McAdam as a witness. He played a vital part in important events.
The Lumbers chose Sons because of Sons’ reputation and the Lumbers’ desire for
a “pedigree” for the house, and because of Mr Lumbers’ confidence in
Mr McAdam. In his evidence, Mr Warwick Lumbers emphasised that, because of
his frequent absences overseas, he wanted someone whom he could trust to
assess and approve invoices. Part of the explanation for the informality of the
contract was the trust of Mr Lumbers in Mr McAdam. Sons was a licensed
builder. Builders was not. Mr Lumbers’ evidence was that he would not have
agreed to an unlicensed builder’s undertaking the work because that would have
put his insurance policy at risk.
416 AUSTRALIAN LAW REPORTS HCA

[10] The building contract between the Lumbers and Sons was never reduced
to writing. The trial judge found that Sons agreed to undertake the building work
according to specifications and plans prepared by the Lumbers’ architect. Some
of the work was to be performed by Mr Warwick Lumbers himself. He held a
restricted builders licence. His brother-in-law, an architect, designed the house. 5
The trial judge said that “[t]he parties did not employ the traditional form of
progress claims and payments, choosing instead, ad hoc, lump sum payments”.
Payments were to be made to Sons, which would, in turn, pay any subcontractors.
No fixed price was agreed. However, it is not in dispute that the price payable to
Sons included the cost charged for the work performed by Sons and by 10
subcontractors and for the supply of materials. There was some disagreement
about an additional charge for supervision and management. The amount of the
supervision charge was not agreed, but the trial judge considered that 10% of the
project costs was a reasonable fee. No invoices were ever rendered; throughout
the building work, Mr McAdam would telephone Mr Warwick Lumbers and state 15
that he needed a certain sum of money, and Mr Lumbers paid that sum of money
by cheque directed to Sons. The payments bore no direct relationship to actual
expenditure in respect of the building work.
[11] In its statement of claim, Builders made the following allegations
concerning the contract between Sons and the Lumbers: 20
The express oral terms of the building contract included terms to the effect
(a) That [Sons] would perform certain building work (the building work) on the
land.
(b) That the building work would be in accordance with plans and specifications
provided by [the Lumbers]. 25
(c) That [the Lumbers] could make variations to the plans and specifications from
time to time.
(d) That there would not be a fixed price for the contract works, but rather the
price payable by [the Lumbers] to [Sons] would consist of
(i) the cost charged by sub-contractors for the performance of all 30
components of the work;
(ii) the cost charged for the supply of materials for the work;
(iii) an additional charge of 10% of the above costs (including such costs
incurred directly by [the Lumbers]) for the supervision of the building
work and the management of the building contract by [Sons].
(e) That [Sons] could submit invoices or demands to [the Lumbers] for progress 35
payments at intervals to be determined by [Sons], which invoices or demands
[the Lumbers] would be obliged to pay.
(f) The amount claimable in such invoices or demands was to be the amount paid
or payable by [Sons] for sub-contract work and supply of materials, together
with 10% for supervision and management by [Sons] … 40
(g) [Sons] could itself carry out work and supply materials for the building work,
in which case it would be treated under the above terms as if it were a
sub-contractor. The price claimable for the work or materials was to be a
reasonable price.
[12] The term alleged in (e) reflected the relationship between Mr Lumbers and 45
Mr McAdam. It was left to Sons (effectively Mr McAdam) to decide the timing
and the amounts of the progress payments. This term was admitted in the
Lumbers’ defence. In fact, save for the matter of the 10% supervision fee, which
was in dispute, there was no issue on the pleadings as to the formation of the
building contract between Sons and the Lumbers, or as to such of its terms as are 50
presently material. That is the basis on which the case was conducted and decided
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 417

in the South Australian courts, and it is the basis upon which the present appeal
must be decided. The respondent sought, by notice of contention in this court,
to dispute for the first time the existence of the contract it alleged in its statement
of claim. This should not be permitted. If the contract, which in a number of
respects formed the basis of Builders’ claims, and in particular its claim founded
on assignment, had been disputed by Builders, then the argument could well have
been met by calling further evidence. It appears that the principal ground upon
which Builders now seeks to deny the existence of a contract is uncertainty.
If that point had been taken at trial, it would have been necessary for trial counsel
and the trial judge to deal more extensively with some matters of fact and
building practice. It is too late to raise the point now.1
[13] Preparation of the site commenced in November 1993, and building work
commenced in February 1994. Mr Jeffrey Cook was the supervisor, and was in
control of the subcontractors who came on site.
Reorganisation
[14] In February 1994, there was a reorganisation within the Cook group of
companies, after which Sons’ business was restricted to joinery and carpentry,
and Builders undertook construction work. The reorganisation was informal.
There was no evidence of directors’ meetings or of any documentation setting out
the respective roles of the two companies. The evidence was that the
reorganisation was devised by Mr McAdam; Mr Jeffrey Cook had little detailed
understanding of its purpose or basis.
[15] The same employees, including Mr Jeffrey Cook, continued with the
building work after the reorganisation. The trial judge inferred that Portrush
Traders continued to administer both Sons and Builders. Mr McAdam resigned
as a director of Builders in March 1994. However, he continued to occupy an
office adjoining Mr Cook and maintained direct contact with Mr Warwick
Lumbers. The Lumbers were not informed of the reorganisation and were
unaware of the existence of Builders. At no relevant time was Builders a licensed
builder.
[16] After the reorganisation, Builders, rather than Sons, performed the
construction work, which, to a substantial extent, involved the engagement and
supervision of subcontractors. On 1 March 1994, an invoice reflecting the cost of
work done by Sons to the date of the reorganisation, prepared by Mr McAdam,
was rendered by Sons to Builders, and entered in the journal of Builders, also by
Mr McAdam. After the reorganisation, payments to subcontractors were debited
to Builders’ accounts, though the evidence did not reveal whether the payments
were made from Cook group funds and then debited to Builders’ accounts
through journal entries, or whether they were made from separate accounts of
Builders.
[17] Reference has already been made to the allegations in the statement of
claim concerning a contract between Builders and Sons in February 1994.
The “arrangements”, said by Builders to have resulted in a contract, involved a
proposal made by Mr McAdam on behalf of Sons which was accepted by
Mr Jeffrey Cook on behalf of Builders. Builders alleged that it was unable to give
full details of what was agreed between Mr McAdam and Mr Cook (thereby
revealing what was confirmed in the evidence, that is to say, that Mr Jeffrey Cook

1. See Water Board v Moustakas (1988) 180 CLR 491 at 497; 77 ALR 193 at 196; [1988] HCA 12.
418 AUSTRALIAN LAW REPORTS HCA

did not understand completely what Mr McAdam was doing administratively).


The statement of claim alleged that the terms were that “[a]s between [Sons] and
[Builders], all future costs of the building work were to be charged to [Builders]
rather than [Sons]”, that Mr Jeffrey Cook would continue to supervise and
manage the building work “on behalf of the builder” and that “[Builders] would 5
be entitled to recover all amounts payable by [the Lumbers] in respect of the
building work, including the additional charge of 10% for the supervision of the
building work and management of the building contract.” It was said to be a
“legal effect” of the contract that Builders became contractually bound to Sons to
carry out the building work and, further, that the benefit of the building contract, 10
and future property in the price payable by the Lumbers to Sons, was assigned
by Sons to Builders. There was no allegation that the Lumbers were parties to,
or were aware of, this. In their defence, the Lumbers said that they did not know
and could not admit the facts alleged by Builders, but asserted that, if the facts
were true, they were not disclosed to the Lumbers. 15
[18] The Lumbers occupied the house in December 1994, although, as noted
above, construction was not completed until May 1995. Subject to specific
defects, the value of which was agreed, the completed building was satisfactory
to the Lumbers.
20
Payments
[19] At the time of the reorganisation, no request had been made by
Mr McAdam to the Lumbers for any payment. The Lumbers were first requested
to pay money on 30 April 1994. Every payment made by the Lumbers was made
by cheque payable to Sons. Save for a final amount paid in December 1997, the 25
remainder of the payments were made between 30 April 1994 and 16 May 1995.
These payments followed requests from Mr McAdam for round sums, rather than
progress payments specifically related to costs incurred. The Lumbers paid all
amounts that were requested by Sons.
[20] In 1999, Builders sent a notice to the Lumbers claiming that the difference 30
between the amount recorded as incurred on the building project and the amount
received from the Lumbers was $181,904. There was no explanation of why no
part of that sum had been requested from the Lumbers earlier. Nothing was
allocated in the books of Builders for the supervision fee until after the
liquidation. 35

Subsequent events
[21] On 26 May 1998, Builders was placed into voluntary administration.
It went into liquidation on 22 June 1998.
[22] By letter dated 1 February 1999, Mr Malcolm Cook, a director of Sons, 40
wrote to Mr Warwick Lumbers in the following terms:
Following a restructuring of the Company in 1994, Mr Jeffrey R Cook, a director of
[Sons], took over all building & construction operations currently in progress, operating
as [Builders] … and continued building operations until May 1998, when [Builders]
went into liquidation. 45

[Builders] operated as a separate entity, maintaining its own records in accordance with
normal requirements, lodged taxation returns, & conducted its day-to-day business
independently from [Sons]. All invoicing & receipts in relation to the [house at North
Haven], (and all other building projects) were through the accounts system of 50
[Builders].
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 419


We can not comment on any claims made by the liquidator of [Builders], however we
do advise you that there are no outstanding amounts owing either by yourself, or any
other person or entity, to [Sons] in relation to the construction of the above residence.

[23] The circumstances in which that letter was written do not appear from the
evidence, and Mr Malcolm Cook, like Mr McAdam, did not testify. It appears
that, at least by the time that letter was written, Sons and Builders were at arm’s
length, although whether they were yet in dispute is not clear. Mr Malcolm
Cook’s reasons for writing the letter were not explained. Because Sons was not
an active party to the litigation, following the stay of proceedings against it, the
legal effect of the letter as between Sons and the Lumbers was never tested.
Whether, for example, if Sons had been found to have been liable to Builders,
Sons would have had a claim against the Lumbers was never decided.
[24] On 8 November 1999, Builders served the Lumbers with a notice of
demand for payment of $274,791, comprising the alleged deficiency of $181,904,
together with a 10% supervision fee of $92,887. On 11 November 1999, Builders
caused a workers’ lien to be registered on the title to the property. Builders’ claim
was made some 4 years after the construction had been completed. Mr Warwick
Lumbers suggested in his evidence that the claim might have been considered
differently had he been provided with a bundle of invoices rather than a notice of
demand.
The decision of the primary judge
[25] Some features of the procedural context in which the matter came for
hearing before Judge Beazley have been noted above. He remarked that
“complexity has arisen from the casual basis upon which the parties have chosen
to deal with each other, and indeed in the manner in which they have conducted
the litigation.” The fact that Sons took no part in the trial, that Mr McAdam did
not give evidence, and that Mr Jeffrey Cook, although an experienced builder,
was “able to give only scant evidence with respect to ‘administration issues’”
added to the difficulties. It may be remarked that the restitutionary principles on
which the respondent relied were designed to overcome what otherwise would
have been deficiencies in the law, but in the present case they appear to have been
called in aid principally to overcome deficiencies in evidence and unusual aspects
of procedure.
[26] There were issues at trial, not presently relevant, concerning the amount of
the claim; there were questions of the total amount of payments to
subcontractors, allowances for defects, and the fee for supervision and
management. The trial judge resolved most of those issues in favour of Builders,
and quantified the claim at $261,715.
[27] There was also an issue, which was the subject of argument in the present
appeal but which may be put to one side for the moment, arising out of the fact
that Builders was unlicensed. Section 39 of the Builders Licensing Act 1986 (SA)
provided:
An unlicensed person who performs building work in circumstances in which a
licence is required under this Act shall not be entitled to recover any fee or other
consideration in respect of the building work unless the Tribunal or any court hearing
proceedings for recovery of the fee or consideration is satisfied that the person’s failure
to be licensed resulted from inadvertence only.
420 AUSTRALIAN LAW REPORTS HCA

[28] For reasons that turned upon the evidence of Mr Jeffrey Cook, the primary
judge found that Builders’ failure to obtain a licence did not result from
inadvertence. There is no challenge to that finding.
[29] The main issue was a dispute as to whether Builders was entitled to claim
5
directly against the Lumbers. Referring to the conduct of Mr Jeffrey Cook after
the reorganisation, the judge said:
He did not speak to Mr McAdam, Warwick Lumbers or [the architect] about the terms
of the contract which he and his immediate family were apparently taking over in
Builders. He did not raise the question of price despite the fact that all of the major 10
variations took place after the re-organisation. He had no involvement in quantifying
the amounts to be requested of the Lumbers, despite the large sums being debited to
Builders’ accounts for the work.
I have already discussed the failure of Builders to obtain a licence. Jeffrey Cook did
not request the Lumbers to make payments direct to Builders rather than Sons … 15
Finally when the building work was completed, Mr Cook appears to have made no
attempt to quantify what was outstanding or seek payment from the Lumbers. It was
only well after the liquidation of Builders that anyone put the Lumbers on notice that
any sum was outstanding, and suggested a direct claim as an equitable assignee.

[30] The claim to be an equitable assignee of the 1993 building contract was in 20
the forefront of the Builders’ case at trial against the Lumbers. The claim was
rejected by the primary judge, and by all three members of the Full Court. For
reasons that will be apparent when considering the alternative restitutionary
claim, and notwithstanding the form of the statement of claim, Builders was 25
concerned to disavow a role as a subcontractor to Sons. The Lumbers, for their
part, argued that there was a building contract between the Lumbers and Sons,
which was never the subject either of novation or termination, and a subcontract
between Sons and Builders. Whether the making of the subcontract, and the
subsequent performance of the work by Builders, involved Sons in a breach of 30
its contract with the Lumbers was immaterial. The Lumbers were unaware of any
such breach, and never terminated their contract with Sons on account of it. They
were not pursuing a claim for damages against Sons in that respect.
[31] The primary judge described the principal argument of Builders as being
that it was an equitable assignee of the benefit of the agreement between the 35
Lumbers and Sons, and that it was entitled to recover in an action in its own name
against the Lumbers. He noted that the alleged assignment was not in writing and
did not comply with the requirements of s 15 of the Law of Property Act
1936 (SA).
40
[32] In the light of the subsequent history of the litigation, it is possible to deal
with this issue briefly. Judge Beazley rejected Builders’ argument for two
reasons. First, he was concerned about the high degree of personal confidence
placed by the Lumbers in Sons when the original building contract was made.
The identity of the builder was a matter of importance to Mr Warwick Lumbers. 45
The substitution, without his consent, of another corporate entity, even one
associated with the Cook group, as the recipient of the benefit of the contract
would have made a significant difference to him. Builders was a company in
which Mr McAdam had no personal interest. Mr Warwick Lumbers relied on
being able to negotiate personally with Mr McAdam about matters such as 50
defects and fees. The judge referred to Tolhurst v Associated Portland Cement
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 421

Manufacturers (1900) Ltd2 and Linden Gardens Trust Ltd v Lenesta Sludge
Disposals Ltd.3 Mr Lumbers, whose evidence the judge accepted, was adamant
that he would not have agreed to such an assignment, and the judge considered
there were good reasons for this. Secondly, the judge was unable to find, in the
state of the evidence, that there was any intention on the part of Sons to assign
the benefit of the contract to Builders or otherwise to effect any assignment as
alleged in the statement of claim. Again, the absence of Mr McAdam was critical.
The judge concluded that Builders performed its work on the project, not as an
assignee of the benefit of the contract, but as a subcontractor to Sons.
The allegations made by Builders in its statement of claim as to its contract with
Sons are set out above. At trial, the Lumbers did not dispute that there was a
contract between Sons and Builders, although they did not profess to know its
terms, and challenged the assertion that its “legal effect” included an assignment
of the benefit of the 1993 contract or the amount ultimately to be paid under that
contract. The only direct evidence of the contract was Mr Jeffrey Cook’s account
of a conversation he had with Mr McAdam. Although his account was vague, he
was clear about the fact that it was agreed that, after the “changeover”, the
building work (including the work presently in question) was to be done by
Builders. The evidence of Mr Cook supported the allegations in the statement of
claim except in one important respect, that is to say, the matter of the alleged
assignment of rights from Sons to Builders. It was consistent with the evidence
of Mr Cook that, as alleged in the statement of claim, Builders became
contractually bound to Sons to perform future work and supervision on the
building. As the primary judge said, once the allegation of an agreement as to
assignment is rejected, it is appropriate to describe this as a subcontract.
[33] In the alternative, Builders argued that it was “entitled to fair and just
compensation for the benefit or enrichment accepted by the Lumbers.” The judge
said (references omitted):
At all times there was extant an agreement between the Lumbers and Sons which
covered the work said to have been undertaken by Builders. Insofar as a claim ought to
have been made by Builders it ought to have been against Sons. Sons remained liable
under the Contract with the Lumbers. It cannot be said that the Lumbers have an
obligation to make restitution to Builders, irrespective of whether Builders was
mistaken as to its position when allegedly constructing the house. There was of course
no evidence at all as to the allegedly mistaken understanding of Builders. In my opinion
Builders could not succeed against the Lumbers under this alternative claim.

The decision of the Full Court


[34] The Full Court of the Supreme Court of South Australia, by majority
(Sulan and Layton JJ, Vanstone J dissenting) upheld Builders’ appeal.4
[35] All three members of the Full Court rejected Builders’ case on assignment.
The majority regarded the trial judge’s conclusion that there was insufficient
evidence to find the existence of an intention to assign as soundly based. They
found it unnecessary to deal with the question whether the contract was of such
a nature that assignment was not possible. Vanstone J pointed out that, under the
building contract, it was for the builder to determine the payments that were to
be made over the course of construction. She considered that it would have been

2. [1902] 2 KB 660.
3. [1994] 1 AC 85; [1993] 3 All ER 417.
4. W Cook Builders Pty Ltd (in liq) v Lumbers (2007) 96 SASR 406; [2007] SASC 20.
422 AUSTRALIAN LAW REPORTS HCA

inconsistent with the trust reposed in Mr McAdam by Mr Warwick Lumbers,


which accounted for the informal and in some respects open-ended nature of the
contract, to permit another party to stipulate the amount of those payments.
She concluded that the contract was of a personal nature and incapable of
assignment. 5
[36] The majority also decided that any claim by Builders to recover what they
described as “contractual damages” would have been defeated by s 39 of the
Builders Licensing Act. Vanstone J found it unnecessary to deal with this point.
The majority said, however, that “[w]here an unlicensed person carries out
10
building work, they may nevertheless bring an action in unjust enrichment in
which damages will be calculated on a quantum meruit basis.” They went on to
deal with the claim described by Builders in its statement of claim as
“restitution/unjust enrichment”.
[37] The majority commenced their reasoning by putting to one side the 15
subsisting contractual relationship between Sons and the Lumbers. This was a
rather important, and controversial, first step. They justified it on two grounds.
First, they referred to the letter signed by Mr Malcolm Cook, in February 1999,
in which Sons said that it had no claim against the Lumbers. They did not discuss
the legal effect of the letter, or explain how it would operate to defeat a claim by 20
Sons. They simply referred to its existence. As mentioned earlier, the evidence
did not show how it came to be written. Nor did it show that the Lumbers altered
their position or otherwise acted in reliance on the letter. No doubt they were
pleased to have it, but that does not mean that it was of legal consequence.
Secondly, the majority said that Sons did not perform its obligations under the 25
contract. Presumably they meant by this that Sons, without the knowledge of the
Lumbers, delegated the performance of its obligations to Builders. Again, it is not
clear what was said to be the legal consequence of this as between Sons and the
Lumbers. If the delegation constituted a breach of contract by Sons, then the
Lumbers might have had a claim for damages against Sons, if they could show 30
they suffered harm. The contract, however, was never terminated; the building
was built, generally to the satisfaction of the Lumbers; and the majority did not
express a conclusion as to whether the Lumbers were liable to Sons under the
building contract and, if not, why not. Furthermore, the majority gave no express 35
consideration to the question of Builders’ rights against Sons. They appear to
have regarded those as irrelevant.
[38] Understandably, the majority introduced their discussion of the subject of
restitution by referring to the decision of this court in Pavey & Matthews Pty Ltd
v Paul.5 That was a building case. There was only one contract, that is to say, 40
a contract between an owner and a builder. Because the contract was not in
writing, it was (by statute) unenforceable by the builder. The issue6 in that case
was whether the builder, in bringing a quantum meruit claim, was attempting to
do that which the statute prohibited, that is, attempting to enforce the contract.
In answering that question in the negative, the court explained that the nature of 45
the builder’s claim against the owner was restitutionary, not contractual. The
general principles stated in the course of that explanation have been taken up in
later decisions. The majority referred to some of those decisions.

5. (1987) 162 CLR 221; 69 ALR 577; [1987] HCA 5 (Pavey & Matthews). 50
6. Pavey & Matthews at CLR 245; ALR 596.
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 423

[39] The present was not a case of the performance by Builders of services for
the Lumbers at the request of the Lumbers; or of acquiescence in the provision
of services by Builders knowing that the services were not being rendered
gratuitously; or of the provision of services necessary for the protection of the
Lumbers’ property. The majority, however, identified the case as one “where the
service conferred incontrovertible benefit on the defendant, and it would be
unconscionable for the defendant to keep the benefit of the service without
paying a reasonable sum for it”.7 There are, they said, “three basic elements of
unjust enrichment”, subject to any available defence. The first is that the
defendant must receive a benefit. The second is that the benefit must be received
at the plaintiff’s expense. The third is that it would be unconscionable for the
defendant to retain the benefit. They discussed “incontrovertible benefit” and
“free acceptance”.
[40] As to the former, they said (at [73]–[76]):
[73] The first point that may be noted was that the services provided by Builders saved
the Lumbers from an expense. A significant part of Builders’ claim is for expenses that
it incurred during the course of the construction, in addition to the part of Builders’
claim relating to its own provision of services. These expenses were incurred on the
Lumbers’ behalf.
[74] However, even that portion of Builders’ claim which pertains to the cost of the
services it provided directly, can be characterised as saving the Lumbers from an
expense. The Lumbers decided to construct a house, and expected to pay the full
amount for its construction. The cost of the construction of the house, including the
expenses incurred by Builders, and the cost of the services provided directly by
Builders, was a cost that the Lumbers chose to incur. Builders, by incurring costs on
their behalf and providing services, saved the Lumbers from an expense that they would
otherwise have incurred.
[75] Secondly, we consider that having the house constructed was an incontrovertible
benefit independently of the question whether this saved the Lumbers from an expense.
The provision of a house in which to live, which also represented an improvement to
the land, conferred a benefit which no reasonable person could deny. The Lumbers have
had a house constructed to their specifications and are able to live in that house. The
Lumbers have also had an improvement to their land which has a realisable value upon
sale.
[76] It is also true that the Lumbers intended that the constructed house would have the
“pedigree” associated with having been constructed by Sons, a reputable and
established firm. However, the fact that they did not receive the benefit of the
“pedigree” of the house does not render the benefits they did in fact receive any less
valuable, given the matters referred to above.
[41] As to the latter, they said (at [83]–[85] references omitted):
[83] In this case, Builders incurred actual expenses from which the Lumbers benefited.
There was acceptance by the Lumbers of the services of subcontractors for which
Builders incurred a cost. Furthermore, the services provided were with the knowledge
of Lumbers. The Lumbers benefited. The benefit was conferred at the expense of
Builders. The Lumbers agreed to the work being carried out. The Lumbers, by moving
in and occupying the house, accepted the benefit. The Lumbers knew that the services
were not being provided gratuitously, as they had made a request to Sons for the
provision of the services, and had made arrangements for payment with David
McAdam.

7. Compare Monks v Poynice Pty Ltd (1987) 8 NSWLR 662.


424 AUSTRALIAN LAW REPORTS HCA

[84] The only factor which could be said to vitiate the free acceptance by the Lumbers
is the fact that they were unaware that the work was being conducted by Builders rather
than Sons. The fact that Warwick Lumbers said he would not have accepted the benefit
if he had known Builders was doing the work, and because he relied on Sons’ name and
the fact that Sons was licensed and, therefore, insured is, in our view, ultimately not to
the point. There has been no suggestion that there was any difference in the quality of 5
the construction of the house as a consequence of its having been built by Builders
rather than Sons. In this regard, it is relevant that Jeffrey Cook acted as the supervisor.
Also, David McAdam acted as the administrator of the building work and was
responsible for sourcing materials and labour in the same way, presumably, that he
would have been had the project been on the books of Sons rather than Builders. There 10
was no suggestion that the house would have been built differently, or to a higher
standard, had Sons completed the project. Indeed, the evidence of the [Lumbers] was
that externally, there was nothing to indicate that it was Builders that was building the
house rather than Sons. The fact that the Lumbers were mistaken about who provided
the benefit does not vitiate their acceptance of it.
[85] It should be noted that the conduct of Builders and Sons in failing to inform the
15
Lumbers about their internal arrangements is not inconsequential. Builders is unable to
recover the contractual sum to which Sons would have been entitled had it completed
the work. Instead, Builders can recover solely on a quantum meruit basis, as identified
above.
20
[42] The majority went on to find that it was clear that the provision of services,
and the payments to subcontractors, were at Builders’ expense and that it would
be unconscionable for the Lumbers to retain the benefit without payment.
[43] Vanstone J, dissenting, said that there was no free acceptance of, or
conferring of, any benefit. There was a contract between the Lumbers and Sons, 25
and another contract between Sons and Builders. Builders’ work on the Lumbers’
project was performed under obligations owed by Builders to Sons. Its remedies
lay under its contract with Sons. It had no additional or alternative restitutionary
claim against the Lumbers.
[44] For the reasons that follow, the conclusion of Vanstone J is to be preferred. 30
The restitutionary claim
[45] In considering Builders’ restitutionary claim, the contractual relations
between the Lumbers and Sons, and between Sons and Builders, cannot be put
to one side as an inconvenient distraction. The original structure of the litigation 35
has been described above. The circumstances that, by reason of a failure on the
part of Builders to comply with an order for security for costs, Sons has taken no
active part in the litigation, and that, by reason of the absence of any evidence
from Mr McAdam, what went on between Sons and Builders is obscure, do not
displace the necessity of identifying the contractual position. The case was 40
conducted and decided in the South Australian courts on the basis that,
as Builders alleged, there was a contract between the Lumbers and Sons. Builders
claimed that there was an assignment to it by Sons of the benefit of that contract.
That claim failed. The primary judge held that the work performed by Builders
was performed pursuant to a further contract which was made between Sons and 45
Builders; a contract that was entered into without the knowledge of the Lumbers.
That finding was not reversed in the Full Court, although it is not clear how the
majority accommodated it to their reasoning. It was adopted by Vanstone J.
The finding should be accepted. No reason has been shown to doubt that it was
correct. As the trial judge pointed out, once the possibility of assignment is 50
rejected, and in the absence of any suggestion of novation, the characterisation of
247 ALR 412 LUMBERS v W COOK BUILDERS (Gleeson CJ) 425

the “arrangements” between Sons and Builders as a contract is appropriate.


Even if the conduct of Sons in making such a contract and thereby delegating the
performance of its obligations amounted to a breach of its contract with the
Lumbers, the contract between the Lumbers and Sons remained in force.
There was, therefore, a head contract between the Lumbers and Sons, and a
subcontract between Sons and Builders.
[46] So far as appears from the evidence, Builders had, and may still have,
a viable claim against Sons. The claim was not defeated on the merits or
otherwise in any relevant respect rendered worthless. Builders and Sons have
their own separate creditors and members. The contractual arrangements that
were made effected a certain allocation of risk; and there is no occasion to disturb
or interfere with that allocation. On the contrary, there is every reason to respect
it. There was no mistake or misunderstanding on the part of Builders. It was
accepted on both sides in argument that in the ordinary case a building
subcontractor does not have a restitutionary claim against a property owner, but
must look for payment to the head contractor.8 That was said to be subject to
exceptions,9 but the difficulty for Builders was to show that the case fell within
any recognised exception or within general principles justifying a new exception.
[47] In Pan Ocean Shipping Co Ltd v Creditcorp Ltd,10 Lord Goff of Chieveley
said:
I am of course well aware that writers on the law of restitution have been exploring
the possibility that, in exceptional circumstances, a plaintiff may have a claim in
restitution when he has conferred a benefit on the defendant in the course of performing
an obligation to a third party (see, eg, Goff and Jones on the Law of Restitution,
4th ed (1993), pp 55 et seq, and (for a particular example) Burrows on the Law of
Restitution, (1993) pp 271–272). But, quite apart from the fact that the existence of a
remedy in restitution in such circumstances must still be regarded as a matter of debate,
it is always recognised that serious difficulties arise if the law seeks to expand the law
of restitution to redistribute risks for which provision has been made under an
applicable contract.

[48] In some Australian jurisdictions, there has been legislation enacted to


protect the interests of building subcontractors, but such protection is confined
within a certain statutory framework.11 The fact that such legislation exists
should discourage, rather than encourage, attempts to extend the scope of
restitutionary claims beyond the bounds set by legal principle,12 especially where
to do so would be to cut across or disturb contractual relationships and
established allocation of risk.
[49] To repeat, Builders’ services were not performed at the request of the
Lumbers, but pursuant to a contact between Sons and Builders. There was no
acquiescence by the Lumbers in the provision of services by Builders.
The Lumbers were unaware of the existence or role of Builders. As far as they

8. Hampton v Glamorgan County Council [1917] AC 13.


9. See Restatement of the Law: Restitution and Unjust Enrichment, 3d, Tentative Draft No 3,
2004, §29.
10. [1994] 1 All ER 470 at 475; [1994] 1 WLR 161 at 166.
11. For example, Worker’s Liens Act 1893 (SA); Subcontractors’ Charges Act 1974 (Qld).
12. Compare Photo Production Ltd v Securicor Transport Ltd [1980] AC 827 at 843; [1980]
1 All ER 556 at 561; Esso Australia Resources Ltd v FCT (1999) 201 CLR 49 at 62 [24];
168 ALR 123 at 131; [1999] HCA 67.
426 AUSTRALIAN LAW REPORTS HCA

were concerned, the services were being provided by Sons under the building
contract. That was not provision of services for the protection of the Lumbers’
property.
[50] The majority in the Full Court decided the case on the basis that Builders
performed services that conferred an incontrovertible benefit on the Lumbers, 5
and that it would be unconscionable for the Lumbers to keep the benefit of those
services without paying a reasonable sum for them. In their application to the
facts of the present case, each of the two elements in that proposition should be
rejected.
10
[51] As to the concept of conferring of benefit, what was involved was the
performance of building work on property owned by the Lumbers in
circumstances where there was a building contract between the Lumbers and
Sons obliging Sons to perform that work and the Lumbers to pay Sons for it,
and a subcontract between Sons and Builders obliging Builders to perform the
15
work and Sons to pay Builders. As it happens, there was no material difference
between the total price to be paid under the contracts. However, the case for
Builders can be tested by supposing that there had been such a difference.
Furthermore, the unusual agreement as to progress payments made between the
Lumbers and Sons, an agreement that was closely connected with the personal
20
relationship between Mr Warwick Lumbers and Mr McAdam, highlights the
significance of the 1993 contract as, from the point of view of the Lumbers, the
source of their legal rights and obligations. In Steele v Tardiani,13 which in one
sense was a simpler case than the present because there was only one contact
involved, Dixon J explained the problems of identifying, for the purpose of a
25
quantum meruit claim not based on the contract, a “benefit” conferred on a
building owner by the performance of work otherwise than in accordance with
the contract. He accepted that, where building work is done outside the contract,
and the benefit of the work is taken, there may arise an obligation to pay for the
work. He went on to refer, however, to “the dilemma in which a building owner
30
is placed”. He quoted Collins LJ, who said, in Sumpter v Hedges:14
Where, as in the case of work done on land, the circumstances are such as to give the
defendant no option whether he will take the benefit of the work or not, then one must
look to other facts than the mere taking the benefit of the work in order to ground the
inference of a new contract … The mere fact that a defendant is in possession of what
35
he cannot help keeping, or even has done work upon it, affords no ground for such an
inference.
[52] The reference to an “inference of a new contract” may reflect an approach
since overtaken by Pavey & Matthews, but the problem involved in identifying
a conferring or accepting of a benefit remains. 40
[53] The concept of “free acceptance” invoked by the majority in the Full
Court, whatever its exact scope, is commonly related to a defendant who “did not
take a reasonable opportunity open to him to reject the proffered services”.15 That
was not the situation of the Lumbers in the present case. Similarly, what was
sought to be characterised as an “incontrovertible benefit” was that which Sons 45
had undertaken to provide for the Lumbers and for which the Lumbers had

13. (1946) 72 CLR 386 at 402–3; [1946] HCA 21.


14. [1898] 1 QB 673 at 676.
15. Compare R L A Goff and G H Jones, The Law of Restitution, 7th ed, Sweet & Maxwell, 50
London, 2007, at [1–019].
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 427

agreed to pay Sons. If the principle relied upon by Builders extends to the claim
by Builders against the Lumbers, it is difficult to see why it would not extend also
to the work performed by the numerous subcontractors engaged by Sons and later
by Builders. Much, perhaps most, of the physical construction work on the site
was performed, and many of the physical materials brought to the site were
supplied, by such subcontractors. Why Builders was in a different position from
them vis-à-vis the Lumbers was not explained. In a broad colloquial sense, they
were conferring benefits on the Lumbers, and the Lumbers were accepting those
benefits, but that was not so in any legal sense.
[54] It was argued that the Lumbers had received a “windfall” and that it would
be unconscionable of them to refuse to pay Builders for the work in question.
This characterisation proceeds upon assumptions as to the respective rights and
obligations of the Lumbers, Sons and Builders which, for reasons already stated,
have not been justified. In so far as the Lumbers have been relieved from liability
to pay the full agreed price for the work done on their property, it appears
principally to be the consequence of Builders’ failure to make or pursue a prompt
claim against Sons, and Builders’ failure to pursue its claim against Sons in the
present proceedings. If that claim had been pursued, it may well have resulted in
a claim by Sons against the Lumbers. Alternatively, it may be the consequence
of the unexplained attitude of Sons in the letter written by Mr Malcolm Cook in
early 1999. The procedural and evidentiary deficiencies in the case make it
impossible to conclude that the conduct of the Lumbers in refusing to pay
Builders is unconscionable. If they have been enriched, it is at the expense of
Sons. If any party has been enriched at the expense of Builders, it is Sons.
[55] The restitutionary claim of Builders has not been made out.
Builders Licensing Act
[56] In view of the conclusion reached above, it is unnecessary to consider the
defence based on s 39 of this Act.
Conclusion
[57] The appeal should be allowed. The orders of the Full Court of the Supreme
Court of South Australia should be set aside and in their place it should be
ordered that the appeal to that court be dismissed with costs. The respondent
should pay the costs of the appellants of the appeal to this court.
[58] Gummow, Hayne, Crennan and Kiefel JJ. Between about February
1994 and April or May 1995 a house was built in a suburb of Adelaide. The house
was large, of unusual design, and expensive. The respondent, W Cook Builders
Pty Ltd (in liq) (Builders) claims that the appellants — the Lumbers — have not
paid all that should be paid for building the house. That claim was first made by
the liquidator of Builders more than 4 years after the building work was
completed.
[59] The first appellant, Mr Matthew Lumbers, owned the land on which the
house was built. He granted his father, the second appellant, an unregistered lease
of the property for life. It was the father, Mr Warwick Lumbers, who had most
of the dealings about building the house, but for the most part it will not be
necessary to distinguish between the appellants.
[60] The Lumbers say that they never had any dealings with Builders. They say
their dealings were with a different company — W Cook & Sons Pty Ltd (Sons)
— and that they have paid Sons all that Sons has ever asked them to pay.
428 AUSTRALIAN LAW REPORTS HCA

The Lumbers first became aware of Builders, and of the claimed involvement of
Builders in the matter, in August 1998, more than 3 years after the building work
was completed.
[61] It is not, and never has been, disputed that the Lumbers agreed with Sons
that Sons would build the house. Neither that agreement, nor any of the other 5
agreements or arrangements to which it will be necessary to refer, was reduced
to writing. The agreement the Lumbers made with Sons about building the house
was constituted by conversations between Mr Warwick Lumbers and a Mr David
McAdam. It is not, and never has been, disputed that Mr McAdam was then
10
acting on behalf of Sons or that the conversations constituted an agreement for
Sons to build the house according to the design and instructions of a named
architect. No price was fixed for the work. It was agreed that Sons would be paid
“cost plus”. Yet it is Builders, not Sons, who now claims for the balance of the
price of the work of building the house. These reasons will show that Builders’ 15
claim fails.
[62] Work was performed by subcontractors. But it should be indicated at once
that this was not a case where by reason of supervening events, such as the
insolvency of the head contractor, an unpaid subcontractor seeks to recover by
direct action against the owner, whether under a “mechanics’ lien” statute such as 20
the Worker’s Liens Act 1893 (SA) or under the general law.16 Further, Builders
made no claim under that statute as a subcontractor of Sons.
[63] Neither the issues that are to be decided in this appeal, nor the way in
which those issues are decided, can be understood without first observing some
25
features of the way in which the litigation developed.

Builders’ pleaded case


[64] Builders brought proceedings in the District Court of South Australia
against not only the Lumbers but also Sons. By its pleading, Builders made 30
claims in contract and in “Restitution/Unjust Enrichment”. It made some other
claims as well, including a claim to enforce a lien under the Worker’s Liens Act
as a “contractor”,17 but it will not be necessary to examine those other claims.
[65] Builders alleged in its pleading that the Lumbers (or one of them) had
made an oral building contract with Sons. Builders further alleged that, some 35
months after the Lumbers had made their contract with Sons, Builders made an
oral contract with Sons by which the benefit of Sons’ contract with the Lumbers
was assigned to Builders, and Builders was obliged (to Sons) to perform the work
that had to be done under the Lumbers contract with Sons. Builders pleaded that,
as a result of the agreement between the Lumbers and Sons, and the subsequent 40
agreement between Builders and Sons, either the Lumbers were (or one of them
was) liable to Builders on the basis that the building contract had been assigned
to Builders or, if the building contract had not been assigned, the Lumbers were

16. Compare Hampton v Glamorgan County Council [1917] AC 13; Winterton Constructions 45
Pty Ltd v Hambros Australia Ltd (1991) 101 ALR 363 (Winterton Constructions); Pan Ocean
Shipping Co Ltd v Creditcorp Ltd [1994] 1 All ER 470; [1994] 1 WLR 161 (Pan Ocean
Shipping Co); P Watts, “Does a subcontractor have restitutionary rights against the employer?”,
(1995) LMCLQ 398.
17. Defined in s 2 of the Worker’s Liens Act 1893 (SA) as “a person (not being a sub-contractor)
contracting with or employed by another person to do work, or to procure work to be done, or to 50
furnish materials in connection with work” (emphasis added).
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 429

(or one of them was) liable to Sons. If the Lumbers’ liability was to Sons,
Builders alleged that Sons was liable to Builders for the amount owing under the
building contract.
[66] Builders pleaded claims in “Restitution/Unjust Enrichment” against the
Lumbers and alternative claims against Sons. As against the Lumbers, Builders
alleged that they received the benefit of the completed house “at the expense of”
Builders (because it, Builders, had done the work) and alleged that “[i]t would be
unconscionable, unconscientious and unjust” for the Lumbers “to accept such
benefits without making payment of the full value of the construction work
carried out on the land”.
[67] Builders’ claim in “Restitution/Unjust Enrichment” against Sons took
generally the same form as the claim against the Lumbers. But on this branch of
its claim, Builders alleged that the benefit which Sons had received was Sons’
right to sue the Lumbers for the price of the work done, and Sons having met its
contractual obligations to perform the building contract. Again, Builders alleged
that this benefit was obtained at the expense of Builders because Builders did the
work and paid for it, and it was said to be “unconscionable, unconscientious and
unjust” for Sons to retain that benefit without making payment to Builders.
The pleading, which was not settled by counsel, failed to specify with the
necessary clarity the material facts upon which Builders relied to demonstrate
that conclusion in law. The pleading was embarrassing in the technical sense of
that term.18 This deficiency in the pleading by Builders of its case has contributed
to difficulties apparent at all subsequent stages in the litigation.
The Lumbers’ defences
[68] As noted earlier, the Lumbers admitted that they had made a building
contract with Sons. They denied any knowledge of the alleged agreement or
arrangement between Builders and Sons. The Lumbers alleged that Builders was
not licensed under the Builders Licensing Act 1986 (SA) (in force at the time of
building) or the Building Work Contractors Act 1995 (SA) (which later repealed
and replaced the earlier Act) and that, by operation of one or other of those Acts,
Builders was precluded from recovering “any fee or other consideration in
respect of the building work”19 unless the failure to hold and maintain a licence
was inadvertent, which the Lumbers alleged was not the case here.
[69] The Lumbers counterclaimed for damages, for allegedly defective work,
but the detail of that counterclaim need not be examined.
Builders’ case at trial
[70] Builders’ case at trial was much affected by the fact that, before trial, Sons
obtained an order requiring Builders to provide security for its costs. Builders did
not provide that security, and further proceedings by Builders against Sons were
then stayed. The case that Builders prosecuted at trial was, therefore, radically
different from the case which it had pleaded. The case which Builders had
pleaded had made alternative claims against the Lumbers and Sons. The case
which Builders prosecuted at trial made claims only against the Lumbers.

18. Winterton Constructions at 375–6.


19. Section 39 of the Builders Licensing Act 1986 (SA); compare s 6(2) of the Building Work
Contractors Act 1995 (SA) — “fee, other consideration or compensation under or in relation to
a contract”.
430 AUSTRALIAN LAW REPORTS HCA

[71] At trial, the chief weight of argument on behalf of Builders was placed
upon its contention that Builders and Sons had made a contract by which Sons
assigned the benefit of its building contract with the Lumbers to Builders. The
Lumbers denied any knowledge of the arrangements which it was alleged had
been made between Builders and Sons; there was no evidence to the contrary. 5
Builders’ assignment argument failed and its claims against the Lumbers were
dismissed.
Builders’ case in the Full Court
[72] On appeal to the Full Court of the Supreme Court of South Australia there 10
was a marked shift in the way in which Builders put its case. Chief weight was
then placed upon its restitution claim against the Lumbers. A majority of the
Full Court (Sulan and Layton JJ; Vanstone J dissenting) held that the restitution
claim should succeed.20 The majority concluded that the Lumbers had received
“an incontrovertible benefit”21 which the Lumbers had freely accepted,22 that the 15
benefit was received at Builders’ expense,23 and that it would be unconscionable
for the Lumbers to retain the benefit without paying for it.24 That Builders was
not licensed under the Builders Licensing Act, and that the failure to hold a
licence was not inadvertent, was held25 not to preclude its recovering the sum it
claimed from the Lumbers. 20
[73] Builders’ appeal, therefore, was allowed. The judgment entered at trial in
favour of the Lumbers was set aside and judgment entered for Builders.
[74] It is against those orders that the Lumbers now appeal to this court. The
appeal to this court should be allowed, and orders made restoring the judgment
entered at trial dismissing Builders’ claims against the Lumbers. 25
The framework for analysis
[75] The analysis undertaken by the majority in the Full Court proceeded from
principles stated at a high level of abstraction. There were four elements in the
framework of the analysis made by the Full Court: “benefit” (or “incontrovertible 30
benefit”),26 “acceptance” (or “free acceptance”),27 “expense” and
unconscionability. Obviously, much turns on what is meant by those terms and

20. W Cook Builders Pty Ltd (in liq) v Lumbers (2007) 96 SASR 406; [2007] SASC 20 (W Cook
Builders). 35
21. W Cook Builders at 422 [75].
22. W Cook Builders at 423–4 [83]–[84].
23. W Cook Builders at 424 [86].
24. W Cook Builders at 426 [95].
25. W Cook Builders at 426 [99]–[100].
26. The word “incontrovertible” has been used in this context to direct attention to whether what
has been done results in an accretion to the defendant’s wealth. As Beatson pointed out in
40
A G Guest et al (eds), Chitty on Contracts, 26th ed, Sweet & Maxwell, London, 1989, vol 1,
p 1317 [2040]: “[i]n the case of the rendering of services as opposed to the payment of money,
‘the identity and value of the resulting benefit to the recipient may be debatable’
[BP Exploration Co (Libya) Ltd v Hunt (No 2) [1982] 1 All ER 925 at 937; [1979] 1 WLR 783
at 799]”.
27. The word “free” has been used in this context to direct attention to whether the recipient of a 45
benefit had an opportunity to accept or reject the benefit. Compare Munro v Butt (1858)
8 E & B 738; 120 ER 275; Sumpter v Hedges [1898] 1 QB 673; Forman & Co Pty Ltd v Ship
“Liddesdale” [1900] AC 190. Writing in successive editions of Chitty, Beatson suggested that
English law “appears hostile to claims for services rendered or work done in the absence of a
contract (express or implied) between the parties [and that] [t]he mere receipt of a benefit, when
the defendant had no real option to accept or reject it, does not justify a claim for quantum 50
meruit” (footnotes omitted). See Chitty, 25th ed, 1983, vol 1, p 1153 [2050]; 26th ed, 1989,
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 431

upon what are the features said to make retention of the “benefit”
unconscionable. Adding words like “incontrovertible” and “free” to some of the
terms emphasises the evident difficulties of definition. As is especially relevant
here, much also turns on the particular facts and circumstances to which the terms
are to be applied. None of the terms “benefit”, “acceptance” or “expense” can
usefully be defined or applied without deciding whether attention is to be
confined to the party who is identified as conferring the benefit and the recipient
of that benefit, or account must be taken of the legal relationships that exist
between one or other of those two parties and some third party or parties in
relation to the events and transactions said to constitute conferring a “benefit”, its
“acceptance”, or the incurrence of “expense”.
[76] In the present case, the majority in the Full Court directed principal
attention to the relationship which it was held should be found to exist between
Builders and the Lumbers. The legal relationship between the Lumbers and Sons
was put to one side. Two bases for taking that step were identified. First, it was
said28 that Sons “did not perform its obligations” under its contract with the
Lumbers. It was said29 to be “not to the point for the Lumbers to claim that they
are not liable to Builders because they have a contract with Sons, if Sons did not
perform their part of the contract”. Secondly, emphasis was given to the fact that
Sons had acknowledged30 that it has no claim against the Lumbers. The majority
in the Full Court concluded31 that in these circumstances “to uphold a claim in
restitution by Builders in no way interferes with the contractual relationship
between Sons and the Lumbers”.
[77] These reasons will demonstrate that the legal relationship between Sons
and the Lumbers cannot be dismissed from consideration, whether on the bases
assigned by the majority in the Full Court or otherwise. When proper account is
taken of the rights and obligations that existed between Sons and the Lumbers
under their contract, the analysis made by the majority in the Full Court is shown
to be flawed. The Lumbers are not shown to have received a “benefit” at
Builders’ “expense” which they “accepted”, and which it would be
unconscionable for them to retain without payment. No less importantly, proper
analysis of the legal relationships revealed by the evidence will illustrate the
dangers inherent in “top-down reasoning”.32
[78] The application of a framework for analysis expressed only at the level of
abstraction adopted in this case, by reference to “benefit”, “expense” and
“acceptance”, coupled with considerations of unconscionability, creates a serious
risk of producing a result that is discordant with accepted principle, thus creating
a lack of coherence with other branches of the law.33 There are two reasons of
particular relevance to this case why that is so. They may be identified by

vol 1, pp 1408–9 [2145]; 27th ed, 1994, vol 1, p 1490 [29–127]; 28th ed, 1999, vol 1,
p 1564 [30–186]; compare 29th ed, 2004, vol 1, pp 1698 [29–109] and 1708 [29–131].
28. W Cook Builders at 416 [45].
29. W Cook Builders at 416 [47].
30. W Cook Builders at 416 [45].
31. W Cook Builders at 416 [45].
32. Roxborough v Rothmans of Pall Mall (2001) 208 CLR 516 at 544 [73]; 185 ALR 335 at 355;
[2001] HCA 68 per Gummow J; McGinty v Western Australia (1996) 186 CLR 140 at 232;
134 ALR 289 at 345; [1995] HCA 46 per McHugh J.
33. See Sullivan v Moody (2001) 207 CLR 562 at 580–1 [53]–[55]; 183 ALR 404 at 416;
28 Fam LR 104 at 116; [2001] HCA 59 per Gleeson CJ, Gaudron, McHugh, Hayne and
Callinan JJ.
432 AUSTRALIAN LAW REPORTS HCA

reference to two questions which, although expressed separately, will later be


seen to intersect in several ways. First, does applying the posited framework for
analysis to the facts of the present case extend the availability of recovery beyond
the circumstances in which a claim for work and labour done (or money paid) for
and at the request of the defendant would be available? Secondly, and no less 5
importantly, how is the result of applying this framework for analysis consistent
with the obligations relevant parties undertook by their contractual
arrangements?
[79] The doing of work, or payment of money, for and at the request of another,
10
are archetypal cases in which it may be said that a person receives a “benefit” at
the “expense” of another which the recipient “accepts” and which it would be
unconscionable for the recipient to retain without payment. And as is well
apparent from this court’s decision in Steele v Tardiani,34 an essential step in
considering a claim in quantum meruit (or money paid) is to ask whether and how
15
that claim fits with any particular contract the parties have made. It is essential
to consider how the claim fits with contracts the parties have made because, as
Lord Goff of Chieveley rightly warned in Pan Ocean Shipping Co,35 “serious
difficulties arise if the law seeks to expand the law of restitution to redistribute
risks for which provision has been made under an applicable contract”. In a
20
similar vein, in the comments upon §29 of the proposed Restatement (3d),
“Restitution and Unjust Enrichment”,36 the reporter says:
Even if restitution is the claimant’s only recourse, a claim under this Section will be
denied where the imposition of a liability in restitution would overturn an existing
allocation of risk or limitation of liability previously established by contract. 25
[80] Likewise, it is essential to consider whether the facts of the present case
yield to analysis as a claim for work and labour done, or money paid, because
where one party (in this case, Builders) seeks recompense from another (here the
Lumbers) for some service done or benefit conferred by the first party for or on
the other, the bare fact of conferral of the benefit or provision of the service does 30
not suffice to establish an entitlement to recovery. As Bowen LJ said in Falcke v
Scottish Imperial Insurance Co:37
The general principle is, beyond all question, that work and labour done or money
expended by one man to preserve or benefit the property of another do not according
35
to English law create any lien upon the property saved or benefited, nor, even if standing
alone, create any obligation to repay the expenditure. Liabilities are not to be forced
upon people behind their backs any more than you can confer a benefit upon a man
against his will. [Emphasis added.]
The principle is not unqualified. Bowen LJ identified38 salvage in maritime law 40
as one qualification. Other cases, including other cases of necessitous
intervention, may now be seen as further qualifications to the principle, but it is
not necessary to examine in this case how extensive are those further
qualifications or what is their content. For the purposes of this case the critical
observations to make are, first, that Builders’ restitutionary claim does not yield 45

34. (1946) 72 CLR 386; [1946] HCA 21.


35. Pan Ocean Shipping Co at All ER 475; WLR 166.
36. Tentative Draft No 3, 22 March 2004. Section 29 deals with the topic of restitution in cases of
“Self-Interested Intervention”.
37. (1886) 34 Ch D 234 at 248 (Falcke). 50
38. Falcke at 248.
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 433

to analysis as a claim for work and labour done or money paid and, secondly, that
Builders’ restitutionary claim, if allowed, would redistribute not only the risks but
also the rights and obligations for which provision was made by the contract the
Lumbers made with Sons.

A claim for work and labour done or money paid?


[81] At trial, Builders did not frame its claim against the Lumbers as a claim
for work and labour done or money paid at the Lumbers’ request. Builders,
therefore, did not seek to prove that the Lumbers had ever asked Builders to do
whatever Builders did in connection with building the Lumbers’ house. And the
evidence that was led at trial showed that the Lumbers had never asked Builders
to do anything in connection with the Lumbers’ house.
[82] On the hearing of the appeal to this court, however, Builders submitted
that acceptance of a benefit, without a request, would be sufficient, at least in this
case, to found an action by Builders for work and labour done or money paid.
Builders submitted that this conclusion was supported, if not required, by this
court’s decision in Pavey & Matthews Pty Ltd v Paul.39 That is not so.
[83] In Pavey & Matthews, a majority of this court held40 that the right to
recover on a quantum meruit does not depend on the existence of an implied
contract but on a claim to restitution or one based on unjust enrichment.
The concept of unjust enrichment was described41 by Deane J in Pavey &
Matthews as constituting:
… a unifying legal concept which explains why the law recognises, in a variety of
distinct categories of case, an obligation on the part of a defendant to make fair and just
restitution for a benefit derived at the expense of a plaintiff and which assists in the
determination, by the ordinary processes of legal reasoning, of the question whether the
law should, in justice, recognise such an obligation in a new or developing category
of case.
[84] It is important to recognise two points about Pavey & Matthews. First,
there was no issue in that case about whether the plaintiff, a builder, had a claim
for work and labour done and materials supplied. The issue in the case was
whether that claim was defeated by a statutory provision42 analogous to s 4 of the
Statute of Frauds 1677 (UK) (“no action shall be brought upon any agreement …
unless the agreement upon which such action shall be brought or some
memorandum or note thereof shall be in writing and signed by the party to be
charged therewith or some other person thereunto by him lawfully authorised”).
In particular, the issue was whether the builder’s action on a quantum meruit was
a direct or indirect enforcement of the oral contract the parties had made.
The majority in Pavey & Matthews held43 that because “the true foundation of
the right to recover on a quantum meruit does not depend on the existence of an
implied contract” the action was not “one by which the plaintiff seeks to enforce
the oral contract”.

39. (1987) 162 CLR 221; 69 ALR 577; [1987] HCA 5 (Pavey & Matthews).
40. Pavey & Matthews at CLR 227; ALR 582–3 per Mason and Wilson JJ, CLR 256–7; ALR 604
per Deane J.
41. Pavey & Matthews at CLR 256–7; ALR 604.
42. Section 45 of the Builders Licensing Act 1971 (NSW).
43. Pavey & Matthews at CLR 227; ALR 582–3 per Mason and Wilson JJ; see also at CLR 256;
ALR 604 per Deane J.
434 AUSTRALIAN LAW REPORTS HCA

[85] The second point to be noted is that unjust enrichment was identified as a
legal concept unifying “a variety of distinct categories of case”.44 It was not
identified as a principle which can be taken as a sufficient premise for direct
application in particular cases. Rather, as Deane J emphasised45 in Pavey &
Matthews, it is necessary to proceed by “the ordinary processes of legal 5
reasoning” and by reference to existing categories of cases in which an obligation
to pay compensation has been imposed. “To identify the basis of such actions as
restitution and not genuine agreement is not to assert a judicial discretion to do
whatever idiosyncratic notions of what is fair and just might dictate.”46 On the
10
contrary, what the recognition of the unifying concept does is to assist “in the
determination, by the ordinary processes of legal reasoning, of the question
whether the law should, in justice, recognise such an obligation in a new or
developing category of case” (emphasis added).47
[86] Builders’ submission that acceptance of a benefit, without a request, 15
suffices to found an action for work and labour done or money paid thus finds no
direct support in Pavey & Matthews. That issue did not arise and was not decided
in that case. Rather, the question to which Pavey & Matthews directs attention is
whether the long-established and well-recognised category of cases constituted
by claims for work and labour done or money paid at the request of another 20
should be extended or developed in the manner for which Builders contended.
And in that regard Builders emphasised what had been said by Doyle CJ, for the
Full Court of the Supreme Court of South Australia, in Angelopoulos v
Sabatino.48
25
[87] It is convenient to consider the decision in Angelopoulos by reference to
Builders’ submission that, subject to one immaterial qualification, all the nine
factors identified49 by Doyle CJ in Angelopoulos as relevant to “acceptance” of
a benefit, were present in this case. It is important, however, to preface that
consideration by observing that although Builders’ argument was directed 30
immediately to demonstrating that “acceptance” of a benefit suffices to found an
action for work and labour done or money paid, its arguments about the
availability of an action for work and labour done or money paid were directed
ultimately to the proposition that adopting the framework for analysis used by the
majority in the Full Court in this case was not inconsistent with long-established 35
principles governing actions for work and labour done or money paid.
[88] Adapting what was said by Doyle CJ in Angelopoulos to the facts of this
case, the nine factors identified by Builders as supporting its claim were:
(a) the plaintiff (here, Builders) did not do the work gratuitously;
40
(b) Builders did not act “entirely at [its] own initiative”50 but at the implied
request of the Lumbers;
(c) payment for doing the work was not subject to fulfilment of a
subsequent condition;
45
44. Pavey & Matthews at CLR 257; ALR 582–3 per Deane J.
45. Pavey & Matthews at CLR 257; ALR 582–3.
46. Pavey & Matthews at CLR 256; ALR 582 per Deane J.
47. Pavey & Matthews at CLR 257; ALR 604–5 per Deane J.
48. (1995) 65 SASR 1 (Angelopoulos).
49. Angelopoulos at 12–13. 50
50. Angelopoulos at 13.
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 435

(d) the work was not done “on a basis from which [Builders] chose to
depart”;51
(e) the Lumbers benefited from what Builders did;
(f) the benefit was conferred at the expense of Builders;
(g) the Lumbers “approved of or agreed to”52 Builders carrying out the
work it did;
(h) the circumstances were such that the Lumbers “must have known as …
reasonable [persons] that [Builders] expected to be remunerated for [its]
services”;53 and
(i) there is no particular circumstance (such as change of position) by virtue
of which it would be unjust to require the Lumbers to remunerate
Builders.
[89] It will be noted that the second of the matters identified was the making of
an “implied request” by the Lumbers to Builders to do the work and to pay
money. At once it should be pointed out that, if Builders did whatever work it did
and paid whatever money it paid at the Lumbers’ request, Builders’ claim for a
reasonable price for the work and for the money it paid would fall neatly within
long-established principles. It would matter not at all whether the request was
made expressly, or its making was to be implied from the actions of the parties
in the circumstances of the case.54 Builders would have an action for work and
labour done or money paid for and at the request of the Lumbers.
[90] And if Builders did work or paid money at the Lumbers’ request, it would
also follow that it would be neither necessary nor appropriate to consider any of
the other eight factors identified in Angelopoulos in deciding whether Builders
could recover a fair price for the work it had done and the amount it had paid for
and at the request of the Lumbers. To the extent that Angelopoulos is understood
as requiring separate or additional consideration of those other factors, where a
plaintiff seeks to recover a fair price for work done at the defendant’s request,
or the amount the plaintiff has paid for the defendant at the defendant’s request,
Angelopoulos is wrong and should not be followed.
[91] But in the end Builders did not submit that it could be found that the
Lumbers had made any request directed to Builders. Rather, Builders’ arguments
proceeded from the premise that, in the present case, the Lumbers’ request
(or requests) for work to be done and money paid was (or were) directed to Sons
and not to Builders. Although Builders thus accepted that, unlike Angelopoulos,
it could not be said that the Lumbers made any request directed to Builders,
this difference from Angelopoulos was said to be immaterial. The identity of the
party to whom the request was directed was said to be of no moment because
confusion about which company in a group of companies is party to a contract
is a common occurrence in modern corporate life.55 And although no case of
mistake was run at trial, or on appeal to the Full Court, the possibility of
confusion of identity between Sons and Builders was said by Builders to be

51. Angelopoulos at 13.


52. Angelopoulos at 13.
53. Angelopoulos at 13.
54. Birmingham and District Land Co v London and North Western Railway Co (1886)
34 Ch D 261 at 274 per Bowen LJ; Way v Latilla [1937] 3 All ER 759 at 765 per Lord Wright.
55. Compare Qintex Australia Finance Ltd v Schroders Australia Ltd (1990) 3 ACSR 267 at 268
(Qintex).
436 AUSTRALIAN LAW REPORTS HCA

reason enough to treat the fact of a request, regardless of the identity of the party
to whom the request was directed, as the relevant consideration.
[92] The propositions just described take several steps that would require the
closest consideration before they could be accepted. First, it may greatly be
doubted that any sufficient foundation was laid in the evidence adduced or 5
arguments advanced in the courts below for either an argument based in mistake
about the identity of the party with whom the Lumbers dealt, or an argument
based in some confusion of identity between Sons and Builders. Secondly, even
if it were to be accepted that confusion about the identity of the relevant
contracting parties can and sometimes does occur when a contract is made with 10
one of a group of companies, the legal consequences of any such confusion have
hitherto been determined by application of the law of contract and doctrines of
mistake.56
[93] It is not necessary, however, to pursue these aspects of the matter further.
Rather, it is important to recognise that, although expressed in different terms, 15
Builders’ argument that the identity of the party to whom the Lumbers directed
their request to do work and pay money should be dismissed as irrelevant, was
an argument that sought to treat the contract made between the Lumbers and Sons
as irrelevant.
[94] And it will be recalled that it was a necessary element of the reasoning of 20
the majority in the Full Court to put aside further consideration of the contract
between Sons and Lumbers. It will further be recalled that the majority in the
Full Court took that step on the bases, first, that Builders “did the work” and Sons
“did not perform its obligations” under its contract with the Lumbers, and
secondly, that Sons acknowledged it had no claim against the Lumbers. 25
[95] Both bases for putting aside the contract between Sons and Lumbers are
flawed.
Builders did the work?
30
[96] The first proposition made by the majority in the Full Court was expressed
in several different ways but each can be seen as a variant of a single compound
proposition: that “Builders did the work, and Sons did not”. To say that “Builders
did the work, and Sons did not” elides a number of different ideas. Neither
Builders nor Sons “did” any work. Each is a corporation. The work that was done
35
in the construction of the house, whether it was done at the building site or in an
office, was done by individuals. Before deciding which company “did” the work
it would be necessary to identify for which company the relevant individuals
were working. Here, as in so much else of the trial of this litigation, the evidence
was exiguous and such evidence as was adduced was less than clear.
40
[97] On any view of the matter, Mr McAdam was an important participant in
relevant events. He negotiated the original contract with the Lumbers. As noted
earlier, there was no dispute that he did this on behalf of Sons. But Mr McAdam
was also, so it seems, the originator of the idea that Builders should “take over”
the work on the Lumbers’ contract from Sons. And it was Mr McAdam who was 45
said to have made the agreement or arrangement between Builders and Sons that
Builders would “take over” the work, and it was he who then carried that
agreement or arrangement into effect. But neither side in the present litigation
called Mr McAdam to give evidence.
50
56. Qintex at 276–7.
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 437

[98] Such little evidence as was given about the relationships between Builders
and Sons was given by Mr Jeffrey Cook. Two aspects of those relationships
require examination: first, the corporate relationship between the two entities and
second, the agreement or arrangement made between them to effect a
“changeover” of the company that was to be responsible for the construction of
the Lumbers’ house.
[99] The evidence led at trial suggested that, in 1993, Sons was, and for many
years had been, the chief building company in a group of companies associated
with several members of the Cook family who were third or subsequent
generation descendants of the eponymous W Cook. The companies traced their
history to about 1910.
[100] Mr Jeffrey Cook was a director of Sons up to at least 1993, the year
before Sons made its contract with the Lumbers. At that time there were two
shareholders of Sons: an investment company associated with Mr Jeffrey Cook
and his family, and another investment company associated with another branch
of the Cook family. The shareholding and directorate of Builders were said to
differ from those of Sons, but no details of those differences were given in
evidence. In 1993, Mr Jeffrey Cook “sat at the top of the apex for managing the
building side of the business” of Sons. Sons also operated a joinery workshop and
in 1993 Mr Jeffrey Cook managed that part of the business as well.
[101] Mr McAdam began working in the Cook businesses in 1959. He was
appointed a director of Sons in 1964, the year in which it was incorporated.
In 1993, he was responsible for the financial and contract administration of Sons.
[102] At the start of 1994, Mr McAdam proposed to Mr Jeffrey Cook
“separating” the joinery business of Sons from its building business. Mr Cook
agreed that this should be done, and agreed that, “after the changeover”, building
work would be done by Builders (then a company which did not operate in any
way). This “changeover”, Mr Cook said, was done by book entries and took
effect from about April 1994. At trial he said that he understood the changeover
“was going to be effective in relation to probably the separation and then the
viability of keeping them [the joinery and the building businesses] separate to
make them more financial”. Mr Cook’s evidence-in-chief was that the so-called
“changeover” was effected “in the books”. He said that Sons carried out the work
on the Lumbers’ house until the changeover, but that after the changeover “[i]n
the books it was W. Cook Builders” (emphasis added).
[103] At the outset of the trial, counsel then appearing for the Lumbers
indicated that there was no dispute that “the subcontractors were, in fact, paid by
[Builders]”. Given that it was not disputed that the Lumbers had paid some
subcontractors directly, this statement of what was not disputed was expressed
too widely. Nonetheless, the conventional basis upon which the litigation has
been conducted at all stages is that Builders paid those subcontractors whom the
Lumbers did not pay.
[104] The books in which entries were made to effect the “changeover” about
which Mr Jeffrey Cook gave evidence were not tendered. No evidence was led
to show what happened, if anything, about employment contracts or bank
accounts. In particular, the trial judge was unable to say whether payments made
to subcontractors after the changeover were made from a separate bank account
of Builders or from what he described as “Cook Group funds, with the payments
being debited through journal entries to the Builders accounts”. As his Honour
went on to say:
438 AUSTRALIAN LAW REPORTS HCA

Externally … nothing appeared to have changed. The same employees, including


Mr Jeffrey Cook, continued with the building work. Mr McAdam continued to occupy
an office adjoining that of Mr Cook, and maintained direct contact with Mr Warwick
Lumbers. Neither Mr Jeffrey Cook nor Mr McAdam made any mention to the Lumbers
or the architect Mr Fielder of the existence of Builders, or even the re-organisation.
5
[105] As noted earlier, Mr Warwick Lumbers paid directly some subcontractors
who worked on the house. Otherwise, all payments made by the Lumbers were
directed to Sons; none was directed to Builders. The payments the Lumbers made
to Sons were made in response to oral requests by Mr McAdam. No written
progress claims or invoices were said to have been prepared or sent to the 10
Lumbers, whether on behalf of Sons or on behalf of Builders.
[106] There was a dispute at trial about what amount should be allowed for
supervision of the work that was done. (The claim for supervision was the largest
part of the claim that Builders made against the Lumbers.) The trial judge found
that 10% of cost was a fair allowance for supervision. This finding is not now 15
challenged and the dispute about the quantum of this aspect of the claim may be
put aside. But while the evidence at trial assumed that Mr Jeffrey Cook played an
important part in supervising the construction of the house, no evidence was led
of what he did, or of what were the arrangements pursuant to which he undertook
that work. 20
Who “did the work”?
[107] To say, in these circumstances, that Builders “did the work” obscures
what were the legal relationships that brought about the result described. The end
result described is as consistent with Builders having performed or procured 25
performance of the work in satisfaction of an obligation it owed to Sons, as it is
with Builders performing or procuring performance of the work in satisfaction of
an obligation it understood that it owed to the Lumbers. And if Builders
performed or procured performance of the work in satisfaction of an obligation
it owed to Sons, Sons thereby procured the performance of the obligation it owed 30
the Lumbers.
[108] Issues about the possible intersections between contractual arrangements,
on the one hand between Builders and Sons, and on the other between the
Lumbers and Sons, were not explored at trial. The evidence that was led at trial
required the conclusion, however, that whatever may have been the legal effect 35
of the arrangements which Mr McAdam had sought to effect between Builders
and Sons, and whatever it was that Builders later did in performance of those
arrangements, anything that Builders did in relation to the building of the
Lumbers’ house was done with the knowledge and assent of Sons.
[109] It is possible that the informality of the “changeover” arrangements 40
which Mr McAdam made was such that it could not be said that Builders and
Sons agreed upon terms to effect that “changeover” that were sufficiently certain
to be enforceable as a contract between Builders and Sons. If that were so, it may
not be apt to describe the relationship between those entities as a subcontract. It is
also possible, however, that despite the informality of the arrangement, 45
an enforceable agreement was reached that Builders would perform Sons’ work
under the Lumbers contract. Indeed, making such an agreement was an important
element in the assignment case Builders had advanced at trial.
[110] It is only in this court that Builders sought for the first time to advance
a different case and argue (under cover of a notice of contention) that the 50
arrangements between Builders and Sons were too uncertain to admit of
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 439

enforcement. It is too late for Builders to advance such a case.57 If the point had
been taken at trial different evidence may well have been adduced.
[111] In any event, however, if no concluded agreement was made between
Builders and Sons before work was done or money was paid, there is no doubt
that, if the work was done by Builders it was done at Sons’ request, or that,
if Builders paid money, it did so at Sons’ request. It follows that, if Builders did
work or paid money, it had a claim against Sons for work done and money paid
at Sons’ request. That is, if Builders did work or paid money, Builders could look
to Sons for payment for the work it did and the money it paid at the request of
Sons in performance of the building works which Sons had agreed to perform
under its contract with the Lumbers. However, if an enforceable contract were
made then no action would lie for a quantum meruit while the contract remained
on foot.58
[112] It also follows that, if Builders did work or paid money, Sons could point
to that work or that payment by Builders as done or paid in performance of Sons’
obligations to the Lumbers. Sons could do that because nothing in the evidence
suggested that Sons could not engage persons other than its employees to build
the Lumbers’ house. Such evidence as was led at trial suggested that,
in accordance with common building practice, both the Lumbers and Sons
assumed that subcontractors would be engaged to perform the work.
[113] It follows that the compound premise for the conclusions reached by the
majority in the Full Court, that “Builders did the work and Sons did not”,
obscured much more than it illuminated. To the extent that the proposition
identifies who paid subcontractors or material suppliers, it is a proposition that is
incomplete in relevant respects. It is incomplete because it does not identify what
were the legal relationships that governed those payments. Further, to the extent
that the proposition asserts that it was employees or subcontractors of Builders
who worked at the site of the Lumbers’ house, the proposition is again
incomplete in a relevant respect. It is incomplete to the extent that it does not
reflect the evidence led at trial that demonstrated that Sons procured Builders to
do the work that Sons had contracted to perform. It procured that result either by
making a contract with Builders to that effect or, if there was no contract,
by asking that Builders do it. And contrary to the conclusion reached by the
majority in the Full Court it follows that the evidence led at trial did not establish
that Sons had “failed” to do the work its contract with the Lumbers required it to
perform, or that Sons was otherwise in breach of its contract with the Lumbers
in any relevant respect.
[114] For these reasons, the first of the two bases on which the majority in the
Full Court put aside, as irrelevant, the legal relationship between the Lumbers
and Sons (that Builders did the work and Sons did not) is shown to be wrong.
What of the other basis relied on by the Full Court: Sons’ disavowal of any claim
against the Lumbers?
Sons makes no claim?
[115] By a letter dated 1 February 1999, signed by Mr Malcolm J Cook as a
director of Sons, Mr Warwick Lumbers was told that “there are no outstanding
amounts owing either by yourself, or any other person or entity, to [Sons] in

57. Water Board v Moustakas (1988) 180 CLR 491; 77 ALR 193; [1988] HCA 12.
58. Matthes v Carter (1955) 55 SR (NSW) 357 at 364; Gino D’Allesandro Constructions Pty Ltd
v Powis [1987] 2 Qd R 40 at 59.
440 AUSTRALIAN LAW REPORTS HCA

relation to the construction” of the Lumbers’ house. Reference was made in that
letter to “a restructuring of the company [Sons] in 1994” and to Mr Jeffrey Cook
taking over “all building & construction operations currently in progress,
operating as [Builders] … and [continuing] building operations until May 1998,
when [Builders] went into liquidation”. The letter said that “[a]ll invoicing & 5
receipts in relation to [the Lumbers’ house] (and all other building projects) were
through the accounts system of [Builders]”. The letter concluded by saying that
“Mr Jeffrey Cook has had no input into this reply” and that he had “had no
contact with [Sons] in relation to the day-to-day operations of the company, since
about May of 1998”. 10
[116] No evidence was led at trial about how or why this letter was written.
In particular, Mr Warwick Lumbers was not asked any question about how the
letter came about. Be this as it may, it is plain from the letter’s text that, at least
in February 1999, Sons made no claim to any further payment in respect of the 15
construction of the Lumbers’ house. And there was no evidence led at trial that
Sons had thereafter sought any further payment from the Lumbers.
[117] The majority in the Full Court treated the fact that Sons has made no
claim for further payment from the Lumbers as bearing upon whether allowing
a claim in restitution by Builders “interferes with the contractual relationship 20
between Sons and the Lumbers”.59 But the absence of any claim by Sons against
the Lumbers does not, without more, say anything about the nature or the content
of the contractual relationship between Sons and the Lumbers. And the absence
of a claim by Sons does not demonstrate, as the majority in the Full Court
assumed, that the Lumbers would obtain some “windfall” unless the Lumbers 25
were found liable to Builders.
[118] It is necessary to say something more about both the relevance of the
contractual relationship between Sons and the Lumbers and about the notion of
“windfall”. Because the two matters are related it will be convenient to begin by 30
saying something about the notion of “windfall”.
[119] An important element in the reasoning of the majority in the Full Court
was that if the Lumbers were not held liable to Builders they would have obtained
a house for which they had not paid enough. The amount paid was characterised
as not “enough” by taking the amount that had been outlaid for subcontractors 35
and materials, adding an amount for supervision and the agreed profit margin,
and comparing that with the total payments made by the Lumbers. And because
the total of outlays, supervision, and profit exceeded the total payments made,
it was said that the Lumbers would receive a “benefit”, a “gain” or a “windfall”
if they were not found to be liable to Builders. 40
[120] The accuracy and the relevance of any such characterisation depends
upon whether the Lumbers had performed their obligations under their contract
with Sons. If the Lumbers have not fully performed their obligations under their
contract with Sons, by not paying all that is due to Sons, it is evident that the 45
Lumbers have not received any benefit, gain or windfall. They would remain
liable to Sons. Questions of benefit, gain or windfall could arise only if Sons has
no further claim against the Lumbers. Two possible bases for the conclusion that
Sons has no further claim against Lumbers should be examined.
50
59. W Cook Builders at 416 [45].
247 ALR 412 LUMBERS v W COOK BUILDERS (Gummow J et al) 441

[121] If the Lumbers have paid all that they owe Sons under the agreement they
made with Sons, it may then be possible to say that Sons made an improvident
bargain. But whether that description of the bargain is apt is not now relevant.
What is presently important would be the conclusion that the Lumbers have
satisfied their obligations to Sons, not any commercial characterisation of the
bargain. Yet as earlier explained, notions of “benefit”, “gain” or “windfall”
employed in this case do not depend upon an analysis of the legal obligations of
the parties. They seek to invoke some broader economic analysis comparing the
“worth” or “value” of the end product (determined by totalling the outlays made
to construct the house) with the amount the Lumbers have paid.
[122] If, on the other hand, the Lumbers have not paid Sons all that Sons could
lawfully demand under the agreement between the Lumbers and Sons, there may
be some question about the legal effect of the letter written on behalf of Sons.
If that letter were to be held to now stand in the way of Sons recovering amounts
otherwise due under the agreement, the sending of the letter may again be
described as improvident or commercially unwise. But again, such a
characterisation of the letter is not to the point. If the letter does provide an
impediment to further recovery by Sons from the Lumbers, the Lumbers would
have obtained, in effect, a sufficient discharge from Sons of their obligations.
But no matter whether the Lumbers have paid all that they owe, or the letter
written by Sons presents some legal obstacle to Sons’ recovering further sums
owed by the Lumbers, it is not right to describe the result as one in which the
Lumbers have in any sense obtained a “windfall”. The economic result arrived at
follows either from the bargain that Sons made with them, or from the way in
which Sons has subsequently dealt with that bargain. It is not a result that follows
from anything that the Lumbers sought to have Builders do or refrain from doing.
[123] For these reasons, the second of the bases upon which the majority in the
Full Court put aside from consideration the contractual obligations undertaken by
the Lumbers and Sons is also flawed.
The relevance of the contract between the Lumbers and Sons
[124] When account is taken of the contractual relationship between the
Lumbers and Sons several observations may then be made.
[125] First, the Lumbers accepted no benefit at the expense of Builders which
it would be unconscionable to retain. The Lumbers made a contract with Sons
which either has been fully performed by both parties or has not. Sons made an
arrangement or agreement with Builders which again has either been fully
performed or it has not. If either the agreement between Sons and the Lumbers
or the agreement or arrangement between Sons and Builders has not been fully
performed (because all that is owed by one party to the other has not been paid)
that is a matter between the parties to the relevant agreement. A failure of
performance of either agreement is no reason to conclude that Builders should
then have some claim against the Lumbers, parties with whom Builders has no
contract.
[126] Because Builders had no dealings with the Lumbers, Builders has no
claim against the Lumbers for the price of any work and labour Builders
performed or for any money that Builders may have paid in relation to the
construction. Builders has no such claim because it can point to no request by the
Lumbers directed to Builders that Builders do any work it did or pay any money
it did. Reference to whether the Lumbers “accepted” any work that Builders did
or “accepted” the benefit of any money it paid is irrelevant. It is irrelevant
442 AUSTRALIAN LAW REPORTS HCA

because it distracts attention from the legal relationships between the three
parties: the Lumbers, Sons and Builders. To now impose on the Lumbers an
obligation to pay Builders would constitute a radical alteration of the bargains the
parties struck and of the rights and obligations which each party thus assumed.
There is no warrant for doing that. 5
[127] The second observation to be made is more general. It is that
identification of the rights and obligations of the parties, in this as in any matter,
requires close attention to the particular facts and circumstances of the case.
Necessarily that requires close attention to what contractual or other obligations
each owes to the other. 10
Conclusion and orders
[128] Builders’ claim in restitution against the Lumbers fails. It is then not
necessary to consider the Lumbers’ defence to that claim founded in the Builders
Licensing Act or the Building Work Contractors Act. 15
[129] The appeal should be allowed with costs, the orders of the Full Court of
the Supreme Court of South Australia set aside and in their place there should be
orders that the appeal to that court is dismissed with costs.

Orders 20
(1) Appeal allowed with costs.
(2) Set aside the orders of the Full Court of the Supreme Court of South
Australia made on 1 March 2007 and, in their place, order that the
appeal to that court be dismissed with costs.
25
JONATHON DOOLEY
SOLICITOR

30

35

40

45

50

You might also like